CN103195450A - Hydraulic tunnel inverted arch operation trolley and inverted arch construction method - Google Patents

Hydraulic tunnel inverted arch operation trolley and inverted arch construction method Download PDF

Info

Publication number
CN103195450A
CN103195450A CN2013101144458A CN201310114445A CN103195450A CN 103195450 A CN103195450 A CN 103195450A CN 2013101144458 A CN2013101144458 A CN 2013101144458A CN 201310114445 A CN201310114445 A CN 201310114445A CN 103195450 A CN103195450 A CN 103195450A
Authority
CN
China
Prior art keywords
template
hinged
inverted arch
oil cylinder
hydraulic pressure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013101144458A
Other languages
Chinese (zh)
Other versions
CN103195450B (en
Inventor
瞿伦建
沈承福
刘江涛
李可军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Yuandong Steel Mould Co ltd
Original Assignee
Hunan Yuandong Steel Mould Electronic Science & Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Yuandong Steel Mould Electronic Science & Technology Co Ltd filed Critical Hunan Yuandong Steel Mould Electronic Science & Technology Co Ltd
Priority to CN201310114445.8A priority Critical patent/CN103195450B/en
Publication of CN103195450A publication Critical patent/CN103195450A/en
Application granted granted Critical
Publication of CN103195450B publication Critical patent/CN103195450B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a hydraulic tunnel inverted arch operation trolley and an inverted arch construction method. The hydraulic tunnel inverted arch operation trolley comprises a main beam, a plurality of templates and at least three rows of screw rods, wherein each of the templates comprises a first template body and a second template body, first template bodies are hinged with second template bodies, the plurality of templates are connected into a whole in a hinge mode, two tailstocks are arranged on the upper end of the main beam, two ends of each of the tailstocks are hinged with upper ends of two lifting oil cylinders respectively, lower ends of the two lifting oil cylinders are hinged with corresponding templates respectively, two control frames are arranged at positions on the main beam, which correspond to the two tailstocks, control frames are hinged with one end of a translation oil cylinder, the other end of the translation oil cylinder is hinged with the lifting oil cylinder which is located at the same end as the two tailstocks, lower ends of the three rows of screw rods are hinged with two ends and middle portions of templates respectively, and upper ends of the three rows of screw rods are hinged with the main beam. The hydraulic tunnel inverted arch operation trolley is simple to operate and capable of accelerating the construction schedule of a tunnel inverted arch and improving the quality of inverted arch construction.

Description

Hydraulic pressure tunnel invert operation trolley and inverted arch job practices
Technical field
The present invention relates to a kind of hydraulic pressure tunnel invert operation trolley for highway, water conservancy, railway tunnel work and inverted arch job practices.
Background technology
Inverted arch is one of chief component of tunnel structure, is lining cutting basis commonly used in the present constructing tunnel.It will effectively be delivered to underground by the tunnel side wall structure load on tunnel upper formation pressure and the road surface on the one hand, also will effectively resist the counter-force that the understratum is transmitted on the other hand, so inverted arch plays crucial effects to whole Stability of Tunnel.Therefore the construction of the inverted arch in tunnel becomes the important step in the whole constructing tunnel process, and in the work progress of inverted arch, and invert operation trolley is requisite construction equipment wherein.
In existing constructing tunnel, usually used invert operation trolley comprises girder truss, some templates and screw mandrel, each template is mutually permanently connected and becomes one, girder truss comprises crossbeam and vertical supports, crossbeam and vertical supports are welded as a whole, vertical supports stand on ground or the inverted arch that completed on, with the whole inverted arch mould bases of support bearing, fixedly connected with template with described crossbeam respectively in the two ends of screw mandrel, thereby whole mould bases passes through screw mandrel and support shuttering.Before the installing of inverted arch mould bases, at the corresponding reinforcing bar of inverted arch position of sound production, install the inverted arch mould bases then, and by finish the construction to inverted arch to template below placing of concrete.
When adopting above-mentioned invert operation trolley that inverted arch is constructed, owing to be with the fixedly connected mode one that is formed by connecting between each template, therefore, during use, template is difficult to the location, and after inverted arch once constructed, template need integral body be carried out the dismounting operation, so that carry out next time constructing operation, so the labour have high input and efficient low; The bearing capacity of existing inverted arch mould bases is big inadequately in addition, thereby the length of the feasible inverted arch of once constructing is shorter, has prolonged the time of inverted arch construction; And because bearing capacity is big inadequately, whole inverted arch mould bases is in carrying out the inverted arch work progress, and easy deformation makes the supporting role of template is had a greatly reduced quality, and makes the template skew easily, thereby influences the quality after the inverted arch construction.
Summary of the invention
In order to solve the problems of the technologies described above, the invention provides a kind of hydraulic pressure tunnel invert operation trolley simple to operate and inverted arch job practices, both improved the construction speed in tunnel, improved the construction quality in tunnel again.
The technical solution used in the present invention is: a kind of hydraulic pressure tunnel invert operation trolley, comprise girder, a plurality of template and at least three row's screw mandrels, each described template comprises first template and second template, and first template and second template are hinged, and a plurality of templates are connected to become an integral body in hinged mode; Described girder comprises crossbeam and vertical supports, and described crossbeam and vertical supports are connected to one; The upper end of described girder is provided with two tailstocks, the two ends of each tailstock are hinged with the upper end of a hoist cylinder respectively, the lower end of two hoist cylinders is hinged with corresponding template respectively, also be provided with two control framves corresponding to two tailstock places on the described girder, one end of control frame and translation oil cylinder is hinged, the hoist cylinder of the other end of translation oil cylinder and the same end of two tailstocks is hinged, and described three row's screw mandrel lower ends are hinged on two ends and the middle part of template respectively, and the upper end all is hinged on the girder.
In the above-mentioned hydraulic pressure tunnel invert operation trolley, be provided with logical beam with the screw mandrel hinged place on the described template, the length of logical beam is all template length sums.
In the above-mentioned hydraulic pressure tunnel invert operation trolley, the front end both sides of described girder are equipped with a forward foot in a step, and each forward foot in a step comprises supporting leg and bearing, supporting leg is packed in the girder front end, bearing is sleeved on the outside of supporting leg, is equipped with pin hole on supporting leg and the bearing, connects by pin; The lower end of described bearing is provided with threaded base.
In the above-mentioned hydraulic pressure tunnel invert operation trolley, the both sides, rear end of described girder are equipped with a rear foot assembly, and each rear foot assembly comprises two supporting legs, support oil cylinder and roller; Two supporting legs and support oil cylinder are packed in main beam rear end; Support oil cylinder is between two supporting legs, and the lower end of support oil cylinder is connected with roller by shoulder pole.
In the above-mentioned hydraulic pressure tunnel invert operation trolley, the upper end of described template is equipped with the waterstop holder, and the waterstop holder comprises cramping body and binding clip, and binding clip is hinged on the cramping body.
Utilize the inverted arch job practices of hydraulic pressure tunnel invert operation trolley to comprise the steps:
1) the position excavation pit of inverted arch is set at needs, and must removes clean to the empty slag in the foundation ditch, foreign material, ponding etc.; The inverted arch steelframe is set in foundation ditch then;
2) the hydraulic pressure tunnel invert operation trolley is in place, guarantee line parallel in hydraulic pressure tunnel invert operation trolley and the tunnel foundation ditch, the primer fluid pressing system is packed up support oil cylinder and is adjusted the girder level;
3) operation hydraulic system makes hoist cylinder descend and the adjustment template, makes template near predetermined altitude, installs two row's screw mandrels at template two ends;
4) operation hydraulic system makes the cross cylinder action adjust template and reaches inverted arch absolute altitude position, behind the complete operation, screws two row's screw mandrels at template two ends, the row's screw mandrel in the middle of the installation template;
5) with all oil cylinder releases, fill concrete in the gap between tunnel, lining cutting position and the template then, one-time-concreting is finished;
6) screw mandrel of dismounting hydraulic pressure tunnel invert operation trolley, the operation hydraulic system makes hoist cylinder move climbing shuttering, the demoulding;
7) the operation hydraulic system makes support oil cylinder stretch out, and the supporting leg of rear foot assembly is propped up, and lifting hydraulic pressure tunnel invert operation trolley front end moves to next place's construction location with it.
The invention has the beneficial effects as follows: template of the present invention is connected with girder by lift cylinder, and is simple in structure, can realize " floating the putting " of template, and the location is fast; The present invention is after the inverted arch construction is finished, hoist cylinder can be packed up the demoulding, no longer need the template dismounting operation of integral body is carried out the constructing operation at next place, alleviated working strength of workers, and make to two serving as a contrast or abutment wall is constructed and separated of being connected with inverted arch, guaranteed that two linings, abutment wall are connected circle along can't faulting of slab ends with the inverted arch base plate, improved the quality of inverted arch construction; In addition, template accepted two linings or abutment wall are constructed, inverted arch is separated with two linings or the constructing operation of abutment wall carried out, do not influence the speed of whole constructing tunnel simultaneously again, improved the progress that inverted arch is constructed.
Description of drawings
Fig. 1 is front view of the present invention.
Fig. 2 is left view of the present invention.
Fig. 3 is the structure chart of demoulding state of the present invention.
The specific embodiment
The present invention is further illustrated below in conjunction with accompanying drawing.
As shown in Figure 1, 2, the present invention includes girder 1, a plurality of template 2 and three row's screw mandrels 3, each described template 2 comprises that first template 21 and second template, 22, the first templates 21 and second template 22 are hinged, and a plurality of templates 2 are connected to become an integral body in hinged mode; Described girder 1 comprises crossbeam 12 and vertical supports 11, and described crossbeam 12 is connected to one with vertical supports 11; The upper end of described girder 1 is provided with two tailstocks 4, and the two ends of each tailstock 3 are hinged with the upper end of a hoist cylinder 41 respectively, and the lower end of hoist cylinder 41 is hinged with corresponding template 2 respectively.Also be provided with two control framves 13 corresponding to two tailstocks, 4 places on the described girder 1, control frame 13 is hinged with an end of translation oil cylinder 14, the hoist cylinder 41 of the other end of translation oil cylinder 14 and two tailstocks, 4 same ends is hinged, described three row's screw mandrels 3 lower ends are hinged with two ends and the middle part of template 2 respectively, and the upper end all is hinged on the girder 1.
The front end both sides of described girder 1 are equipped with a forward foot in a step 5, each forward foot in a step 5 comprises two supporting legs 61 and two bearings 62, supporting leg 61 is packed in girder 1 front end, bearing 52 is sleeved on the outside of supporting leg 61, be equipped with pin hole 64 on supporting leg 61 and the bearing 62, spacing between the adjacent pin hole 64 equates, supporting leg 61 and bearing 62 are connected by pin; The lower end of described bearing 62 is provided with threaded base 63.
The both sides, rear end of described girder 1 are equipped with a rear foot assembly 5, and each rear foot assembly 5 comprises two supporting legs 54, support oil cylinder 53 and roller 51; Two supporting legs 54 and support oil cylinder 53 are packed in the rear end of girder 1; Support oil cylinder 53 is between two supporting legs 54, and the lower end of support oil cylinder 53 is connected with roller 51 by shoulder pole 52.
Be provided with logical beam 23 with screw mandrel 3 hinged places on the described template 2, the length of logical beam 23 is all template 2 length sums.The upper end of described template 2 is equipped with waterstop holder 24, and waterstop holder 24 comprises cramping body 241 and binding clip 242, and binding clip 242 is hinged on the cramping body 241.
The step that use the present invention carries out the inverted arch construction is as follows:
1) the position excavation pit of inverted arch is set at needs, and must removes clean to the empty slag in the foundation ditch, foreign material, ponding etc.; The inverted arch steelframe is set in foundation ditch then;
2) the hydraulic pressure tunnel invert operation trolley is in place, guarantee line parallel in hydraulic pressure tunnel invert operation trolley and the tunnel foundation ditch, the primer fluid pressing system is packed up support oil cylinder 53 and is adjusted girder 1 level;
3) operation hydraulic system makes hoist cylinder 41 descend and adjustment template 2, makes template 2 near predetermined altitude, installs two row's screw mandrels 3 at template 2 two ends;
4) operation hydraulic system makes cross cylinder 14 actions adjust template 2 and makes it reach inverted arch absolute altitude position, behind the complete operation, screws two row's screw mandrels 3 at template 2 two ends, the row's screw mandrel 3 in the middle of installation template 2;
5) with all oil cylinder releases, fill concrete in the gap between tunnel, lining cutting position and the template then;
6) screw mandrel 3 of dismounting hydraulic pressure tunnel invert operation trolley, the operation hydraulic system makes hoist cylinder 41 move climbing shuttering 2, the demoulding;
7) the operation hydraulic system makes support oil cylinder 53 stretch out, and the supporting leg 54 of rear foot assembly is propped up, and lifting hydraulic pressure tunnel invert operation trolley front end moves to next place's construction location with it.

Claims (6)

1. hydraulic pressure tunnel invert operation trolley, it is characterized in that: comprise girder, a plurality of template and at least three row's screw mandrels, each described template comprises first template and second template, and first template and second template are hinged, and a plurality of templates are connected to become an integral body in hinged mode; Described girder comprises crossbeam and vertical supports, and described crossbeam and vertical supports are connected to one; The upper end of described girder is provided with two tailstocks, the two ends of each tailstock are hinged with an end of a hoist cylinder respectively, the other end of two hoist cylinders is hinged with corresponding template respectively, also be provided with two control framves corresponding to two tailstock places on the described girder, one end of control frame and translation oil cylinder is hinged, the hoist cylinder of the other end of translation oil cylinder and the same end of two tailstocks is hinged, and described three row's screw mandrel lower ends are hinged on two ends and the middle part of template respectively, and the upper end all is hinged on the girder.
2. hydraulic pressure tunnel invert operation trolley as claimed in claim 1 is characterized in that: be provided with logical beam with the screw mandrel hinged place on the described template, the length of logical beam is all template length sums.
3. hydraulic pressure tunnel invert operation trolley as claimed in claim 1, it is characterized in that: the front end both sides of described girder are equipped with a forward foot in a step, each forward foot in a step comprises supporting leg and bearing, supporting leg is packed in the girder front end, bearing is sleeved on the outside of supporting leg, be equipped with pin hole on supporting leg and the bearing, connect by pin; The lower end of described bearing is provided with threaded base.
4. hydraulic pressure tunnel invert operation trolley as claimed in claim 1, it is characterized in that: the both sides, rear end of described girder are equipped with a rear foot assembly, and each rear foot assembly comprises two supporting legs, support oil cylinder and roller; Two supporting legs and support oil cylinder are packed in main beam rear end; Support oil cylinder is between two supporting legs, and the lower end of support oil cylinder is connected with roller by shoulder pole.
5. hydraulic pressure tunnel invert operation trolley as claimed in claim 1, it is characterized in that: the upper end of described template is equipped with the canvas cloth holder, and the canvas cloth holder comprises cramping body and binding clip, and binding clip is hinged on the cramping body.
6. a tunnel invert job practices comprises the steps:
1) the position excavation pit of inverted arch is set at needs, and must removes clean to the empty slag in the foundation ditch, foreign material, ponding etc.; The inverted arch steelframe is set in foundation ditch then;
2) the hydraulic pressure tunnel invert operation trolley is in place, guarantee line parallel in hydraulic pressure tunnel invert operation trolley and the tunnel foundation ditch, the primer fluid pressing system is packed up support oil cylinder and is adjusted the girder level;
3) operation hydraulic system makes hoist cylinder descend and the adjustment template, makes template near predetermined altitude, installs two row's screw mandrels at template two ends;
4) operation hydraulic system makes the cross cylinder action adjust template and reaches inverted arch absolute altitude position, behind the complete operation, screws two row's screw mandrels at template two ends, the row's screw mandrel in the middle of the installation template;
5) with all oil cylinder releases, fill concrete in the gap between tunnel, lining cutting position and the template then, one-time-concreting is finished;
6) screw mandrel of dismounting hydraulic pressure tunnel invert operation trolley, the operation hydraulic system makes hoist cylinder move climbing shuttering, the demoulding;
7) the operation hydraulic system makes support oil cylinder stretch out, and the supporting leg of rear foot assembly is propped up, and lifting hydraulic pressure tunnel invert operation trolley front end moves to next place's construction location with it.
CN201310114445.8A 2013-04-03 2013-04-03 Hydraulic pressure tunnel invert operation trolley and inverted arch construction method Active CN103195450B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310114445.8A CN103195450B (en) 2013-04-03 2013-04-03 Hydraulic pressure tunnel invert operation trolley and inverted arch construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310114445.8A CN103195450B (en) 2013-04-03 2013-04-03 Hydraulic pressure tunnel invert operation trolley and inverted arch construction method

Publications (2)

Publication Number Publication Date
CN103195450A true CN103195450A (en) 2013-07-10
CN103195450B CN103195450B (en) 2015-08-05

Family

ID=48718249

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310114445.8A Active CN103195450B (en) 2013-04-03 2013-04-03 Hydraulic pressure tunnel invert operation trolley and inverted arch construction method

Country Status (1)

Country Link
CN (1) CN103195450B (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103352710A (en) * 2013-07-25 2013-10-16 成都锐龙机械制造有限公司 Suspension overturn type tunnel inverted arch formwork trolley and construction method thereof
CN104514569A (en) * 2014-12-12 2015-04-15 中铁十九局集团有限公司 High-speed railway tunnel inverted arch back mold integral installing-positioning mobile trolley
CN104564103A (en) * 2014-12-12 2015-04-29 中铁十九局集团有限公司 Positioning device used for tunnel invert arch back form disassembly and assembly
CN106677802A (en) * 2016-12-28 2017-05-17 杭州江润科技有限公司 Construction method of tunnel inverted arch pouring structure
CN106988762A (en) * 2017-05-11 2017-07-28 四川省创力隧道机械设备有限公司 Tunneling boring two serves as a contrast inverted arch Suporting structure
CN108150197A (en) * 2018-02-05 2018-06-12 中铁隧道集团处有限公司 Radially overturning inverted arch trestle and its installation position method for demoulding to arc formwork
CN108643942A (en) * 2018-07-16 2018-10-12 西安科技大学 Inverted arch when a kind of hydraulic pressure adjustable adjacent
CN111749712A (en) * 2020-07-08 2020-10-09 长沙理工大学 Tunnel construction equipment
CN111749710A (en) * 2020-07-08 2020-10-09 长沙理工大学 Tunnel construction process
CN111779506A (en) * 2020-07-08 2020-10-16 中铁二十局集团有限公司 Rotatable inverted arch template

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2093127U (en) * 1990-12-30 1992-01-15 中国人民解放军驻青岛铁路分局军事代表办事处 Folding type automatically-fixing scotch block
JPH07310498A (en) * 1994-05-17 1995-11-28 Maeda Corp Form opening and closing device for tunnel
CN2266324Y (en) * 1996-08-02 1997-11-05 张政青 Two-purpose tea table
JP2007291794A (en) * 2006-04-27 2007-11-08 Kumagai Gumi Co Ltd Form device
CN101586464A (en) * 2008-05-22 2009-11-25 中铁十一局集团第一工程有限公司 Construction method of railway tunnel lining side wall concrete
CN101929341A (en) * 2010-01-12 2010-12-29 中铁隧道集团二处有限公司 Construction method for TBM synchronization lining
CN101967985A (en) * 2010-09-08 2011-02-09 中铁隧道集团三处有限公司 Self-propelled inverted arch template construction method
CN102102320A (en) * 2009-12-19 2011-06-22 襄樊金鹰轨道车辆有限责任公司 Liftable supporting leg device
CN202250110U (en) * 2011-10-24 2012-05-30 中铁十七局集团第四工程有限公司 Buried waterstop fixing device in secondary tunnel liner
CN102787850A (en) * 2012-08-29 2012-11-21 中铁二十三局集团第一工程有限公司 Inverted arch formwork for tunnel inverted arch construction
CN202569294U (en) * 2011-12-06 2012-12-05 青岛康顿钢塑制品发展有限公司 Multifunctionnal exerciser
CN203130107U (en) * 2013-04-03 2013-08-14 湖南远东钢模电子科技有限责任公司 Hydraulic tunnel inverted arch operation trolley

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2093127U (en) * 1990-12-30 1992-01-15 中国人民解放军驻青岛铁路分局军事代表办事处 Folding type automatically-fixing scotch block
JPH07310498A (en) * 1994-05-17 1995-11-28 Maeda Corp Form opening and closing device for tunnel
CN2266324Y (en) * 1996-08-02 1997-11-05 张政青 Two-purpose tea table
JP2007291794A (en) * 2006-04-27 2007-11-08 Kumagai Gumi Co Ltd Form device
CN101586464A (en) * 2008-05-22 2009-11-25 中铁十一局集团第一工程有限公司 Construction method of railway tunnel lining side wall concrete
CN102102320A (en) * 2009-12-19 2011-06-22 襄樊金鹰轨道车辆有限责任公司 Liftable supporting leg device
CN101929341A (en) * 2010-01-12 2010-12-29 中铁隧道集团二处有限公司 Construction method for TBM synchronization lining
CN101967985A (en) * 2010-09-08 2011-02-09 中铁隧道集团三处有限公司 Self-propelled inverted arch template construction method
CN202250110U (en) * 2011-10-24 2012-05-30 中铁十七局集团第四工程有限公司 Buried waterstop fixing device in secondary tunnel liner
CN202569294U (en) * 2011-12-06 2012-12-05 青岛康顿钢塑制品发展有限公司 Multifunctionnal exerciser
CN102787850A (en) * 2012-08-29 2012-11-21 中铁二十三局集团第一工程有限公司 Inverted arch formwork for tunnel inverted arch construction
CN203130107U (en) * 2013-04-03 2013-08-14 湖南远东钢模电子科技有限责任公司 Hydraulic tunnel inverted arch operation trolley

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103352710B (en) * 2013-07-25 2016-07-13 成都锐龙机械制造有限公司 The convertible tunnel overhead arch mould plate trolley of a kind of suspension and construction method thereof
CN103352710A (en) * 2013-07-25 2013-10-16 成都锐龙机械制造有限公司 Suspension overturn type tunnel inverted arch formwork trolley and construction method thereof
CN104514569A (en) * 2014-12-12 2015-04-15 中铁十九局集团有限公司 High-speed railway tunnel inverted arch back mold integral installing-positioning mobile trolley
CN104564103A (en) * 2014-12-12 2015-04-29 中铁十九局集团有限公司 Positioning device used for tunnel invert arch back form disassembly and assembly
CN104564103B (en) * 2014-12-12 2017-01-18 中铁十九局集团有限公司 Positioning device used for tunnel invert arch back form disassembly and assembly
CN104514569B (en) * 2014-12-12 2017-02-22 中铁十九局集团有限公司 High-speed railway tunnel inverted arch back mold integral installing-positioning mobile trolley
CN106677802A (en) * 2016-12-28 2017-05-17 杭州江润科技有限公司 Construction method of tunnel inverted arch pouring structure
CN106677802B (en) * 2016-12-28 2018-07-24 浙江沧海建设有限公司 The construction method of tunnel inverted arch pouring structure
CN106988762B (en) * 2017-05-11 2023-08-01 四川省创力隧道机械设备有限公司 Full-section two-lining inverted arch shield equipment
CN106988762A (en) * 2017-05-11 2017-07-28 四川省创力隧道机械设备有限公司 Tunneling boring two serves as a contrast inverted arch Suporting structure
CN108150197A (en) * 2018-02-05 2018-06-12 中铁隧道集团处有限公司 Radially overturning inverted arch trestle and its installation position method for demoulding to arc formwork
CN108150197B (en) * 2018-02-05 2024-04-05 中铁隧道集团一处有限公司 Radial overturning inverted arch trestle of arc-shaped template and mounting, positioning and demolding method thereof
CN108643942A (en) * 2018-07-16 2018-10-12 西安科技大学 Inverted arch when a kind of hydraulic pressure adjustable adjacent
CN108643942B (en) * 2018-07-16 2023-11-10 西安科技大学 Temporary inverted arch with adjustable hydraulic pressure
CN111749712A (en) * 2020-07-08 2020-10-09 长沙理工大学 Tunnel construction equipment
CN111749710A (en) * 2020-07-08 2020-10-09 长沙理工大学 Tunnel construction process
CN111779506A (en) * 2020-07-08 2020-10-16 中铁二十局集团有限公司 Rotatable inverted arch template
CN111749712B (en) * 2020-07-08 2021-10-19 长沙理工大学 Tunnel construction equipment

Also Published As

Publication number Publication date
CN103195450B (en) 2015-08-05

Similar Documents

Publication Publication Date Title
CN103195450A (en) Hydraulic tunnel inverted arch operation trolley and inverted arch construction method
CN205000974U (en) A tire formula automatic rising equipment rack for tunnel excavation construction
CN203768814U (en) High-pier minor-radius curve cast-in-situ box girder novel moving die carrier
CN103541744A (en) Tire walking full-hydraulic lining trolley
CN203022024U (en) Integrally-movable formwork for pipe gallery cast-in-situ construction
CN104763446B (en) The multi-functional chassis of metro station construction
CN102966121A (en) Integrally movable mould frame for pipe rack cast-in-site construction
CN204899941U (en) Whole movable tunnel ditch cable duct formworking jumbo
CN104109999A (en) Construction method for bridge tower transverse beams
CN104894986A (en) Integrated movable box type culvert internal template equipment
CN105350454A (en) Steel arch rib outer wrapped concrete construction method for steel trussed arch bridge
CN202544854U (en) Lining trolley for subway station
CN204023424U (en) A kind of Hanging Basket You Ding back-pressure mechanism
CN203248170U (en) Lining trolley for secondary lining construction of pedestrian crosswalk
CN109356618A (en) A kind of simple integral movable type square type tunnel frame and its construction method
CN102561193A (en) Construction technology of closure section for rotary continuous beam for overpass electrified railway and hanging basket thereof
CN106368714A (en) Tire type automatic lifting assembly rack for tunnel excavation construction
CN203834370U (en) Arch ring steel formwork trolley for circular arch culvert
CN104929660B (en) Formation and construction set for continuous open-cut tunnel
CN203130107U (en) Hydraulic tunnel inverted arch operation trolley
CN204386615U (en) A kind of self-propelled tunnel invert construction trolley
CN203603928U (en) Rubber-tyred walking full-hydraulic lining trolley
CN204139466U (en) A kind of concrete prefabricated cushion block
CN106013014A (en) Small-section tunnel side wall lining formwork erecting construction device
CN104894943A (en) Integral formwork for road and bridge drainage ditch construction concrete pouring

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP03 Change of name, title or address

Address after: 411300 Hunan province Shaoshan Fuyuan Road hi tech Development Zone

Patentee after: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Address before: 411300 Yongquan science and Technology Park, Xiangtan, Hunan, Shaoshan

Patentee before: HUNAN YUANDONG STEEL MOULD ELECTRONIC SCIENCE & TECHNOLOGY Co.,Ltd.

PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Hydraulic tunnel inverted arch operation trolley and inverted arch construction method

Effective date of registration: 20190128

Granted publication date: 20150805

Pledgee: Shaoshan Hunan rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Registration number: 2019330000041

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20200113

Granted publication date: 20150805

Pledgee: Shaoshan Hunan rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Registration number: 2019330000041

PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Hydraulic tunnel inverted arch operation trolley and inverted arch construction method

Effective date of registration: 20200115

Granted publication date: 20150805

Pledgee: Shaoshan Hunan rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Registration number: Y2020330000035

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20210112

Granted publication date: 20150805

Pledgee: Shaoshan Hunan rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Registration number: Y2020330000035

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Hydraulic tunnel invert operation trolley and invert construction method

Effective date of registration: 20210112

Granted publication date: 20150805

Pledgee: Shaoshan Hunan rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Registration number: Y2021990000037

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220111

Granted publication date: 20150805

Pledgee: Shaoshan Hunan rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Registration number: Y2021990000037

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Hydraulic tunnel inverted arch operation trolley and inverted arch construction method

Effective date of registration: 20220111

Granted publication date: 20150805

Pledgee: Shaoshan Hunan rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Registration number: Y2022990000016

PE01 Entry into force of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20230103

Granted publication date: 20150805

Pledgee: Shaoshan Hunan rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Registration number: Y2022990000016

PC01 Cancellation of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Hydraulic tunnel invert work trolley and invert construction method

Effective date of registration: 20230105

Granted publication date: 20150805

Pledgee: Shaoshan Hunan rural commercial bank Limited by Share Ltd.

Pledgor: HUNAN YUANDONG STEEL MOULD Co.,Ltd.

Registration number: Y2023980030315

PE01 Entry into force of the registration of the contract for pledge of patent right