CN102856839A - 架线施工撩线器 - Google Patents

架线施工撩线器 Download PDF

Info

Publication number
CN102856839A
CN102856839A CN2012103269824A CN201210326982A CN102856839A CN 102856839 A CN102856839 A CN 102856839A CN 2012103269824 A CN2012103269824 A CN 2012103269824A CN 201210326982 A CN201210326982 A CN 201210326982A CN 102856839 A CN102856839 A CN 102856839A
Authority
CN
China
Prior art keywords
stay pipe
line device
raising
construction
anchor ear
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012103269824A
Other languages
English (en)
Inventor
唐钧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
State Grid Hebei Electric Power Co Ltd
Baoding Power Supply Co of State Grid Hebei Electric Power Co Ltd
Original Assignee
Baoding Power Supply Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Baoding Power Supply Co Ltd filed Critical Baoding Power Supply Co Ltd
Priority to CN2012103269824A priority Critical patent/CN102856839A/zh
Publication of CN102856839A publication Critical patent/CN102856839A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Electric Cable Installation (AREA)

Abstract

本发明公开了一种架线施工撩线器,在撩线器下部装一可固定在圆形杆塔上的抱箍,架线支撑管相对固定在抱箍上,支撑管通过升降螺杆分成上下两段,上段***一个可上、下移动的调整杆,调整杆上安装容纳导线的U型导线槽,导线槽侧下部固定有拉环;在支撑管的上段有调整固定长度的卡槽,中部有连续调长度的螺杆、螺母;撩线器结合架空线路施工的特点,综合利用杠杆原理,将特殊场地的高空施工由人工转变为半机械化,提高了工作效率和施工安全性。

Description

架线施工撩线器
技术领域
本发明涉及一种电力施工作业工具,尤其涉及一种用于线路施工的架线施工撩线器。
背景技术
目前,在农业电力网施工中,架线施工与以前相比,发生的明显不同之处就是由于供电负荷的增大,导线截面增加,导线的自重量上升,由此导致架线横担相应加长,中相的直立绝缘子相应加高;上述导线截面尺寸的增大给人力架线施工带来了一定难度,将导线越过横担往每相绝缘子上放置时越来越困难,尤其是中间相绝缘子放置导线更是难上加难,由于导线较重,人工靠手臂外伸不便用力,已经是面临的施工中需解决的一个重要问题,到目前为止,还没有解决这项特殊高空作业的专业工具。 
本发明结合施工现场的特点,利用杠杆组合代替人工手臂撩线,结合实际设计,满足架线过程需要,极大地减轻了工作强度,提高了架线工效。
发明内容
本发明的目的是解决架线施工存在的上述问题,提供一种适用于在35KV以下输电线路施工检修中使用的架线施工撩线器。
为达上述目的,本发明的撩线器由抱箍、上下两段支撑管、升降螺杆、调整杆、U型导线槽组合构成,升降螺杆将支撑管分为上下两段,在下段支撑管的下端部设有一个可固定在圆形杆塔上的抱箍,抱箍由2个带边沿的半圆形扁金属带组成,通过连接孔和支撑管底端部的连接螺栓和轴承将支撑管相对固定在抱箍上;在上段支撑管内***一个可上下移动的调整杆,调整杆的外露端部装有一个转向轴,转向轴上安装U型导线槽,在U型导线槽侧下部固定一个拉环。
在上段支撑管的下端部,装有一个调节撩线器整体长度的升降螺母,升降螺杆上设有防滑螺母。
在上段支撑管上,有一道管壁通透的长槽,在长槽边上有4个等间隔分布卡槽。
在U型导线槽的开口处端部,都开有凹槽,凹槽边上各有一锁孔,两端带孔的栓杆其一端与锁孔活动连接,另一端则可锁定、可打开。
在抱箍的一个半圆形扁金属带的两个边沿部位,各加工一个带螺寇的孔,另一个半圆形扁金属带的对应处只加工相同的圆孔。
由于本发明结合架空线路施工的特点,巧妙的利用了杠杆原理,将特殊场地的施工由人工转变为半机械化,降低了人力施工强度,提高了工作效率和施工安全性。
附图说明
    图 1架线施工撩线器结构示意图;
在图中,1—连接孔、2—锁紧螺钉、3—抱箍、4—连接螺栓、5—轴承、6—升降螺杆、7—防滑螺母、8—升降螺母、9—扳手、10—支撑管、11—调整杆、12—卡槽、13—调整螺丝、14—转向轴、15—U型导线槽、16—拉环、17—锁孔、18—栓杆;
图 2 架线施工撩线器侧视图; 
图 3架线施工撩线器调整杆视图;
在图中,19—圆孔。
具体实施方式
    以下结合附图,对架线施工撩线器及其结构进行详细说明:
由图1、图2可见,架线施工撩线器由抱箍3、上下两段支撑管10、升降螺杆6、调整杆11、U型导线槽15组合构成,升降螺杆6将支撑管10分为上下两段,在下段支撑管10的下端部设有一个可固定在圆形杆塔上的抱箍3,抱箍3由2个形状相同、带边沿的半圆形扁金属带组成,可采用50×5mm的扁铁制做;在抱箍3的两个边沿部位各设有一个带螺寇的孔,另一个抱箍3的对应处只设相同的圆孔,利用2个锁紧螺钉2便可将撩线器的抱箍3固定在输电线路圆形杆塔的任意部位上。
利用抱箍3上连接孔1和下段支撑管10底端部的连接螺栓4和轴承5将下段支撑管10相对固定在抱箍3上;在上段支撑管10内***一个可上下移动的调整杆11,调整杆11的外露端部装有一个转向轴14,转向轴14上安装U型导线槽15,在U型导线槽15侧下部固定一个拉环16,利用绳索牵动拉环16,可以使支撑管10依托抱箍3运动,将放置在U型导线槽15内的架空线路导线送达期望的位置,方便施工作业。
在上段支撑管10的下端部,装有一个可连续调节撩线器整体长度的升降螺母8,升降螺杆6上设有防滑螺母7,旋转升降螺杆6可以连续改变整个支撑管10的有效长度,通过防滑螺母7锁定,为方便旋转在上段支撑管10的下端部设有扳手9。
由图2、图3可见,在上段支撑管10上,有一道管壁通透的长槽,在长槽边上有4个等间隔分布卡槽12;在调整杆11上,设有4个圆孔19,卡槽12、调整螺丝13和圆孔19相配合,可等距离调整调整杆11的外伸长度,每一档可伸长150mm,达到调整撩线器的总长度。
在U型导线槽15的开口处端部,都开有一个凹槽,凹槽边上各设有一锁孔17,两端带孔的栓杆18其一端与锁孔17活动连接,另一端可锁定、可打开,用于施工时方便导线放入、拿出。
在抱箍3的一个半圆形扁金属带的两个边沿部位,各加工一个带螺寇的孔,在另一个半圆形扁金属带的对应处,只加工相同的圆孔,确保锁紧螺钉2对抱箍3的有效固定。
实施例如下
架线施工撩线器可采用轻型金属材料或普通金属材料制作, 以普通金属材料为例,支撑管采用直径33mm钢管,调整杆采用直径27mm钢管,U型导线槽的尺寸为:高50mm、宽40mm,抱箍可采用50×5mm的扁铁制做,架线施工撩线器整体安装后可获得的直线高度为1600~2500mm, 撩线器的轴承、螺栓、螺杆等各部件全部选用标准件,其中采用部件、螺栓、螺母、凹槽、开孔的尺寸以最佳配合为标准,在此不进行详细说明。

