CN102785996A - Tool for overturning and lifting of steel plate with holes and its using method - Google Patents

Tool for overturning and lifting of steel plate with holes and its using method Download PDF

Info

Publication number
CN102785996A
CN102785996A CN2012102478837A CN201210247883A CN102785996A CN 102785996 A CN102785996 A CN 102785996A CN 2012102478837 A CN2012102478837 A CN 2012102478837A CN 201210247883 A CN201210247883 A CN 201210247883A CN 102785996 A CN102785996 A CN 102785996A
Authority
CN
China
Prior art keywords
holes
steel plate
suspension hook
hole
instrument
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012102478837A
Other languages
Chinese (zh)
Other versions
CN102785996B (en
Inventor
王兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Dalian nuclear power and Petrochemical Co., Ltd
China First Heavy Industries Co Ltd
Original Assignee
China No1 Heavy Machinery Group Corp Dalian Hydrogenation Reactor Manufa
China First Heavy Industries Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China No1 Heavy Machinery Group Corp Dalian Hydrogenation Reactor Manufa, China First Heavy Industries Co Ltd filed Critical China No1 Heavy Machinery Group Corp Dalian Hydrogenation Reactor Manufa
Priority to CN201210247883.7A priority Critical patent/CN102785996B/en
Publication of CN102785996A publication Critical patent/CN102785996A/en
Application granted granted Critical
Publication of CN102785996B publication Critical patent/CN102785996B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Engaging Elements For Cranes (AREA)

Abstract

The invention discloses a tool for overturning and lifting of a steel plate with holes and its using method. The tool comprises a clamping end and a shackle that is fixedly connected with a lifting lug arranged at the upper end of the clamping end. Besides, the provided tool is characterized in that: a U-shaped groove is arranged at the lower end surface of the clamping end and a positioning through hole I that is matched with a positioning shaft is arranged on the clamping end; and a positioning through hole II is arranged between the top end of the U-shaped groove and the upper end surface of the clamping end. One end of a pin roll is fixed inside the positioning through hole II by a roll sleeve and the other end of the roll sleeve is provided with a baffle plate and a lifting ring, wherein the baffle plate can be rotated around the pin roll by any angle. Two baffle plate limit holes are arranged above the positioning through hole II and springs are arranged inside the baffle plate limit holes; pressure bars are arranged at the front ends of the springs; the front ends of the pressure bars are projected out of one ends of the baffle plate limit holes; and the tail ends of the springs are fixed with the other ends of the baffle plate limit holes by fastening components. According to the invention, the characteristics of simple structure, strong practicability and high reliability and security and the like are realized.

Description

Steel plate upset handling with holes is with instrument and method of application thereof
Technical field
The present invention relates to a kind of suspender, specifically a kind of steel plate upset handling with holes is with instrument and method of application thereof.
Background technology
At present, steel plate with holes circular steel plate especially with holes all adopts medium plate or stainless steel sheet to process mostly, forms hundreds of well-distributed profiled holes through boring, broaching.In the whole machining process process, circular steel plate will be through conversion broaching tool moulding several times, and reconditioning and finishing not only will be cleared up in the steel plate two sides, but also want vertical display, needs repetitious level, vertical and upset handling.Because circular steel plate can't be used dental forceps suspender upset handling behind fine limit work, and the position that is installed is restricted.Therefore be necessary to design the handling that a kind of special hanger and handling upset technology realize steel plate.
Summary of the invention
According to the technical matters of above-mentioned proposition, and provide a kind of steel plate upset handling with holes with instrument and method of application thereof.The technological means that the present invention adopts is following:
Instrument is used in a kind of steel plate upset handling with holes; Comprise bare terminal and the shackle of captiveing joint with the hanger that is arranged on said bare terminal upper end, it is characterized in that: the lower surface of said bare terminal has U-lag, and the groove width of said U type groove is L; L satisfies: L >=b, and wherein b is a steel plate thickness with holes; Said bare terminal is provided with the positioning through hole I that is complementary with fix shaft, and said positioning through hole I connects the two side of said U type groove and vertical with the two side of said U type groove, and the hole of said positioning through hole I and said steel plate with holes is complementary; Also be provided with the positioning through hole II that is parallel to said positioning through hole I between the upper surface of said U type groove top and said bare terminal; One end of bearing pin is fixed in the said positioning through hole II through axle sleeve; The other end of said axle sleeve is provided with baffle plate and suspension ring, and said baffle plate can be around the arbitrarily angled rotation of said bearing pin; Said positioning through hole II top also is provided with two baffle plate spacing holes that are parallel to said positioning through hole II; Be provided with spring in the said baffle plate spacing hole; The front end of said spring is provided with depression bar; The front end of said depression bar protrudes from an end of said baffle plate spacing hole, and the tail end of said spring is fixed through the other end of fastener and said baffle plate spacing hole.
As preferably, the number of said positioning through hole I is at least 4, and the number of said fix shaft is smaller or equal to the number of said positioning through hole I.
As preferably, the inwall of said U-lag is provided with backing plate.
The present invention also provides the method for application of a kind of steel plate upset handling with holes with instrument, comprises the steps:
1. two steel plate upset handlings with holes are fastened said unloading with steel rope respectively with instrument and buckle, and hang on the suspension hook of overhead traveling crane, press said depression bar,, said fix shaft is all taken out said baffle plate half-twist with hand;
2. two steel plate upset handlings with holes are sling with instrument; Under the on even keel; Two said U type grooves are inserted into respectively on the steel plate with holes side end face of need handling of horizontal positioned; Two steel plate upset handlings with holes should be installed in instrument on the line of centers two ends correspondence position of steel plate with holes, when the hole on all said positioning through hole I and the steel plate with holes matches, are inserted into said fix shaft in the said positioning through hole I; With said baffle plate rotation return, said depression bar ejects said baffle plate is fixed;
3. with the handling of overturning of completing steps steel plate with holes 2..
Said upset handling is parallel motion, upset 90 ° and 180 ° of upsets of level.
Said parallel motion is that the steel rope of two mounted with holes steel plate upset handlings with instrument all hung on the main suspension hook of overhead traveling crane, together slings, and steel plate with holes is hung other positions with moving of overhead traveling crane by level.
