CN103147586A - 用于爬模架的安全护网装置 - Google Patents

用于爬模架的安全护网装置 Download PDF

Info

Publication number
CN103147586A
CN103147586A CN2013101057055A CN201310105705A CN103147586A CN 103147586 A CN103147586 A CN 103147586A CN 2013101057055 A CN2013101057055 A CN 2013101057055A CN 201310105705 A CN201310105705 A CN 201310105705A CN 103147586 A CN103147586 A CN 103147586A
Authority
CN
China
Prior art keywords
frame
inner frame
safety guard
outside framework
guard net
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2013101057055A
Other languages
English (en)
Inventor
王涛
许向华
程湘伟
李筱斌
曹仁杰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NINTH CONSTRUCTION OF ZHONGTIAN CONSTRUCTION GROUP CO Ltd
Original Assignee
NINTH CONSTRUCTION OF ZHONGTIAN CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NINTH CONSTRUCTION OF ZHONGTIAN CONSTRUCTION GROUP CO Ltd filed Critical NINTH CONSTRUCTION OF ZHONGTIAN CONSTRUCTION GROUP CO Ltd
Priority to CN2013101057055A priority Critical patent/CN103147586A/zh
Publication of CN103147586A publication Critical patent/CN103147586A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

本发明公开一种用于爬模架的安全护网装置,包括外框架,在外框架内嵌设有冲孔钢板网片,在外框架上还设置有抱箍,还包括内框架,冲孔钢板网片固定在内框架内,内框架固定在外框架内。采用上述技术方案,本发明有以下优点和效果:本发明制作简单,安装便捷,可通过抱箍直接安装在爬模架上,形成稳固的安全护网,确保高空施工的安全性;该安全护网装置可定型制作,安装拆卸方便,可重复使用,能够降低施工成本,产生明显的经济效益和社会效益。

Description

用于爬模架的安全护网装置
技术领域
本发明属于建筑领域,具体地说涉及一种用于爬模架的安全防护网。
背景技术
近年来超高层建筑已经在众多城市蓬勃发展,为缩短施工工期,施工通常采用不等高施工工艺,核心筒采用液压爬模架施工。而爬模架的安全防护一般采用普通防护栏杆和密目安全网。由于高空风压力或人为缘故,密目安全网经常会因为扎丝不牢固而敞开,给操作施工人员带来非常大的安全隐患;同时可能会因为高空坠物,造成极大的安全事故。这种普通的安全防护方式,效果并不令人满意,隐藏的安全隐患较多。另一方面,这种密目安全网是一次性的,不能重复利用。
发明内容
本发明的目的在于克服上述不足提供一种用于爬模架的安全护网装置,它即绿色环保节能,保护性能高,且周转使用,降低成本。      
为实现上述目的,本发明采用以下技术方案:
一种用于爬模架的安全护网装置,包括外框架,在外框架内嵌设有冲孔钢板网片。
上述用于爬模架的安全护网装置,还包括内框架,冲孔钢板网片固定在内框架内,内框架固定在外框架内。
上述用于爬模架的安全护网装置,所述外框架是矩形方管框架。
上述用于爬模架的安全护网装置,所述内框架是方管框架。
上述用于爬模架的安全护网装置,所述外框架由横框和竖框构成,横框与竖框通过加长螺栓连接,横框与竖框不在同一平面内。
上述用于爬模架的安全护网装置,内框架由相互固定连接的在同一平面内的多根方管构成,冲孔钢板网片通过自攻螺丝固定在内框架上。
上述用于爬模架的安全护网装置,内框架通过角钢片固定在外框架的竖框内侧。
采用上述技术方案,本发明有以下优点和效果:本发明制作简单,安装便捷,可通过抱箍直接安装在爬模架上,形成稳固的安全护网,确保高空施工的安全性;该安全护网装置可定型制作,安装拆卸方便,可重复使用,能够降低施工成本,产生明显的经济效益和社会效益。
附图说明
图1是本发明的结构示意图。
图2是本发明A-A向剖视图。
图3是本发明安装有冲孔钢板网片的内框架的结构示意图。、
图4是本发明外框架结构示意图。
图5是图4中A部位左视放大图。
图6是图4中B部位局部放大图。
具体实施方式
如图1、图2、图3、图4、图5和图6所示的一种用于爬模架的安全护网装置,包括外框架1和嵌设在外框架内的内框架2,冲孔钢板网片3固定在内框架2内。所述外框架1是矩形方管框架,外框架1由横框和竖框构成,横框与竖框通过加长螺栓5连接,横框与竖框不在同一平面内,横框方管根据爬模架水平支撑架调整位置和尺寸。所述内框架是小型矩形方管框架,内框架2由相互固定连接的在同一平面内的多根方管构成,冲孔钢板网片通过自攻螺丝6固定在内框架2上,冲孔钢板网片3由厂家加工制作成品。内框架2通过角钢片4固定在外框架1的竖框内侧,以确保镶嵌牢固。在安装使用过程中,通过抱箍7将本发明的外框架1的横框和爬模架8固定在一起,安装和拆卸都很方便。
本发明的内框架由数根小型矩形方管焊接而成,外框架的横框和爬模架通过抱箍紧密连接,从而实现了本发明装置的固定。

Claims (7)

