CN103147573A - Natatorium roof beam slab high formwork construction method - Google Patents

Natatorium roof beam slab high formwork construction method Download PDF

Info

Publication number
CN103147573A
CN103147573A CN2013100876088A CN201310087608A CN103147573A CN 103147573 A CN103147573 A CN 103147573A CN 2013100876088 A CN2013100876088 A CN 2013100876088A CN 201310087608 A CN201310087608 A CN 201310087608A CN 103147573 A CN103147573 A CN 103147573A
Authority
CN
China
Prior art keywords
vertical rod
vertical
template
horizontal
spacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2013100876088A
Other languages
Chinese (zh)
Other versions
CN103147573B (en
Inventor
成军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NANJING FENGXUN ENERGY TECHNOLOGY Co Ltd
NANJING NINTH BUILDING INSTALLATION ENGINEERING Co Ltd
Jiangsu Nantong No 2 Construction Group Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201310087608.8A priority Critical patent/CN103147573B/en
Publication of CN103147573A publication Critical patent/CN103147573A/en
Application granted granted Critical
Publication of CN103147573B publication Critical patent/CN103147573B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a natatorium roof beam slab high formwork construction method, which includes the steps of floorslab formwork construction, beam formwork construction and the like. The method has the advantages of convenient and reasonable construction, fast construction progress, good construction quality and safety.

Description

Swimming hall raising-plate high-supported formwork job practices
Technical field
The present invention relates to a kind of swimming hall raising-plate high-supported formwork job practices.
Background technology
Existing swimming hall raising-plate high-supported formwork difficulty of construction is large, construction is complicated, requires further improvement.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, the swimming hall raising-plate high-supported formwork job practices that construction effect is good.
Technical solution of the present invention is:
A kind of swimming hall raising-plate high-supported formwork job practices is characterized in that: comprise the following steps:
(1) slab form construction
(1) set up form
Roof plate template adopts the thick bamboo plywood of 12mm, adopts 50mm * 80mm flitch to do inferior stupefied, middle apart from 300mm, adopt Φ 48 * 3.0mm steel pipe to decide stupefied, spacing 1200mm adopts the full steel pipe scaffold of ф 48 * 3.0 to do support system, vertical rod spacing in length and breadth is 1200mm, step pitch h=1.2m; The level liftoff 200mm of bar that sweeps the floor, crossbar is stretched out and is effluxed vertical rod 0.1m; At the 4.5m place, wall-connecting piece is set and is connected with agent structure, wall-connecting piece spacing 6.0m, the opposite face 0.9m that staggers arranges; The inside and outside facade of support surrounding is completely established bridging, and establish together every 4~6m at the middle part; Frame bottom, top arrange one level and add layer; The piece of template die is with on tape sticker, and the piece of template die and beam form all arranges sponge strip, with mortar leakage prevention;
(2) set up order
Set up and frontly first swimming pool bottom is cleaned out, when setting up, the shelf bottom of upright rod adds base, erect successively end vertical rod to both sides from the bight, after the bottom is fixing with the bar snapping of vertically sweeping the floor, install the bar of laterally sweeping the floor, and fix with vertical rod, after 3~4 vertical rods are holded up on every limit, install immediately first step vertical equity bar and transverse horizontal bar; Proofread and correct the vertical and horizon bar level of vertical rod, tighten fastening bolt by 45~55Nm moment, form the initial segment of framed bent, extend forward successively by above-mentioned requirements and set up, complete until first step frame is handed over to enclose; Second step, the 3rd step are set up in operation procedure and requirement by first step frame; Along with setting up process installing wall-connecting piece and shearing support, add plain net;
The shuttering supporting steel pipe is at the flooring snap the line, underlay 50mm * 100mm flitch; The steel pipe framed bent is set up smooth vertical and horizontal, is communicated with in length and breadth, and levels support top position consistency, horizontal stay bolt is communicated with; Template first row time stupefied flitch is near wallboard, and if any gap weather strip sealing of hole, between template and template, splicing seams less than 1mm, otherwise seals with adhesive tape; Top board grid in length and breadth digs into same specification with thicknesser, and draws logical line levelling; The grid of surrounding, snap the line remain on same absolute altitude, and plate and grid are fixing with 50mm spike, and Grill space 300mm after plate has spread, proofreaies and correct absolute altitude with level gauge, and uses the guiding ruler levelling; During laying surrounding template, flush with wall, add weather strip, when the template die turnover is used, the cement mortar on surface is cleaned out, the brushing release agent is in time repaired and changes to guarantee that seam is tight the template of distortion and surrounding breakage, and the plate face is smooth; After template has spread, foreign material are cleaned out, brushed release agent;
(2) beam forms construction
Set up vertical rod longitudinal pitch 600mm, vertical rod horizontal spacing 300mm, vertical rod step pitch 600mm with the full hall of floor bracing frame; Sweep the floor bar apart from ground 200mm; Frame bottom, top, centre arrange one horizontal bracing diagonal as horizontal enhancement Layer every 4m;
At the bottom of beam, side form adopts the thick veneer of 18mm, the back side adopts the elongated vertical wood of 50mm * 100mm stupefied, wooden stupefied spacing: bed die is that 200mm, side form are 300mm; Formwork edge joint is less than 1.5mm, and vertical rod is 600mm along beam span direction spacing, and at the bottom of beam, the load-bearing vertical rod is 3, and little cross bar spacing is 300mm, and the scaffold step pitch is 600mm, 8.4 meters of scaffold building height; The steel pipe main joist is adopted at steel pipe framed bent top, wooden a tree, used in making timber for boats joist, and upper berth overlay film composite board forms large beam bottom board; The split bolt steel pipe clamp is not more than 550mm along the spacing of beam length direction, and vertical spacing is 300mm, and split bolt is selected φ 14 reinforcement fabrications, and bolt adopts totally four roads up and down.Clamp: adopt φ 48 * 3.0 steel pipes;
