CN102966016A - Internal double-layer prefabricated traffic lane structure of shield tunnel - Google Patents

Internal double-layer prefabricated traffic lane structure of shield tunnel Download PDF

Info

Publication number
CN102966016A
CN102966016A CN2012105528518A CN201210552851A CN102966016A CN 102966016 A CN102966016 A CN 102966016A CN 2012105528518 A CN2012105528518 A CN 2012105528518A CN 201210552851 A CN201210552851 A CN 201210552851A CN 102966016 A CN102966016 A CN 102966016A
Authority
CN
China
Prior art keywords
track
upper strata
lane
longeron
precast plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012105528518A
Other languages
Chinese (zh)
Other versions
CN102966016B (en
Inventor
黄�俊
徐国平
李勇
权县民
刘洪洲
刘明虎
张亚果
赵光
刘昌鹏
王善高
马明
陈佳
张忠宇
黄清飞
陈虎成
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CCCC Highway Consultants Co Ltd
Original Assignee
CCCC Highway Consultants Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CCCC Highway Consultants Co Ltd filed Critical CCCC Highway Consultants Co Ltd
Priority to CN201210552851.8A priority Critical patent/CN102966016B/en
Publication of CN102966016A publication Critical patent/CN102966016A/en
Application granted granted Critical
Publication of CN102966016B publication Critical patent/CN102966016B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The invention provides an internal double-layer prefabricated traffic lane structure of a shield tunnel. The internal double-layer prefabricated traffic lane structure mainly comprises a square fabricated component of a lower lane, a lane foundation, a vertical column of an upper lane, a lane column contact beam, a vertical beam of the upper lane and an upper fabricated lane board, wherein concrete foundations are cast at the both sides of the square fabricated component of the lower lane, so as to form a lower lane road surface structure and a lane foundation structure; the vertical column of the upper lane, the lane column contact beam and the upper fabricated lane board form a cast-in-place reinforced concrete structure; brackets are arranged at the inner side of the vertical beam of the upper lane; and the upper lane column contact beam is erected across the brackets at the inner side of the vertical beam of the upper lane, so as to form an entire structure by casting concrete. According to the internal double-layer prefabricated traffic lane structure provided by the invention, the standardization, the module production and the rapid construction speed can be realized, so that the large amount of labor and materials in field construction can be saved, and the better social benefits can be obtained.

Description

The inner double-deck prefabricated runway structure of a kind of shield tunnel
Technical field
The present invention relates to tunnel and bridge technology field, relate to particularly a kind of structure of the prefabricated units that in the inner double-deck runway of shield tunnel, adopt.
Background technology
Along with the exploitation of urban underground space, major diameter, long-distance shield structure method tunnel have obtained a large amount of application in the construction of city expressway.The tunnel railway network planning constantly increases, and the tunnel channel condition is more complicated, and present river, the tunnel over strait crossed be all toward the future development such as dark, large, long, difficult, constructing tunnel has occurred that difficulty is large, complex process, long in time limit, a series of difficult points such as have a big risk.
The inner double decked lanes structure of shield structure is generally cast-in-place concrete structure.Many modes that chassis is constructed simultaneously of the general employing of concrete cast-in-situ construction, every section construction all need be carried out the work such as chassis location, assembling reinforcement, concreting, curing concrete, form removal, and the constructor who needs is numerous.The shield tunnel inner space is narrow and small, and personnel are intensive, and equipment is numerous, and when the inner lane structure of shield structure and shield structure synchronous construction, the construction organization difficulty is large, and potential safety hazard is many.
The concrete cast-in-situ working procedure is many, long construction period, and speed of application is slower.For solving the speed of application problem, must address this problem from method for designing." prefabricated, modularization " is frontline technology and the developing direction of at present design and construction, be prefabricated units with the primary structure member designs, adopt mechanized construction, pipelining, saving manpower, reducing in the tunnel aspect such as cast-in-place construction amount larger advantage is arranged, it is the important channel of accelerating speed of application.
Summary of the invention
The object of the present invention is to provide the inner double-deck prefabricated runway structure of a kind of shield tunnel, to adapt to the requirement of present rapid construction.
For achieving the above object, the inner double-deck prefabricated runway structure of shield tunnel provided by the invention, it mainly comprises:
The square shape prefabricated units of flyunder, basis, track, track, upper strata column, track post contact beam, the prefabricated lane plate of track, upper strata longeron and upper strata; Wherein:
The concreting basis, square shape prefabricated units both sides of flyunder forms flyunder road structure and track foundation structure;
Track, upper strata column, track post contact beam and track, upper strata longeron are monolithic reinforced concrete structure, and longeron inboard, track, upper strata is provided with bracket;
Track, upper strata precast plate crossbearer forms overall structure by rear pouring concrete on the bracket of longeron inboard, track, upper strata.
The inner double-deck prefabricated runway structure of described shield tunnel, wherein, track, upper strata precast plate is hollowcore slab.
The inner double-deck prefabricated runway structure of described shield tunnel, wherein, the two ends of track, upper strata precast plate and longeron top, track, upper strata are reserved with reinforcing bar, and track, upper strata precast plate crossbearer forms overall structure by reserved steel bar and rear pouring concrete on the bracket of longeron inboard, track, upper strata the time.
The inner double-deck prefabricated runway structure of described shield tunnel, wherein, track, upper strata precast plate crossbearer is on the bracket of longeron inboard, track, upper strata the time, leave hinge seam between the side of track, per two upper stratas precast plate, make between the precast plate of track, upper strata by rear pouring concrete during installation to form overall structure.
The present invention has realized the form of construction work of assembly unit in outer prefabricated, the tunnel of shield tunnel inside lane structure tunnel, has reduced the tunnel internal constructor, has accelerated the lane structure speed of application, has realized that tunnel piercing and internal construction are synchronous, the breakthrough of rapid construction.
Description of drawings
Fig. 1 is flyunder layout plan of the present invention;
Fig. 2 is track of the present invention sectional drawing;
Fig. 3 is track, upper strata of the present invention layout plan;
Fig. 4 is track, upper strata of the present invention precast plate cross-sectional view (middle span precast plate);
Fig. 5 is track, upper strata of the present invention precast plate cross-sectional view (end bay precast plate).
Sign flag explanation in the accompanying drawing:
1 square shape prefabricated units, basis, 2 tracks, track, 3 upper strata column, track, 4 upper strata precast plate, 5 hinge seams, 6 deformation joints, track, 7 upper strata longeron, longeron delay-pour joint district, 8 track, 9 reserve connecting reinforcement, 10 track longeron brackets, 11 track post contact beams.
The specific embodiment
Provided by the invention for the prefabricated structure of the double-deck runway in shield tunnel inside, in this structure, the method for track, prefabricated upper strata precast plate outside the tunnel has been adopted in the track, upper strata; Track, upper strata column, track post contact beam, track, upper strata longeron are cast-in-place structural; Track, upper strata precast plate is connected by reserved steel bar with track, upper strata longeron, track, upper strata column, and is connected to form structural entity by rear pouring concrete.Be connected to form integral body by the hinge seam between the precast plate of track, upper strata.
Specifically, technical solution of the present invention is:
The structure design that flyunder adopts the square shape prefabricated units to combine with basis, cast-in-place track; Track, upper strata column and track, upper strata longeron adopt monolithic reinforced concrete structure; The structure design of watering behind prefabricated lane plate+beam slab node is adopted in the track, upper strata, and track, upper strata precast plate and track, upper strata longeron form overall structure by reserved steel bar and rear pouring concrete.Adopt the hinge seam to connect between the precast plate of track, upper strata.
Flyunder structure of the present invention comprises square shape prefabricated units and basis, track two parts, flyunder is hoisting port font prefabricated units at first, then implant the track reinforcement foundation at square shape prefabricated units both sides shield duct piece, concreting forms complete flyunder and track basis.The square shape prefabricated units are precast reinforced concrete structure.
Track, upper strata of the present invention precast plate is pre-fabricated reinforced concrete hollow plate, and two ends are reserved with reinforcing bar, and reinforcing bar and track, the upper strata longeron reserved by two ends are connected to become integral body by rear pouring concrete.Adopt the hinge seam to be connected to become integral body between the precast plate of track, upper strata.
Track, upper strata of the present invention longeron is built at twice, and track, upper strata longeron is reserved the link position of track, upper strata precast plate in advance when building for the first time, and longeron inboard, track, upper strata arranges bracket, is used for lifting track, upper strata precast plate; Building for the second time is that track, upper strata longeron and track, upper strata precast plate are connected to become integral body.
The present invention is specially adapted to the rapid construction of the inner double decked lanes structure of shield tunnel.
Embodiment:
1) referring to Fig. 1, at the flyunder square shape prefabricated units 1 of mating formation;
2) referring to Fig. 2, build in the square shape prefabricated units both sides that flyunder has been mated formation basis, track 2, track, upper strata column 3, track post contact beam 11, with track, upper strata longeron 7, longeron 7 inboards, track, upper strata arrange track longeron bracket 10 (as shown in Figure 4);
3) referring to Fig. 2 and Fig. 3, hang oneself on basis, track, upper strata 2 and to load onto a layer track precast plate 4.When lifting track, upper strata precast plate 4, leave working hinge seam 5 between track, the per two upper stratas precast plate 4, wait lift finish after hinge between track, upper strata precast plate 4 stitch 5 place's concretings, and at track, upper strata precast plate 4 and track, upper strata longeron 7 delay-pour joint districts 8 place's concretings, make between track, the upper strata precast plate 4, and form overall structure between track, upper strata precast plate 4 and track, the upper strata longeron 7.
4) repeat above-mentioned steps 1-3, can realize the rapid construction of double-deck runway structure.

Claims (4)

1. the inner double-deck prefabricated runway structure of a shield tunnel, it mainly comprises:
The square shape prefabricated units of flyunder, basis, track, track, upper strata column, track post contact beam, the prefabricated lane plate of track, upper strata longeron and upper strata; Wherein:
The concreting basis, square shape prefabricated units both sides of flyunder forms flyunder road structure and track foundation structure;
Track, upper strata column, track post contact beam and track, upper strata longeron are monolithic reinforced concrete structure, and longeron inboard, track, upper strata is provided with bracket;
Track, upper strata precast plate crossbearer forms overall structure by rear pouring concrete on the bracket of the inboard of track, upper strata longeron.
2. the inner double-deck prefabricated runway structure of shield tunnel according to claim 1, wherein, track, upper strata precast plate is hollowcore slab.
3. the inner double-deck prefabricated runway structure of shield tunnel according to claim 1 and 2, wherein, the two ends of track, upper strata precast plate and longeron top, track, upper strata are reserved with reinforcing bar, track, upper strata precast plate crossbearer forms overall structure by reserved steel bar and rear pouring concrete on the bracket of longeron inboard, track, upper strata the time.
4. the inner double-deck prefabricated runway structure of shield tunnel according to claim 1, wherein, track, upper strata precast plate crossbearer is on the bracket of longeron inboard, track, upper strata the time, leave hinge seam between the side of track, per two upper stratas precast plate, make between the precast plate of track, upper strata by rear pouring concrete during installation to form overall structure.
CN201210552851.8A 2012-12-18 2012-12-18 The prefabricated runway structure of a kind of shield tunnel internal double layers Expired - Fee Related CN102966016B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210552851.8A CN102966016B (en) 2012-12-18 2012-12-18 The prefabricated runway structure of a kind of shield tunnel internal double layers

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210552851.8A CN102966016B (en) 2012-12-18 2012-12-18 The prefabricated runway structure of a kind of shield tunnel internal double layers

Publications (2)

Publication Number Publication Date
CN102966016A true CN102966016A (en) 2013-03-13
CN102966016B CN102966016B (en) 2016-01-13

Family

ID=47796430

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210552851.8A Expired - Fee Related CN102966016B (en) 2012-12-18 2012-12-18 The prefabricated runway structure of a kind of shield tunnel internal double layers

Country Status (1)

Country Link
CN (1) CN102966016B (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104564101A (en) * 2015-01-14 2015-04-29 中交第二航务工程局有限公司 Single-tube double-layer tunnel simultaneous construction method
CN106400629A (en) * 2016-10-17 2017-02-15 上海市政工程设计研究总院(集团)有限公司 Round-tunnel double-layer lane frame structure system and full-prefabricated construction method thereof
CN106436513A (en) * 2016-10-17 2017-02-22 上海市政工程设计研究总院(集团)有限公司 Round tunnel double-decked lane frame structured system and fully-prefabricated construction method thereof
CN108194095A (en) * 2018-03-20 2018-06-22 上海市城市建设设计研究总院(集团)有限公司 The prefabricated superposed type vehicle driving passage structure of subterranean tunnel or gallery
CN108756933A (en) * 2018-04-27 2018-11-06 同济大学 A kind of bellows-type quick connecting method of double layer tunnel inside prefabricated components
CN109751061A (en) * 2019-03-26 2019-05-14 西南交通大学 A kind of combined highway and metro single-tube double-layer shield tunnel
CN110374623A (en) * 2019-08-07 2019-10-25 上海市机械施工集团有限公司 Prefabricated platform and its installation method
CN113417671A (en) * 2021-08-06 2021-09-21 中交(广州)建设有限公司 Construction method for quickly assembling prefabricated parts in shield tunnel
CN113503176A (en) * 2021-08-06 2021-10-15 中交(广州)建设有限公司 Integrated intelligent assembling trolley for prefabricated parts in tunnel

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0097113A2 (en) * 1982-06-16 1983-12-28 Wayss & Freytag Aktiengesellschaft Method of driving a tunnel in stressed rock
JP2003064994A (en) * 2001-08-27 2003-03-05 Nippon Koatsu Concrete Kk Invert
JP3458176B2 (en) * 2000-09-20 2003-10-20 大成建設株式会社 Construction method of floor slab in tunnel
CN2856417Y (en) * 2005-12-27 2007-01-10 上海市隧道工程轨道交通设计研究院 Dual-layer round tunnel with deforming controller
CN101294495A (en) * 2008-06-25 2008-10-29 上海隧道工程股份有限公司 Tunnel shield propulsion and inside double-layer road synchronous construction method
KR100980798B1 (en) * 2010-03-11 2010-09-10 이형훈 Precast slab construction method for large section ground tunnel
CN203021884U (en) * 2012-12-18 2013-06-26 中交公路规划设计院有限公司 Internal double-layer prefabricated carriageway structure of shield tunnel

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0097113A2 (en) * 1982-06-16 1983-12-28 Wayss & Freytag Aktiengesellschaft Method of driving a tunnel in stressed rock
JP3458176B2 (en) * 2000-09-20 2003-10-20 大成建設株式会社 Construction method of floor slab in tunnel
JP2003064994A (en) * 2001-08-27 2003-03-05 Nippon Koatsu Concrete Kk Invert
CN2856417Y (en) * 2005-12-27 2007-01-10 上海市隧道工程轨道交通设计研究院 Dual-layer round tunnel with deforming controller
CN101294495A (en) * 2008-06-25 2008-10-29 上海隧道工程股份有限公司 Tunnel shield propulsion and inside double-layer road synchronous construction method
KR100980798B1 (en) * 2010-03-11 2010-09-10 이형훈 Precast slab construction method for large section ground tunnel
CN203021884U (en) * 2012-12-18 2013-06-26 中交公路规划设计院有限公司 Internal double-layer prefabricated carriageway structure of shield tunnel

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
杨继范: "双层越江隧道上层道路的施工技术", 《现代隧道技术》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104564101A (en) * 2015-01-14 2015-04-29 中交第二航务工程局有限公司 Single-tube double-layer tunnel simultaneous construction method
CN106400629A (en) * 2016-10-17 2017-02-15 上海市政工程设计研究总院(集团)有限公司 Round-tunnel double-layer lane frame structure system and full-prefabricated construction method thereof
CN106436513A (en) * 2016-10-17 2017-02-22 上海市政工程设计研究总院(集团)有限公司 Round tunnel double-decked lane frame structured system and fully-prefabricated construction method thereof
CN108194095A (en) * 2018-03-20 2018-06-22 上海市城市建设设计研究总院(集团)有限公司 The prefabricated superposed type vehicle driving passage structure of subterranean tunnel or gallery
CN108756933A (en) * 2018-04-27 2018-11-06 同济大学 A kind of bellows-type quick connecting method of double layer tunnel inside prefabricated components
CN109751061A (en) * 2019-03-26 2019-05-14 西南交通大学 A kind of combined highway and metro single-tube double-layer shield tunnel
CN109751061B (en) * 2019-03-26 2023-10-17 西南交通大学 Single-pipe double-layer shield tunnel built by common rail and common rail
CN110374623A (en) * 2019-08-07 2019-10-25 上海市机械施工集团有限公司 Prefabricated platform and its installation method
CN110374623B (en) * 2019-08-07 2021-10-15 上海市机械施工集团有限公司 Prefabricated platform and installation method thereof
CN113417671A (en) * 2021-08-06 2021-09-21 中交(广州)建设有限公司 Construction method for quickly assembling prefabricated parts in shield tunnel
CN113503176A (en) * 2021-08-06 2021-10-15 中交(广州)建设有限公司 Integrated intelligent assembling trolley for prefabricated parts in tunnel

Also Published As

Publication number Publication date
CN102966016B (en) 2016-01-13

Similar Documents

Publication Publication Date Title
CN102966016B (en) The prefabricated runway structure of a kind of shield tunnel internal double layers
CN105089669B (en) A kind of underground station of use prefabricated parts and its construction method
CN203021884U (en) Internal double-layer prefabricated carriageway structure of shield tunnel
CN107119711B (en) Connecting structure for large-range adjacent existing transfer station and construction method
CN102767141B (en) Construction method for huge capping beam utilizing reinforced concrete thin wall as permanent formwork
CN108867310A (en) The short rib T beam bridge of pretensioning prestressed concrete and its construction method
CN106978777B (en) A kind of make-shift bridge device
CN112609912B (en) Construction method for newly building canopy in overhead operation subway station
CN211257077U (en) Prefabricated assembly and cast-in-place utility tunnel who mixes construction
CN104032854A (en) Assembly-type T-shaped mixed coupled wall and construction method thereof
CN103850171B (en) A kind of all steel assembled overpass on an empty stomach
CN108086353A (en) Hollow wall plate mixed prefabricated assembly type comprehensive pipe gallery spliced by cast-in-place hidden beams and construction method thereof
CN214005379U (en) Prefabricated part for expanding existing elevated operation subway station platform
CN113073540A (en) Pile-beam integrated fully-prefabricated assembled bridge substructure, bridge and construction method thereof
CN204920961U (en) Adopt underground station of prefabricated component construction
CN115094949A (en) Construction method of assembly type subway station with permanently-adjacent combination of enclosure and main body
CN112610244B (en) Prefabricated part for expanding existing elevated operation subway station platform and installation method thereof
CN214195056U (en) Prefabricated shear wall with assembling holes arranged in staggered mode reserved in assembling mode and assembling structure of prefabricated shear wall
CN203905215U (en) Assembled type steel beam joint straight-line-shaped blend coupled wall
CN104912200B (en) Building method of underground shallow layer fully automatic parking garage
CN102444089B (en) Prefabricated part assembled windproof open cut tunnel in gale region and joint assembling and connecting method thereof
CN104032859A (en) Assembly-type L-shaped mixed coupled wall and construction method thereof
CN215252255U (en) Pile-beam integrated fully-prefabricated assembled bridge substructure and bridge
CN104032863B (en) Assembled in-line mixing coupled wall and construction method thereof
CN113668388B (en) Pier-beam collaborative integral rapid installation and removal method based on vehicle-mounted equipment

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20160113

Termination date: 20171218