CN103170837A - Jackscrew alignment method of grate of air heating furnace - Google Patents
Jackscrew alignment method of grate of air heating furnace Download PDFInfo
- Publication number
- CN103170837A CN103170837A CN2013101049078A CN201310104907A CN103170837A CN 103170837 A CN103170837 A CN 103170837A CN 2013101049078 A CN2013101049078 A CN 2013101049078A CN 201310104907 A CN201310104907 A CN 201310104907A CN 103170837 A CN103170837 A CN 103170837A
- Authority
- CN
- China
- Prior art keywords
- jackscrew
- fire grate
- grate
- levelness
- base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Furnace Housings, Linings, Walls, And Ceilings (AREA)
Abstract
Disclosed is a jackscrew alignment method of a grate of an air heating furnace. The method comprises the steps: leading out transversal and longitudinal center lines of the grate on a furnace bottom board according to the size of a designed drawing; setting four jackscrew devices on each transversal and longitudinal center line of a grate support base, wherein each jackscrew is composed of a base and an adjusting nut; symmetrically setting locating pins on one sides of two jackscrew bases on each longitudinal center line; firmly welding the jackscrew bases and the locating pins with the furnace bottom board; and after support pillars of the grate are hoisted to the places, aligning levelness through the adjusting nuts according to the actually-measured height difference on the levelness of an upper plane of each support pillar of the grate by a level instrument. The jackscrew alignment method is simple in operation, convenient and fast to achieve, high in alignment efficiency, and capable of greatly shortening the alignment time of the grate, creating conditions for building the air heating furnace, shortening the project period and reducing cost.
Description
Technical field
The present invention relates to equipment mounting technique field, is a kind of Grates for Blast Heating Furnace jackscrew aligning method specifically, is applicable to the installation centering of Grates for Blast Heating Furnace equipment.
Background technology
In existing metallurgical construction, the aligning method that Grates for Blast Heating Furnace is installed mainly utilizes the taper liner plate to regulate, and time-consuming, the scope of operation is little, is difficult for adjusting, and efficient is low, and cost is high, affects the installation period that hot-blast stove is built by laying bricks or stones.
Summary of the invention
Purpose of the present invention is exactly the above-mentioned shortcoming that exists for prior art, and a kind of Grates for Blast Heating Furnace jackscrew aligning method is provided, and shortens the centering time of fire grate equipment, improves work efficiency, reduces costs.
fire grate jackscrew aligning method of the present invention is achieved in that a kind of Grates for Blast Heating Furnace jackscrew aligning method, be characterized in: first emit fire grate center line in length and breadth according to the layout design size on drop-bottom, on center line, four jackscrew devices are set in length and breadth at each fire grate bearing, jackscrew is comprised of base and adjusting nut, then two jackscrew base one sides on longitudinal centre line are symmetrical arranged alignment pin, again with jackscrew base and alignment pin and drop-bottom firm welding, after the fire grate pillar type hoisted is in place, according to the discrepancy in elevation of spirit level to plane levelness actual measurement on the fire grate pillar, come the centering levelness by adjusting nut, its step is as follows:
1) measure unwrapping wire: according to the layout design size on drop-bottom the measuring fire grate in length and breadth to center line;
2) install jackscrew base and alignment pin: install four jackscrew bases on center line in length and breadth at each fire grate pillar, then two jackscrew base one sides on longitudinal centre line are symmetrical arranged alignment pin, then with jackscrew base and alignment pin and drop-bottom firm welding;
3) by adjusting nut centering levelness: the fire grate pillar type hoisted to the jackscrew adjusting nut, according to the discrepancy in elevation of spirit level to plane levelness actual measurement on the fire grate pillar, is then adjusted the levelness on plane on the fire grate pillar by regulating the jackscrew nut.
The present invention is simple to operate, and is convenient and swift, and centering efficient is high, greatly shortened the centering time of fire grate, and the condition created of building by laying bricks or stones for hot-blast stove has shortened the duration, has reduced cost.
The invention will be further described below in conjunction with accompanying drawing and example.
Description of drawings
Fig. 1 is top view of the present invention.
Fig. 2 is cutaway view of the present invention.
In figure: 1, drop-bottom 2, jackscrew base 3, adjusting nut 4, alignment pin 5, fire grate pillar.
The specific embodiment
As shown in the figure, the present invention be first according to the layout design size on drop-bottom 1 measuring fire grate pillar 5 in length and breadth to center line, install four jackscrew bases 2 on center line in length and breadth at each fire grate pillar 5, then two jackscrew bases 2 on longitudinal centre line are symmetrical arranged alignment pin 4, again with jackscrew base 2 and alignment pin 4 and drop-bottom 1 firm welding, after fire grate pillar 5 hoisted in position, according to the discrepancy in elevation of spirit level to plane levelness actual measurement on fire grate pillar 5, adjust the levelness on plane on fire grate pillar 5 by adjusting nut 3.
Grates for Blast Heating Furnace jackscrew aligning method carries out as follows:
The first step is measured unwrapping wire.According to the layout design size on drop-bottom the measuring fire grate in length and breadth to center line.
Second step is laid jackscrew base 2 and alignment pin 4.On center line, four jackscrew bases 2 are set in length and breadth at each fire grate pillar 5, then two jackscrew base 2 one sides on longitudinal centre line are symmetrical arranged alignment pin 4, then with jackscrew base 2 and alignment pin 4 and drop-bottom 1 firm welding.
The 3rd step, adjusting nut centering levelness.Fire grate pillar 5 is lifted to jackscrew adjusting nut 3, according to the discrepancy in elevation of spirit level to plane levelness actual measurement on fire grate pillar 3, adjust the levelness on plane on fire grate pillar 5 by regulating jackscrew nut 3.
Used Grates for Blast Heating Furnace jackscrew aligning method of the present invention to carry out centering to fire grate when carrying out 2*1580m3 blast furnace (9#, 10#) Grates for Blast Heating Furnace installation in certain steel plant in 2012.On the effect fire grate, the difference in height on plane reaches 2mm, the deviation (on the standard fire grate, the plane levelness permissible variation is 4mm) that the plant equipment project installation acceptance specification that is better than smelting iron allows.Every Grates for Blast Heating Furnace centering time only needs 5 calendar day, needs 7 calendar day if carry out centering with the taper liner plate, 12 days reductions of erection time, 50000 yuan of two Grates for Blast Heating Furnace co-falling low costs.
Claims (1)
1. Grates for Blast Heating Furnace jackscrew aligning method, it is characterized in that: first emit fire grate center line in length and breadth according to the layout design size on drop-bottom, on center line, four jackscrew devices are set in length and breadth at each fire grate bearing, jackscrew is comprised of base and adjusting nut, then two jackscrew base one sides on longitudinal centre line are symmetrical arranged alignment pin, again with jackscrew base and alignment pin and drop-bottom firm welding, after the fire grate pillar type hoisted is in place, according to the discrepancy in elevation of spirit level to plane levelness actual measurement on the fire grate pillar, come the centering levelness by adjusting nut, its step is as follows:
1) measure unwrapping wire: according to the layout design size on drop-bottom the measuring fire grate in length and breadth to center line;
2) install jackscrew base and alignment pin: install four jackscrew bases on center line in length and breadth at each fire grate pillar, then two jackscrew base one sides on longitudinal centre line are symmetrical arranged alignment pin, then with jackscrew base and alignment pin and drop-bottom firm welding;
3) by adjusting nut centering levelness: the fire grate pillar type hoisted to the jackscrew adjusting nut, according to the discrepancy in elevation of spirit level to plane levelness actual measurement on the fire grate pillar, is then adjusted the levelness on plane on the fire grate pillar by regulating the jackscrew nut.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013101049078A CN103170837A (en) | 2013-03-29 | 2013-03-29 | Jackscrew alignment method of grate of air heating furnace |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2013101049078A CN103170837A (en) | 2013-03-29 | 2013-03-29 | Jackscrew alignment method of grate of air heating furnace |
Publications (1)
Publication Number | Publication Date |
---|---|
CN103170837A true CN103170837A (en) | 2013-06-26 |
Family
ID=48631260
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2013101049078A Pending CN103170837A (en) | 2013-03-29 | 2013-03-29 | Jackscrew alignment method of grate of air heating furnace |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103170837A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111451764A (en) * | 2020-05-19 | 2020-07-28 | 中国十七冶集团有限公司 | Staggered installation method for lower furnace shell of hot blast stove and equipment in stove |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070272127A1 (en) * | 2006-05-27 | 2007-11-29 | Antonio Puccio | Marble mix kit and method of producing same |
CN101749946A (en) * | 2008-12-10 | 2010-06-23 | 中冶天工建设有限公司 | Installation method of annular heating furnace equipment |
CN102634616A (en) * | 2012-04-26 | 2012-08-15 | 中国十七冶集团有限公司 | Blast furnace top flange jackscrew aligning method |
CN102747177A (en) * | 2012-07-30 | 2012-10-24 | 王继平 | Blast furnace hot blast stove and construction method thereof |
-
2013
- 2013-03-29 CN CN2013101049078A patent/CN103170837A/en active Pending
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20070272127A1 (en) * | 2006-05-27 | 2007-11-29 | Antonio Puccio | Marble mix kit and method of producing same |
CN101749946A (en) * | 2008-12-10 | 2010-06-23 | 中冶天工建设有限公司 | Installation method of annular heating furnace equipment |
CN102634616A (en) * | 2012-04-26 | 2012-08-15 | 中国十七冶集团有限公司 | Blast furnace top flange jackscrew aligning method |
CN102747177A (en) * | 2012-07-30 | 2012-10-24 | 王继平 | Blast furnace hot blast stove and construction method thereof |
Non-Patent Citations (1)
Title |
---|
房政,吴晴冬: "某钢厂1580m3高炉之热风炉炉箅子设备安装施工技术", 《安徽建筑》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111451764A (en) * | 2020-05-19 | 2020-07-28 | 中国十七冶集团有限公司 | Staggered installation method for lower furnace shell of hot blast stove and equipment in stove |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN210766774U (en) | Positioning device for steel reinforcement cage and lattice column | |
CN203640309U (en) | Adjustable pipe carrier used on large-span steel structure roof primary truss general assembly jig frame | |
CN203440753U (en) | Multifunctional steel bar locating framework | |
CN205116029U (en) | Pre -buried steel sheet adjusting device of breast | |
CN203783165U (en) | Multi-directional accurate adjusting device for embedded part | |
CN102634616A (en) | Blast furnace top flange jackscrew aligning method | |
CN203404564U (en) | Calibration device used for centering and leveling in installing process of equipment | |
CN103862251B (en) | A kind of hanging method of the main equipment by restricted by three-dimensional space | |
CN103170837A (en) | Jackscrew alignment method of grate of air heating furnace | |
CN202957493U (en) | Transformer rack overall installation device | |
CN103557693B (en) | Rotary kiln barrel mounting method | |
CN113090040A (en) | Installation device and method for vertical prefabricated part | |
CN104895106A (en) | Installing device and method for lower anchor plate for wind driven generator construction | |
CN104727339A (en) | Electrical equipment foundation two-step type construction method | |
CN111633397A (en) | Furnace roller correction method for vertical annealing furnace | |
CN105438982A (en) | A rapid replacing method of a grate of a hot-blast stove of a blast furnace | |
CN204434076U (en) | Lifting hook capable of adjusting attitude of shield machine component in underground hoisting process of shield machine | |
CN105442868A (en) | Adjustable steel-structure reticulated shell spliced scaffold | |
CN205476528U (en) | Precast pile device of taking one's place fast | |
CN204662489U (en) | A kind of conveying circuit bracket base pre-embedded device | |
CN104695717A (en) | Upwarp degree precontrol adjusting equipment of revolving platform | |
CN204019070U (en) | Derrick assembling combination steelframe | |
CN104015261B (en) | Combined, scalable prefabricated concrete element built-in fitting positions loose tool and construction technology thereof | |
CN103741710B (en) | Without the construction method of parallels erection equipment | |
CN202501750U (en) | Shell simple assembling platform for ironmaking system furnace shell |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C02 | Deemed withdrawal of patent application after publication (patent law 2001) | ||
WD01 | Invention patent application deemed withdrawn after publication |
Application publication date: 20130626 |