CN102872647A CN2012103958066A CN201210395806A CN102872647A CN 102872647 A CN102872647 A CN 102872647A CN 2012103958066 A CN2012103958066 A CN 2012103958066A CN 201210395806 A CN201210395806 A CN 201210395806A CN 102872647 A CN102872647 A CN 102872647A
Authority
CN
China
Prior art keywords
coal
gutter
waste water
catch pit
pump
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103958066A
Other languages
Chinese (zh)
Inventor
涂昌德
逯桂平
刘建平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Original Assignee
Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuhan Design and Research Institute of China Coal Technology and Engineering Group filed Critical Wuhan Design and Research Institute of China Coal Technology and Engineering Group
Priority to CN2012103958066A priority Critical patent/CN102872647A/en
Publication of CN102872647A publication Critical patent/CN102872647A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Separation Of Suspended Particles By Flocculating Agents (AREA)

Abstract

The invention discloses a long-distance pipeline coal transporting head-end wastewater treatment system and a treatment method. The system comprises a drainage ditch, a water collection pit, a sweeping pump, a waste slurry pool, a submersible slurry pump and a coal-dressing concentration workshop, wherein washed wastewater is collected to the drainage ditch through a trench or a pipe, the water collection pit is connected with the waste slurry pool through the pipe, wastewater in the water collection pit is transferred to the waste slurry pool through the sweeping pump, and the waste slurry pool is connected with the coal-dressing concentration workshop through the submersible slurry pump and the pipe. The washed wastewater treatment system and method disclosed by the invention are wide in application scope and easy to operate, and can greatly reduce the operation cost of deep treatment; the recovery rate of wastewater is more than 95%; colors, odors and most of organic pollutants and poisonous heavy metal substances in water can he effectively removed, thereby reducing the turbidity of water; and the system and method disclosed by the invention are economic and reasonable, low in energy consumption, and widely used in the coal water slurry pipeline transporting industry.

Description

The defeated coal head end Waste Water Treatment of long-distance pipe and processing method
Technical field
The present invention relates to wastewater treatment, be specifically related to the defeated coal head end Waste Water Treatment of long-distance pipe and processing method.
Background technology
In general, on the one hand, the present sewage treatment capacity of China does not still catch up with the rapid expansion of water scale, and the auxiliary facility construction such as pipe network, Treatment of Sludge seriously lag behind.On the other hand, the wastewater treatment rate of China also exist obvious gap, and the rate of load condensate for the treatment of facility is low compared with developed countries.
Wastewater treatment in China is experiencing by small scale, level is low, kind is single, seriously can not satisfy the demands to has the deep transformation that considerable scale and level, variety and quality significantly improved and tentatively satisfied national economic development requirement, and the sewage disposal demand will progressively realize self-sufficiency.Although because country and governments at all levels are to the improving constantly of environmental protection attention degree, Chinese sewage treatment industry is just at rapid growth, the sewage disposal total amount increases year by year, and the town sewage handling rate improves constantly.But present Chinese sewage treatment industry still is in the primary stage of development.
Summary of the invention
The purpose of this invention is to provide a kind of simple in structurely, easy to operate, improve to greatest extent the flushing waste water treatment system of the defeated coal slurry head end of pipe of coal recovery rate.
Another object of the present invention provides method of wastewater treatment.
In order to overcome the deficiencies in the prior art, technical solution of the present invention is to solve like this: the defeated coal head end Waste Water Treatment of a kind of long-distance pipe comprises the gutter, catch pit, the slag stock pump, useless stock tank, coal separation concentrates the workshop, special character of the present invention is that described flushing waste water is pooled to the gutter along ground line gradient, described gutter is connected with catch pit by pipeline, described catch pit is connected with useless stock tank by sweep the floor pump and pipeline, and described useless stock tank is connected with the concentrated workshop of coal separation by diving slurry pump and pipeline.
A kind of method of wastewater treatment of described system, carry out successively in the steps below:
1), does the gutter at gatehead and slurrying surge bunker bottom architecture indoor below ground, the collection flushing waste water;
2), flushing waste water imports indoor catch pit after collect in the gutter, establish grid or screen pack in the catch pit;
3), the black water in the waste water through the gutter, grid or the screen pack precipitation of catch pit, hold back, contain the less waste water of coal slime in the useless stock tank and be delivered to the concentrated workshop recycling of head end coal separation by diving slurry pump;
4), hold back with the coal slime periodic cleaning that precipitates to the recycling of coal slime pond in gutter, catch pit, the useless stock tank.
The present invention compared with prior art, this each inter process of flushing waste water treatment system is rationally distributed, procedure connection is good, uses this system and can reclaim fully coal slime in the waste water, improves coal recovery rate.Be widely used in the water-coal-slurry pipeline carrier have simple in structure, easy to operate, environmental protection, energy-saving and emission-reduction and improve to greatest extent the order of coal recovery rate.
Description of drawings:
Fig. 1 is Waste Water Treatment structural representation of the present invention.
Among the figure: the 1-flushing waste water, the 2-gutter, 3-catch pit, 4-one slag stock pump, the 5-stock tank that gives up, the 6-diving slurry pump, the 7-coal separation concentrates the workshop, 8-coal slime pond.
The specific embodiment
Accompanying drawing is embodiments of the invention.
Below in conjunction with accompanying drawing content of the present invention is further described:
With reference to Fig. 1, the defeated coal head end Waste Water Treatment of a kind of long-distance pipe comprises the gutter, catch pit, the pump of sweeping the floor, useless stock tank, coal separation concentrates the workshop, described flushing waste water 1 is pooled to gutter 2 along ground line gradient, described gutter 2 is connected with catch pit 3 by pipeline, and described catch pit 3 is connected with useless stock tank 5 by sweep the floor pump 4 and pipeline, and the described pond 5 of transferring is connected with the concentrated workshop 7 of coal separation by diving slurry pump 6 and pipeline.
A kind of method of wastewater treatment of described system, carry out successively in the steps below:
1), does gutter 2 at gatehead and slurrying surge bunker bottom architecture indoor below ground, collection flushing waste water 1;
2), flushing waste water 1 imports indoor catch pit 3 after collect in gutter 2, establish grid or screen pack in the catch pit 3;
3), the black water in the waste water 1 through the gutter 2, grid or the screen pack precipitation of catch pit 3, hold back, contain the less waste water of coal slime in the useless stock tank 5 and be delivered to concentrated workshop 7 recyclings of head end coal separation by another diving slurry pump 6;
4), hold back in gutter 2, catch pit 3, the useless stock tank 5 with the coal slime periodic cleaning that precipitates to coal slime pond 8, recycle.
In sum, the defeated coal head end Waste Water Treatment of long-distance pipe involved in the present invention and processing method, rationally distributed between device, be connected good between technique, the flushing waste water major impurity is coal slime, cinder and a small amount of greasy dirt, according to current specifications and practical experience, take first certain measure to hold back the bulk cinder, hold back and contain the less waste water of coal slime behind the cinder and discharged by water pump single tube pressure, finally enter the flushing waste water treating stations and focus on reuse, the auxiliary facility of pipe network and Treatment of Sludge is advanced, and the rate of load condensate for the treatment of facility is high.
The above has carried out exemplary description to the present invention by reference to the accompanying drawings; obvious realization of the present invention is not subjected to the restriction of aforesaid way; as long as the various improvement of having adopted device design of the present invention and technical scheme to carry out; or without improving design of the present invention and technical scheme are directly applied to other occasion, all in protection scope of the present invention.

Claims (2)

1. a long-distance pipe is failed coal head end Waste Water Treatment, this system comprises the gutter, catch pit, the pump of sweeping the floor, useless stock tank, diving slurry pump, coal separation concentrates the workshop, it is characterized in that described flushing waste water (1) is pooled to gutter (2) along ground line gradient, described gutter (2) is connected with catch pit (3) by pipeline, described catch pit (3) is connected with useless stock tank (5) by the pump of sweeping the floor (4) and pipeline, and described useless stock tank (5) is connected with the concentrated workshop (7) of coal separation by diving slurry pump (6) and pipeline.
2. method of wastewater treatment of system as claimed in claim 1, carry out successively in the steps below:
1), does gutter (2) at gatehead and slurrying surge bunker bottom architecture indoor below ground, collection flushing waste water (1);
2), flushing waste water (1) remittance indoor catch pit (3) after collect gutter (2), catch pit is established grid or screen pack in (3);
3), grid or the screen pack precipitation of body refuse (2), catch pit (3) through the gutter in the flushing waste water (1), hold back, contain the less waste water of coal slime in the useless stock tank (5) and be delivered to the head end coal separation by diving slurry pump (6) and concentrate workshop (7) recycling;
4), hold back with the coal slime periodic cleaning that precipitates to coal slime pond (8) recycling in gutter (2), catch pit (3), the useless stock tank (5).
CN2012103958066A 2012-10-18 2012-10-18 Long-distance pipeline coal transporting head-end wastewater treatment system and treatment method Pending CN102872647A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103958066A CN102872647A (en) 2012-10-18 2012-10-18 Long-distance pipeline coal transporting head-end wastewater treatment system and treatment method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103958066A CN102872647A (en) 2012-10-18 2012-10-18 Long-distance pipeline coal transporting head-end wastewater treatment system and treatment method

Publications (1)

Publication Number Publication Date
CN102872647A true CN102872647A (en) 2013-01-16

Family

ID=47474296

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103958066A Pending CN102872647A (en) 2012-10-18 2012-10-18 Long-distance pipeline coal transporting head-end wastewater treatment system and treatment method

Country Status (1)

Country Link
CN (1) CN102872647A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105107238A (en) * 2015-07-30 2015-12-02 江苏金曼科技有限责任公司 Recycling device in production of formaldehyde-free soybean meal-based adhesive
CN107376505A (en) * 2017-09-15 2017-11-24 贺州市骏鑫矿产品有限责任公司 A kind of feldspar in powder produces waste recycle system
CN110523333A (en) * 2019-09-19 2019-12-03 中煤科工集团武汉设计研究院有限公司 A kind of pipeline moulded coal slurry recyclable device and its recovery method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101586404A (en) * 2008-05-19 2009-11-25 贵阳铝镁设计研究院 Plane layout method for coal pile yard area
CN101723543A (en) * 2008-10-10 2010-06-09 朱艳玲 Method for treating domestic wastewater
KR101106778B1 (en) * 2011-05-24 2012-01-18 한국바이오시스템(주) Wastewater treatment apparatus for public facilities and apartment house by natural purification and wastewater treatment method and water circulation system using the wastewater treatment apparatus
CN102407048A (en) * 2011-09-29 2012-04-11 山西潞安环保能源开发股份有限公司 Underground coal slime water processing system
CN202865022U (en) * 2012-10-18 2013-04-10 中煤科工集团武汉设计研究院 Wastewater treatment system of long-distance pipeline coal conveying head end

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101586404A (en) * 2008-05-19 2009-11-25 贵阳铝镁设计研究院 Plane layout method for coal pile yard area
CN101723543A (en) * 2008-10-10 2010-06-09 朱艳玲 Method for treating domestic wastewater
KR101106778B1 (en) * 2011-05-24 2012-01-18 한국바이오시스템(주) Wastewater treatment apparatus for public facilities and apartment house by natural purification and wastewater treatment method and water circulation system using the wastewater treatment apparatus
CN102407048A (en) * 2011-09-29 2012-04-11 山西潞安环保能源开发股份有限公司 Underground coal slime water processing system
CN202865022U (en) * 2012-10-18 2013-04-10 中煤科工集团武汉设计研究院 Wastewater treatment system of long-distance pipeline coal conveying head end

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘龙海: "《输煤冲洗废水回收处理***》", 《江苏电机工程》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105107238A (en) * 2015-07-30 2015-12-02 江苏金曼科技有限责任公司 Recycling device in production of formaldehyde-free soybean meal-based adhesive
CN107376505A (en) * 2017-09-15 2017-11-24 贺州市骏鑫矿产品有限责任公司 A kind of feldspar in powder produces waste recycle system
CN107376505B (en) * 2017-09-15 2018-07-31 贺州市骏鑫矿产品有限责任公司 A kind of feldspar in powder production waste recycle system
CN110523333A (en) * 2019-09-19 2019-12-03 中煤科工集团武汉设计研究院有限公司 A kind of pipeline moulded coal slurry recyclable device and its recovery method
CN110523333B (en) * 2019-09-19 2020-09-04 中煤科工集团武汉设计研究院有限公司 Pipeline conveying type coal slurry recycling device and recycling method thereof

Similar Documents

Publication Publication Date Title
CN204939112U (en) A kind of waste disposal plant
CN206233333U (en) Initial rainwater filtering, precipitating, discarding and collecting treatment system
CN202000464U (en) Automatic purification rainwater inspection well
CN203419813U (en) Comprehensive treatment system of rural environment
CN102872647A (en) Long-distance pipeline coal transporting head-end wastewater treatment system and treatment method
CN203568938U (en) Domestic sewage treatment system
CN206027235U (en) Domestic sewage treatment device
CN205024802U (en) Energy -saving rainwater recycling system
CN202865022U (en) Wastewater treatment system of long-distance pipeline coal conveying head end
CN203568940U (en) Pulping sewage recycling system
CN107162330A (en) Solar energy moving bed biological strengthens ecological purified water system
CN208650180U (en) A kind of sanitary sewage centralized collection device of hydroelectric project underground power house
CN112661358A (en) Thermal power plant waste water grading comprehensive treatment system
CN102155036A (en) Engineering rainfall or rainwater recycling system
CN201605173U (en) Waste water recycling device for power plant
CN205088035U (en) Novel desulfurization wastewater treatment system
CN204219842U (en) A kind of potassium permanganate composites
CN205613097U (en) Rainwater continuous precipitation separator
CN205516723U (en) Rain -proof industry effluent water sump
CN213895440U (en) Copper resin desorption system for copper wastewater treatment
CN204058089U (en) Seasonal high turbid original sub-block device
CN111622326B (en) Sponge city rainwater regeneration utilizes device
CN205151863U (en) Sewage treatment system that purification efficiency is high
CN210367352U (en) Sewage emission reduction system of phthalic anhydride device
CN202090381U (en) System for recycling engineering dewatering and rain water

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130116