CN103091604B - 一种光伏并网发电***的孤岛检测方法和检测装置 - Google Patents
一种光伏并网发电***的孤岛检测方法和检测装置 Download PDFInfo
- Publication number
- CN103091604B CN103091604B CN201310033557.0A CN201310033557A CN103091604B CN 103091604 B CN103091604 B CN 103091604B CN 201310033557 A CN201310033557 A CN 201310033557A CN 103091604 B CN103091604 B CN 103091604B
- Authority
- CN
- China
- Prior art keywords
- frequency
- voltage
- inverter
- point
- grid
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Supply And Distribution Of Alternating Current (AREA)
- Inverter Devices (AREA)
- Photovoltaic Devices (AREA)
Abstract
本发明公开了一种光伏并网发电***的孤岛检测方法和检测装置,通过微处理器控制逆变电源,并改变逆变电源的输出电压的频率,使得每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf;实时检测公共耦合点的电压的频率,判断公共耦合点的电压的频率是否达到***的频率保护的阈值;当公共耦合点的电压的频率大于阈值时,控制逆变器停止工作;当公共耦合点的电压的频率不大于阈值时,继续检测公共耦合点处的电平的频率,很好的实现了对光伏并网发电***中孤岛效应的准确检测,且检测方法简单,检测时间短检测迅速,可靠性高,易操作,成本较低。
Description
技术领域
本发明涉及光伏并网发电技术领域,尤其涉及的是一种光伏并网发电***的孤岛检测方法和检测装置。
背景技术
光伏并网发电***是由光伏电池方阵、控制器和并网逆变器组成,不经过蓄电池储能,通过并网逆变器直接将电能输入公共电网。太阳能光伏并网发电***与离网太阳能光伏发电***相比,省掉了蓄电池储能和释放的过程,减少了其中的能量消耗,节约了占地空间,还降低了配置成本。
但在光伏并网发电***中会产生孤岛效应,发电***并网运行时如果处于孤岛状态将会对设备造成损坏,影响电力***安全正常运行,严重时甚至可能威胁线路检修人员的人身安全。所谓孤岛效应是指电网由于电气故障、误操作或自然因素等原因中断供电时,光伏发电***未能及时检测出停电状态而脱离电网,仍然向公共电网馈送电量,使太阳能并网发电***和周围的负载组成了一个电力公司无法掌握的自给供电孤岛。因此,在光伏并网发电***的应用中必须防止孤岛效应。
现有的检测方法包括:
被动检测法,具体为利用电网断电时逆变器输出端电压、频率、相位或谐波的变化进行孤岛效应检测。但当光伏***输出功率与局部负载功率平衡时,则被动式检测方法将失去孤岛效应检测能力,存在较大的非检测区域。
主动检测法,具体为指通过控制逆变器,使其输出功率、频率或相位存在一定的扰动。电网正常工作时,由于电网的平衡作用,检测不到这些扰动。一旦电网出现故障,逆变器输出的扰动将快速累积并超出允许范围,从而触发孤岛效应检测电路。该方法检测精度高,非检测区小,但是控制较复杂。
因此,现有技术还有待于改进和发展。
发明内容
本发明要解决的技术问题在于,针对现有技术的上述缺陷,提供一种光伏并网发电***的孤岛检测方法和检测装置。
本发明解决技术问题所采用的技术方案如下:
一种光伏并网发电***的孤岛检测方法,其中,包括以下步骤:
A、微处理器控制逆变电源,并改变逆变电源的输出电压的频率,使得每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf;
B、实时检测公共耦合点的电压的频率,判断公共耦合点的电压的频率是否达到***的频率保护的阈值;
C、当公共耦合点的电压的频率大于阈值时,控制逆变器停止工作;当公共耦合点的电压的频率不大于阈值时,执行步骤B。
所述的光伏并网发电***的孤岛检测方法,其中,所述步骤A之前还包括:
A0、判断***是否处于并网发电状态,当***处于并网发电状态时,进入步骤A。
所述的光伏并网发电***的孤岛检测方法,其中,所述步骤A还包括:
A1、微处理器控制逆变电源的输出电压的频率高于电网电压的频率。
所述的光伏并网发电***的孤岛检测方法,其中,所述步骤A还包括:
A2、当***中有多个逆变电源时,微处理器控制每一个逆变电源的每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf。
所述的光伏并网发电***的孤岛检测方法,其中,所述步骤B还包括:
B1、当***没有发生孤岛效应时,逆变电源的输出频率为电网电压输出频率,即公共耦合点的频率与电网电压的频率相同,即频率不会发生改变;当***发生孤岛效应时,公共耦合点的频率会高于前一周期从该点测得的频率。
一种光伏并网发电***的孤岛检测装置,其中,包括:
频率处理模块,用于控制逆变电源,并改变逆变电源的输出电压的频率,使得每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf;
频率检测模块,用于实时检测公共耦合点的电压的频率;
第一判断模块,用于判断公共耦合点的电压的频率是否达到***的频率保护的阈值;