1.一种用于爬模架的安全护网装置,其特征在于:包括外框架,在外框架内嵌设有冲孔钢板网片。
2.根据权利要求1所述的用于爬模架的安全护网装置,其特征在于:还包括内框架,冲孔钢板网片固定在内框架内,内框架固定在外框架内。
3.根据权利要求2所述的用于爬模架的安全护网装置,其特征在于:所述外框架是矩形方管框架。
4.根据权利要求2所述的用于爬模架的安全护网装置,其特征在于:所述内框架是方管框架。
5.根据权利要求2所述的用于爬模架的安全护网装置,其特征在于:所述外框架由横框和竖框构成,横框与竖框通过加长螺栓连接,横框与竖框不在同一平面内。
6.根据权利要求4所述的用于爬模架的安全护网装置,其特征在于:内框架由相互固定连接的在同一平面内的多根方管构成,冲孔钢板网片通过自攻螺丝固定在内框架上。
7.根据权利要求5所述的用于爬模架的安全护网装置,其特征在于:内框架通过角钢片固定在外框架的竖框内侧。
CN2013101057055A 2013-03-29 2013-03-29 用于爬模架的安全护网装置 Pending CN103147586A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2013101057055A CN103147586A (zh) 2013-03-29 2013-03-29 用于爬模架的安全护网装置

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2013101057055A CN103147586A (zh) 2013-03-29 2013-03-29 用于爬模架的安全护网装置

Publications (1)

Publication Number Publication Date
CN103147586A true CN103147586A (zh) 2013-06-12

Family

ID=48545877

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2013101057055A Pending CN103147586A (zh) 2013-03-29 2013-03-29 用于爬模架的安全护网装置

Country Status (1)

Country Link
CN (1) CN103147586A (zh)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700830A (zh) * 2017-11-14 2018-02-16 浙江乔兴建设集团有限公司 一种建筑用爬模结构
CN107882322A (zh) * 2017-11-14 2018-04-06 浙江乔兴建设集团有限公司 一种拆装方便的爬模架结构

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2093900A (en) * 1981-03-03 1982-09-08 Layher Eberhard Safety device for metal scaffolding
KR100260674B1 (ko) * 1998-04-20 2000-07-01 이정국 사장교식 낙하물 방지망
EP1972739A2 (en) * 2007-03-15 2008-09-24 Bromall, S.L. Extendable safety guardrail
CN201610632U (zh) * 2009-12-18 2010-10-20 中国建筑第四工程局有限公司 一种自爬式施工平台
CN201627355U (zh) * 2010-01-14 2010-11-10 上海富安脚手架工程有限公司 建筑施工脚手架安全防护围挡
CN102182324A (zh) * 2011-04-02 2011-09-14 中天建设集团有限公司第五建设公司 安全防坠网
CN203113819U (zh) * 2013-03-29 2013-08-07 中天建设集团有限公司第九建设公司 一种用于爬模架的安全护网装置

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB2093900A (en) * 1981-03-03 1982-09-08 Layher Eberhard Safety device for metal scaffolding
KR100260674B1 (ko) * 1998-04-20 2000-07-01 이정국 사장교식 낙하물 방지망
EP1972739A2 (en) * 2007-03-15 2008-09-24 Bromall, S.L. Extendable safety guardrail
CN201610632U (zh) * 2009-12-18 2010-10-20 中国建筑第四工程局有限公司 一种自爬式施工平台
CN201627355U (zh) * 2010-01-14 2010-11-10 上海富安脚手架工程有限公司 建筑施工脚手架安全防护围挡
CN102182324A (zh) * 2011-04-02 2011-09-14 中天建设集团有限公司第五建设公司 安全防坠网
CN203113819U (zh) * 2013-03-29 2013-08-07 中天建设集团有限公司第九建设公司 一种用于爬模架的安全护网装置

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107700830A (zh) * 2017-11-14 2018-02-16 浙江乔兴建设集团有限公司 一种建筑用爬模结构
CN107882322A (zh) * 2017-11-14 2018-04-06 浙江乔兴建设集团有限公司 一种拆装方便的爬模架结构

Similar Documents

Publication Publication Date Title
WO2014172640A3 (en) Method and system of construction project management
MX2015003008A (es) Montaje de puntal restingido en pandeo.
RU2015150962A (ru) Ветровая установка и башня ветровой установки
CN103147586A (zh) 用于爬模架的安全护网装置
WO2015112865A3 (en) Mitigation scope and costs of structural water damage costs predictive model
MX352550B (es) Hueco reforzado para torre de aerogenerador.
CN203113819U (zh) 一种用于爬模架的安全护网装置
CN206003461U (zh) 一种用于市政建设具有灌溉功能的绿化带警示牌
CN203856380U (zh) 一种兼有防盗和逃生功能的组合窗体
CN204024693U (zh) 一种隧道用射流风机
CN203684282U (zh) 一种可灭火的井盖
CN204973237U (zh) 过滤网板
CN203129615U (zh) 水平洞口防护栅
CN205123603U (zh) 一种箱体整流模块固定线束方孔板面
CN203783112U (zh) 外墙脚手架内档防护装置
CN204983716U (zh) 一种剪力墙开口式临边防护扣件
CN204001673U (zh) 钢板网固定装置
CN204212446U (zh) 一种可提升的爬架防护装置
CN204060039U (zh) 冲身洗眼房
CN203556203U (zh) 一种不易破损的内嵌式滤网
CN207685252U (zh) 一种用于芽孢杆菌固液分离的筛网筒
CN202942568U (zh) 船舶用灭火器架
CN203347252U (zh) 一种水平洞口防护用具
CN204510922U (zh) 集装箱逆变机房用的出风口挡雨罩结构
CN204960358U (zh) 应用于建筑外框楼板的外防护***

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20130612