During the beam bottom mother plate construction, absolute altitude by design elevation adjustment support, then the levelling of mounting rail soffit formwork, and bracing wire, when beam base plate span greater than and when equaling 4m, span centre beam bottom is by the designing requirement arch camber, as when designing no requirement (NR), springing height is 3/1000ths of beam span, during the primary-secondary beam handing-over, first girder arch camber, rear arch camber secondary beam;
When setting up, the vertical rod advance of beam lower bolster support is arranged along the beam axis direction; The vertical rod transfer is arranged to bilateral symmetry centered by center line at the bottom of beam, and the outermost vertical rod is not more than 150mm apart from beam side distance; Be located at the adjustable base at falsework bottom of upright rod or top, its screw mandrel external diameter is not less than 36mm, and extension elongation is no more than 200mm; When falsework is set up under beam laterally horizon bar stretch in the falsework of beam biside plate and be no less than two vertical rods, and with the vertical rod snapping; The swimming hall falsework carries out anchoring with rigid connecting tube in horizontal enhancement Layer position and frame column; Go up most one cross bar and be not more than 400mm from top template distance; The vertical rod spreading adopts docking, and every bottom of upright rod all arranges chock or scaffold floor; Falsework four limits with middle every 4~6 row's vertical rods should arrange together with vertical bridging, arranged continuously by the end to top; The falsework two ends begin every 2~4 steps, horizontal cross brace to be set downwards from top layer every 4~6 row's vertical rods with middle; The falsework top is connected horizontal enhancement Layer with the bottom: horizontal cross brace is connected with "the" shape with horizontal brace, horizontal brace width is not less than 3m; Setting up steel pipe framed bent in process presses closer tightly with concrete column, the table of having built; Under beam under main joist steel pipe and plate framed bent be linked to be integral body;
The method of taking under prestressed frame beam to increase vertical rod is reinforced, and vertical pole ' s span is 600mm, and ater-casting place's vertical rod supports to the base plate on basis, guarantees that high carriage load energy safe transfer is to sole plate.
Easy construction of the present invention, reasonable, construction speed is fast, and construction quality is good, safety.
The invention will be further described below in conjunction with embodiment.
The specific embodiment
A kind of swimming hall raising-plate high-supported formwork job practices comprises the following steps:
(1) slab form construction
(1) set up form
Roof plate template adopts the thick bamboo plywood of 12mm, adopts 50mm * 80mm flitch to do inferior stupefied, middle apart from 300mm, adopt Φ 48 * 3.0mm steel pipe to decide stupefied, spacing 1200mm adopts the full steel pipe scaffold of ф 48 * 3.0 to do support system, vertical rod spacing in length and breadth is 1200mm, step pitch h=1.2m; The level liftoff 200mm of bar that sweeps the floor, crossbar is stretched out and is effluxed vertical rod 0.1m; At the 4.5m place, wall-connecting piece is set and is connected with agent structure, wall-connecting piece spacing 6.0m, the opposite face 0.9m that staggers arranges; The inside and outside facade of support surrounding is completely established bridging, and establish together every 4~6m at the middle part; Frame bottom, top arrange one level and add layer; The piece of template die is with on tape sticker, and the piece of template die and beam form all arranges sponge strip, with mortar leakage prevention;
(2) set up order
Set up and frontly first swimming pool bottom is cleaned out, when setting up, the shelf bottom of upright rod adds base, erect successively end vertical rod to both sides from the bight, after the bottom is fixing with the bar snapping of vertically sweeping the floor, install the bar of laterally sweeping the floor, and fix with vertical rod, after 3~4 vertical rods are holded up on every limit, install immediately first step vertical equity bar and transverse horizontal bar; Proofread and correct the vertical and horizon bar level of vertical rod, tighten fastening bolt by 45~55Nm moment, form the initial segment of framed bent, extend forward successively by above-mentioned requirements and set up, complete until first step frame is handed over to enclose; Second step, the 3rd step are set up in operation procedure and requirement by first step frame; Along with setting up process installing wall-connecting piece and shearing support, add plain net;
The shuttering supporting steel pipe is at the flooring snap the line, underlay 50mm * 100mm flitch; The steel pipe framed bent is set up smooth vertical and horizontal, is communicated with in length and breadth, and levels support top position consistency, horizontal stay bolt is communicated with; Template first row time stupefied flitch is near wallboard, and if any gap weather strip sealing of hole, between template and template, splicing seams less than 1mm, otherwise seals with adhesive tape; Top board grid in length and breadth digs into same specification with thicknesser, and draws logical line levelling; The grid of surrounding, snap the line remain on same absolute altitude, and plate and grid are fixing with 50mm spike, and Grill space 300mm after plate has spread, proofreaies and correct absolute altitude with level gauge, and uses the guiding ruler levelling; During laying surrounding template, flush with wall, add weather strip, when the template die turnover is used, the cement mortar on surface is cleaned out, the brushing release agent is in time repaired and changes to guarantee that seam is tight the template of distortion and surrounding breakage, and the plate face is smooth; After template has spread, foreign material are cleaned out, brushed release agent;
(2) beam forms construction
Set up vertical rod longitudinal pitch 600mm, vertical rod horizontal spacing 300mm, vertical rod step pitch 600mm with the full hall of floor bracing frame; Sweep the floor bar apart from ground 200mm; Frame bottom, top, centre arrange one horizontal bracing diagonal as horizontal enhancement Layer every 4m;
At the bottom of beam, side form adopts the thick veneer of 18mm, the back side adopts the elongated vertical wood of 50mm * 100mm stupefied, wooden stupefied spacing: bed die is that 200mm, side form are 300mm; Formwork edge joint is less than 1.5mm, and vertical rod is 600mm along beam span direction spacing, and at the bottom of beam, the load-bearing vertical rod is 3, and little cross bar spacing is 300mm, and the scaffold step pitch is 600mm, 8.4 meters of scaffold building height; The steel pipe main joist is adopted at steel pipe framed bent top, wooden a tree, used in making timber for boats joist, and upper berth overlay film composite board forms large beam bottom board; The split bolt steel pipe clamp is not more than 550mm along the spacing of beam length direction, and vertical spacing is 300mm, and split bolt is selected φ 14 reinforcement fabrications, and bolt adopts totally four roads up and down.Clamp: adopt φ 48 * 3.0 steel pipes;
During the beam bottom mother plate construction, absolute altitude by design elevation adjustment support, then the levelling of mounting rail soffit formwork, and bracing wire, when beam base plate span greater than and when equaling 4m, span centre beam bottom is by the designing requirement arch camber, as when designing no requirement (NR), springing height is 3/1000ths of beam span, during the primary-secondary beam handing-over, first girder arch camber, rear arch camber secondary beam;
When setting up, the vertical rod advance of beam lower bolster support is arranged along the beam axis direction; The vertical rod transfer is arranged to bilateral symmetry centered by center line at the bottom of beam, and the outermost vertical rod is not more than 150mm apart from beam side distance; Be located at the adjustable base at falsework bottom of upright rod or top, its screw mandrel external diameter is not less than 36mm, and extension elongation is no more than 200mm; When falsework is set up under beam laterally horizon bar stretch in the falsework of beam biside plate and be no less than two vertical rods, and with the vertical rod snapping; The swimming hall falsework carries out anchoring with rigid connecting tube in horizontal enhancement Layer position and frame column; Go up most one cross bar and be not more than 400mm from top template distance; The vertical rod spreading adopts docking, and every bottom of upright rod all arranges chock or scaffold floor; Falsework four limits with middle every 4~6 row's vertical rods should arrange together with vertical bridging, arranged continuously by the end to top; The falsework two ends begin every 2~4 steps, horizontal cross brace to be set downwards from top layer every 4~6 row's vertical rods with middle; The falsework top is connected horizontal enhancement Layer with the bottom: horizontal cross brace is connected with "the" shape with horizontal brace, horizontal brace width is not less than 3m; Setting up steel pipe framed bent in process presses closer tightly with concrete column, the table of having built; Under beam under main joist steel pipe and plate framed bent be linked to be integral body;
The method of taking under prestressed frame beam to increase vertical rod is reinforced, and vertical pole ' s span is 600mm, and ater-casting place's vertical rod supports to the base plate on basis, guarantees that high carriage load energy safe transfer is to sole plate.