控制模块,用于根据判断模块的结果来控制逆变器的工作状态。
所述的光伏并网发电***的孤岛检测装置,其中,还包括:
第二判断模块,用于判断光伏并网发电***是否处于并网发电状态。
本发明所提供的光伏并网发电***的孤岛检测方法和检测装置,很好的实现了对光伏并网发电***中的孤岛效应的准确检测,克服了现有反孤岛方案的缺陷,即被动检测方法存在较大的非检测区域,而主动检测法的检测精度高,非检测区小,但是控制较复杂的问题,本发明所提供的光伏并网发电***的孤岛检测方法简单,检测时间短,可靠性高,易操作。
附图说明
图1为现有技术中分布式并网逆变器发电***的电路原理图。
图2为本发明提供的光伏并网发电***的孤岛检测方法流程图。
图3为本发明提供的光伏并网发电***的孤岛检测方法的逆变电源输出电压和电网电压的波形图。
图4为本发明提供的光伏并网发电***的孤岛检测装置的结构框图。
具体实施方式
本发明提供了一种光伏并网发电***的孤岛检测方法和检测装置,为使本发明的目的、技术方案及优点更加清楚、明确,以下参照附图并举实施例对本发明进一步详细说明。应当理解,此处所描述的具体实施例仅仅用以解释本发明,并不用于限定本发明。
请参阅图1,图1为现有技术中分布式并网逆变器发电***的电路原理图。所述分布式并网逆变器发电***包括逆变电源10、电网20以及并联RLC负载。其中A为公共耦合点,RLC为局部负载。逆变电源10的输出电压是由电网20控制的,其电压频率和相位与电网20电压相同。所述逆变电源10也就是并网逆变器。并网逆变器将太阳能光伏组件产生的直流转换为交流。并网逆变器一般分为光伏并网逆变器、风力发电并网逆变器、动力设备并网逆变器和其他发电设备并网逆变器。所述光伏电池方阵、控制器和并网逆变器构成一光伏并网发电***,在电网中,相当于一分布式电源。当分布式电源与电网20连接时,由于电网20强大的蓄电子能力,逆变电源10输出电压波形将被电网20拉成同电网20电压波形相似,即频率不会被改变的,譬如我国电网标准为220V AC,频率为50Hz,则公共耦合点A处电压的频率等于电网频率50hz。一旦分布式电源与电网20断开连接,公共耦合点A处电压的频率将会向上发生偏移。
基于上述原理,本发明提供了一种光伏并网发电***的孤岛检测方法,如图2所示,包括以下步骤:
步骤S100、微处理器控制逆变电源,并改变逆变电源的输出电压的频率,使得每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf;
步骤S200、实时检测公共耦合点的电压的频率,判断公共耦合点的电压的频率是否达到***的频率保护的阈值;
步骤S300、当公共耦合点的电压的频率大于阈值时,***产生孤岛效应,控制逆变器停止工作;当公共耦合点的电压的频率不大于阈值时,***没有产生孤岛效应,执行步骤S200。
下面结合具体的实施例对上述步骤进行详细的描述。
在步骤S100中,微处理器控制光伏并网发电***中的逆变器,从而控制并网逆变器的输出频率,也就是控制逆变电源的输出电压的频率。并进一步地改变逆变电源输出电压的频率,让每一个周期的电压频率都比前一周期的电压频率高一预定值Δf,即fi(k)=fv(k-1)+Δf,其中,K为正整数,fv(k-1)表示前一周期逆变电源的输出电压的频率,而fi(k)表示相邻下一个周期逆变电源的输出电压的频率。也就是说,随着周期的增加,逆变电源的输出电压的频率逐渐增加,并且响铃周期增加的频率值为预定值Δf。
优选地,所述步骤S100还包括:S101、微处理器控制逆变电源的输出电压的频率高于电网电压的频率。如图3所示,u1为电网电压的波形图,u2为逆变电源的输出电压的波形图,fu1<fu2。其中,微处理器控制逆变电源的输出电压频率略高于电网电压的频率,从而通过控制逆变器输出频率,得到一个略微失真的电压。由于电网的作用,即使微处理器控制光伏并网发电***中逆变器的输出频率,公共耦合点处的频率也不会变化,等于电网频率。
在步骤S200中,实时检测公共耦合点的电压的频率,判断公共耦合点的电压的频率是否达到***的频率保护的阈值。由于分布式电源与电网断开连接后,也就是光伏并网***产生孤岛效应,公共耦合点处电压的频率将会向上发生偏移。逆变电源电压将会以比前一周期从公共耦合点测得的频率略高的频率运行,这种情况一直持续到频率偏移足够大,直到超过设定的频率保护的阈值。也就是说,当***没有发生孤岛效应时,逆变电源的输出频率为电网电压输出频率,即公共耦合点的频率与电网电压的频率相同,即频率不会发生改变;当***发生孤岛效应时,公共耦合点的频率会高于前一周期从该点测得的频率。
在步骤S300中,实时检测公共耦合点的电压的频率,当公共耦合点的电压的频率大于阈值时,则表明***产生了孤岛效应,控制逆变器停止工作;当公共耦合点的电压的频率不大于阈值时,则表明***没有产生孤岛效应,返回步骤S200。
进一步地,所述步骤S100还包括:步骤S102、判断***是否处于并网发电状态,当***处于并网发电状态时,进入步骤S100。当***不处于并网发电状态时,则进入等待状态,不检测孤岛效应。
进一步地,在光伏并网发电***中包含多个逆变电源时,微处理器控制每一个逆变电源的每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf。在连接有多台并网逆变电源的***中,需要统一不同并网逆变器的频率偏移方向才能维持该方法的有效性。如果有一部分并网逆变电源采用频率向上偏移,而另一部分采用向下偏移频率的方法,其综合效果可能会相互抵消。因此,微处理器控制每个逆变电源的频率向上偏移。
通过上述步骤,可以很好的实现对光伏并网发电***中孤岛效应的准确检测,检测方法简单,检测方法时间短,可靠性高,易操作,成本较低。
