CN103215956A - Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm - Google Patents
Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm Download PDFInfo
- Publication number
- CN103215956A CN103215956A CN2013101165859A CN201310116585A CN103215956A CN 103215956 A CN103215956 A CN 103215956A CN 2013101165859 A CN2013101165859 A CN 2013101165859A CN 201310116585 A CN201310116585 A CN 201310116585A CN 103215956 A CN103215956 A CN 103215956A
- Authority
- CN
- China
- Prior art keywords
- pile
- steel pipe
- pipe pile
- many
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Foundations (AREA)
- Wind Motors (AREA)
Abstract
The invention discloses a multi-pile pile gripper and a multi-pile guide pipe frame foundation construction method for a shallow wind power farm. The multi-pipe pile gripper comprises a rotary shaft, a large arm, a rotary arm and a small arm; the rotary shaft is arranged in the seat center of an air blower; the large arm is sleeved on the rotary shaft; the rotary arm is sleeved on the rotary shaft; and the small arm is arranged at one end of the rotary shaft and has a small arm center. The multi-pile pile gripper is provided with a plurality of pile centers which are in the same circle together with the small arm center; and the plurality of pile centers are uniformly arranged on the circle. The multi-pile guide pipe frame foundation construction method for the shallow wind farm comprises the following steps of positioning the coordinates of the multi-pipe pile gripper in the seat center, positioning a conveying ship, fixing steel pipe pile on the multi-pile pile gripper to perform pile sinking, and sleeving the guide pipe frame on the steel pipe pile to perform grouting. By adopting the multi-pile pile gripper and the method provided by the invention, the difficulty for driving multi-pile at one ship position is solved, and the efficiency is improved.
Description
Technical field
The present invention relates to offshore wind farm industry Foundation Design field, relate in particular to a kind of shallow sea wind power field many pile leaders frame foundation construction method.
Background technology
Wind-power electricity generation develops into present marine intertidal zone, offshore sea waters by traditional land wind-powered electricity generation along with progress of science and technology; Multiple structures such as highrise pile cap, single pile and many pile leaders frame have also appearred in wind power generation structure foundation structure.The installed capacity of separate unit blower fan is also developed to 5MW in the future or bigger direction by 2.5MW, the 3MW of present main flow, cause basic pile body increasing, weight is increasing, difficulty of construction is increasing, and be subjected to the influence of each side such as equipment, construction technology factor up till now, take all factors into consideration each side's cost, the fan foundation structure of offshore sea waters (5~30 meters depth of water) relatively is fit to adopt many pile leaders shelf structure.
Traditional many pile leaders of blower fan frame foundation construction scheme is crept into platform jacket foundation construction process with reference to the ocean, and two cover main flow technologies are arranged: a cover is jacket elder generation sinking seabed, piling then; Another set of elder generation beats many, then according to many position customization jackets.There is following shortcoming in this two covers method: 1) the first cover construction technology needs the seabed leveling, and need every dozen 1 pile leveling once during the piling of back, need a large amount of large lifting equipment inputs, efficiency of construction is low, it is bigger influenced by sea conditions, and usually efficient is 1 cover basis/15 days; 2) though the second cover constructure scheme is less with respect to the first cover constructure scheme operation, owing to need cause efficiency of construction very low, about 1 cover basis/20 days according to many stake position size customization jackets.
In view of this, how designing a kind of shallow sea wind power field many pile leaders frame foundation construction method, solve the problem that an accommodation is difficult to beat many steel pipe piles, and reduce the site error between many dresses, is the problem that the insider needs solution badly.
Summary of the invention
In prior art, shallow sea wind power field many pile leaders frame foundation construction method, exist an accommodation to be difficult to beat many steel pipe piles, site error between many dresses is bigger, and defectives such as cost is higher, construction period is long the invention provides a kind of shallow sea wind power field many pile leaders frame foundation construction method.
According to an aspect of the present invention, provide a kind of many pile holding devices, wherein, having comprised:
Rotating shaft is positioned at center, blower fan seat in the plane;
Big arm is sheathed in the described rotating shaft;
Cursor is sheathed in the described rotating shaft; And
Forearm is arranged at an end of described cursor, and described forearm has the forearm center;
Wherein, described many pile holding utensils have several centers, position, and several described stake centers, position and described forearm are centered close on the same circle, and several centers, described stake position are distributed on the described circle.