Claims (1)

1. a swimming hall raising-plate high-supported formwork job practices, is characterized in that: comprise the following steps:
(1) slab form construction
(1) set up form
Roof plate template adopts the thick bamboo plywood of 12mm, adopts 50mm * 80mm flitch to do inferior stupefied, middle apart from 300mm, adopt Φ 48 * 3.0mm steel pipe to decide stupefied, spacing 1200mm adopts the full steel pipe scaffold of ф 48 * 3.0 to do support system, vertical rod spacing in length and breadth is 1200mm, step pitch h=1.2m; The level liftoff 200mm of bar that sweeps the floor, crossbar is stretched out and is effluxed vertical rod 0.1m; At the 4.5m place, wall-connecting piece is set and is connected with agent structure, wall-connecting piece spacing 6.0m, the opposite face 0.9m that staggers arranges; The inside and outside facade of support surrounding is completely established bridging, and establish together every 4~6m at the middle part; Frame bottom, top arrange one level and add layer; The piece of template die is with on tape sticker, and the piece of template die and beam form all arranges sponge strip, with mortar leakage prevention;
(2) set up order
Set up and frontly first swimming pool bottom is cleaned out, when setting up, the shelf bottom of upright rod adds base, erect successively end vertical rod to both sides from the bight, after the bottom is fixing with the bar snapping of vertically sweeping the floor, install the bar of laterally sweeping the floor, and fix with vertical rod, after 3~4 vertical rods are holded up on every limit, install immediately first step vertical equity bar and transverse horizontal bar; Proofread and correct the vertical and horizon bar level of vertical rod, tighten fastening bolt by 45~55Nm moment, form the initial segment of framed bent, extend forward successively by above-mentioned requirements and set up, complete until first step frame is handed over to enclose; Second step, the 3rd step are set up in operation procedure and requirement by first step frame; Along with setting up process installing wall-connecting piece and shearing support, add plain net;
The shuttering supporting steel pipe is at the flooring snap the line, underlay 50mm * 100mm flitch; The steel pipe framed bent is set up smooth vertical and horizontal, is communicated with in length and breadth, and levels support top position consistency, horizontal stay bolt is communicated with; Template first row time stupefied flitch is near wallboard, and if any gap weather strip sealing of hole, between template and template, splicing seams less than 1mm, otherwise seals with adhesive tape; Top board grid in length and breadth digs into same specification with thicknesser, and draws logical line levelling; The grid of surrounding, snap the line remain on same absolute altitude, and plate and grid are fixing with 50mm spike, and Grill space 300mm after plate has spread, proofreaies and correct absolute altitude with level gauge, and uses the guiding ruler levelling; During laying surrounding template, flush with wall, add weather strip, when the template die turnover is used, the cement mortar on surface is cleaned out, the brushing release agent is in time repaired and changes to guarantee that seam is tight the template of distortion and surrounding breakage, and the plate face is smooth; After template has spread, foreign material are cleaned out, brushed release agent;
(2) beam forms construction
Set up vertical rod longitudinal pitch 600mm, vertical rod horizontal spacing 300mm, vertical rod step pitch 600mm with the full hall of floor bracing frame; Sweep the floor bar apart from ground 200mm; Frame bottom, top, centre arrange one horizontal bracing diagonal as horizontal enhancement Layer every 4m;
At the bottom of beam, side form adopts the thick veneer of 18mm, the back side adopts the elongated vertical wood of 50mm * 100mm stupefied, wooden stupefied spacing: bed die is that 200mm, side form are 300mm; Formwork edge joint is less than 1.5mm, and vertical rod is 600mm along beam span direction spacing, and at the bottom of beam, the load-bearing vertical rod is 3, and little cross bar spacing is 300mm, and the scaffold step pitch is 600mm, 8.4 meters of scaffold building height; The steel pipe main joist is adopted at steel pipe framed bent top, wooden a tree, used in making timber for boats joist, and upper berth overlay film composite board forms large beam bottom board; The split bolt steel pipe clamp is not more than 550mm along the spacing of beam length direction, and vertical spacing is 300mm, and split bolt is selected φ 14 reinforcement fabrications, and bolt adopts totally four roads up and down.Clamp: adopt φ 48 * 3.0 steel pipes;
During the beam bottom mother plate construction, absolute altitude by design elevation adjustment support, then the levelling of mounting rail soffit formwork, and bracing wire, when beam base plate span greater than and when equaling 4m, span centre beam bottom is by the designing requirement arch camber, as when designing no requirement (NR), springing height is 3/1000ths of beam span, during the primary-secondary beam handing-over, first girder arch camber, rear arch camber secondary beam;
When setting up, the vertical rod advance of beam lower bolster support is arranged along the beam axis direction; The vertical rod transfer is arranged to bilateral symmetry centered by center line at the bottom of beam, and the outermost vertical rod is not more than 150mm apart from beam side distance; Be located at the adjustable base at falsework bottom of upright rod or top, its screw mandrel external diameter is not less than 36mm, and extension elongation is no more than 200mm; When falsework is set up under beam laterally horizon bar stretch in the falsework of beam biside plate and be no less than two vertical rods, and with the vertical rod snapping; The swimming hall falsework carries out anchoring with rigid connecting tube in horizontal enhancement Layer position and frame column; Go up most one cross bar and be not more than 400mm from top template distance; The vertical rod spreading adopts docking, and every bottom of upright rod all arranges chock or scaffold floor; Falsework four limits with middle every 4~6 row's vertical rods should arrange together with vertical bridging, arranged continuously by the end to top; The falsework two ends begin every 2~4 steps, horizontal cross brace to be set downwards from top layer every 4~6 row's vertical rods with middle; The falsework top is connected horizontal enhancement Layer with the bottom: horizontal cross brace is connected with "the" shape with horizontal brace, horizontal brace width is not less than 3m; Setting up steel pipe framed bent in process presses closer tightly with concrete column, the table of having built; Under beam under main joist steel pipe and plate framed bent be linked to be integral body;
The method of taking under prestressed frame beam to increase vertical rod is reinforced, and vertical pole ' s span is 600mm, and ater-casting place's vertical rod supports to the base plate on basis, guarantees that high carriage load energy safe transfer is to sole plate.
CN201310087608.8A 2013-03-19 2013-03-19 Natatorium roof beam slab high formwork construction method Active CN103147573B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310087608.8A CN103147573B (en) 2013-03-19 2013-03-19 Natatorium roof beam slab high formwork construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310087608.8A CN103147573B (en) 2013-03-19 2013-03-19 Natatorium roof beam slab high formwork construction method

