CN102798775A - 一种大电流冲击发生***及其试验方法 - Google Patents

一种大电流冲击发生***及其试验方法 Download PDF

Info

Publication number
CN102798775A
CN102798775A CN2012102034111A CN201210203411A CN102798775A CN 102798775 A CN102798775 A CN 102798775A CN 2012102034111 A CN2012102034111 A CN 2012102034111A CN 201210203411 A CN201210203411 A CN 201210203411A CN 102798775 A CN102798775 A CN 102798775A
Authority
CN
China
Prior art keywords
current
coil
generation systems
impact generation
time
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012102034111A
Other languages
English (en)
Inventor
李柏奎
侯雨田
邓宏芬
韩筛根
张新
唐可新
白雪峰
柏志新
李东良
吴燕
石卓平
刘岚
丁妍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Electric Power Research Institute Co Ltd CEPRI filed Critical China Electric Power Research Institute Co Ltd CEPRI
Priority to CN2012102034111A priority Critical patent/CN102798775A/zh
Publication of CN102798775A publication Critical patent/CN102798775A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Testing Of Short-Circuits, Discontinuities, Leakage, Or Incorrect Line Connections (AREA)

Abstract

本发明公开了一种大电流冲击发生***及其试验方法,该***包括依次连接的继电器、控制电路、自耦调压器、升流变压器和线圈、套在线圈上的互感器,接收互感器感应出的电流的测量***。本发明自耦调压器输出交流电压,升流变压器输出端产生低电压、大电流的方式在相应匝数的铜线圈上叠加出K倍大电流,最后利用时间继电器控制短路电流与输出时间I-t关系,用录波仪来完成大电流的测量,来实现大电流短路冲击目的。在时间控制方面本发明加入了时间状态序列,使整个***能够正常运转的同时,还能达到以下效果:1)高时间精度控制;2)时间状态任意组合控制;3)自动化水平较高,能够完全实现人和***分离的状态;4)安全系数较高。

Description

一种大电流冲击发生***及其试验方法
技术领域
本发明涉及测试技术领域,具体涉及一种大电流冲击发生***及其试验方法。
背景技术
目前各种具有大电流发生的***被广泛应用于故障指示器等大电流短路冲试验领域。这样的***通常是利用冲击电源变压器、阻抗、数据采集和时间控制,按照一定操作顺序(程序)的方式达到大电流冲击发生目的的。因故障指示器等产品在电力***(线路上)中运行要求能够承受相应的现场短路故障大电流冲击能力,而不损坏。为确保电力***或线路运行安全,必需采用能够承受大电流短路冲击能力的电力开关、故障指示器等设备。但要在试验室组建或搭建这样的短路冲击大电流***很复杂,需要的设备、人力相对较多,特别是生产厂家要搭建此***更是困难。这样如何节省人力、物力及试验场地的问题十分迫切,通常生产厂家出厂试验或技术摸底的方法是到相应的试验室去做试验。这些方式有效果但也存在着许多问题:1、耗费人力、财力。2、试验时间较短,很难看出或测出具体的问题。3、相应的试验室要投入大量人员来搭建和操作大电流冲击***。4、不适合生产厂家长期技术摸底。因此,故障指示器或相应的产品大电流短路冲击是生产厂家或试验室的一个难题,长期以来未能有效解决。
在试验室或生产厂家做大电流短路冲击试验,包括一些220kV变压器、10kV冲击变压器、高压阻抗和低压阻抗等,不管何种方式,但它们都有一个共同的特点,那就是都需要搭建大电流短路冲击试验***。它们共同的缺点就是试验场地较大、投入的人力、物力较高。
发明内容
针对现有技术的不足,本发明提供一种大电流冲击发生***及其试验方法,有效地避免了现有技术中的测试场地较大、投入人力物力较高的问题,且具有较高的实用价值和经济价值。
本发明提供的一种大电流冲击发生***,其改进之处在于,所述***包括继电器K、控制电路、自耦调压器T1、升流变压器T2、线圈L、互感器H和测量***;
所述继电器K、控制电路、自耦调压器T1、升流变压器T2和线圈L依次连接;所述互感器H套在所述线圈L上,将感应出的电流传给所述测量***;所述控制电路控制所述继电器K。
其中,所述线圈L输入端与所述升压变压器T2副边输出端连接,所述线圈L输出端与所述升压变压器T2副边输入端连接。
其中,所述线圈L为铜线圈。
其中,所述线圈L的匝数与所述升流变压器T2副边匝数相同。
其中,所述测量***包括计算机或录波仪。
本发明基于另一目的提供的一种大电流冲击发生***的试验方法,其改进之处在于,所述方法包括如下步骤:
(1)设定所述大电流冲击发生***产生的冲击电流值;
(2)在控制电路中加入时间控制单元;
(3)将控制电路设定为自动控制模式,产生冲击电流值。
其中,所述时间控制单元包括时间状态序列控制组件,用于设定时间状态序列。
其中,判断步骤(3)产生的冲击电流值是否与设定的冲击电流值等值,若不等则调整所述大电流冲击发生***的参数,使产生的冲击电流值等于设定的冲击电流值。
其中,所述大电流冲击发生***的参数包括升流变压器T2的比值。
与现有技术比,本发明的有益效果为:
本发明搭建***简单,通过现有装置易于实现。
本发明需要的人力、物力、财力较少,节省了资源和成本。
本发明占用场地很小。
本发明安全系数较高,有效地保证了人身安全和财产安全。
本发明在控制电路中加入时间控制单元,能够很好的控制整个电路中冲击电流的时间。
附图说明
图1为本发明提供的大电流短路冲击***示意图。
图2为本发明提供的自藕调压器T1示意图。
图3为本发明型提供的升流变压器T2示意图。
图4为本发明提供的电流线圈L示意图。
其中,T1为自耦调压器;T2为升流变压器;L为线圈;H为互感器;K为时间继电器。
具体实施方式
下面结合附图对本发明的具体实施方式作进一步的详细说明。
本实施例提供的大电流短路冲击***如图1所示,该***包括时间继电器K、控制电路、自耦调压器T1、升流变压器T2、线圈L、互感器H和测量***;自藕调压器T1如图2所示,升流变压器T2如图3所示,电流线圈L如图4所示。
自耦调压器T1的原边与交流电源连接,其副边与升流变压器T2的原边连接,升流变压器T2的副边输出端与线圈L的输入端连接,升流变压器T2的副边输入端与线圈L的输出端连接。互感器H套在线圈L上,将感应出的电流传给测量***。控制电路用于控制时间继电器K。
其中,线圈L为铜线圈。线圈L的匝数与升流变压器T2副边匝数相同,线圈的线径根据自耦变压器的容量确定,其一般取为2.5mm2
其中,测量***包括计算机或录波仪。
本实施例的自耦调压器输出交流电压,升流变压器输出端产生低电压、大电流的方式在相应匝数的铜线圈上叠加出K倍(K:铜线圈匝数)大电流,最后利用时间继电器(或其他电子电路)控制短路电流与输出时间I-t关系,控制大电流冲击时间(即大电流冲击到一定值的时候整个电路断开,***停电),用录波仪来完成大电流的测量,来实现大电流短路冲击目的。而在时间控制方面本发明加入了时间状态序列,使整个***能够正常运转的同时,还能达到以下效果:1)高时间精度控制;2)时间状态任意组合控制;3)自动化水平较高,能够完全实现人和***分离的状态;4)安全系数较高。例如:用时间状态序列控制大电流短路冲击***时,可以设定***在通电XX秒后,***停电,在停电XX秒后***重新启动,往复循环。
本实施例大电流最终的发生装置为一个N匝线圈,无论试验室还是生产厂家试验可以根据需求自行改变线圈的匝数,最终的短路冲击电流值结果,由测量***完成。为了能在最小的容量范围内,实现最好的或最高的短路电流冲击值,线圈材料的选择要适当,要选择阻抗较小的材料。当测量***测到的大电流大于或小于预期值时,操作人员可以适当的调节升流变压器T2输出,来改变升流变压器的输出电流值,来确定当前电流值是否满足要求,能否达到预期目的。
本发明可以通过改进和缩小***来实现大电流短路试验,提高试验过程中的安全系数,从而有效提高试验效率。
最后应当说明的是:以上实施例仅用以说明本发明的技术方案而非对其限制,尽管参照上述实施例对本发明进行了详细的说明,所属领域的普通技术人员应当理解:依然可以对本发明的具体实施方式进行修改或者等同替换,而未脱离本发明精神和范围的任何修改或者等同替换,其均应涵盖在本发明的权利要求范围当中。

Claims (9)

1.一种大电流冲击发生***,其特征在于,所述***包括继电器K、控制电路、自耦调压器T1、升流变压器T2、线圈L、互感器H和测量***;
所述继电器K、控制电路、自耦调压器T1、升流变压器T2和线圈L依次连接;所述互感器H套在所述线圈L上,将感应出的电流传给所述测量***;所述控制电路控制所述继电器K。
2.如权利要求1所述的大电流冲击发生***,其特征在于,所述线圈L输入端与所述升压变压器T2副边输出端连接,所述线圈L输出端与所述升压变压器T2副边输入端连接。
3.如权利要求1所述的大电流冲击发生***,其特征在于,所述线圈L为铜线圈。
4.如权利要求1所述的大电流冲击发生***,其特征在于,所述线圈L的匝数与所述升流变压器T2副边匝数相同。
5.如权利要求1所述的大电流冲击发生***,其特征在于,所述测量***包括计算机或录波仪。
6.一种大电流冲击发生***的试验方法,其特征在于,所述方法包括如下步骤:
(1)设定所述大电流冲击发生***产生的冲击电流值;
(2)在控制电路中加入时间控制单元;
(3)将控制电路设定为自动控制模式,产生冲击电流值。
7.如权利要求6所述的试验方法,其特征在于,所述时间控制单元包括时间状态序列控制组件,用于设定时间状态序列。
8.如权利要求6所述的试验方法,其特征在于,判断步骤(3)产生的冲击电流值是否与设定的冲击电流值等值,若不等则调整所述大电流冲击发生***的参数,使产生的冲击电流值等于设定的冲击电流值。
9.如权利要求6所述的试验方法,其特征在于,所述大电流冲击发生***的参数包括升流变压器T2的比值。 
CN2012102034111A 2012-06-15 2012-06-15 一种大电流冲击发生***及其试验方法 Pending CN102798775A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012102034111A CN102798775A (zh) 2012-06-15 2012-06-15 一种大电流冲击发生***及其试验方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012102034111A CN102798775A (zh) 2012-06-15 2012-06-15 一种大电流冲击发生***及其试验方法

Publications (1)

Publication Number Publication Date
CN102798775A true CN102798775A (zh) 2012-11-28

Family

ID=47197941

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012102034111A Pending CN102798775A (zh) 2012-06-15 2012-06-15 一种大电流冲击发生***及其试验方法

Country Status (1)

Country Link
CN (1) CN102798775A (zh)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103105549A (zh) * 2012-12-31 2013-05-15 北京无线电计量测试研究所 一种脉冲电压转换为脉冲电流的方法
CN103630775A (zh) * 2013-11-16 2014-03-12 中国科学院电工研究所 一种交流大电流冲击测试装置和测试方法
CN103983818A (zh) * 2014-04-04 2014-08-13 国网山东桓台县供电公司 一体化升流升压装置
CN104049209A (zh) * 2014-06-30 2014-09-17 国网上海市电力公司 一种便携式水电阻型大电流升流器
CN106249082A (zh) * 2016-08-30 2016-12-21 潍柴重机股份有限公司 一种发电机组控制屏试验方法与装置
CN106405467A (zh) * 2016-05-04 2017-02-15 中国电力科学研究院 一种低压电流互感器短时热电流自动化试验装置及试验方法
CN111624376A (zh) * 2020-04-23 2020-09-04 中国南方电网有限责任公司超高压输电公司检修试验中心 一种套管试验用大电流发生装置及其使用方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2205080Y (zh) * 1994-09-07 1995-08-09 岳大正 电流电压调节仪
JPH11295369A (ja) * 1998-04-09 1999-10-29 Soukou Denki Seisakusho:Kk 継電器試験装置
CN2792015Y (zh) * 2004-12-24 2006-06-28 上海电器科学研究所(集团)有限公司 一种大电流组合发生器
CN201796057U (zh) * 2010-08-12 2011-04-13 常熟理工学院 基于虚拟仪器技术的电流发生装置

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2205080Y (zh) * 1994-09-07 1995-08-09 岳大正 电流电压调节仪
JPH11295369A (ja) * 1998-04-09 1999-10-29 Soukou Denki Seisakusho:Kk 継電器試験装置
CN2792015Y (zh) * 2004-12-24 2006-06-28 上海电器科学研究所(集团)有限公司 一种大电流组合发生器
CN201796057U (zh) * 2010-08-12 2011-04-13 常熟理工学院 基于虚拟仪器技术的电流发生装置

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103105549A (zh) * 2012-12-31 2013-05-15 北京无线电计量测试研究所 一种脉冲电压转换为脉冲电流的方法
CN103630775A (zh) * 2013-11-16 2014-03-12 中国科学院电工研究所 一种交流大电流冲击测试装置和测试方法
CN103630775B (zh) * 2013-11-16 2016-03-02 中国科学院电工研究所 一种交流大电流冲击测试装置和测试方法
CN103983818A (zh) * 2014-04-04 2014-08-13 国网山东桓台县供电公司 一体化升流升压装置
CN104049209A (zh) * 2014-06-30 2014-09-17 国网上海市电力公司 一种便携式水电阻型大电流升流器
CN104049209B (zh) * 2014-06-30 2016-05-18 国网上海市电力公司 一种便携式水电阻型大电流升流器
CN106405467A (zh) * 2016-05-04 2017-02-15 中国电力科学研究院 一种低压电流互感器短时热电流自动化试验装置及试验方法
CN106249082A (zh) * 2016-08-30 2016-12-21 潍柴重机股份有限公司 一种发电机组控制屏试验方法与装置
CN106249082B (zh) * 2016-08-30 2020-06-02 潍柴重机股份有限公司 一种发电机组控制屏试验装置
CN111624376A (zh) * 2020-04-23 2020-09-04 中国南方电网有限责任公司超高压输电公司检修试验中心 一种套管试验用大电流发生装置及其使用方法
CN111624376B (zh) * 2020-04-23 2022-05-13 中国南方电网有限责任公司超高压输电公司检修试验中心 一种套管试验用大电流发生装置及其使用方法

Similar Documents

Publication Publication Date Title
CN102798775A (zh) 一种大电流冲击发生***及其试验方法
CN109407036B (zh) 一种基于plc控制的批量电流互感器全自动检定装置
CN101424728B (zh) 一种高压电流互感器现场准确度检测试验线路
KR101400009B1 (ko) 스마트그리드 교육용 실습장치
CN201319064Y (zh) 一种高压电流互感器现场准确度检测试验线路
CN105044479A (zh) 大型油浸式变压器空、负载综合试验设备及方法
CN101726715A (zh) 一种电力***用电压互感器误差特性在线校验方法
CN104569545A (zh) 一种基于罗氏线圈型电流互感器宽范围测量用控制电路
CN102680861A (zh) 变压器或电抗器的短路承受能力试验***及其方法
CN103558536A (zh) 测试串联电容器耐受过负荷能力的电路及其工作方法
CN103884933A (zh) 一种大型变压器温升试验方法
CN105259382A (zh) 多变比电流互感器统一倍率进表计量的方法及装置
CN101614798B (zh) 电子式互感器极性检测***
CN103698730A (zh) 一种交直流双电源的电流互感器校验***
CN105467239A (zh) 一种电压互感器励磁特性试验***
CN102608414B (zh) 高压电气开关设备的嵌入式电能计量方法及扩展应用方法
CN104808022A (zh) 一种三相三绕组变压器三侧联合运行温升试验接线方法
CN104749461B (zh) 一种一次加压通流装置、智能变电***及其控制方法
CN204241652U (zh) 多工位全自动电机定子综合测试装置
CN106653336B (zh) 一种制备具有简化误差测试功能的电流互感器的方法
CN102866378A (zh) 一种电压或电流互感器在线测试装置及方法
CN103543305A (zh) 一种电力设备局部放电检测用弱阻尼交流高压发生器
CN103605101B (zh) 工频分段升压试验仪
CN102576485A (zh) 负载检测型高效率变压器装置
CN102269786A (zh) 三倍频变压器负载试验装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20130425

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20130425

Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Applicant after: China Electric Power Research Institute

Applicant after: State Grid Corporation of China

Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Applicant before: China Electric Power Research Institute

C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20121128