CN103061544A CN 201310009678 CN201310009678A CN103061544A CN 103061544 A CN103061544 A CN 103061544A CN 201310009678 CN201310009678 CN 201310009678 CN 201310009678 A CN201310009678 A CN 201310009678A CN 103061544 A CN103061544 A CN 103061544A
Authority
CN
China
Prior art keywords
fast
square tube
assembling
operating room
keel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN 201310009678
Other languages
Chinese (zh)
Inventor
马兆勇
邱磊
马兆川
杨利利
杨四根
艾先英
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SUZHOU TONGKUAI PURIFICATION TECHNOLOGY Co Ltd
Original Assignee
SUZHOU TONGKUAI PURIFICATION TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SUZHOU TONGKUAI PURIFICATION TECHNOLOGY Co Ltd filed Critical SUZHOU TONGKUAI PURIFICATION TECHNOLOGY Co Ltd
Priority to CN 201310009678 priority Critical patent/CN103061544A/en
Publication of CN103061544A publication Critical patent/CN103061544A/en
Withdrawn legal-status Critical Current

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention discloses a plug fast-installation auxiliary room for clean operating rooms. The plug fast-installation auxiliary room for clean operating rooms comprises four lower keel parts which are disposed on a building floor and enclose a rectangular structure. Upper keel parts are inserted on the lower keep arts. The ends of the upper keel parts are linked through foot arcs. Two vertical square tubes are disposed at two ends of each foot arc. The upper ends of the vertical square tubes are connected into a rectangular frame through transverse and longitudinal square tubes. A plurality of fast-installation wall panels are spliced into an operating room wall on the upper keel parts among the vertical square tubes. The rectangular frames formed by connecting the transverse and longitudinal square tubes are spliced into an operating room roof through a plurality of fast-installation top plates. The parts of the plug fast-installation auxiliary room for clean operating rooms are all in plug fast-installation structures, and the technical quality of the overall process is high. Installation components are inserted on the construction site only by the plug fast-installation non-welding installation process, the construction process of the operating room is simplified, construction period is shortened, and the plug fast-installation auxiliary room for clean operating rooms is convenient to maintain and upgrade later.