Publications (2)

Publication Number Publication Date
CN103147573A true CN103147573A (en) 2013-06-12
CN103147573B CN103147573B (en) 2015-01-28

Family

ID=48545864

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310087608.8A Active CN103147573B (en) 2013-03-19 2013-03-19 Natatorium roof beam slab high formwork construction method

Country Status (1)

Country Link
CN (1) CN103147573B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410311A (en) * 2013-08-20 2013-11-27 南通鑫金建设集团有限公司 Raising-plate high-formwork construction method of indoor pool
CN103726654A (en) * 2014-01-10 2014-04-16 北京城建十建设工程有限公司 Method for constructing special-shaped thin shell of concrete structure
CN104344723A (en) * 2014-10-29 2015-02-11 中冶天工集团有限公司 Construction method for one-step casting of refractory material of water beam of annealing furnace
WO2019222896A1 (en) * 2018-05-21 2019-11-28 增城市碧桂园物业发展有限公司 Floor panel and construction method thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2248541A1 (en) * 1972-10-04 1974-06-27 Arnold Peiffer LOWERED SLAB FORMWORK FOR HIGH STRUCTURES ETC
FR2210200A5 (en) * 1972-12-12 1974-07-05 Poivre Robert
CN102003009A (en) * 2010-10-26 2011-04-06 吴方伯 Reinforced concrete hollow floorslab and construction method
CN102140841A (en) * 2010-12-31 2011-08-03 青岛一建集团有限公司 Construction method of building superstructure in high-rise steel-concrete mixed structure with few supporting formworks
CN102561690A (en) * 2012-03-12 2012-07-11 中天建设集团有限公司 Construction method for supporting structures on two sides of post-cast strip by use of brick column

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2248541A1 (en) * 1972-10-04 1974-06-27 Arnold Peiffer LOWERED SLAB FORMWORK FOR HIGH STRUCTURES ETC
FR2210200A5 (en) * 1972-12-12 1974-07-05 Poivre Robert
CN102003009A (en) * 2010-10-26 2011-04-06 吴方伯 Reinforced concrete hollow floorslab and construction method
CN102140841A (en) * 2010-12-31 2011-08-03 青岛一建集团有限公司 Construction method of building superstructure in high-rise steel-concrete mixed structure with few supporting formworks
CN102561690A (en) * 2012-03-12 2012-07-11 中天建设集团有限公司 Construction method for supporting structures on two sides of post-cast strip by use of brick column

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103410311A (en) * 2013-08-20 2013-11-27 南通鑫金建设集团有限公司 Raising-plate high-formwork construction method of indoor pool
CN103726654A (en) * 2014-01-10 2014-04-16 北京城建十建设工程有限公司 Method for constructing special-shaped thin shell of concrete structure
CN103726654B (en) * 2014-01-10 2015-12-02 北京城建十建设工程有限公司 The construction method of the special-shaped shell of concrete structure
CN104344723A (en) * 2014-10-29 2015-02-11 中冶天工集团有限公司 Construction method for one-step casting of refractory material of water beam of annealing furnace
WO2019222896A1 (en) * 2018-05-21 2019-11-28 增城市碧桂园物业发展有限公司 Floor panel and construction method thereof

Also Published As

Publication number Publication date
CN103147573B (en) 2015-01-28

Similar Documents

Publication Publication Date Title
CN101818570B (en) Method for constructing girder structure conversion layer of high-rise building
CN103046746B (en) Construction method of conversion beam reinforcing bars for tall building structure
CN108265885B (en) Construction method of high-large non-orthogonal large-inclination-angle special-shaped concrete inclined column
CN104480922B (en) Space truss formwork system and construction method thereof
CN111779248A (en) High formwork system and construction method thereof
CN107227814B (en) Sectional construction method for large cantilever concrete structure
CN103147573B (en) Natatorium roof beam slab high formwork construction method
CN103410311A (en) Raising-plate high-formwork construction method of indoor pool
CN103993666A (en) Improved supporting system construction method suitable for large overhung outer floating plate roof
CN107401279A (en) Disposable one-piece casting staircase wall ladder combined steel formwork installation construction method
CN212507296U (en) High formwork system
CN111005547B (en) Construction method of outer scaffold of two-way bending and twisting staggered floor elevation
CN212129218U (en) Basement outer wall single face formwork system
CN114427295B (en) Pre-buried ground anchor pulling connection and holding column combined ultrahigh and ultralimit formwork system and construction method thereof
CN216616835U (en) Ultrahigh ultralimit combined formwork system
CN201915630U (en) Combined platform of fire control joint gallery form supporting steel beam
CN202596161U (en) Combined formwork device of HR heavy type gantry and reinforced concrete temporary structural column
CN115627912A (en) Construction method of assembled externally-mounted flower basket type overhanging scaffold
CN212175531U (en) Steel pipe keel structure for super-thick concrete top plate
CN102454298B (en) Large-sized reinforced concrete construction of frame beam method
CN203891464U (en) Improved support device suitable for parapet flare plate
CN113898171A (en) Ultrahigh two-side floor-free wall supporting system and construction method
CN219343935U (en) Cantilever frame construction system of overlength cantilever balcony structure
CN212927033U (en) Formwork support frame for large-span post-tensioned prestressed beam haunch structure
CN220167506U (en) Supporting structure for reinforcing side beam template

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: NANJING NINTH CONSTRUCTION INSTALLATION ENGINEERIN

Free format text: FORMER OWNER: CHENG JUN

Effective date: 20141219

Owner name: NANTONG SECOND CONSTRUCTION GROUP NANJING FENGXUN

Effective date: 20141219

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Wu Jianhua

Inventor after: Lu Hanshi

Inventor after: Wu Haihong

Inventor after: Gu Hua

Inventor after: Wu Jiang

Inventor after: Wang Yujie

Inventor after: Chen Kailei

Inventor after: Cheng Zhangjianing

Inventor before: Cheng Jun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: CHENG JUN TO: WU JIANHUA LU HANSHI WU HAIHONG GU HUA WU JIANG WANG YUJIE CHEN KAILEI ZHANGJIANING CHENG

Free format text: CORRECT: ADDRESS; FROM: 226300 NANTONG, JIANGSU PROVINCE TO: 211500 NANJING, JIANGSU PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20141219

Address after: 211500 Liuhe Economic Development Zone, Jiangsu, Nanjing

Applicant after: NANJING THE NINTH BUILDING INSTALLATION ENGINEERING CO., LTD.

Applicant after: Nantong Second Construction Group

Applicant after: NANJING FENGXUN ENERGY TECHNOLOGY CO., LTD.

Address before: Tongzhou District Xingyuan road Jiangsu city of Nantong province sunshine mansion 226300 Building No. 63 Room 201

Applicant before: Cheng Jun

C14 Grant of patent or utility model
GR01 Patent grant