90 ° of said upsets comprise by 90 ° of flip horizontals becoming vertically and becoming level for 90 ° by vertical upset; Said vertically is to have installed steel plate with holes upset handling with two to be hung on the main suspension hook and secondary suspension hook of overhead traveling crane with the steel rope of instrument by 90 ° of one-tenth of flip horizontal; After the main suspension hook of overhead traveling crane and secondary suspension hook be raised to certain altitude simultaneously; Main suspension hook continues toward rising, and secondary suspension hook stops to rise or descending, and is in vertical state up to steel plate with holes; Instrument is used in the steel plate upset handling of laying down on the secondary suspension hook with holes, again steel plate with holes is winched to the position that needs placement; Said is steel plate upset handling with holes to be installed on the top of the steel plate with holes under the vertical state use instrument by 90 ° of one-tenth levels of vertical upset; And said steel rope hung on the main suspension hook of overhead traveling crane, main suspension hook rises steel plate with holes is hung vertical position, will hang over steel plate upset handling with holes on the secondary suspension hook is installed in steel plate with holes with instrument lower end again; Secondary suspension hook rises; Main suspension hook descends, and till steel plate with holes is horizontal, and is placed into assigned address.
180 ° of upsets of said level are to have installed steel plate with holes upset handling with two to be hung on the main suspension hook and secondary suspension hook of overhead traveling crane with the steel rope of instrument; After the main suspension hook of overhead traveling crane and secondary suspension hook be raised to certain altitude simultaneously; Main suspension hook continues toward rising, and secondary suspension hook stops to rise or descending, when steel plate with holes is in vertical state; Steel plate upset handling with holes on the secondary suspension hook is contained on the original position with instrument is counter; Secondary suspension hook is risen, and main suspension hook descends, till steel plate with holes is horizontal.
The present invention is simple in structure, and is practical, and knock hole cooperates with alignment pin and the location cooperation of baffle plate and depression bar can improve the reliability and security of steel plate with holes in the handling process.The present invention can extensively promote in fields such as mechanical equipment manufacturings for the foregoing reasons, is applicable to comprise the handling of circular steel plate with holes in the apertured plate member of interior arbitrary shape.
Description of drawings
Below in conjunction with the accompanying drawing and the specific embodiment the present invention is done further detailed explanation.
Fig. 1 is a structural representation of the present invention.
Fig. 2 is a front view of the present invention.
Fig. 3 be among Fig. 1 A-A to view.
Fig. 4 is the scheme drawing that carries out parallel motion with the present invention.
Fig. 5 is with overturn 90 ° scheme drawing of the present invention.
Fig. 6 is the scheme drawing that carries out vertical handling with the present invention.
Among the figure: 1, shackle 2, backing plate 3, axle sleeve 4, bearing pin 5, fastener 6, spring 7, bare terminal 8, depression bar 9, suspension ring 10, baffle plate 11, fix shaft 12, positioning through hole I 13, main suspension hook 14, steel rope 15, steel plate with holes 16, secondary suspension hook
The specific embodiment
Like Fig. 1, Fig. 2 and shown in Figure 3, instrument is used in a kind of steel plate upset handling with holes, comprises bare terminal 7 and the shackle 1 of captiveing joint with the hanger that is arranged on said bare terminal 7 upper ends.The lower surface of said bare terminal 7 has U-lag; The groove width of said U type groove is L, and L satisfies: L >=b, and wherein b is steel plate 15 thickness with holes; The inwall of said U-lag is provided with backing plate 2; On the lower surface of bare terminal 7, backing plate 2 can effectively prevent steel plate 15 with holes and U type groove direct contact and the finished surface surface tear that causes etc. through packing ring and screw retention for backing plate 2; Said bare terminal 7 is provided with the positioning through hole I 12 that is complementary with fix shaft 11; In the present embodiment; The number of said positioning through hole I 12 is 16; The number of said fix shaft 11 is 8, the two side of the said U type groove of said positioning through hole I 12 perforations and vertical with the two side of said U type groove, and said positioning through hole I 12 is complementary with the hole of said steel plate 15 with holes; Also be provided with the positioning through hole II that is parallel to said positioning through hole I 12 between the upper surface of said U type groove top and said bare terminal 7; One end of bearing pin 4 is fixed in the said positioning through hole II through axle sleeve 3; The other end of said axle sleeve 4 is provided with baffle plate 10 and suspension ring 9; Can make operator's convenient its stability of control when steel plate upset handling with holes is installed with instrument through lifting said suspension ring 9; The upper end of said baffle plate 10 is provided with positioning convex, and said baffle plate 10 can be around said bearing pin 4 arbitrarily angled rotations, and baffle plate 10 can make fix shaft 11 not break away from bare terminal 7; Said positioning through hole II top also is provided with two baffle plate spacing holes that are parallel to said positioning through hole II; Said baffle plate spacing hole is arranged on the both sides of baffle plate 10 positioning convex; Be provided with spring 6 in the said baffle plate spacing hole, the front end of said spring 6 is provided with depression bar 8, and the front end of said depression bar 8 protrudes from an end of said baffle plate spacing hole; The tail end of said spring 6 is fixed through the fastener 5 and the other end of said baffle plate spacing hole; Two depression bars 8 block the positioning convex on the baffle plate 10, but fix shaft 11 reliability of fixation are guaranteed in the position of fixed dam 10.