Claims (5)

1.一种架线施工撩线器,其特征在于:所述撩线器由抱箍(3)、上下两段支撑管(10)、升降螺杆(6)、调整杆(11)、U型导线槽(15)组合构成,升降螺杆(6)将支撑管(10)分为上下两段,在下段支撑管(10)的下端部设有一个可固定在圆形杆塔上的抱箍(3),抱箍(3)由2个带边沿的半圆形扁金属带组成,通过连接孔(1)和支撑管(10)底端部的连接螺栓(4)和轴承(5)将支撑管(10)相对固定在抱箍(3)上;在上段支撑管(10)内***一个可上下移动的调整杆(11),调整杆(11)的外露端部装有一个转向轴(14),转向轴(14)上安装U型导线槽(15),在U型导线槽(15)侧下部固定一个拉环(16)。
2.根据权利要求1所述的架线施工撩线器,其特征在于:在上段支撑管(10)的下端部,装有一个调节撩线器整体长度的升降螺母(8),升降螺杆(6)上设有防滑螺母(7)。
3.根据权利要求1所述的架线施工撩线器,其特征在于:在上段支撑管(10)上,有一道管壁通透的长槽,在长槽边上有4个等间隔分布卡槽(12)。
4.根据权利要求1所述的架线施工撩线器,其特征在于:所述U型导线槽(15)的开口处端部,都开有凹槽,凹槽边上各有一锁孔(17),两端带孔的栓杆(18)其一端与锁孔(17)活动连接,另一端则可锁定、可打开。
5.根据权利要求1所述的架线施工撩线器,其特征在于:在所述抱箍(3)的一个半圆形扁金属带的两个边沿部位,各加工一个带螺寇的孔,另一个半圆形扁金属带的对应处只加工相同的圆孔。
CN2012103269824A 2012-09-06 2012-09-06 架线施工撩线器 Pending CN102856839A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012103269824A CN102856839A (zh) 2012-09-06 2012-09-06 架线施工撩线器

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012103269824A CN102856839A (zh) 2012-09-06 2012-09-06 架线施工撩线器

Publications (1)

Publication Number Publication Date
CN102856839A true CN102856839A (zh) 2013-01-02