2. many pile holding devices as claimed in claim 1 is characterized in that, described big arm adjustable range is a 20-30 rice.
Preferably, the adjustable range of described cursor is a 10-15 rice.
Preferably, may further comprise the steps:
(a) with the coordinate setting of many pile holding devices in center, described blower fan seat in the plane, and cargo ship located;
(b) steel pipe pile is fixed on described many pile holding devices and carries out pile sinking; And
(c) jacket is placed on the steel pipe pile is in the milk.
Preferably, in the described step (b), comprise the following steps:
(b1) the described cursor of described many pile holding devices of rotation to described forearm center corresponding to center, described stake position;
(b2) two cover rigging upper ends are hung on respectively on two gib heads of crane, then every cover rigging lower end are hung on respectively on the upper and lower hanger of steel pipe pile;
(b3) the hoist suspension hook of described crane, to lift described steel pipe pile to safe altitude, erect until steel pipe pile hoist the simultaneously described steel pipe pile upper end and the described steel pipe pile lower end that descends;
(b4) the described rigging on the hanger of the described steel pipe pile of dismounting lower end;
(b5) jib of the described crane of rotation, the described stake position that described steel pipe pile is placed described many pile holding devices is held described forearm tightly in the heart;
(b6) upper end of the described steel pipe pile of decline, the described steel pipe pile of drowning oneself is removed the described rigging on the hanger of described steel pipe pile upper end;
(b7) utilize described crane that pile hammer is risen and winch to described steel pipe pile upper end, and hammer, start described pile hammer described steel pipe pile is carried out continuous pile sinking.
(b8) repeating step (b1)~(b7) carries out pile sinking to remaining described steel pipe pile.
Preferably, the described lockset of every cover comprises 1 200T hanging beam, 4 100T shackles, 2 100T-32 rice wire rope and 2 100T-16 rice wire rope.
Preferably, described crane is the 800T crane.
Preferably, the hoist speed of the described steel pipe pile upper end and the described steel pipe pile that descends is 2-4 rice/min.
Preferably, in the described step (c), comprise the following steps:
(c1) utilize the double hook of crane that described jacket is lifted to the top, seat in the plane, the described crane double hook that descends then is placed in the jacket sleeve on each described steel pipe pile;
(c2) by the described jacket of jack leveling, make described jacket upper flange gradient≤2 ‰; And
(c3) material that will be in the milk injects in the cavity between described jacket sleeve and the described steel pipe pile, waits for that grouting expects that intensity reaches 75%.
Preferably, in the described step (a), the boat-carrying GPS by self formula lifting platform with the coordinate setting of described many pile holding devices in center, described seat in the plane.
Advantage of the present invention is: a kind of adjustable many pile holding devices are installed on the self-rising crane platform; this many pile leaders of cover shallow sea area wind energy turbine set frame foundation construction method; have construction equipment at present now and increase a kind of adjustable many pile holding devices in conjunction with domestic; optimized traditional many pile leaders frame foundation construction method greatly; greatly reduce construction cost; improved efficiency of construction; advance the process of shallow sea area wind energy turbine set large-scale production greatly, greatly reduced coastal waters many pile leaders of wind energy turbine set frame foundation construction cost.Be specially: 1, solved the difficult problem that many piles are beaten at the accommodation; 2, fine center, the piling bar position relative position deviation of having controlled, having solved jacket needs a difficult problem customized; 3, improved the efficient of offshore construction greatly.
Description of drawings
In order to be illustrated more clearly in the embodiment of the invention or technical scheme of the prior art, to do to introduce simply to the accompanying drawing of required use in embodiment or the description of the Prior Art below, apparently, accompanying drawing in describing below only is some embodiments of the present invention, for those of ordinary skills, under the prerequisite of not paying creative work, can also obtain other accompanying drawing according to these accompanying drawings.
Fig. 1 shows the structural representation according to many pile holding devices of one aspect of the invention.