The invention still further relates to the method for application of a kind of steel plate upset handling with holes, comprise the steps: with instrument
1. two steel plate upset handlings with holes are fastened in said shackle 1 with steel rope 14 respectively with instrument, and hang on the suspension hook of overhead traveling crane, press said depression bar 8,, said fix shaft 11 is all taken out said baffle plate 10 half-twists with hand;
2. two steel plate upset handlings with holes are sling with instrument; Under the on even keel; Two said U type grooves are inserted into respectively on steel plate with holes 15 side end faces of need handling of horizontal positioned; Two steel plate upset handlings with holes should be installed in instrument on the line of centers two ends correspondence position of steel plate 15 with holes, when the hole on all said positioning through hole I 12 and the steel plate 15 with holes matches, are inserted into said fix shaft 11 in the said positioning through hole I 12; With said baffle plate 10 rotation returns, said depression bar 8 ejects fixes said baffle plate 10;
3. completing steps steel plate with holes 15 is 2. carried out the upset handling of parallel motion, 90 ° of upsets and 180 ° of upsets of level.
Wherein, said parallel motion (as shown in Figure 4) is that the steel rope 14 of two mounted with holes steel plate upset handlings with instrument all hung on the main suspension hook 13 of overhead traveling crane, together slings, and steel plate 15 with holes is hung other positions with moving of overhead traveling crane by level.
Said upset 90 ° (as shown in Figure 5) comprises by 90 ° of flip horizontals becoming vertically and becoming level for 90 ° by vertical upset; Said vertically is to have installed steel plate with holes upset handling with two to be hung on the main suspension hook 13 and secondary suspension hook 16 of overhead traveling crane with the steel rope 14 of instrument by 90 ° of one-tenth of flip horizontal; After main suspension hook of overhead traveling crane 13 and secondary suspension hook 16 be raised to certain altitude simultaneously; Main suspension hook 13 continues toward rising; And secondary suspension hook 16 stops to rise or descending; Be in vertical state (as shown in Figure 6) up to steel plate 15 with holes, instrument is used in the steel plate upset handling of laying down on the secondary suspension hook 16 with holes, again steel plate 15 with holes is winched to the position that needs placement; Said is steel plate upset handling with holes to be installed on the top of the steel plate with holes 15 under the vertical state use instrument by 90 ° of one-tenth levels of vertical upset; And said steel rope 14 hung on the main suspension hook 13 of overhead traveling crane, main suspension hook 13 rises steel plate 15 with holes is hung vertical position, will hang over steel plate upset handling with holes on the secondary suspension hook 16 is installed in steel plate 15 with holes with instrument lower end again; Secondary suspension hook 16 rises; Main suspension hook 13 descends, and till steel plate 15 with holes is horizontal, and is placed into assigned address.
180 ° of upsets of said level are to have installed steel plate with holes upset handling with two to be hung on the main suspension hook 13 and secondary suspension hook 16 of overhead traveling crane with the steel rope 14 of instrument; After main suspension hook of overhead traveling crane 13 and secondary suspension hook 16 be raised to certain altitude simultaneously; Main suspension hook 13 continues toward rising, and secondary suspension hook 16 stops to rise or descending, when steel plate 15 with holes is in vertical state; Steel plate upset handling with holes on the secondary suspension hook 16 is contained on the original position with instrument is counter; Also can not dismantle steel plate with holes upset handling and use instrument, only the ring in the shackle 1 rotated to bottom surface (the upper surface relative opposite side surface of the bottom surface of steel plate 15 with holes for its a horizontal positioned the time) side of steel plate 15 with holes and get final product, with secondary suspension hook 16 rises with hanger is fixing; Main suspension hook 13 descends, till steel plate 15 with holes is horizontal.
The above; Be merely the preferable specific embodiment of the present invention; But protection scope of the present invention is not limited thereto; Any technical personnel of being familiar with the present technique field is equal to replacement or change according to technical scheme of the present invention and inventive concept thereof in the technical scope that the present invention discloses, all should be encompassed within protection scope of the present invention.

Claims (8)

1. instrument is used in a steel plate upset handling with holes; Comprise bare terminal (7) and the shackle (1) of captiveing joint with the hanger that is arranged on said bare terminal (7) upper end; It is characterized in that: the lower surface of said bare terminal (7) has U-lag; The groove width of said U type groove is L, and L satisfies: L >=b, and wherein b is steel plate with holes (a 15) thickness; Said bare terminal (7) is provided with the positioning through hole I (12) that is complementary with fix shaft (11); The two side of the said U type groove of said positioning through hole I (12) perforation and vertical with the two side of said U type groove, said positioning through hole I (12) is complementary with the hole of said steel plate with holes (15); Also be provided with the positioning through hole II that is parallel to said positioning through hole I (12) between the upper surface of said U type groove top and said bare terminal (7); One end of bearing pin (4) is fixed in the said positioning through hole II through axle sleeve (3); The other end of said axle sleeve (4) is provided with baffle plate (10) and suspension ring (9), and said baffle plate (10) can be around the arbitrarily angled rotation of said bearing pin (4); Said positioning through hole II top also is provided with two baffle plate spacing holes that are parallel to said positioning through hole II; Be provided with spring (6) in the said baffle plate spacing hole; The front end of said spring (6) is provided with depression bar (8); The front end of said depression bar (8) protrudes from an end of said baffle plate spacing hole, and the tail end of said spring (6) is fixed through the fastener (5) and the other end of said baffle plate spacing hole.
2. steel plate upset handling with holes according to claim 1 is with instrument and method of application thereof; It is characterized in that: the number of said positioning through hole I (12) is at least 4, and the number of said fix shaft (11) is smaller or equal to the number of said positioning through hole I (12).
3. steel plate upset handling with holes according to claim 1 is with instrument and method of application thereof, and it is characterized in that: the inwall of said U-lag is provided with backing plate (2).
4. one kind by the method for application of the described steel plate with holes upset of claim 1 handling with instrument, comprises the steps:
1. use steel rope (14) to fasten in said shackle (1) respectively with instrument two steel plate upset handlings with holes; And hang on the suspension hook of overhead traveling crane; Press said depression bar (8) with hand,, said fix shaft (11) is all taken out said baffle plate (10) half-twist;
2. two steel plate upset handlings with holes are sling with instrument; Under the on even keel; Two said U type grooves are inserted into respectively on steel plate with holes (15) side end face of need handling of horizontal positioned; Two steel plate upset handlings with holes should be installed in instrument on the line of centers two ends correspondence position of steel plate with holes (15), when the hole on all said positioning through hole I (12) and the steel plate with holes (15) matches, are inserted into said fix shaft (11) in the said positioning through hole I (12); With said baffle plate (10) rotation return, said depression bar (8) ejects said baffle plate (10) fixing;
3. with the handling of overturning of completing steps steel plate with holes (15) 2..
5. steel plate upset handling with holes according to claim 4 is characterized in that with the method for application of instrument: said upset handling is parallel motion, upset 90 ° and 180 ° of upsets of level.
6. steel plate upset handling with holes according to claim 5 is with the method for application of instrument; It is characterized in that: said parallel motion is that the steel rope (14) of two mounted with holes steel plate upset handlings with instrument all hung on the main suspension hook (13) of overhead traveling crane; Together sling, steel plate with holes (15) is hung other positions with moving of overhead traveling crane by level.
7. steel plate with holes upset handling according to claim 5 is characterized in that with the method for application of instrument: 90 ° of said upsets comprise by 90 ° of flip horizontals become vertical with become level for 90 ° by vertical upset; Said vertically is to have installed steel plate with holes upset handling with two to be hung on the main suspension hook (13) and secondary suspension hook (16) of overhead traveling crane with the steel rope (14) of instrument by 90 ° of one-tenth of flip horizontal; After the main suspension hook (13) of overhead traveling crane and secondary suspension hook (16) be raised to certain altitude simultaneously; Main suspension hook (13) continues toward rising; And secondary suspension hook (16) stops to rise or descending; Be in vertical state up to steel plate with holes (15), instrument is used in the steel plate upset handling of laying down on the secondary suspension hook (16) with holes, again steel plate with holes (15) is winched to the position that needs placement; Said is steel plate upset handling with holes to be installed on the top of the steel plate with holes (15) under the vertical state use instrument by 90 ° of one-tenth levels of vertical upset; And said steel rope (14) hung on the main suspension hook (13) of overhead traveling crane; Main suspension hook (13) rises steel plate with holes (15) is hung vertical position; The steel plate with holes upset handling that will hang over again on the secondary suspension hook (16) is installed in the lower end of steel plate with holes (15) with instrument, and secondary suspension hook (16) rises, and main suspension hook (13) descends; Till steel plate with holes (15) is horizontal, and be placed into assigned address.
8. steel plate upset handling with holes according to claim 5 is with the method for application of instrument; It is characterized in that: 180 ° of upsets of said level are to have installed steel plate with holes upset handling with two to be hung on the main suspension hook (13) and secondary suspension hook (16) of overhead traveling crane with the steel rope (14) of instrument; After the main suspension hook (13) of overhead traveling crane and secondary suspension hook (16) be raised to certain altitude simultaneously; Main suspension hook (13) continues toward rising, and secondary suspension hook (16) stops to rise or descending, up to steel plate with holes (15) when being in vertical state; Steel plate upset handling with holes on the secondary suspension hook (16) is contained on the original position with instrument is counter; Secondary suspension hook (16) is risen, and main suspension hook (13) descends, till steel plate with holes (15) is horizontal.
CN201210247883.7A 2012-07-16 2012-07-16 Tool for overturning and lifting of steel plate with holes and its using method Active CN102785996B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210247883.7A CN102785996B (en) 2012-07-16 2012-07-16 Tool for overturning and lifting of steel plate with holes and its using method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210247883.7A CN102785996B (en) 2012-07-16 2012-07-16 Tool for overturning and lifting of steel plate with holes and its using method

Publications (2)

Publication Number Publication Date
CN102785996A true CN102785996A (en) 2012-11-21
CN102785996B CN102785996B (en) 2014-10-15

Family

ID=47151612

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210247883.7A Active CN102785996B (en) 2012-07-16 2012-07-16 Tool for overturning and lifting of steel plate with holes and its using method

Country Status (1)

Country Link
CN (1) CN102785996B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107055324A (en) * 2017-06-21 2017-08-18 中船第九设计研究院工程有限公司 A kind of equipment for supporting patient with burn of luxury liner thin plate segmentation
CN107512659A (en) * 2017-09-19 2017-12-26 张家港凯航通力船用设备有限公司 A kind of steel plate hoisting sling
CN109626201A (en) * 2018-12-29 2019-04-16 武船重型工程股份有限公司 A kind of truss bridge piece purlin turnover hoisting suspender and its application method
CN110104545A (en) * 2019-04-30 2019-08-09 哈电集团(秦皇岛)重型装备有限公司 A kind of tube sheet component hoisting and overturning tooling and hoisting and overturning method
CN112125157A (en) * 2020-10-19 2020-12-25 中国五冶集团有限公司 Turnover device for assisting in turnover of track beam and turnover method thereof

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5719275A (en) * 1980-07-03 1982-02-01 Hitachi Plant Eng & Constr Co Hanging device for remote control
DE3030041A1 (en) * 1980-08-08 1982-02-18 Dr.-Ing. Ludwig Müller + Söhne Gesellschaft für Bautechnik mbH & Co KG, 3550 Marburg WITH A MOBILE TOWING DEVICE, FOR EXAMPLE EASELY PROVIDED LOAD STOP DEVICE
JPH0683683U (en) * 1993-05-14 1994-11-29 レンフロージャパン株式会社 Clamp for hanging iron plate
DE10018549A1 (en) * 2000-04-14 2001-10-18 Thyssen Krupp Ag Load stop device with closing bolt has compression spring to load bolt in closing direction and cavity in end of bolt to receive spring
JP2002321890A (en) * 2001-04-25 2002-11-08 Sankyo Trading:Kk Suspender
CN202245719U (en) * 2011-09-27 2012-05-30 贵州赤天化股份有限公司 Steel plate fixture for lifting and overturning steel plate

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5719275A (en) * 1980-07-03 1982-02-01 Hitachi Plant Eng & Constr Co Hanging device for remote control
DE3030041A1 (en) * 1980-08-08 1982-02-18 Dr.-Ing. Ludwig Müller + Söhne Gesellschaft für Bautechnik mbH & Co KG, 3550 Marburg WITH A MOBILE TOWING DEVICE, FOR EXAMPLE EASELY PROVIDED LOAD STOP DEVICE
JPH0683683U (en) * 1993-05-14 1994-11-29 レンフロージャパン株式会社 Clamp for hanging iron plate
DE10018549A1 (en) * 2000-04-14 2001-10-18 Thyssen Krupp Ag Load stop device with closing bolt has compression spring to load bolt in closing direction and cavity in end of bolt to receive spring
JP2002321890A (en) * 2001-04-25 2002-11-08 Sankyo Trading:Kk Suspender
CN202245719U (en) * 2011-09-27 2012-05-30 贵州赤天化股份有限公司 Steel plate fixture for lifting and overturning steel plate

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107055324A (en) * 2017-06-21 2017-08-18 中船第九设计研究院工程有限公司 A kind of equipment for supporting patient with burn of luxury liner thin plate segmentation
CN107055324B (en) * 2017-06-21 2018-06-19 中船第九设计研究院工程有限公司 A kind of equipment for supporting patient with burn of luxury liner thin plate segmentation
CN107512659A (en) * 2017-09-19 2017-12-26 张家港凯航通力船用设备有限公司 A kind of steel plate hoisting sling
CN109626201A (en) * 2018-12-29 2019-04-16 武船重型工程股份有限公司 A kind of truss bridge piece purlin turnover hoisting suspender and its application method
CN110104545A (en) * 2019-04-30 2019-08-09 哈电集团(秦皇岛)重型装备有限公司 A kind of tube sheet component hoisting and overturning tooling and hoisting and overturning method
CN112125157A (en) * 2020-10-19 2020-12-25 中国五冶集团有限公司 Turnover device for assisting in turnover of track beam and turnover method thereof

Also Published As

Publication number Publication date
CN102785996B (en) 2014-10-15

Similar Documents

Publication Publication Date Title
CN102785996B (en) Tool for overturning and lifting of steel plate with holes and its using method
CN205600571U (en) Automobile gallows or skeleton push down automatic clamping device
WO2014169903A4 (en) Lashing plate and lashing means for lashing containers to a vehicle, in particular a ship, and the lashing system consisting thereof
CN206417777U (en) A kind of suspender of gravity-center adjustable position
CN202429879U (en) Unit type curtain plate hoisting device
CN204569129U (en) A kind of instrument of Novel hanging hot-rolled coil strap
CN214570169U (en) Many function combination cardboard hoist
CN108879472A (en) A kind of separation preventing coaster used for transmission line
CN204842646U (en) Drift device and punch press device
CN209608258U (en) A kind of cable testing bridge convenient for assembling
CN205826316U (en) Automobile metal plate work detection support
CN208214290U (en) A kind of low pressure casting machine installation mold mobile device
CN209210179U (en) A kind of steelmaking system buggy ladle follower replacement suspender
CN205740047U (en) Self-locking girder steel hoisting device
CN205380188U (en) Support base axle punching die
CN206104660U (en) Take drift of spring buckle
CN103171978A (en) Quick connector and tower crane with same
CN220811586U (en) Bearing frame handling appurtenance
CN204221627U (en) A kind of support changing shot-blasting machine ramming head
CN221253572U (en) Raw material hoisting tool for large-scale engineering truck rim production
CN209420058U (en) A kind of easy-to-dismount electrical cabinet of high-speed rail communication
CN203865834U (en) Tooling for mounting and dismounting diameter-expanding head
CN113942936B (en) Half wheel pair auxiliary overturning device and technology thereof
CN217966840U (en) Bearing dismounting horizontal press
CN214930973U (en) Battery module allotment couple

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CP03 Change of name, title or address
CP03 Change of name, title or address

Address after: 116113 No.1-1, MianHuaDao Road, Ganjingzi District, Dalian City, Liaoning Province

Co-patentee after: CHINA FIRST HEAVY INDUSTRIES

Patentee after: Dalian nuclear power and Petrochemical Co., Ltd

Address before: 116113 No. 1 cotton road, Dalian Bay, Ganjingzi District, Liaoning, Dalian

Co-patentee before: CHINA FIRST HEAVY INDUSTRIES

Patentee before: China First Heavy Machinery Group Dalian hydrogenation reactor Manufacturing Co.,Ltd.