Family

ID=47403157

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012103269824A Pending CN102856839A (zh) 2012-09-06 2012-09-06 架线施工撩线器

Country Status (1)

Country Link
CN (1) CN102856839A (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104882821A (zh) * 2015-06-01 2015-09-02 国家电网公司 一种输电线路架空地线的旋转升降装置
CN105186383A (zh) * 2015-11-04 2015-12-23 国家电网公司 导线上瓶器
CN106532569A (zh) * 2016-11-29 2017-03-22 国网河南栾川县供电公司 一种架线施工撩线器
CN107039919A (zh) * 2017-05-05 2017-08-11 国网江苏省电力公司常州供电公司 一种架线装置
CN109346985A (zh) * 2018-11-20 2019-02-15 国家电网有限公司 一种接地线安全拆装辅助装置

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101834424A (zh) * 2010-05-03 2010-09-15 辽宁省电力有限公司锦州供电公司 水平排列10kv绝缘线线路加装架空避雷线方法及避雷器支架
CN201679808U (zh) * 2010-03-18 2010-12-22 金城集团有限公司 一种伸缩杆
JP2012157149A (ja) * 2011-01-26 2012-08-16 Chugoku Electric Power Co Inc:The 間接活線工法用圧縮装置
CN202856239U (zh) * 2012-09-06 2013-04-03 保定供电公司 架线施工撩线器

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201679808U (zh) * 2010-03-18 2010-12-22 金城集团有限公司 一种伸缩杆
CN101834424A (zh) * 2010-05-03 2010-09-15 辽宁省电力有限公司锦州供电公司 水平排列10kv绝缘线线路加装架空避雷线方法及避雷器支架
JP2012157149A (ja) * 2011-01-26 2012-08-16 Chugoku Electric Power Co Inc:The 間接活線工法用圧縮装置
CN202856239U (zh) * 2012-09-06 2013-04-03 保定供电公司 架线施工撩线器

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104882821A (zh) * 2015-06-01 2015-09-02 国家电网公司 一种输电线路架空地线的旋转升降装置
CN105186383A (zh) * 2015-11-04 2015-12-23 国家电网公司 导线上瓶器
CN106532569A (zh) * 2016-11-29 2017-03-22 国网河南栾川县供电公司 一种架线施工撩线器
CN107039919A (zh) * 2017-05-05 2017-08-11 国网江苏省电力公司常州供电公司 一种架线装置
CN109346985A (zh) * 2018-11-20 2019-02-15 国家电网有限公司 一种接地线安全拆装辅助装置

Similar Documents

Publication Publication Date Title
CN102856839A (zh) 架线施工撩线器
CN107724660B (zh) 一种多功能的电力维修操作平台
CN104963543A (zh) 一种电力线路用横担
CN202856239U (zh) 架线施工撩线器
CN102761077B (zh) 1000kV特高压交流线路耐张绝缘子串绝缘起吊支架
CN205489270U (zh) 微调式地线提升装置
CN104638589A (zh) 管型母线吊装专用工具
CN202564866U (zh) 高压电缆头制作用支撑架
CN103779809B (zh) 带电调整双***子导线间距作业方法
CN103594964A (zh) 杆塔导线支撑支架
CN202405695U (zh) 一种钢管杆架空地线提线工具
CN204103349U (zh) 电力带电作业操作杆辅助固定升降调节装置
CN205314654U (zh) 送电线路的加固铁塔
CN204391599U (zh) 管型母线吊装专用工具
CN205159932U (zh) 一种电力线路弧垂调整工具
CN202840363U (zh) 1000kV特高压交流线路耐张绝缘子串绝缘起吊支架
CN204258160U (zh) 更换线塔绝缘子工具
CN202424020U (zh) 一种导线提升工具
CN102570351A (zh) 一种导线提升工具
CN206602316U (zh) 一种用于更换护线条的托线器
CN201266807Y (zh) 更换绝缘子装置
CN205489269U (zh) 高压输电线路用架空地线提升装置
CN104201606B (zh) 一种800kv耐张绝缘子串脱离用卡具
CN104500512A (zh) 一种集束线归方器与电杆固定结构
CN106602465A (zh) 输电线路直线塔第一片绝缘子更换工具

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: BAODING POWER SUPPLY COMPANY

Effective date: 20131127

Owner name: STATE GRID HEBEI ELECTRIC POWER COMPANY BAODING PO

Effective date: 20131127

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 071051 BAODING, HEBEI PROVINCE TO: 100761 DONGCHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20131127

Address after: 100761 West Chang'an Avenue, Beijing, No. 86

Applicant after: State Grid Corporation of China

Applicant after: State Grid Hebei Electric Power Company

Applicant after: Baoding Power Supply Branch Company, State Grid Hebei Electric Power Company

Address before: 071051 No. 138 sunny north street, new urban district, Hebei, Baoding

Applicant before: Baoding Power Supply Company

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20130102

WD01 Invention patent application deemed withdrawn after publication