The specific embodiment
Below in conjunction with the accompanying drawing in the embodiment of the invention, the technical scheme in the embodiment of the invention is clearly and completely described, obviously, described embodiment only is the present invention's part embodiment, rather than whole embodiment.Based on the embodiment among the present invention, those of ordinary skills belong to the scope of protection of the invention not making the every other embodiment that is obtained under the creative work prerequisite.
Fig. 1 shows the structural representation according to many pile holding devices of one aspect of the invention.With reference to Fig. 1, many pile holding devices comprise rotating shaft 10, big arm 11, cursor 12 and forearm 13.Wherein, rotating shaft is positioned at center, blower fan seat in the plane.Big arm 11 is sheathed in the rotating shaft 10, and can rotate around rotating shaft 10.The adjustable range of the length of big arm 11 is a 20-30 rice, for example 15 meters.One end of cursor 12 also is sheathed in the rotating shaft 10, can rotate around rotating shaft 10 equally.The other end of cursor 12 is connected with forearm 13, and the adjustable range of the length of cursor 12 is a 10-15 rice, for example 12 meters.Forearm 13 specifically comprises a connecting rod and two handgrips, and the centre of connecting rod is connected on the cursor 12, and two handgrips then vertically are connected in the connecting rod two ends respectively, and forearm 13 has the forearm center, and the forearm center is the line of centres of two handgrips.In addition, many pile holding utensils have several centers, position 141, be centered close on the same circle 14 with forearm, and several centers, position 141 are distributed on the circle 14.
Shallow sea wind power field many pile leaders frame foundation construction method is specific as follows described:
In center, blower fan seat in the plane, and with cargo ship location, cargo ship is used for transporting blower fan with the coordinate setting of many pile holding devices.At first, utilize boat-carrying GPS by self formula lifting platform, many pile holding device centre coordinates are moved to (about 2 meters of deviations) near the center, seat in the plane, then, utilize 3 anchor ships that 4 positioning anchors are drawn and be thrown into the seabed, the self lift type lifting platform accurately is positioned at pile holding device centre coordinate on the design seat in the plane (errors of centration is less than 200mm) by positioning anchor, next, the self lift type lifting platform begins the ballast cargo ship, lifting cargo ship (cargo ship being lifted away from the water surface) after ballast finishes by 4 supporting legs, after the hull bottom of cargo ship breaks away from the water surface with an amount of venting of ballast tank water, continuing lifting rises to the cargo ship hull from stopping about 6 meters on the lowest water level water surface, by the anchor ship cargo ship is dragged to self lift type lifting platform side, and throws 4 positioning anchor location.Above self lift type lifting platform location, steady ship and cargo ship about 2 days of time spent of location.
Then, steel pipe pile is fixed on many pile holding devices and carries out pile sinking.The cursor 12 that rotates many pile holding devices makes the forearm center corresponding to 141 places, center, a stake position to the forearm center.Two cover rigging upper ends are hung on respectively on two gib heads of crane, and every cover lockset all comprises 1 200T hanging beam, 4 100T shackles, 2 100T-32 rice wire rope and 2 100T-16 rice wire rope, and crane is the 800T crane.Then every cover rigging lower end is hung on respectively on the last hanger and following hanger of steel pipe pile.Then, the suspension hook of the crane that hoists is raised up to safe altitude with steel pipe pile, and erect until steel pipe pile slowly hoist simultaneously steel pipe pile upper end and decline steel pipe pile lower end.With the speed of 2-4 rice/min hoist steel pipe pile upper end and decline steel pipe pile lower end.Then, the rigging on the hanger of dismounting steel pipe pile lower end.The jib of revolving crane is positioned over steel pipe pile on the center, a stake position 141 of many pile holding devices, holds forearm tightly to catch steel pipe pile.The upper end of decline steel pipe pile, the steel pipe pile of drowning oneself is then removed the rigging on the hanger of steel pipe pile upper end.Utilize crane that pile hammer is worked the upper end that winches to steel pipe pile, and hammer, start pile hammer steel pipe pile is carried out continuous pile sinking.Repeat above step and carry out pile sinking remaining described steel pipe pile.
At last, jacket is placed on the steel pipe pile is in the milk.To the top, seat in the plane, the double hook of the crane that descends then is placed in the sleeve of jacket on each steel pipe pile the double hook that utilizes crane with the jacket lifting.By jack leveling jacket, make jacket upper flange gradient≤2 ‰.The grouting material is injected in the sleeve and the cavity between the steel pipe pile of jacket, wait for that grouting material intensity reaches 75%.