Description

A kind of auxiliary room of grafting fast-assembling clean operating room and mounting process thereof
Technical field
The present invention relates to medical surgery room finishing field, relate in particular to a kind of auxiliary room of grafting fast-assembling clean operating room and mounting process thereof.
Background technology
At present, the specialized factory of domestic design construction purified operation room is more, and design and construction technology are different, mainly are Site Welding formula and traditional pin-connected panel.Wherein the Site Welding formula is because the process characteristic of the secondary operations such as necessary Site Welding, it is yielding to present installation component, installation accuracy is lower, be welded and fixed difficult the adjustment, the characteristics such as the difficult grasp of in-situ spraying technique, cause the installation of purified operation room difficult, difficult quality guarantee, not easy care and replacing.Traditional pin-connected panel operating room is half assembly unit operating room, and wherein the parts such as keel need Site Welding, and wallboard is assembled structure, because the part assembly unit presents welding keel planeness and requires height, assembling process requires high, be difficult to the characteristics such as grasp, cause at last construction quality to be difficult to guarantee.
Summary of the invention
Technical problem to be solved by this invention is, provide that a kind of technology quality is high, human factor on the impact of product quality less, upgrading is convenient, peg graft the fast and accurately auxiliary room of fast-assembling clean operating room and mounting process thereof are installed.
In order to solve the problems of the technologies described above, the present invention is achieved by the following technical solutions:
The auxiliary room of a kind of grafting fast-assembling clean operating room, comprise that four are arranged on the lower keel spare that building floor surrounds rectangular configuration, be plugged with keel on the lower keel spare, upper keel is by being arranged on the screw mechanism adjustment level in the lower keel spare, pass through the lower margin circular arc dovetail between each end of described upper keel, the two ends of described each lower margin circular arc respectively are provided with a vertical square tube, connect into rectangle frame by horizontal and vertical square tube between each vertical square tube upper end; Be spliced into the operating room metope by some fast assembling wall slabs on the upper keel between the described vertical square tube, be fixedly connected with connecting key by fixture behind the wallboard between the every fast assembling wall slab, be spliced into the operating room end face by some fast-assembling top boards between the rectangle frame that horizontal and vertical square tube connects into, and every fast-assembling top board top is fixedly connected with construction ceiling by the furred ceiling hanging hook assembly all; Connect by arc plate between described operating room metope and the operating room end face, be connected by bulb between the adjacent arc plate end.
Preferably, be connected by angle connector between described horizontal and vertical square tube and the vertical square tube, and fix with the staking nut that is arranged in the square tube by the set bolt that is arranged on the angle connector.
Preferably, described vertical square tube top is connected angle connector and is connected with building floor with construction ceiling respectively with the bottom, and fix by being arranged on swell fixture on the angle connector and construction ceiling and building floor, and pass through rivet between described angle connector and the vertical square tube.
Preferably, described splicing is connected by the top board fixture between the fast-assembling top board of horizontal and vertical square tube inboard and square tube.
Preferably, described furred ceiling hanging hook assembly is made of connection box, threaded rod and hook, connection box is arranged on the threaded rod top, hook is arranged on the threaded rod bottom, all fix by locking nut and spring shim between connection box and hook and the threaded rod, wherein the connection box top is provided with the swell fixture that is connected with construction ceiling, and hook is connected with described fast-assembling top board.
Preferably, the arc radius R of described bulb and arc plate is 50mm~350mm.
The auxiliary room of a kind of grafting fast-assembling clean operating room mounting process may further comprise the steps:
A, at first to the ground snap the line: before the snap the line, cleaning and ground grading are confirmed ground flat degree within 3mm/2m, without shelling, play the powder phenomenon; Then determine the benchmark line of ink marker, eject vertical guideline, determine with Pythagorean theorem, guarantee that operating room and unwrapping wire benchmark are smooth vertical and horizontal; Then verification operating room diagonal error≤± 3mm; Then according to the unwrapping wire drawing, eject the metope line of ink marker and the keel line of ink marker and determine the square tube position;
B, according to figure paper size and the keel line of ink marker and square tube position, vertical vertical square tube is installed, with setscrew, angle connector and angle connector, being fixed on building floor and the construction ceiling perpendicular to ground direction square tube; Then lower keel spare is fixed on the building floor with setscrew according to designing requirement; Insert upper keel downwards, regulate levelling bolt, make keel part level, smooth; Then be connected with hold-down screw according to designing requirement with angle connector according to designing requirement and be installed on staking nut in the square tube, be connected and fixed horizontal square tube;
C, according to designing requirement with rivet bulb, arc plate and lower margin circular arc;
D, in upper keel sword groove, insert connecting key, insert fast assembling wall slab downwards, at the fixing fixture behind the wallboard of fast assembling wall slab upper rear portion riveted joint, be fixed on grafting Quick-mounting board top, in grafting Quick-mounting board sidewall aluminum alloy frame skeleton groove, insert connecting key, prepare to connect next grafting Quick-mounting board;
E, install the remaining parts of furred ceiling hanging hook assembly except setscrew in advance,, connect and install in advance furred ceiling hanging hook assembly parts at construction ceiling fixed expansion screw according to the designing requirement position, finish the installation of furred ceiling hanging hook assembly; According to designing requirement the fast-assembling top board is raised to level altitude, hook in top board fixture, the furred ceiling hanging hook assembly is colluded in the fast-assembling top board sidewall aluminium alloy plate peripheral frame skeleton internal groove, and with rivet top board fixture riveted joint is fixed on the square tube, in the sidewall aluminium alloy plate peripheral frame skeleton inner groovy of fast-assembling top board, insert connecting key, prepare to connect next fast-assembling top board.
Compared with prior art, usefulness of the present invention is: each parts of the auxiliary room of this grafting fast-assembling clean operating room are the grafting quick fixation structure, cooperate simple efficiently grafting fast-assembling welding mounting process, so that the auxiliary room of whole grafting fast-assembling clean operating room all over products is finished in factory, owing to be to process at the professional production streamline, the integrated artistic technical quality is high; Only need when constructing at the scene installation component by the installation of pegging graft of grafting fast-assembling welding mounting process, simplified the construction technology of operating room, shortened construction period, lower to the requirement of field worker level, reduced greatly the impact of human factor on product quality; And this structure is so that later maintenance and upgrading are extremely convenient.
Description of drawings:
Fig. 1 is the present invention's auxiliary room of fast-assembling clean operating room structural representation of pegging graft;
Fig. 2 is the auxiliary room of grafting fast-assembling clean operating room top view;
Fig. 3 is the structure sectional view of A-A among Fig. 2;
Fig. 4 is without the auxiliary room of vertical, horizontal square pipe keel structural representation;
Fig. 5 is without the auxiliary room of vertical, horizontal square pipe keel top view;
Fig. 6 is the structure sectional view of B-B among Fig. 5;
Fig. 7 is grafting fast-assembling clean operating room auxiliary room arc plate and bulb mounting structure schematic diagram;
Fig. 8 is the auxiliary room of grafting fast-assembling clean operating room fast assembling wall slab mounting structure schematic diagram;
Fig. 9 is the auxiliary room of the lifting clean operating room fast-assembling top plate mounting structure schematic diagram of pegging graft;
Figure 10 is grafting fast-assembling clean operating room auxiliary room fast assembling wall slab and fast assembling wall slab or fast-assembling top board and fast-assembling mounting of roof plate syndeton schematic diagram;
Figure 11 is the partial enlarged drawing of a among Fig. 1;
Figure 12 is the partial enlarged drawing of b among Fig. 1;
Figure 13 is the partial enlarged drawing of c among Fig. 1;
Figure 14 is furred ceiling hanging hook assembly structural representation.
Among the figure: 1, square tube; 2, staking nut; 3, hold-down screw; 4, swell fixture; 5, rivet; 6,7, angle connector; 8, lower keel spare; 9, upper keel; 10, lower margin circular arc; 11, fixture behind the wallboard; 12, bulb; 13, arc plate; 14, connecting key; 15, fast assembling wall slab; 16, fast-assembling top board; 17, top board fixture; 18, furred ceiling hanging hook assembly; 181, connection box; 182, threaded rod; 183, locking nut; 184, spring shim; 185, hook; 19, construction ceiling; 20, building floor.
The specific embodiment:
Describe the present invention below in conjunction with the drawings and specific embodiments.
Fig. 1 Fig. 2 and the auxiliary room of a kind of grafting fast-assembling clean operating room shown in Figure 3, comprise some lower keel spares 8 that are arranged on building floor, be plugged with keel 9 on the lower keel spare 8, upper keel 9 can be by being arranged on the screw mechanism accurate adjustment level in the lower keel spare 8, integral level basis and ground material installing space and the border in fast assembling wall slab 15 and the auxiliary room of whole grafting fast-assembling clean operating room installed in formation, installs with the ground material for follow-up fast assembling wall slab 15 to facilitate; Be connected by lower margin circular arc 10 between described upper keel 9 each end, the two ends of described each lower margin circular arc 10 respectively are provided with a vertical square tube 1, connect into rectangle frame by horizontal and vertical square tube 1 between each vertical square tube 1 upper end; As shown in Figure 8, be spliced into the operating room metope by some fast assembling wall slabs 15 on the upper keel 9 between the described vertical square tube 1, be fixedly connected with as shown in figure 13 connecting key 14 by fixture behind the wallboard 11 between every fast assembling wall slab 15; As shown in Figure 9, be spliced into the operating room end face by some fast-assembling top boards 16 between the rectangle frame that horizontal and vertical square tube 1 connects into, and every fast-assembling top board 16 tops are fixedly connected with construction ceiling 19 by furred ceiling hanging hook assembly 18 all; As shown in figure 14, described furred ceiling hanging hook assembly 18 is by connection box 181, threaded rod 182 and link up with 185 and consist of, connection box 181 is arranged on threaded rod 182 tops, hook 185 is arranged on threaded rod 182 bottoms, connection box 181 and link up with 185 and threaded rod 182 between all fixing by locking nut 183 and spring shim 184, wherein connection box 181 tops are provided with the swell fixture 4 that is connected with construction ceiling 19, and hook 185 is connected with described fast-assembling top board 16; As shown in Figure 7, connect by arc plate 13 between described operating room metope and the operating room end face, be connected by bulb 12 between adjacent arc plate 13 ends, the arc radius R of described bulb 12 and arc plate 13 is 50mm~350mm.
As shown in figure 11, be connected by angle connector 7 between described horizontal and vertical square tube 1 and the vertical square tube 1, and fixing with the staking nut 2 that is arranged in the square tube 1 by the set bolt 3 that is arranged on the angle connector 7; As shown in figure 12, described vertical square tube 1 top is connected angle connector 6 and is connected with building floor with construction ceiling 19 respectively and is connected with the bottom, and be fixing with construction ceiling 19 and building floor 20 by the swell fixture 4 that is arranged on the angle connector 6, and pass through rivet 5 between described angle connector 6 and the vertical square tube 1 and rivet; Described splicing is connected by top board fixture 17 between the fast-assembling top board 16 of horizontal and vertical square tube 1 inboard and square tube.
Such as Fig. 4, Fig. 5 and shown in Figure 6, according to actual conditions, auxiliary room also can need not vertical, horizontal square tube 1 and corresponding connection; Described fast assembling wall slab 15 direct fast-assemblings are plugged on the horizontal keel assembly, and form auxiliary room metope by connecting key 14 mutual pegging graft; Shown in fast-assembling top board 16 be lifted on the construction ceiling 19 by furred ceiling hanging hook assembly 18, and peg graft mutually by connecting key 14 and to form auxiliary roof faces, fixedly finish installation after securing member; As shown in figure 10, mutually peg graft by connecting key 3 between grafting fast assembling wall slab 5 and grafting fast assembling wall slab 5 or grafting fast-assembling top board 6 and the grafting fast-assembling top board 6.
Its concrete mounting process step is as follows:
A, at first to the ground snap the line: before the snap the line, cleaning and ground grading are confirmed ground flat degree within 3mm/2m, without shelling, play the powder phenomenon; Then determine the benchmark line of ink marker, eject vertical guideline, determine with Pythagorean theorem, guarantee that operating room and unwrapping wire benchmark are smooth vertical and horizontal; Then verification operating room diagonal error≤± 3mm; Then according to the unwrapping wire drawing, eject the metope line of ink marker and the keel line of ink marker and determine the square tube position;
B, according to figure paper size and the keel line of ink marker and square tube position, vertical vertical square tube 1 is installed, with setscrew 4, angle connector 6 and angle connector 7, being fixed on building floor 20 and the construction ceiling 19 perpendicular to ground direction square tube; Then lower keel spare 8 is fixed on the building floor 20 with setscrew 4 according to designing requirement; Insert upper keel 9 downwards, regulate levelling bolt, make keel part 9 levels, smooth; Then are connected with hold-down screw to connect according to designing requirement with angle connector 6 according to designing requirement and are installed on staking nut 2 in the square tube, be connected and fixed horizontal square tube 1;
C, according to designing requirement with rivet 5 riveted joint bulb 12, arc plate 13 and lower margin circular arcs 10;
D, in upper keel sword 9 grooves, insert connecting key 14, insert fast assembling wall slab 15 downwards, at the fixing fixture 11 behind the wallboard of fast assembling wall slab 15 upper rear portion riveted joints, be fixed on grafting Quick-mounting board 15 tops, in grafting Quick-mounting board 15 sidewall aluminum alloy frame skeleton grooves, insert connecting key 14, prepare to connect next grafting Quick-mounting board 15;
E, install the remaining parts of furred ceiling hanging hook assembly 18 except setscrew 4 in advance,, connect and install in advance furred ceiling hanging hook assembly 18 parts at construction ceiling 19 fixed expansion screws 4 according to the designing requirement position, finish the installation of furred ceiling hanging hook assembly 18; According to designing requirement fast-assembling top board 16 is raised to level altitude, hook 185 in top board fixture 17, the furred ceiling hanging hook assembly 18 is colluded in the fast-assembling top board 16 sidewall aluminium alloy plate peripheral frame skeleton internal grooves, and with rivet 5 top board fixture 17 riveted joint is fixed on the square tube 1, in the sidewall aluminium alloy plate peripheral frame skeleton inner groovy of fast-assembling top board 16, insert connecting key 14, prepare to connect next fast-assembling top board 16.
Each parts of the auxiliary room of this grafting fast-assembling clean operating room are the grafting quick fixation structure, cooperate simple efficiently grafting fast-assembling welding mounting process, so that the auxiliary room of whole grafting fast-assembling clean operating room all over products is finished in factory, owing to be to process at the professional production streamline, the integrated artistic technical quality is high; Only need when constructing at the scene installation component by the installation of pegging graft of grafting fast-assembling welding mounting process, simplified the construction technology of operating room, shortened construction period, lower to the requirement of field worker level, reduced greatly the impact of human factor on product quality; And this structure is so that later maintenance and upgrading are extremely convenient.
It is emphasized that: above only is preferred embodiment of the present invention, be not that the present invention is done any pro forma restriction, every foundation technical spirit of the present invention all still belongs in the scope of technical solution of the present invention any simple modification, equivalent variations and modification that above embodiment does.

Claims (7)

1. auxiliary room of grafting fast-assembling clean operating room, it is characterized in that, comprise that four are arranged on the lower keel spare (8) that building floor (20) surrounds rectangular configuration, be plugged with keel (9) on the lower keel spare (8), upper keel (9) is adjusted level by the screw mechanism that is arranged in the lower keel spare (8), be connected by lower margin circular arc (10) between each end of described upper keel (9), the two ends of described each lower margin circular arc (10) respectively are provided with a vertical square tube (1), connect into rectangle frame by horizontal and vertical square tube (1) between each vertical square tube (1) upper end; Upper keel (9) between the described vertical square tube (1) is upper to be spliced into the operating room metope by some fast assembling wall slabs (15), be fixedly connected with connecting key (14) by fixture behind the wallboard (11) between the every fast assembling wall slab (15), be spliced into the operating room end face by some fast-assembling top boards (16) between the rectangle frame that horizontal and vertical square tube (1) connects into, and every fast-assembling top board (16) top is fixedly connected with construction ceiling (19) by furred ceiling hanging hook assembly (18) all; Connect by arc plate (13) between described operating room metope and the operating room end face, be connected by bulb (12) between adjacent arc plate (13) end.
2. the auxiliary room of grafting fast-assembling clean operating room according to claim 1, it is characterized in that, be connected by angle connector (7) between described horizontal and vertical square tube (1) and the vertical square tube (1), and fixing with the staking nut (2) that is arranged in the square tube (1) by the set bolt (3) that is arranged on the angle connector (7).
3. the auxiliary room of grafting fast-assembling clean operating room according to claim 1, it is characterized in that, described vertical square tube (1) top is connected angle connector (6) and is connected 20 with construction ceiling (19) with building floor respectively with the bottom) be connected, and be fixing by swell fixture (4) and the construction ceiling (19) and the building floor (20) that are arranged on the angle connector (6), and pass through rivet (5) between described angle connector (6) and the vertical square tube (1) and rivet.
4. the auxiliary room of grafting fast-assembling clean operating room according to claim 1 is characterized in that, described splicing is connected by top board fixture (17) between the inboard fast-assembling top board (16) of horizontal and vertical square tube (1) and square tube.
5. the auxiliary room of grafting fast-assembling clean operating room according to claim 1, it is characterized in that, described furred ceiling hanging hook assembly (18) is by connection box (181), threaded rod (182) and hook (185) consist of, connection box (181) is arranged on threaded rod (182) top, hook (185) is arranged on threaded rod (182) bottom, all fixing by locking nut (183) and spring shim (184) between connection box (181) and hook (185) and the threaded rod (182), wherein connection box (181) top is provided with the swell fixture (4) that is connected with construction ceiling (19), and hook (185) is connected with described fast-assembling top board (16).
6. the auxiliary room of grafting fast-assembling clean operating room according to claim 1 is characterized in that, the arc radius R of described bulb (12) and arc plate (13) is 50mm~350mm.
7. the auxiliary room of a grafting fast-assembling clean operating room mounting process is characterized in that, may further comprise the steps:
A, at first to the ground snap the line: before the snap the line, cleaning and ground grading are confirmed ground flat degree within 3mm/2m, without shelling, play the powder phenomenon; Then determine the benchmark line of ink marker, eject vertical guideline, determine with Pythagorean theorem, guarantee that operating room and unwrapping wire benchmark are smooth vertical and horizontal; Then verification operating room diagonal error≤± 3mm; Then according to the unwrapping wire drawing, eject the metope line of ink marker and the keel line of ink marker and determine the square tube position;
B, according to figure paper size and the keel line of ink marker and square tube position, vertical vertical square tube (1) is installed, with setscrew (4), angle connector (6) and angle connector (7), being fixed on perpendicular to ground direction square tube on building floor (20) and the construction ceiling (19); Then lower keel spare (8) is fixed on the building floor (20) with setscrew (4) according to designing requirement; Insert upper keel (9) downwards, regulate levelling bolt, make keel part (9) level, smooth; Then be connected 3 with angle connector (6) with hold-down screw according to designing requirement) connect according to designing requirement and be installed on staking nut (2) in the square tube, be connected and fixed horizontal square tube (1);
C, according to designing requirement with rivet (5) riveted joint bulb (12), arc plate (13) and lower margin circular arc (10);
D, in upper keel sword (9) groove, insert connecting key (14), insert fast assembling wall slab (15) downwards, at the fixing fixture (11) behind the wallboard of fast assembling wall slab (15) upper rear portion riveted joint, be fixed on grafting Quick-mounting board (15) top, in grafting Quick-mounting board (15) sidewall aluminum alloy frame skeleton groove, insert connecting key (14), prepare to connect next grafting Quick-mounting board (15);
E, install the remaining parts of furred ceiling hanging hook assembly (18) except setscrew (4) in advance, according to the designing requirement position at construction ceiling (19) fixed expansion screw (4), connection installs furred ceiling hanging hook assembly (18) parts in advance, finishes the installation of furred ceiling hanging hook assembly (18); According to designing requirement fast-assembling top board (16) is raised to level altitude, hook (185) in top board fixture (17), the furred ceiling hanging hook assembly (18) is colluded in fast-assembling top board (16) the sidewall aluminium alloy plate peripheral frame skeleton internal groove, and with rivet (5) top board fixture (17) riveted joint is fixed on the square tube (1), in the sidewall aluminium alloy plate peripheral frame skeleton inner groovy of fast-assembling top board (16), insert connecting key (14), prepare to connect next fast-assembling top board (16).
CN 201310009678 2013-01-11 2013-01-11 Plug fast-installation auxiliary room for clean operating rooms and installation process thereof Withdrawn CN103061544A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201310009678 CN103061544A (en) 2013-01-11 2013-01-11 Plug fast-installation auxiliary room for clean operating rooms and installation process thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201310009678 CN103061544A (en) 2013-01-11 2013-01-11 Plug fast-installation auxiliary room for clean operating rooms and installation process thereof

Publications (1)

Publication Number Publication Date
CN103061544A true CN103061544A (en) 2013-04-24

Family

ID=48104406

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201310009678 Withdrawn CN103061544A (en) 2013-01-11 2013-01-11 Plug fast-installation auxiliary room for clean operating rooms and installation process thereof

Country Status (1)

Country Link
CN (1) CN103061544A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103225427A (en) * 2013-04-26 2013-07-31 苏州通快净化科技有限公司 Plug and fast mounting clean operation room assisted room and mounting technology thereof
CN108867878A (en) * 2018-08-31 2018-11-23 江苏达实久信医疗科技有限公司 Modular surgical room
CN110528916A (en) * 2019-09-18 2019-12-03 广州海洁尔医疗设备有限公司 A kind of pin-connected panel operating room
CN112796550A (en) * 2020-12-31 2021-05-14 深圳市美日净化科技有限公司 Clean shed convenient to build
CN114351868A (en) * 2022-01-26 2022-04-15 刘大为 Assembled construction body, assembling method of assembled construction body and house assembling method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103225427A (en) * 2013-04-26 2013-07-31 苏州通快净化科技有限公司 Plug and fast mounting clean operation room assisted room and mounting technology thereof
CN108867878A (en) * 2018-08-31 2018-11-23 江苏达实久信医疗科技有限公司 Modular surgical room
CN110528916A (en) * 2019-09-18 2019-12-03 广州海洁尔医疗设备有限公司 A kind of pin-connected panel operating room
CN112796550A (en) * 2020-12-31 2021-05-14 深圳市美日净化科技有限公司 Clean shed convenient to build
CN114351868A (en) * 2022-01-26 2022-04-15 刘大为 Assembled construction body, assembling method of assembled construction body and house assembling method

Similar Documents

Publication Publication Date Title
CN104775522B (en) A kind of detachable house box
CN103225427A (en) Plug and fast mounting clean operation room assisted room and mounting technology thereof
CN103061544A (en) Plug fast-installation auxiliary room for clean operating rooms and installation process thereof
CN101949212B (en) Slabform detachable support system and construction method thereof
US10006212B2 (en) Assembled house
CN203238991U (en) Clean operating room auxiliary room capable of being quickly assembled in insertion mode
JP2012517361A (en) Modular building construction equipment
CN104532735A (en) Assembly type steel bridge and building method thereof
CN104120811B (en) A kind of metal decking unit curtain wall system
WO2019128291A1 (en) Double-layer stepped suspended ceiling and mounting method
KR101388823B1 (en) Form device
CN106013784A (en) Angle iron frame template and construction method
CN109457955A (en) Prefabricated stacking floor support system
JP2014198963A (en) Panel replacement method
KR101658954B1 (en) Light weight lattice shape-retaining double bottom structure of the floor
JP6970610B2 (en) Building construction method
CN209799469U (en) Box-type room maintenance ground and box-type room
CN205348965U (en) Enclose and keep off sideboard and quick assembly disassembly who constitutes encloses fender thereof
CN210976594U (en) Auxiliary mounting device for laminated plate
CN106320692A (en) Building splicing formwork
CN210164280U (en) Node is installed additional to stand on girder steel
CN208950194U (en) A kind of assembled stair
CN103216087B (en) A kind of two-way self-bearing type construction formwork system
CN108125535B (en) Modular curtain box and installation method
CN206418796U (en) A kind of normal formula pipe combination supporting system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C04 Withdrawal of patent application after publication (patent law 2001)
WW01 Invention patent application withdrawn after publication

Application publication date: 20130424