CN102778215B - 一种矿井地下水库的库容确定方法 - Google Patents
一种矿井地下水库的库容确定方法 Download PDFInfo
- Publication number
- CN102778215B CN102778215B CN 201210256976 CN201210256976A CN102778215B CN 102778215 B CN102778215 B CN 102778215B CN 201210256976 CN201210256976 CN 201210256976 CN 201210256976 A CN201210256976 A CN 201210256976A CN 102778215 B CN102778215 B CN 102778215B
- Authority
- CN
- China
- Prior art keywords
- mine
- storehouse
- mine groundwater
- groundwater
- storage capacity
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 238000000034 method Methods 0.000 title claims abstract description 25
- 239000003245 coal Substances 0.000 claims abstract description 36
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 24
- 239000011435 rock Substances 0.000 claims abstract description 16
- 239000003673 groundwater Substances 0.000 claims description 80
- 238000009933 burial Methods 0.000 claims description 11
- 238000005065 mining Methods 0.000 abstract description 10
- 230000001105 regulatory effect Effects 0.000 abstract 1
- 238000005516 engineering process Methods 0.000 description 4
- 238000004458 analytical method Methods 0.000 description 1
- 239000007900 aqueous suspension Substances 0.000 description 1
- 238000004364 calculation method Methods 0.000 description 1
- 230000002950 deficient Effects 0.000 description 1
- 230000006866 deterioration Effects 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000011084 recovery Methods 0.000 description 1
- 230000001932 seasonal effect Effects 0.000 description 1
- 238000004088 simulation Methods 0.000 description 1
- 239000002351 wastewater Substances 0.000 description 1
Images
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
本发明公开了一种矿井地下水库的库容确定方法,所述方法包括如下步骤:步骤①:测定待测矿井地下水库的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸;步骤②:设定基准矿井地下水库,所述基准矿井地下水库的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸与待测矿井地下水库一致;步骤③:测定基准矿井地下水库的储水量V2、水库面积S及水头H,计算储水系数R=V2/SH;步骤④:测定待测矿井地下水库的水库体积V1,计算待测矿井地下水库的库容V=V1×R。本发明能够获得矿井地下水的库容,藉此调节矿区水资源。
Description
技术领域
本发明涉及一种水库库容确定方法,尤其涉及一种矿井地下水库的库容确定方法。
背景技术
我国西部地区赋存着丰富的煤炭资源,但水资源匮乏,水资源短缺对西部经济发展和人民生活的改善构成了严重威胁。煤炭开采过程中会产生矿井水,平均每开采一顿煤需要排放2吨废水,但是目前矿井地下水仍以抽排到地面为主,由于水资源利用的季节性等因素,造成水资源的极大浪费,加剧当地供给的失衡,同时,目前对矿井水悬浮物及水质的处理方法大多仍是在矿井水由井下排放在地面进行处理,也容易造成二次污染。这样的技术使得矿区用水及周边区域用水紧张的进一步恶化,严重地制约了矿区的正常生产,不利于资源与环境的协调发展。
目前,针对地下水资源的保护已有一些尝试,但是这些方法与技术都是通过井下或者地面处理净化矿井水的方法,对于西部等缺水地区而言,无法解决水资源供给季节性失衡的问题,同时地下水的流失也不利于当地生态环境的恢复,建立矿井地下水库是解决矿区用水难和用水不均衡的重要手段,因此实有必要测定矿井地下水库的库容来合理调配矿井地下水资源。
发明内容
针对现有技术存在的问题,本发明的目的是提供一种矿井地下水库的库容确定方法,该方法能够获得矿井地下水的库容,藉此调节矿区水资源。
本发明上述目的通过下述技术方案实现:
一种矿井地下水库的库容确定方法,所述方法包括如下步骤:
步骤①:测定待测矿井地下水库的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸;
步骤②:设定基准矿井地下水库,所述基准矿井地下水库的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸与待测矿井地下水库一致;
步骤③:测定基准矿井地下水库的储水量V2、水库面积S及水头H,计算储水系数R=V2/SH;
步骤④:测定待测矿井地下水库的水库体积V1,计算待测矿井地下水库的库容V=V1×R。
进一步地,步骤③中,通过充放基准矿井地下水库的储水确定基准矿井地下水库的储水量V2。
进一步地,步骤④中,根据矿井采空区的尺寸确定水库体积V1。
进一步地,所述方法还包括步骤⑤:测定待测矿井地下水库的水库面积S2及水头H2,计算待测矿井地下水库的储水量V3=S2×H2×R。
进一步地,步骤②中,所述基准矿井地下水库为的矿井地下水库模型,该模型具有与所述待测矿井地下水库的相同的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸。
进一步地,所述岩体强度为煤层抗碎强度。
本发明通过测定和计算水库体积及库容系数获得矿井地下水库库容,便于获知矿井地下水库的储水能力,藉此解决矿区调节矿区用水难和用水不均衡的问题,实现对地下水的合理保护。
附图说明
图1是本发明一种优选的矿井地下水库的库容确定方法的流程图。
具体实施方式
下面结合实施例,对发明做详细描述。
本发明提供的矿井地下水库的库容确定方法包括如下步骤:
步骤①:测定待测矿井地下水库的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸。例如地下水库的岩体强度(煤层抗碎强度)为88、煤层埋藏深度为95m、煤层厚度为3.7m及开采尺寸为200m×1500m。
步骤②:设定基准矿井地下水库,所述基准矿井地下水库的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸与待测矿井地下水库一致,本发明可优选地建立基准矿井地下水库模型,使该模型的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸与待测矿井地下水库一致。具体地,本发明的基准矿井地下水库模型通过相似材料模型试验建造并通过数值模拟计算分析。当然,考虑到待测矿井地下水库附近的采空区与待测矿井地下水库的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸相类似,本发明也可以采用与待测矿井地下水库类似的矿井采空区作为基准矿井地下水库,例如:本发明还可以采用神华集团神东矿区大柳塔矿地下水库2-2煤层地下水库、5-2煤层地下水库作为基准矿井地下水库。
步骤③:测定基准矿井地下水库的储水量V2、水库面积S及水头H,计算储水系数R=V2/SH。本发明可优选地通过充放基准矿井地下水库的储水来计算基准矿井地下水库的储水量V2。本发明可以实测单位时间流速、时间,计算储水量,也可以根据水泵参数(每小时排水量)来计算基准矿井地下水库的储水量V2例如,本实施例基准矿井地下水库的储水量V2=45000m3、水库面积S=300000m2、水头H=1m,因此根据R=V2/SH可知,神华集团神东矿区大柳塔矿地下水库2-2煤层六盘区地下水库的储水系数为0.15。
步骤④:测定待测矿井地下水库的水库体积V1,计算待测矿井地下水库的库容V=V1×R。本发明可优选地根据矿井采空区的尺寸确定水库体积V1。例如,神华集团神东矿区大柳塔矿2-2煤层六盘区地下水库的长1500m,宽600m,上覆基岩冒落带高度20m,因此,计算地下水库体积为18×106m3,从而根据V=V1×R可获得大柳塔矿2-2煤层六盘区地下水库的库容为27×105m3。
在获知水库的库容后,本发明还可以进一步地测定水库的储水量,其可通过步骤⑤实现:测定待测矿井地下水库的水库面积S2及水头H2,计算待测矿井地下水库的储水量V3=S2×H2×R。通过测定可知,大柳塔矿2-2煤层六盘区地下水库的水库面积S2为900000m2,水头H高度为1.2m,因此根据V3=S2×H2×R可以计算矿井地下水库的储水量为162000m3。
上述实施例仅供说明本发明之用,而并非是对本发明的限制,有关技术领域的普通技术人员,在不脱离本发明的精神和范围的情况下,还可以做出各种变化和变型,因此所有等同的技术方案也应属于本发明的范畴,本发明的专利保护范围应由各权利要求限定。
Claims (6)
1.一种矿井地下水库的库容确定方法,其特征在于,所述方法包括如下步骤:
步骤①:测定待测矿井地下水库的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸;
步骤②:设定矿井采空区作为基准矿井地下水库,所述基准矿井地下水库的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸与待测矿井地下水库一致;
步骤③:测定基准矿井地下水库的储水量V2、水库面积S1及水头H1,计算储水系数R=V2/S1H1;
步骤④:测定待测矿井地下水库的水库体积V1,计算待测矿井地下水库的库容V=V1×R。
2.根据权利要求1所述的矿井地下水库的库容确定方法,其特征在于,步骤③中,通过充放基准矿井地下水库的储水来确定基准矿井地下水库的储水量V2。
3.根据权利要求1所述的矿井地下水库的库容确定方法,其特征在于,步骤④中,根据矿井采空区的尺寸确定水库体积V1。
4.根据权利要求1所述的矿井地下水库的库容确定方法,其特征在于,所述方法还包括步骤⑤:测定待测矿井地下水库的水库面积S2及水头H2,计算待测矿井地下水库的储水量V3=S2×H2×R。
5.根据权利要求1所述的矿井地下水库的库容确定方法,其特征在于,步骤②中,所述基准矿井地下水库为矿井地下水库模型,该模型具有与所述待测矿井地下水库的相同的岩体强度、煤层埋藏深度、煤层厚度及开采尺寸。
6.根据权利要求5所述的矿井地下水库的库容确定方法,其特征在于,所述岩体强度为煤层抗碎强度。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201210256976 CN102778215B (zh) | 2012-07-23 | 2012-07-23 | 一种矿井地下水库的库容确定方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201210256976 CN102778215B (zh) | 2012-07-23 | 2012-07-23 | 一种矿井地下水库的库容确定方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102778215A CN102778215A (zh) | 2012-11-14 |
CN102778215B true CN102778215B (zh) | 2013-08-21 |
Family
ID=47123215
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201210256976 Active CN102778215B (zh) | 2012-07-23 | 2012-07-23 | 一种矿井地下水库的库容确定方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102778215B (zh) |
Families Citing this family (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102927941B (zh) * | 2012-11-20 | 2016-01-20 | 中国神华能源股份有限公司 | 一种露天煤矿地下水库的库容确定方法 |
CN203022816U (zh) | 2012-11-20 | 2013-06-26 | 中国神华能源股份有限公司 | 一种露天煤矿地下水库 |
CN104268344B (zh) * | 2014-09-28 | 2018-04-17 | 中国水利水电科学研究院 | 一种地下水库调蓄库容计算方法 |
CN107067339B (zh) * | 2017-01-10 | 2020-07-07 | 中国电建集团北京勘测设计研究院有限公司 | 一种寒冷及严寒地区抽水蓄能电站水库冰冻库容的计算方法 |
CN107194615A (zh) * | 2017-06-28 | 2017-09-22 | 中国神华能源股份有限公司 | 煤矿地下水库建设适用性的评价方法 |
CN107218974B (zh) * | 2017-07-17 | 2020-01-07 | 辽宁工程技术大学 | 一种煤矿地下水库储水系数测定装置 |
CN107525557B (zh) * | 2017-10-19 | 2018-08-17 | 中国矿业大学(北京) | 一种准确测量煤矿地下水库库容的方法 |
CN108169093B (zh) * | 2017-11-29 | 2021-06-08 | 中国神华能源股份有限公司 | 一种煤矿地下水库储水系数测定方法 |
CN108536891B (zh) * | 2018-02-23 | 2022-03-22 | 中国神华能源股份有限公司 | 地下水库储水量的计算方法、存储介质和装置 |
CN108457700B (zh) * | 2018-03-15 | 2023-04-18 | 中国矿业大学(北京) | 基于红外图像的矿井水仓监控报警*** |
CN108252740B (zh) * | 2018-03-15 | 2023-04-18 | 中国矿业大学(北京) | 基于图像的矿井涌水和水仓储水量监测*** |
CN109057861B (zh) * | 2018-08-28 | 2023-07-04 | 清华大学 | 一种露天煤矿地下水库、水库储水体及水库库容计算方法 |
CN113863985A (zh) * | 2020-06-30 | 2021-12-31 | 神华神东煤炭集团有限责任公司 | 一种量质耦合的矿井水收集与供应***及方法 |
CN113626991B (zh) * | 2021-07-20 | 2024-05-14 | 中国矿业大学 | 一种废弃被淹煤矿矿井水热储潜能计算方法 |
CN113586148A (zh) * | 2021-07-26 | 2021-11-02 | 国家能源投资集团有限责任公司 | 一种露天煤矿地下水库储水系数确定方法 |
CN116380188B (zh) * | 2023-05-19 | 2023-11-03 | 山东科技大学 | 一种采空区地下水库有效储水量测量方法 |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1659727A1 (ru) * | 1988-11-28 | 1991-06-30 | Институт Мерзлотоведения Со Ан Ссср | Способ определени объема подземной емкости |
US6628119B1 (en) * | 1998-08-28 | 2003-09-30 | Den Norske Stats Oljeselskap A.S. | Method and apparatus for determining the content of subterranean reservoirs |
CN101216338A (zh) * | 2007-12-27 | 2008-07-09 | 武汉理工大学 | 一种船舶排水量测量装置及其测量方法 |
CN101414013A (zh) * | 2007-10-17 | 2009-04-22 | 中国石油天然气股份有限公司 | 一种利用地震资料确定地下流体的方法 |
CN101619972A (zh) * | 2009-08-12 | 2010-01-06 | 国网电力科学研究院 | 一种水库蓄水量的测算方法 |
CN102305944A (zh) * | 2011-07-28 | 2012-01-04 | 李典基 | 一种水下淤积量探测分析处理*** |
CN102505943A (zh) * | 2011-11-21 | 2012-06-20 | 西安科技大学 | 一种水源地中小煤矿用保水采煤方法 |
-
2012
- 2012-07-23 CN CN 201210256976 patent/CN102778215B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SU1659727A1 (ru) * | 1988-11-28 | 1991-06-30 | Институт Мерзлотоведения Со Ан Ссср | Способ определени объема подземной емкости |
US6628119B1 (en) * | 1998-08-28 | 2003-09-30 | Den Norske Stats Oljeselskap A.S. | Method and apparatus for determining the content of subterranean reservoirs |
CN101414013A (zh) * | 2007-10-17 | 2009-04-22 | 中国石油天然气股份有限公司 | 一种利用地震资料确定地下流体的方法 |
CN101216338A (zh) * | 2007-12-27 | 2008-07-09 | 武汉理工大学 | 一种船舶排水量测量装置及其测量方法 |
CN101619972A (zh) * | 2009-08-12 | 2010-01-06 | 国网电力科学研究院 | 一种水库蓄水量的测算方法 |
CN102305944A (zh) * | 2011-07-28 | 2012-01-04 | 李典基 | 一种水下淤积量探测分析处理*** |
CN102505943A (zh) * | 2011-11-21 | 2012-06-20 | 西安科技大学 | 一种水源地中小煤矿用保水采煤方法 |
Non-Patent Citations (3)
Title |
---|
喀斯特地下水库与成库条件;邓自民;《贵州科学》;19950331;第13卷(第03期);17-22 * |
流域防洪***中地下水库调蓄能力分析与计算;郑德凤等;《大连理工大学学报》;20050210;第45卷(第01期);132-137 * |
重庆市海底沟岩溶地下水库研究;缪钟灵;《中国岩溶》;19911225;第10卷(第04期);306-312 * |
Also Published As
Publication number | Publication date |
---|---|
CN102778215A (zh) | 2012-11-14 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102778215B (zh) | 一种矿井地下水库的库容确定方法 | |
AU2013252230B2 (en) | Method for distributed storage and use of underground water in mine | |
CN103902780B (zh) | 固体充填采煤地表变形预计方法 | |
CN102865103B (zh) | 一种矿井地下水的分布式利用方法 | |
CN102071940B (zh) | 煤矿井筒穿越多层采空区的施工方法 | |
CN203658352U (zh) | 煤层采动诱发顶板涌水溃砂灾害模拟试验*** | |
CN103675237A (zh) | 煤层采动诱发顶板涌水溃砂灾害模拟试验***及监测方法 | |
CN103967494B (zh) | 一种浅孔留矿嗣后充填采矿方法 | |
CN101881169A (zh) | 一种分段留矿崩落阶段空场嗣后充填采矿法 | |
CN108303514B (zh) | 一种用于模拟煤矿地下封闭空间的试验装置 | |
CN104240133B (zh) | 地采转露采矿山采空区崩落***处理效果验收方法 | |
CN103089295A (zh) | 多煤层联合开采过程中煤层气抽采试验方法 | |
CN105464700A (zh) | 综采-充填混合开采工作面充填段长度确定方法 | |
CN102862775B (zh) | 一种矿井地下水的分布式存储方法 | |
CN108663724B (zh) | 一种基于水资源转移路径的煤矿地下水库位置选择方法 | |
CN103114827A (zh) | 多场耦合煤层气抽采模拟试验方法 | |
CN102562068B (zh) | 一种矿山开采嗣后胶结和非胶结充填采矿方法 | |
CN102865081A (zh) | 一种保水开采方法 | |
CN103089254A (zh) | 多场耦合煤层气开采物理模拟试验管 | |
CN103437803A (zh) | 一种煤矿高抽钻场钻孔瓦斯抽放结构和方法 | |
CN103557001A (zh) | 一种低段高无底柱留矿嗣后充填采矿法 | |
CN104931675A (zh) | 一种上保护层开采固气耦合相似模拟实验装置及实验方法 | |
CN106354911B (zh) | 一种顶板含水层采前预疏降安全水位确定方法 | |
CN106337687A (zh) | 矿山斜溜井便捷式分段支护方法 | |
CN107942035A (zh) | 一种用于相似模型***实验的裂隙三维形态获取方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |