CN102778008A CN2012102387518A CN201210238751A CN102778008A CN 102778008 A CN102778008 A CN 102778008A CN 2012102387518 A CN2012102387518 A CN 2012102387518A CN 201210238751 A CN201210238751 A CN 201210238751A CN 102778008 A CN102778008 A CN 102778008A
Authority
CN
China
Prior art keywords
monitoring host
host computer
cable
acquisition module
acquiring module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012102387518A
Other languages
Chinese (zh)
Inventor
曾骏林
曹建
闫召进
岳刚
余伟
张锦川
何宾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
MIANYANG ELECTRIC POWER BUREAU SICHUAN ELECTRIC POWER Corp
State Grid Corp of China SGCC
Original Assignee
Mianyang Power Bureau Sichuan Electric Power Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Mianyang Power Bureau Sichuan Electric Power Co ltd filed Critical Mianyang Power Bureau Sichuan Electric Power Co ltd
Priority to CN2012102387518A priority Critical patent/CN102778008A/en
Publication of CN102778008A publication Critical patent/CN102778008A/en
Pending legal-status Critical Current

Links

Landscapes

  • Ventilation (AREA)

Abstract

The invention provides a forced ventilating system of a cable chute. The forced ventilating system comprises a control centre host computer, monitoring host computers and an acquiring module, wherein a control centre is connected with at least one monitoring host computer to receive data of the monitoring host computers and send a control command to the monitoring host computers; each monitoring host computer is connected with the acquiring module arranged in the cable chute; the acquiring module is respectively connected with a water leaking detecting device, a temperature-humidity sensor and an infrared sensing probe so as to acquire the data, thereby the acquired data is transmited to the monitoring host computers; the monitoring host computers transmit a corresponding command according to the data acquired via the acquiring module, and the control command is transmitted to a fan remote control receiver through the acquiring module; and the fan remote controller is connected with a switch of a fan. Due to adoption of the forced ventilating system of the cable chute, therefore, safety of the working condition of a cable can be improved, and high degree of intelligent operation management can be provided..

Description

The cable duct forced ventilation system
Technical field
The present invention relates to be exclusively used in the pressure air draft cooling system of the various cable ducts of power system.
Background technology
At present, the cooling measure of cable duct is blank basically, and is dark moist because the cable duct present position is lower, and after cable channel cover plate covered, cable heating back temperature can not be discharged rapidly, and especially summer high temperature makes surface temperature higher equally, and cable environment of living in is abominable.The cable that the domestic Yin Gaowen that is shown in report causes explodes, causes that fire incident has several that this type of accident impact that betides in the transformer station is even more serious.Common way is to take to strengthen space in the cable duct, reduces cable density, and high pressure and secondary cable divide ditch to lay, the brush anti-flaming dope, and some passive measures of doing fire wall solve.Imperfection, unreliable, easy inefficacy.
Summary of the invention
Based on the problems referred to above, the present invention provides a kind of cable duct forced ventilation system.
The objective of the invention is to realize through following technical scheme:
The cable duct forced ventilation system; Comprise control centre's main frame, monitoring host computer, acquisition module; Said control centre is connected with at least one monitoring host computer, receives the data of monitoring host computer and monitoring host computer is sent control command, and each said monitoring host computer is connected with acquisition module in being located at cable duct; Said acquisition module is connected with water leak detectors, Temperature Humidity Sensor and infrared induction probe respectively; Through water leak detectors, Temperature Humidity Sensor and infrared induction probe image data, and image data sent to monitoring host computer, the data that said monitoring host computer is gathered according to acquisition module are sent corresponding order; Be sent on the blower fan receiver of remote-control sytem through acquisition module, said blower fan receiver of remote-control sytem is connected with the switch of blower fan.
Cable duct forced ventilation system provided by the invention to too high this problem of temperature in the cable duct, is tried to explore; Use for reference existing center monitoring system; Integrated relevant device and parts are formed system, and system intelligence is responded to temperature and humidity in the ditch, and contrast with open-air situation; Automatically control rotation speed of fan, adjusting is sent, exhaust air rate.Realize local and remote intelligent control and management, both satisfied aeration-cooling requirement in the cable duct, guarantee ventilation safety again, energy-saving and cost-reducing, change from passive to active, solved the problems referred to above effectively, improve cable environment for use safety, the intelligent degree of operational management is high.
Description of drawings
According to accompanying drawing and embodiment the present invention is done further explain below.
Fig. 1 is the modular structure figure of the said cable duct forced ventilation system of the embodiment of the invention.
The specific embodiment
As shown in Figure 1; The described cable duct forced ventilation system of the embodiment of the invention comprises control centre's main frame, monitoring host computer, acquisition module, and said control centre is connected with at least one monitoring host computer; Receive the data of monitoring host computer and monitoring host computer is sent control command; Each said monitoring host computer is connected with acquisition module in being located at cable duct, and said acquisition module is connected with water leak detectors, Temperature Humidity Sensor and infrared induction probe respectively, through water leak detectors, Temperature Humidity Sensor and the infrared induction image data of popping one's head in; And image data sent to monitoring host computer; The data that said monitoring host computer is gathered according to acquisition module are sent corresponding order, are sent on the blower fan receiver of remote-control sytem through acquisition module, and said blower fan receiver of remote-control sytem is connected with the switch of blower fan.
Cable duct forced ventilation system provided by the invention to too high this problem of temperature in the cable duct, is tried to explore; Use for reference existing center monitoring system; Integrated relevant device and parts are formed system, and system intelligence is responded to temperature and humidity in the ditch, and contrast with open-air situation; Automatically control rotation speed of fan, adjusting is sent, exhaust air rate.Realize local and remote intelligent control and management, both satisfied aeration-cooling requirement in the cable duct, guarantee ventilation safety again, energy-saving and cost-reducing, change from passive to active, solved the problems referred to above effectively, improve cable environment for use safety, the intelligent degree of operational management is high.
Advantage of the present invention comprises:
1, system automation degree height: advanced computer technology, network communications technology etc. are adopted in this invention, can realize easily each equipment running status is shown processing etc.; Native system has fault and detects and expert diagnosis function and abundant warning function automatically, has greatly alleviated operation maintenance personnel burden, has improved the cable reliability of operation, has realized the scientific management for cable duct.
2, fault warning function: inside and outside sensor fault, exchange alarms such as power failure fault, fire, infrared, water logging;
3, the customized adopted temperature setting of system effectively is provided with start-up temperature according to the ditch internal and external condition, reaches energy-saving effect.And possess the manual-operated emergent function, but enforced opening blower fan in case of necessity.

Claims (1)

1. cable duct forced ventilation system; It is characterized in that, comprise control centre's main frame, monitoring host computer, acquisition module, said control centre is connected with at least one monitoring host computer; Receive the data of monitoring host computer and monitoring host computer is sent control command; Each said monitoring host computer is connected with acquisition module in being located at cable duct, and said acquisition module is connected with water leak detectors, Temperature Humidity Sensor and infrared induction probe respectively, through water leak detectors, Temperature Humidity Sensor and the infrared induction image data of popping one's head in; And image data sent to monitoring host computer; The data that said monitoring host computer is gathered according to acquisition module are sent corresponding order, are sent on the blower fan receiver of remote-control sytem through acquisition module, and said blower fan receiver of remote-control sytem is connected with the switch of blower fan.
CN2012102387518A 2012-07-11 2012-07-11 Forced ventilating system of cable chute Pending CN102778008A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012102387518A CN102778008A (en) 2012-07-11 2012-07-11 Forced ventilating system of cable chute

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012102387518A CN102778008A (en) 2012-07-11 2012-07-11 Forced ventilating system of cable chute

Publications (1)

Publication Number Publication Date
CN102778008A true CN102778008A (en) 2012-11-14

Family

ID=47123017

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012102387518A Pending CN102778008A (en) 2012-07-11 2012-07-11 Forced ventilating system of cable chute

Country Status (1)

Country Link
CN (1) CN102778008A (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103019186A (en) * 2012-11-28 2013-04-03 重庆市电力公司检修分公司 Intelligent comprehensive substation cable trench monitoring and protecting system
CN103163921A (en) * 2013-03-14 2013-06-19 河南省电力公司南阳供电公司 Cable trench intelligent management system
CN104674907A (en) * 2013-11-30 2015-06-03 镇江康元电器有限公司 Leaked water collecting device

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201293422Y (en) * 2008-09-10 2009-08-19 西北电网有限公司西宁输变电运行公司 Intelligent cable trench drafting and moisture removing cover device
CN101656411A (en) * 2009-08-11 2010-02-24 河南省电力公司新乡供电公司 Moisture discharge device of cable trench
CN201504075U (en) * 2009-08-11 2010-06-09 河南省电力公司新乡供电公司 Moisture eliminating device for cable channel
CN201556083U (en) * 2009-06-11 2010-08-18 安徽省电力公司蚌埠供电公司 Cable head temperature integrated monitoring device for cable trench of transformer substation
CN102214383A (en) * 2010-04-02 2011-10-12 秦大为 Temperature-measuring, early-warning and temperature-reducing system for cable connectors
CN202260350U (en) * 2011-09-19 2012-05-30 辽宁省电力有限公司鞍山超高压分公司 Vented exhaust device of cable duct
CN202719719U (en) * 2012-07-11 2013-02-06 四川省电力公司绵阳电业局 Forced ventilation system for cable duct

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201293422Y (en) * 2008-09-10 2009-08-19 西北电网有限公司西宁输变电运行公司 Intelligent cable trench drafting and moisture removing cover device
CN201556083U (en) * 2009-06-11 2010-08-18 安徽省电力公司蚌埠供电公司 Cable head temperature integrated monitoring device for cable trench of transformer substation
CN101656411A (en) * 2009-08-11 2010-02-24 河南省电力公司新乡供电公司 Moisture discharge device of cable trench
CN201504075U (en) * 2009-08-11 2010-06-09 河南省电力公司新乡供电公司 Moisture eliminating device for cable channel
CN102214383A (en) * 2010-04-02 2011-10-12 秦大为 Temperature-measuring, early-warning and temperature-reducing system for cable connectors
CN202260350U (en) * 2011-09-19 2012-05-30 辽宁省电力有限公司鞍山超高压分公司 Vented exhaust device of cable duct
CN202719719U (en) * 2012-07-11 2013-02-06 四川省电力公司绵阳电业局 Forced ventilation system for cable duct

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄翔: "《空调工程》", 31 May 2006 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103019186A (en) * 2012-11-28 2013-04-03 重庆市电力公司检修分公司 Intelligent comprehensive substation cable trench monitoring and protecting system
CN103163921A (en) * 2013-03-14 2013-06-19 河南省电力公司南阳供电公司 Cable trench intelligent management system
CN104674907A (en) * 2013-11-30 2015-06-03 镇江康元电器有限公司 Leaked water collecting device

Similar Documents

Publication Publication Date Title
CN105234952B (en) Household monitoring robot control system based on STM32
CN104868843B (en) Data processing method for solar photovoltaic module array data collection device
CN104793671A (en) Temperature and humidity regulating system and temperature and humidity regulating method of control cubicle of intelligent substation
CN207319330U (en) A kind of wireless security system based on Internet of Things
CN102778008A (en) Forced ventilating system of cable chute
CN202719719U (en) Forced ventilation system for cable duct
CN104238522A (en) Substation equipment fault locating system based on GPS
CN110049283A (en) Battery cupboard intelligent monitor system
CN206959901U (en) A kind of IT-room environment monitoring system
CN103353778A (en) Auxiliary monitoring, early-warning and processing system for power distribution automation
CN107726559A (en) A kind of intelligent building air-conditioning system
CN110944156A (en) Terminal equipment for monitoring power distribution room
CN106843187A (en) A kind of family intelligent monitoring system
CN207182049U (en) A kind of heat exchange station intelligent measurement and control system
CN207249435U (en) Access the things-internet gateway and remote monitoring system of automatic fire alarm control system
CN107329447A (en) A kind of heat exchange station intelligent measurement and control system
CN204595655U (en) A kind of intelligent substation convergence control cabinet temperature humidity regulating system
CN206877180U (en) A kind of circuit breaker mechanism case temperature and humidity control device and unified monitoring system
CN207251654U (en) Fire-fighting things-internet gateway equipment
CN206602590U (en) A kind of video monitoring apparatus
CN208256088U (en) Multifunction wireless measures component
CN204104069U (en) Camera failure detector
CN206330261U (en) A kind of wireless PM2.5 monitoring systems
CN203324867U (en) Smart host based on power distribution automation auxiliary monitoring, early warning and processing system
CN106197698A (en) A kind of power equipment temperature monitoring method and system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
ASS Succession or assignment of patent right

Owner name: MIANYANG ELECTRIC POWER BUREAU OF SICHUAN ELECTRIC

Effective date: 20130618

Owner name: STATE ELECTRIC NET CROP.

Free format text: FORMER OWNER: MIANYANG ELECTRIC POWER BUREAU OF SICHUAN ELECTRIC POWER CORP.

Effective date: 20130618

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 621000 MIANYANG, SICHUAN PROVINCE TO: 100000 XICHENG, BEIJING

TA01 Transfer of patent application right

Effective date of registration: 20130618

Address after: 100000 Xicheng District West Chang'an Avenue, No. 86, Beijing

Applicant after: State Grid Corporation of China

Applicant after: Mianyang Electric Power Bureau, Sichuan Electric Power Corporation

Address before: 621000 Mianyang city of Sichuan Province sword South Road West No. 16

Applicant before: Mianyang Electric Power Bureau, Sichuan Electric Power Corporation

C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20121114

RJ01 Rejection of invention patent application after publication