基于上述本发明提供的光伏并网发电***的孤岛检测方法,本发明还提供了一种光伏并网发电***的孤岛检测装置,如图4所示,所示***包括:
频率处理模块110,用于控制逆变电源,并改变逆变电源的输出电压的频率,使得每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf,具体如上所述;
频率检测模块120,用于实时检测公共耦合点的电压的频率,具体如上所述;
第一判断模块130,用于判断公共耦合点的电压的频率是否达到***的频率保护的阈值,具体如上所述;
控制模块140,用于根据判断模块的结果来控制逆变器的工作状态,具体如上所述。
进一步地,所述孤岛检测装置还包括第二判断模块150,用于判断光伏并网发电***是否处于并网发电状态。具体如上所述。
综上所述,本发明提供的光伏并网发电***的孤岛检测方法和检测装置,通过微处理器控制逆变电源,并改变逆变电源的输出电压的频率,使得每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf;实时检测公共耦合点的电压的频率,判断公共耦合点的电压的频率是否达到***的频率保护的阈值;当公共耦合点的电压的频率大于阈值时,控制逆变器停止工作;当公共耦合点的电压的频率不大于阈值时,继续检测公共耦合点处的电平的频率。本发明很好的实现了对光伏并网发电***中孤岛效应的准确检测,且检测方法简单,检测时间短检测迅速,可靠性高,易操作,成本较低。
应当理解的是,本发明的应用不限于上述的举例,对本领域普通技术人员来说,可以根据上述说明加以改进或变换,所有这些改进和变换都应属于本发明所附权利要求的保护范围。
Claims (5)
1. 一种光伏并网发电***的孤岛检测方法,其特征在于,包括以下步骤:
A、微处理器控制逆变电源,并改变逆变电源的输出电压的频率,使得每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf;
B、实时检测公共耦合点的电压的频率,判断公共耦合点的电压的频率是否达到***的频率保护的阈值;
C、当公共耦合点的电压的频率大于阈值时,控制逆变器停止工作;当公共耦合点的电压的频率不大于阈值时,执行步骤B;
所述步骤A还包括:
A1、微处理器控制逆变电源的输出电压的频率高于电网电压的频率;
所述步骤B还包括:
B1、当***没有发生孤岛效应时,逆变电源的输出频率为电网电压输出频率,即公共耦合点的频率与电网电压的频率相同,即频率不会发生改变;当***发生孤岛效应时,公共耦合点的频率会高于前一周期从该点测得的频率。
2.根据权利要求1所述的光伏并网发电***的孤岛检测方法,其特征在于,所述步骤A之前还包括:
A0、判断***是否处于并网发电状态,当***处于并网发电状态时,进入步骤A。
3.根据权利要求1所述的光伏并网发电***的孤岛检测方法,其特征在于,所述步骤A还包括:
A2、当***中有多个逆变电源时,微处理器控制每一个逆变电源的每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf。
4.一种光伏并网发电***的孤岛检测装置,其特征在于,包括:
频率处理模块,用于控制逆变电源,并改变逆变电源的输出电压的频率,使得每一个周期的电压频率都比前一个周期的电压频率高一预定值Δf;
频率检测模块,用于实时检测公共耦合点的电压的频率;
第一判断模块,用于判断公共耦合点的电压的频率是否达到***的频率保护的阈值;
控制模块,用于根据第一判断模块的结果来控制逆变器的工作状态;
所述频率处理模块,还用于控制逆变电源的输出电压的频率高于电网电压的频率;
当***没有发生孤岛效应时,逆变电源的输出频率为电网电压输出频率,即公共耦合点的频率与电网电压的频率相同,即频率不会发生改变;当***发生孤岛效应时,公共耦合点的频率会高于前一周期从该点测得的频率。
5.根据权利要求4所述的光伏并网发电***的孤岛检测装置,其特征在于,还包括:
第二判断模块,用于判断光伏并网发电***是否处于并网发电状态。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310033557.0A CN103091604B (zh) | 2013-01-29 | 2013-01-29 | 一种光伏并网发电***的孤岛检测方法和检测装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201310033557.0A CN103091604B (zh) | 2013-01-29 | 2013-01-29 | 一种光伏并网发电***的孤岛检测方法和检测装置 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN103091604A CN103091604A (zh) | 2013-05-08 |
CN103091604B true CN103091604B (zh) | 2015-10-28 |
Family
ID=48204413
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201310033557.0A Active CN103091604B (zh) | 2013-01-29 | 2013-01-29 | 一种光伏并网发电***的孤岛检测方法和检测装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN103091604B (zh) |