Advantage of the present invention is: a kind of adjustable many pile holding devices are installed on the self-rising crane platform; this many pile leaders of cover shallow sea area wind energy turbine set frame foundation construction method; have construction equipment at present now and increase a kind of adjustable many pile holding devices in conjunction with domestic; optimized traditional many pile leaders frame foundation construction method greatly; greatly reduce construction cost; improved efficiency of construction; advance the process of shallow sea area wind energy turbine set large-scale production greatly, greatly reduced coastal waters many pile leaders of wind energy turbine set frame foundation construction cost.Be specially: 1, solved the difficult problem that many piles are beaten at the accommodation; 2, fine center, the piling bar position relative position deviation of having controlled, having solved jacket needs a difficult problem customized; 3, improved the efficient of offshore construction greatly.
More than show and described basic principle of the present invention, principal character and advantage of the present invention.The technician of the industry should understand; the present invention is not restricted to the described embodiments; that describes in the foregoing description and the manual just illustrates principle of the present invention; the present invention also has various changes and modifications without departing from the spirit and scope of the present invention, and these changes and improvements all fall in the claimed scope of the invention.The claimed scope of the present invention is defined by appending claims and equivalent thereof.
Claims (10)
1. one kind many pile holding devices is characterized in that, comprising:
Rotating shaft is positioned at center, blower fan seat in the plane;
Big arm is sheathed in the described rotating shaft;
Cursor is sheathed in the described rotating shaft; And
Forearm is arranged at an end of described cursor, and described forearm has the forearm center;
Wherein, described many pile holding utensils have several centers, position, and several described stake centers, position and described forearm are centered close on the same circle, and several centers, described stake position are distributed on the described circle.
2. many pile holding devices as claimed in claim 1 is characterized in that the length adjustment scope of described big arm is a 20-30 rice.
3. many pile holding devices as claimed in claim 1 is characterized in that the adjustable range of the length of described cursor is a 10-15 rice.
4. shallow sea wind power field many pile leaders frame foundation construction method of a utilization such as each described many pile holding devices of claim 1 to 3 is characterized in that, may further comprise the steps:
(a) with the coordinate setting of many pile holding devices in center, described blower fan seat in the plane, and cargo ship located;
(b) steel pipe pile is fixed on described many pile holding devices and carries out pile sinking; And
(c) jacket is placed on the steel pipe pile is in the milk.
5. shallow sea wind power as claimed in claim 4 field many pile leaders frame foundation construction method is characterized in that, in the described step (b), comprises the following steps:
(b1) the described cursor of described many pile holding devices of rotation to described forearm center corresponding to center, described stake position;
(b2) two cover rigging upper ends are hung on respectively on two gib heads of crane, then every cover rigging lower end are hung on respectively on the upper and lower hanger of steel pipe pile;
(b3) the hoist suspension hook of described crane, to lift described steel pipe pile to safe altitude, erect until steel pipe pile hoist the simultaneously described steel pipe pile upper end and the described steel pipe pile lower end that descends;
(b4) the described rigging on the hanger of the described steel pipe pile of dismounting lower end;
(b5) jib of the described crane of rotation, the described stake position that described steel pipe pile is placed described many pile holding devices is held described forearm tightly in the heart;
(b6) upper end of the described steel pipe pile of decline, the described steel pipe pile of drowning oneself is removed the described rigging on the hanger of described steel pipe pile upper end;
(b7) utilize described crane that pile hammer is risen and winch to described steel pipe pile upper end, and hammer, start described pile hammer described steel pipe pile is carried out continuous pile sinking.
(b8) repeating step (b1)~(b7) carries out pile sinking to remaining described steel pipe pile.
6. shallow sea wind power as claimed in claim 5 field many pile leaders frame foundation construction method is characterized in that, the described lockset of every cover comprises 1 200T hanging beam, 4 100T shackles, 2 100T-32 rice wire rope and 2 100T-16 rice wire rope.
7. shallow sea wind power as claimed in claim 5 field many pile leaders frame foundation construction method is characterized in that described crane is the 800T crane.
8. shallow sea wind power as claimed in claim 5 field many pile leaders frame foundation construction method is characterized in that, the speed of the hoist described steel pipe pile upper end and the described steel pipe pile that descends is 2-4 rice/min.
9. shallow sea wind power as claimed in claim 4 field many pile leaders frame foundation construction method is characterized in that, in the described step (c), comprises the following steps:
(c1) utilize the double hook of crane that described jacket is lifted to the top, seat in the plane, the described crane double hook that descends then is placed in the jacket sleeve on each described steel pipe pile;
(c2) by the described jacket of jack leveling, make described jacket upper flange gradient≤2 ‰; And
(c3) material that will be in the milk injects in the cavity between described jacket sleeve and the described steel pipe pile, waits for that grouting expects that intensity reaches 75%.
10. shallow sea wind power as claimed in claim 4 field many pile leaders frame foundation construction method is characterized in that, in the described step (a), the boat-carrying GPS by self formula lifting platform with the coordinate setting of described many pile holding devices in center, described seat in the plane.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310116585.9A CN103215956B (en) | 2013-04-03 | 2013-04-03 | Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310116585.9A CN103215956B (en) | 2013-04-03 | 2013-04-03 | Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103215956A true CN103215956A (en) | 2013-07-24 |
CN103215956B CN103215956B (en) | 2015-04-22 |
Family
ID=48814081
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310116585.9A Active CN103215956B (en) | 2013-04-03 | 2013-04-03 | Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103215956B (en) |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104563119A (en) * | 2015-01-19 | 2015-04-29 | 天津港航工程有限公司 | Rotating type floating pile driving guide frame |
CN105464117A (en) * | 2015-12-25 | 2016-04-06 | 天津港航工程有限公司 | Rotary-type overwater piling guide frame and piling process for overwater pile group foundations |
CN105649080A (en) * | 2015-12-31 | 2016-06-08 | 中交第三航务工程局有限公司宁波分公司 | Single-pile pile sinking method |
CN107119687A (en) * | 2017-04-19 | 2017-09-01 | 合肥学院 | A kind of intertidal zone pile sinking position-limited rack that can significantly rotate and its construction method |
CN107326887A (en) * | 2017-06-22 | 2017-11-07 | 广东华尔辰海上风电工程有限责任公司 | Offshore wind farm elder generation pile leader frame construction method of installation |
CN117552396A (en) * | 2023-10-19 | 2024-02-13 | 华电重工股份有限公司 | Offshore photovoltaic installation method and installation system |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2168406A (en) * | 1984-11-09 | 1986-06-18 | Earl & Wright Ltd | Removable layback pile guide |
JPH0925630A (en) * | 1995-07-12 | 1997-01-28 | Atsushi Yoshino | Pile guide apparatus |
CN201513303U (en) * | 2009-09-25 | 2010-06-23 | 中国水电顾问集团华东勘测设计研究院 | Offshore wind turbine generator foundation structure with multi-pile steel frame |
CN102182205A (en) * | 2011-05-18 | 2011-09-14 | 江苏海上龙源风力发电有限公司 | Construction process for single-pile wind turbine foundation in intertidal zone |
CN102720197A (en) * | 2012-07-05 | 2012-10-10 | 南通中远船务工程有限公司 | Method for hoisting pile legs of self-elevating wind turbine installation vessel in turn-over way |
-
2013
- 2013-04-03 CN CN201310116585.9A patent/CN103215956B/en active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB2168406A (en) * | 1984-11-09 | 1986-06-18 | Earl & Wright Ltd | Removable layback pile guide |
JPH0925630A (en) * | 1995-07-12 | 1997-01-28 | Atsushi Yoshino | Pile guide apparatus |
CN201513303U (en) * | 2009-09-25 | 2010-06-23 | 中国水电顾问集团华东勘测设计研究院 | Offshore wind turbine generator foundation structure with multi-pile steel frame |
CN102182205A (en) * | 2011-05-18 | 2011-09-14 | 江苏海上龙源风力发电有限公司 | Construction process for single-pile wind turbine foundation in intertidal zone |
CN102720197A (en) * | 2012-07-05 | 2012-10-10 | 南通中远船务工程有限公司 | Method for hoisting pile legs of self-elevating wind turbine installation vessel in turn-over way |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104563119A (en) * | 2015-01-19 | 2015-04-29 | 天津港航工程有限公司 | Rotating type floating pile driving guide frame |
CN105464117A (en) * | 2015-12-25 | 2016-04-06 | 天津港航工程有限公司 | Rotary-type overwater piling guide frame and piling process for overwater pile group foundations |
CN105464117B (en) * | 2015-12-25 | 2017-07-25 | 天津港航工程有限公司 | Rotary marine piling saddle and multi-column pier foundation piling technique waterborne |
CN105649080A (en) * | 2015-12-31 | 2016-06-08 | 中交第三航务工程局有限公司宁波分公司 | Single-pile pile sinking method |
CN107119687A (en) * | 2017-04-19 | 2017-09-01 | 合肥学院 | A kind of intertidal zone pile sinking position-limited rack that can significantly rotate and its construction method |
CN107119687B (en) * | 2017-04-19 | 2023-08-22 | 合肥学院 | Inter-tidal zone pile sinking limit frame capable of rotating greatly and construction method thereof |
CN107326887A (en) * | 2017-06-22 | 2017-11-07 | 广东华尔辰海上风电工程有限责任公司 | Offshore wind farm elder generation pile leader frame construction method of installation |
CN107326887B (en) * | 2017-06-22 | 2019-06-18 | 广东华尔辰海上风电工程有限责任公司 | Offshore wind farm elder generation pile leader frame construction method of installation |
CN117552396A (en) * | 2023-10-19 | 2024-02-13 | 华电重工股份有限公司 | Offshore photovoltaic installation method and installation system |
Also Published As
Publication number | Publication date |
---|---|
CN103215956B (en) | 2015-04-22 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103215956B (en) | Multi-pile pile gripper and multi-pile guide pipe frame foundation construction method for shallow wind power farm | |
CN103981867B (en) | The piling position-limited rack of intertidal zone offshore wind power foundation pile sinking and construction method thereof | |
CN103228530B (en) | Floating structure operating system, floating structure, operation ship and floating structure operational method | |
CN109629568A (en) | The process for sinking of the steady stake platform of offshore wind farm jacket foundation steel pipe pile floating | |
CN101565091B (en) | Installation equipment of above-water wind generator and construction method thereof | |
JP2019529286A (en) | Crane, ship including such a crane, and method for erecting a vertical structure | |
CN104032765A (en) | Shallow sea wind power plant rock-socketed monopile foundation construction method | |
CN106828812B (en) | Semi-submersible type deep-sea wind-powered electricity generation mounting platform and its wind power generating set integral installation method | |
CN1767976A (en) | A vessel for transporting wind turbines, methods of moving a wind turbine, and a wind turbine for an off-shore wind farm | |
CN104727336A (en) | Construction method of large single-pipe pile foundation of shallow-sea wind power plant | |
KR101401985B1 (en) | Floating crane with jack-up system for floating structure | |
CN102720197A (en) | Method for hoisting pile legs of self-elevating wind turbine installation vessel in turn-over way | |
CN107804437A (en) | Sit bottom jack up wind-powered electricity generation pile driving barge | |
CN206634171U (en) | Semi-submersible type deep-sea wind-powered electricity generation mounting platform | |
CN113090470B (en) | Installation method of offshore wind turbine | |
CN107313350A (en) | A kind of marine integral hoisting method of profile iron Sarasota | |
CN107795438B (en) | A kind of construction method of assistance platform | |
CN102050198A (en) | Split installation process of submerged barge seat of wind driven generator in shallow water | |
CN110239672A (en) | A kind of wind-powered electricity generation sea oil type sea is stepped on by fore-and-aft gangway | |
CN215884017U (en) | Floating ship hoisting structure | |
NL2007833C2 (en) | Method of installing a high above the sea projecting slender offshore tower with suction pile foundation. | |
CN207257907U (en) | A kind of guide pile ship for over-water construction | |
CN207792620U (en) | A kind of jack up hoistable platform | |
CN207596369U (en) | A kind of boom hoisting for being suitable for marine O&M | |
CN112850488A (en) | Method for overturning steel pipe pile of fixed-boom crane ship |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |