CN102787988A - 一种海上风力发电机组安装方法 - Google Patents
一种海上风力发电机组安装方法 Download PDFInfo
- Publication number
- CN102787988A CN102787988A CN2012102325244A CN201210232524A CN102787988A CN 102787988 A CN102787988 A CN 102787988A CN 2012102325244 A CN2012102325244 A CN 2012102325244A CN 201210232524 A CN201210232524 A CN 201210232524A CN 102787988 A CN102787988 A CN 102787988A
- Authority
- CN
- China
- Prior art keywords
- generator tower
- wind generator
- tower tube
- offshore
- driven generator
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000000034 method Methods 0.000 title claims abstract description 15
- 238000009434 installation Methods 0.000 claims abstract description 25
- 238000003466 welding Methods 0.000 claims abstract description 13
- 238000007789 sealing Methods 0.000 claims description 6
- 230000011218 segmentation Effects 0.000 claims description 5
- 238000007689 inspection Methods 0.000 claims description 3
- 239000000463 material Substances 0.000 claims description 3
- 239000013535 sea water Substances 0.000 claims description 3
- 238000004078 waterproofing Methods 0.000 claims description 3
- 238000010276 construction Methods 0.000 abstract description 6
- 210000001503 joint Anatomy 0.000 description 8
- 230000005611 electricity Effects 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 238000004519 manufacturing process Methods 0.000 description 2
- 208000035126 Facies Diseases 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 238000005516 engineering process Methods 0.000 description 1
Images
Classifications
-
- Y—GENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
- Y02—TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
- Y02P—CLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
- Y02P70/00—Climate change mitigation technologies in the production process for final industrial or consumer products
- Y02P70/50—Manufacturing or production processes characterised by the final manufactured product
Landscapes
- Wind Motors (AREA)
Abstract
本发明涉及一种海上风力发电机组安装方法,包含如下步骤:S1、将分段的风力发电机塔筒(10)水平放置在岸边码头,然后对风力发电机塔筒(10)连接处进行焊接;S2、检查相邻两段风力发电机塔筒(10)连接处焊接的强度;S3、将焊接好的风力发电机塔筒(1)运输至海上风力发电机组安装位置;S4、使用吊装船(3)将风力发电机塔筒(1)安装于海上风力发电机组基础平台(2)上;S5、使用吊装船(3)将风叶(4)安装于风力发电机塔筒(1)上,本发明将海上施工安装调整在码头进行,使得安装变得方便快捷,便于施工,通过焊接的方式取代法兰螺栓联接,提高了风力发电机塔筒的安装精度,提高工作效率,降低了成本。
Description
【技术领域】
本发明涉及一种海上风力发电机组安装方法。
【背景技术】
由于陆地风力资源有限、且陆地风力发电日趋饱和,海洋已成为风力发电的新市场,目前海上风机塔筒的安装依然采用和陆上风机塔筒类似的安装方法,风机塔筒的高度一般在75米-110米之间,特殊情况下塔筒长度更长,对于运输、制造难度较大,现有的塔筒制造厂家将塔筒分成3至4段圆筒体,在陆地上,工作人员将塔筒分段用船舶运输到指定地点,然后进行分段吊装,螺栓铆接安装,海上安装条件和环境相比陆地上有诸多困难,具体缺点有:如果采用浮吊,波浪使得船舶上下飘动,导致塔筒法兰连接时难以准确对接,且对接时容易发生碰撞,破坏法兰,由于塔筒在海上安装需要用大型工程船将分段塔筒吊起来,然后对接,但是浪涌使得船体及吊起的塔筒发生摆动,这种安装方法施工困难,对天气条件要求严格,容易损伤塔筒等部件,另外海上船舶和吊装设备租金昂贵,安装成本高,应尽可能减少每个工作环节的作业时间。
【发明内容】
本发明克服了上述技术的不足,提供了一种海上风力发电机组安装方法,本发明将风力发电机塔筒海上施工安装调整在码头进行,通过焊接的方式联接风力发电机塔筒,该方法使得海上风力发电机组的安装变得方便快捷,便于工作人员对风力发电机塔筒进行施工,该方法通过焊接的方式取代法兰螺栓联接,提高了风力发电机塔筒的安装精度,提高工作效率,降低了成本。
为实现上述目的,本发明采用了下述技术方案:
一种海上风力发电机组安装方法,包含如下步骤:
第一步、将分段的风力发电机塔筒水平放置在岸边码头,通过相应的工装将相邻两段风力发电机塔筒联接起来,调试相邻两段风力发电机塔筒连接处的同轴度并使其达到规定要求,然后对风力发电机塔筒连接处进行焊接;
第二步、检查相邻两段风力发电机塔筒连接处焊接的强度,如果符合要求,则进入下一步工序,如果不符合要求,则返回上步重新操作;
第三步、将焊接好的风力发电机塔筒整体运输至海上风力发电机组安装位置;
第四步、使用吊装船将风力发电机塔筒安装于海上风力发电机组基础平台上。
第五步、使用吊装船将风叶安装于风力发电机塔筒上。
在如上所述第三步中,采用大型驳船将焊接好的风力发电机塔筒整体运输至海上风力发电机组安装位置。
在如上所述第三步中,将将焊接好的风力发电机塔筒两端用防水材料密封,利用吊装设备将风力发电机塔筒吊起并放入海水中,经过密封的风力发电机塔筒依靠自身浮力可漂浮于海面上,然后使用拖船将密封的风力发电机塔筒整体运输至海上风力发电机组安装位置。
本发明的有益效果是:
1、本发明将风力发电机塔筒海上施工安装调整在码头进行,降低了对天气条件的要求,降低了施工危险性和安装成本,减少了因碰撞、施工时间等造成的不安全因素,使得海上风力发电机组的安装变得方便快捷,便于工作人员对风力发电机塔筒进行施工;
2、本发明通过焊接的方式取代法兰螺栓联接风力发电机塔筒,提高了风力发电机塔筒的安装精度,提高工作效率,降低了成本。
【附图说明】
图1为本发明风力发电机塔筒结构示意图;
图2为本发明风力发电机塔筒安装过程示意图;
图3为本发明风叶安装过程示意图。
【具体实施方式】
一种海上风力发电机组安装方法,包含如下步骤:
S1、如图1所示,将分段的风力发电机塔筒10水平放置在岸边码头,通过相应的工装将相邻两段风力发电机塔筒10联接起来,调试相邻两段风力发电机塔筒10连接处的同轴度并使其达到规定要求,然后对风力发电机塔筒10连接处进行焊接;
S2、检查相邻两段风力发电机塔筒10连接处焊接的强度,如果符合要求,则进入下一步工序,如果不符合要求,则返回上步重新操作;
S3、如图2所示,将焊接好的风力发电机塔筒1整体运输至海上风力发电机组安装位置;
S4、使用吊装船3将风力发电机塔筒1安装于海上风力发电机组基础平台2上;
S5、如图3所示,使用吊装船3将风叶4安装于风力发电机塔筒1上
本发明将风力发电机塔筒海上施工安装调整在码头进行,使得海上风力发电机组的安装变得方便快捷,便于工作人员对风力发电机塔筒1进行施工。
作为本发明的一种实施例,在所述S3中,采用大型驳船将焊接好的风力发电机塔筒1整体运输至海上风力发电机组安装位置,驳船运输快捷方便,无需对风力发电机塔筒1进行密封。
作为本发明的另一种实施例,在所述S3中,将将焊接好的风力发电机塔筒 1两端用防水材料密封,利用吊装设备将风力发电机塔筒1吊起并放入海水中,经过密封的风力发电机塔筒1依靠自身浮力可漂浮于海面上,然后使用拖船将密封的风力发电机塔筒1整体运输至海上风力发电机组安装位置,采用对风力发电机塔筒1进行密封包装,采用拖船运输,大大降低运输成本。
Claims (3)
1.一种海上风力发电机组安装方法,其特征在于:包含如下步骤:
第一步、将分段的风力发电机塔筒(10)水平放置在岸边码头,将相邻两段风力发电机塔筒(10)联接起来,调试相邻两段风力发电机塔筒(10)连接处的同轴度,然后对风力发电机塔筒(10)连接处进行焊接;
第二步、检查相邻两段风力发电机塔筒(10)连接处焊接的强度,如果符合要求,则进入下一步工序,如果不符合要求,则返回上步重新操作;
第三步、将焊接好的风力发电机塔筒(1)整体运输至海上风力发电机组安装位置;
第四步、使用吊装船(3)将风力发电机塔筒(1)安装于海上风力发电机组基础平台(2)上。
第五步、使用吊装船(3)将风叶(4)安装于风力发电机塔筒(1)上。
2.根据权利要求1所述的一种海上风力发电机组安装方法,其特征在于:在所述第三步中,采用大型驳船将焊接好的风力发电机塔筒(1)整体运输至海上风力发电机组安装位置。
3.根据权利要求1所述的一种海上风力发电机组安装方法,其特征在于:在所述第三步中,将将焊接好的风力发电机塔筒(1)两端用防水材料密封,利用吊装设备将风力发电机塔筒(1)吊起并放入海水中,经过密封的风力发电机塔筒(1)依靠自身浮力可漂浮于海面上,然后使用拖船将密封的风力发电机塔筒(1)整体运输至海上风力发电机组安装位置。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102325244A CN102787988A (zh) | 2012-07-05 | 2012-07-05 | 一种海上风力发电机组安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102325244A CN102787988A (zh) | 2012-07-05 | 2012-07-05 | 一种海上风力发电机组安装方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102787988A true CN102787988A (zh) | 2012-11-21 |
Family
ID=47153506
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012102325244A Pending CN102787988A (zh) | 2012-07-05 | 2012-07-05 | 一种海上风力发电机组安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102787988A (zh) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104326057A (zh) * | 2014-09-04 | 2015-02-04 | 江苏金风科技有限公司 | 海上风力发电机组的运输结构、运输方法及安装方法 |
CN106499593A (zh) * | 2016-10-31 | 2017-03-15 | 三重型能源装备有限公司 | 塔筒水上运输方法 |
CN110249128A (zh) * | 2017-02-09 | 2019-09-17 | 西门子歌美飒可再生能源公司 | 用于平行于风力涡轮机塔架升高或降低负载的方法和设备 |
CN114087132A (zh) * | 2021-11-15 | 2022-02-25 | 中国华能集团清洁能源技术研究院有限公司 | 一种用于塔筒安装的定位方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2005120775A (ja) * | 2003-10-20 | 2005-05-12 | Tomoe Giken:Kk | 塔状構造物の構築方法 |
EP1058787B1 (en) * | 1998-02-27 | 2005-10-19 | Bonus Energy A/S | Method for installation of wind turbines at sea, foundation for wind turbines and use of such foundation |
CN202007741U (zh) * | 2011-03-16 | 2011-10-12 | 南通市盛东航道工程有限公司 | 海上风力发电机组 |
CN202106122U (zh) * | 2011-01-07 | 2012-01-11 | 胜利油田胜利石油化工建设有限责任公司金属结构厂 | 多工位风力发电塔架外环缝焊接机 |
CN102330646A (zh) * | 2011-08-26 | 2012-01-25 | 姚瑜宁 | 风力发电机塔架及其运输组装方法 |
-
2012
- 2012-07-05 CN CN2012102325244A patent/CN102787988A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP1058787B1 (en) * | 1998-02-27 | 2005-10-19 | Bonus Energy A/S | Method for installation of wind turbines at sea, foundation for wind turbines and use of such foundation |
JP2005120775A (ja) * | 2003-10-20 | 2005-05-12 | Tomoe Giken:Kk | 塔状構造物の構築方法 |
CN202106122U (zh) * | 2011-01-07 | 2012-01-11 | 胜利油田胜利石油化工建设有限责任公司金属结构厂 | 多工位风力发电塔架外环缝焊接机 |
CN202007741U (zh) * | 2011-03-16 | 2011-10-12 | 南通市盛东航道工程有限公司 | 海上风力发电机组 |
CN102330646A (zh) * | 2011-08-26 | 2012-01-25 | 姚瑜宁 | 风力发电机塔架及其运输组装方法 |
Cited By (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN104326057A (zh) * | 2014-09-04 | 2015-02-04 | 江苏金风科技有限公司 | 海上风力发电机组的运输结构、运输方法及安装方法 |
CN104326057B (zh) * | 2014-09-04 | 2017-06-06 | 江苏金风科技有限公司 | 海上风力发电机组的运输结构、运输方法及安装方法 |
CN106499593A (zh) * | 2016-10-31 | 2017-03-15 | 三重型能源装备有限公司 | 塔筒水上运输方法 |
CN110249128A (zh) * | 2017-02-09 | 2019-09-17 | 西门子歌美飒可再生能源公司 | 用于平行于风力涡轮机塔架升高或降低负载的方法和设备 |
US11192759B2 (en) | 2017-02-09 | 2021-12-07 | Siemens Gamesa Renewable Energy A/S | Method and apparatus for raising or lowering a load parallel to a wind turbine tower |
CN110249128B (zh) * | 2017-02-09 | 2021-12-24 | 西门子歌美飒可再生能源公司 | 用于平行于风力涡轮机塔架升高或降低负载的方法和设备 |
CN114087132A (zh) * | 2021-11-15 | 2022-02-25 | 中国华能集团清洁能源技术研究院有限公司 | 一种用于塔筒安装的定位方法 |
CN114087132B (zh) * | 2021-11-15 | 2024-01-19 | 中国华能集团清洁能源技术研究院有限公司 | 一种用于塔筒安装的定位方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Guo et al. | Review of integrated installation technologies for offshore wind turbines: Current progress and future development trends | |
CN102277878B (zh) | 一种可浮运的浮式基础施工方法 | |
EP2604501B1 (en) | System of anchoring and mooring of floating wind turbine towers and corresponding methods for towing and erecting thereof | |
KR101352096B1 (ko) | 트라이포드 석션파일 하부구조물 | |
CN202295236U (zh) | 浮式海上风电平台 | |
US11203398B2 (en) | Buoy and installation method for the buoy | |
CN103010413A (zh) | 一种驳船吊装风机的作业方法 | |
Wang et al. | Investigation on installation of offshore wind turbines | |
CN103661827A (zh) | 海上潮间带区域的风机总成安装***及其施工方法 | |
CN102787988A (zh) | 一种海上风力发电机组安装方法 | |
CN108999975B (zh) | 一种用于海上风机钢桩漂浮运输的密封桩塞器 | |
JP2021172211A (ja) | 浮体式洋上風力発電装置 | |
CN101428712B (zh) | 风力发电机组整体牵引装船的方法 | |
WO2024131858A1 (zh) | 一种双浮筒单点系泊海上风电漂浮式基础及其安装方法 | |
CN114165389A (zh) | 一种海上起重船浮态安装风机部件的施工装置及操作方法 | |
KR101352095B1 (ko) | 석션파일 하부구조물 | |
KR101342138B1 (ko) | 해상풍력발전 장치 및 그 설치 방법 | |
Chatzigiannakou et al. | Offshore deployment of point absorbing wave energy converters with a direct driven linear generator power take-off at the Lysekil test site | |
Casale et al. | Preliminary design of a floating wind turbine support structure and relevant system cost assessment | |
NO336693B1 (no) | Gjennomstrømningsturbin og system for kraftproduksjon | |
CN102050198A (zh) | 浅水区风力发电机组潜水驳船座底分体安装工艺 | |
CN216950679U (zh) | 一种海上起重船浮态安装风机部件的施工装置 | |
CN208085949U (zh) | 一种浮式风机及tlp平台运输安装一体船 | |
KR101297669B1 (ko) | 해상풍력발전기 설치 전용선을 이용한 해상풍력발전기 설치방법 | |
CN203684191U (zh) | 海上潮间带区域的风机施工*** |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20121121 |