Families Citing this family (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103368136A (zh) * | 2013-07-15 | 2013-10-23 | 国家电网公司 | 一种处理电网失电的方法和装置 |
CN104598660B (zh) * | 2013-10-31 | 2017-11-17 | 国际商业机器公司 | 在电力网络拓扑中检测孤岛效应的方法和*** |
US9520819B2 (en) | 2014-02-28 | 2016-12-13 | General Electric Company | System and method for controlling a power generation system based on a detected islanding event |
CN103969549B (zh) * | 2014-04-18 | 2016-08-17 | 珠海许继电气有限公司 | 电源设备的孤岛检测方法及孤岛检测装置 |
CN104730423A (zh) * | 2015-04-07 | 2015-06-24 | 嘉兴金尚节能科技有限公司 | 光伏并网发电***的孤岛效应检测方法 |
CN106124890B (zh) * | 2016-04-14 | 2019-05-17 | 国网辽宁省电力有限公司电力科学研究院 | 一种光伏并网发电***的反孤岛检测方法 |
CN110401223B (zh) * | 2019-07-31 | 2021-04-27 | 珠海格力电器股份有限公司 | 光伏***的控制方法、控制装置和光伏*** |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101257209A (zh) * | 2008-01-10 | 2008-09-03 | 清华大学深圳研究生院 | 光伏并网发电***的孤岛运行检测方法 |
CN101944723A (zh) * | 2010-08-26 | 2011-01-12 | 哈尔滨九洲电气股份有限公司 | 一种光伏并网发电***的孤岛运行检测方法 |
CN102262182A (zh) * | 2011-07-07 | 2011-11-30 | 浙江大学 | 光伏并网逆变器孤岛检测方法 |
CN102437587A (zh) * | 2011-09-23 | 2012-05-02 | 武汉新能源接入装备与技术研究院有限公司 | 一种大功率光伏并网变流器的孤岛检测方法 |
CN102608496A (zh) * | 2012-03-15 | 2012-07-25 | 北京昆兰新能源技术有限公司 | 一种改进型正反馈主动频率偏移孤岛检测法 |
Family Cites Families (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6850074B2 (en) * | 2002-08-05 | 2005-02-01 | Encorp, Inc. | System and method for island detection |
-
2013
- 2013-01-29 CN CN201310033557.0A patent/CN103091604B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101257209A (zh) * | 2008-01-10 | 2008-09-03 | 清华大学深圳研究生院 | 光伏并网发电***的孤岛运行检测方法 |
CN101944723A (zh) * | 2010-08-26 | 2011-01-12 | 哈尔滨九洲电气股份有限公司 | 一种光伏并网发电***的孤岛运行检测方法 |
CN102262182A (zh) * | 2011-07-07 | 2011-11-30 | 浙江大学 | 光伏并网逆变器孤岛检测方法 |
CN102437587A (zh) * | 2011-09-23 | 2012-05-02 | 武汉新能源接入装备与技术研究院有限公司 | 一种大功率光伏并网变流器的孤岛检测方法 |
CN102608496A (zh) * | 2012-03-15 | 2012-07-25 | 北京昆兰新能源技术有限公司 | 一种改进型正反馈主动频率偏移孤岛检测法 |
Non-Patent Citations (3)
Title |
---|
一种新颖的光伏并网***孤岛检测方法;张超 等;《电力电子技术》;20071120;第41卷(第11期);第97-98页第2.1节,图1-2 * |
主动移频法在光伏并网逆变器并联运行下的孤岛检测机理研究;刘方锐 等;《中国电机工程学报》;20090425;第29卷(第12期);第47-51页 * |
基于频率偏移法的光伏并网逆变器孤岛检测;陈曦 等;《2011中国电工技术学会学术年会论文集 》;20110901;第478-482页 * |
Also Published As
Publication number | Publication date |
---|---|
CN103091604A (zh) | 2013-05-08 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11205946B2 (en) | Serially connected inverters | |
CN103091604B (zh) | 一种光伏并网发电***的孤岛检测方法和检测装置 | |
CN103004047B (zh) | 为分布式发电电源提供电弧故障和/或接地故障保护用的***及方法 | |
US20120283890A1 (en) | Control Apparatus for Micro-grid Connect/Disconnect from Grid | |
Yuan et al. | Status and opportunities of photovoltaic inverters in grid-tied and micro-grid systems | |
US9509231B2 (en) | Power converter system, damping system, and method of operating a power converter system | |
CA2831576A1 (en) | Method and apparatus for grid impedance detection | |
Ropp et al. | Discussion of a power line carrier communications-based anti-islanding scheme using a commercial automatic meter reading system | |
US20140077609A1 (en) | Serially connected micro-inverter system with trunk and drop cabling | |
US9748769B2 (en) | Serially connected micro-inverter system having concertina output voltage control | |
Reedy et al. | Power line carrier permissive as a simple and safe method of enabling inverter ride-through operation of distributed grid-tied photovoltaic systems | |
CN203522212U (zh) | 具有低电压穿越和防孤岛保护功能的光伏电站*** | |
US20130200712A1 (en) | Photovoltaic power plant | |
Cao et al. | PMU based islanding detection method for large photovoltaic power station | |
Farooq et al. | A Reliable Approach to Protect and Control of Wind Solar Hybrid DC Microgrids | |
CN103475022A (zh) | 具有低电压穿越和防孤岛保护功能的光伏电站*** | |
CN103887811A (zh) | 具有低电压穿越和防孤岛保护功能的分布式电源***及控制方法 | |
CN203084143U (zh) | 一种光伏并网发电***的孤岛检测装置 | |
Kumari et al. | Passive islanding detection approach for inverter based DG using harmonics analysis | |
Moradzadeh et al. | A novel hybrid islanding detection method for distributed generations | |
Sarangi et al. | Active islanding detection and analysis of total harmonic distortion for inverter-interfaced microgrid based on high-frequency signal installation | |
Son et al. | Islanding detection in DC network | |
Li et al. | A protection method for microgrids based on information sharing | |
Liu et al. | The Research of Islanding Detection about the Photovoltaic Grid-Connected Generation System | |
CN110426600B (zh) | 检测孤岛效应的电流环相关取样法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right | ||
PE01 | Entry into force of the registration of the contract for pledge of patent right |
Denomination of invention: Islanding detection method and device for photovoltaic grid connected power generation system Effective date of registration: 20211213 Granted publication date: 20151028 Pledgee: Shenzhen high tech investment and financing Company limited by guarantee Pledgor: Shenzhen JingQuanHua Electronics Co.,Ltd. Registration number: Y2021980014732 |