CN102767175A - Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof - Google Patents

Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof Download PDF

Info

Publication number
CN102767175A
CN102767175A CN2012102403760A CN201210240376A CN102767175A CN 102767175 A CN102767175 A CN 102767175A CN 2012102403760 A CN2012102403760 A CN 2012102403760A CN 201210240376 A CN201210240376 A CN 201210240376A CN 102767175 A CN102767175 A CN 102767175A
Authority
CN
China
Prior art keywords
reinforcing cage
muscle
reinforcement
reinforcement cage
hole
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012102403760A
Other languages
Chinese (zh)
Inventor
成志辉
曾佳
赵自亮
苏剑良
李慧莹
周翰章
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Hengsheng Construction Engineering Co Ltd
Original Assignee
Guangzhou Hengsheng Construction Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Hengsheng Construction Engineering Co Ltd filed Critical Guangzhou Hengsheng Construction Engineering Co Ltd
Priority to CN2012102403760A priority Critical patent/CN102767175A/en
Publication of CN102767175A publication Critical patent/CN102767175A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a concrete-pouring method for a soft-soil foundation punched filling pile, which comprises the following steps of: a) forming holes in a soft-soil foundation through impacting and cleaning the holes; b) determining the length of steel-reinforcement cages with axial main reinforcements according to the hole depth of pile holes, wherein each steel-reinforcement cage comprises a flow-limiting net which is packaged at the periphery of the steel-reinforcement cage; c) placing the steel-reinforcement cages into the pile holes, and installing in segments when the quantity of the steel-reinforcement cages in the step b) exceeds a segment; and d) pouring concrete to a designed elevation. The invention also discloses the steel-reinforcement cage which is used in the pouring method and comprises an internal spiral reinforcement and a plurality of axial main reinforcements, wherein the internal spiral reinforcement is provided with a central axis, and the axial main reinforcements are arrayed by surrounding the circumference of the central axis and are connected with the internal spiral reinforcement to form a steel-reinforcement cage framework; and the flow-limiting net is arranged on the steel-reinforcement cage framework. According to the method, the peripheral impact of the concrete is limited by utilizing the flow-limiting nets, so that the construction quality of the filling pile is improved. The method is applicable to carrying out the concrete-pouring construction operation of the punched filling pile on the soft-soil foundation.

Description

Soft foundation punching cast-in-place pile concrete pouring procedure and used reinforcing cage thereof
Technical field
The present invention relates to a kind of method of on soft foundation, carrying out the punching pile driving construction, and the reinforcing cage of using in the method.
Background technology
The punching castinplace pile is to adopt the Churn drill pore-forming, and perfusion steel concrete forms in the hole then, is mainly used in pore-forming in the rock-soil layer.Adopt mud off during pore-forming, will after the bevel-type drill bit rises to certain altitude, come broken rock, draw the slag slurry of getting in the hole with positive and negative mud circulation then, transfer reinforcing cage and concreting pile after scarfing cinder meets the demands with the impact force of free-falling.Soft foundation is meant the geological environment that mainly is made up of mud, mucky soil or other high-compressibility soil layers.Mainly be distributed in fluvial facies, lake phase of wave, the marsh equal area in coastal littoral facies, delta facies, inland plain or mountain area.Have high-moisture, the high-voidage ratio, characteristic such as permeability is low, and compressibilty is high, and shear strength is low has characteristics such as significant thixotropy and creep properties.If on soft foundation, carry out being in the milk in percussion drilling, the hole, just be easy to hole, broken pile because concrete impact force and peripheral diffusion-induced stress cause collapsing.For fear of this situation occurring, generally adopt technical measures such as impact energy control, the control of pile monkey diameter, mud balance control at present.
Impact energy control is exactly that pointer adopts different block stamp strokes to different soil layers, reduces in the pore forming process the disturbance of soil layer on every side, and the phenomenon in the hole that prevents to collapse takes place, and reduces counter bore diameter; Select for use less than the pile monkey in design stake footpath (little by 50~80mm) usually when the control of pile monkey diameter is meant practice of construction; In the pore forming process in later stage; Become big because of the thixotropy of weak soil causes drilling diameter, make drilling diameter satisfy designing requirement, reach the purpose that reduces fullness coefficient; Mud balance control is meant the proportion of control slurry coat method, to different soil control mud balance, reduces the probability of happening of collapse hole, necking.But, more than three kinds of measures, all can not realize its effect well, poor control property, and cause site operation and design to disconnect.
Summary of the invention
The object of the invention; Be to provide a kind of method of on soft foundation, carrying out the cast of punching cast-in-place pile concrete; It can let actual stake hole conform to a design stake hole, and needn't adopt the not high technical measures of controllability such as impact energy control, the control of pile monkey diameter, mud balance control avoid collapsing hole, broken pile.
Another object of the present invention also is to provide a kind of reinforcing cage that is used to realize said soft foundation punching cast-in-place pile concrete pouring procedure.
The solution that the present invention solves its technical problem is:
Soft foundation punching cast-in-place pile concrete pouring procedure may further comprise the steps:
A), on soft foundation impact holing, obtain a hole, and to stake Kong Qingkong;
B), according to stake hole hole depth, confirm to have the length of the reinforcing cage of axial main muscle, said reinforcing cage comprises and is wrapped in its peripheral current limiting net;
C), insert the reinforcing cage in the step b) in the hole, when the reinforcing cage quantity in the step b) surpasses one section, need segmentation to install toward stake;
D), concrete perfusion is until design elevation.
As the further improvement of technique scheme, the reinforcing cage segmentation in the said step c) is installed, and may further comprise the steps:
C1), in the stake hole, lift one section reinforcing cage and fixing;
C2), lifting hypomere reinforcing cage, through the overlap welding between the axial main muscle, the bottom of this section reinforcing cage is connected with reinforcing cage in the hole;
C3), linkage section colligation current limiting net and fixing;
C4), will pass through step c3) assembly of the reinforcing cage that comes out of made continues to transfer;
C5), repeat c2)~c4) step, all be linked to be same section until all reinforcing cages, satisfy the dark requirement of stake.
In addition; The reinforcing cage of using in a kind of soft foundation punching cast-in-place pile concrete pouring procedure; It comprises inside spin muscle and the axial main muscle of Duo Gen, and said inside spin muscle has the axis, and said many axial main muscle are circumference array around said axis; And connect with the inside spin muscle, form reinforcement cage skeleton thus; Said reinforcement cage skeleton is provided with current limiting net.
As the further improvement of technique scheme, said current limiting net is an electrowelding net, and its colligation is on the surface of reinforcement cage skeleton.
As the further improvement of technique scheme, on the external surface of said reinforcement cage skeleton, coiling has the external spiral stirrup.
As the further improvement of technique scheme, said reinforcement cage skeleton is provided with a plurality of ear muscle, and said ear muscle is " several " glyph shape, and two ends connect with axial main muscle, and the external spiral stirrup connects with the ear muscle.
As the further improvement of technique scheme, the specification of said electrowelding net is: silk footpath Ф 0.899mm, hole 10.6mm * 10.6mm.
As the further improvement of technique scheme, the height of said ear muscle is greater than 30mm, and it is provided with density and is: whenever along the reinforcement cage skeleton axis establish together at a distance from 0.5m, each road is along 4 of circumference; The external spiral stirrup connects with the spot welding of ear muscle.
As the further improvement of technique scheme, current limiting net adopts the colligation of #20 galvanized wire to the surface of reinforcement cage skeleton.
The invention has the beneficial effects as follows: the present invention inserts the reinforcing cage that the periphery is enclosed with current limiting net in the stake hole on the soft foundation; Can let on the one hand its muscles and bones as the cast-in-place concrete pile pile body; On the other hand when fluid concrete in the stake hole; Current limiting net can limit the radial impact of concrete to peripheral weak soil effectively, has reduced concrete horizontal lateral displacement, has reduced the fullness coefficient of castinplace pile.Adopted job practices of the present invention can need not to correct the stroke size repeatedly, shortened the pore-forming time, practiced thrift the duration of a project according to formation variation; Job practices of the present invention adapts to plastic flow mud, the soft all kinds soft stratums such as shape mud, sandy soil of moulding, and is applied widely; Job practices of the present invention can adopt the pile monkey construction of satisfying the intended diameter size, and the stake diameter into the rock section is met design requirement, and improves the construction quality of castinplace pile.Reinforcing cage among the present invention is exactly to achieve these goals, reaches construction effect design.The present invention is applicable to the pouring concrete construction operation of on soft foundation, carrying out the punching castinplace pile.
Description of drawings
In order to be illustrated more clearly in the technical scheme in the embodiment of the invention, the accompanying drawing of required use is done simple declaration in will describing embodiment below.Obviously, described accompanying drawing is a part of embodiment of the present invention, rather than whole embodiment, and those skilled in the art can also obtain other design schemes and accompanying drawing according to these accompanying drawings under the prerequisite of not paying creative work.
Fig. 1 is that reinforcing cage among the present invention is along the structural representation of its whole radial direction projection;
Fig. 2 is that reinforcing cage among the present invention is along the structural representation of its whole axial direction projection.
The specific embodiment
Below will combine embodiment and accompanying drawing that the technique effect of design of the present invention, concrete structure and generation is carried out clear, complete description, to understand the object of the invention, characteristic and effect fully.Obviously; Described embodiment is a part of embodiment of the present invention, rather than whole embodiment, based on embodiments of the invention; Other embodiment that those skilled in the art is obtained under the prerequisite of not paying creative work all belong to the scope that the present invention protects.In addition, all connection/annexations of being mentioned in the literary composition are not to refer to that singly member directly joins, and are meant and can connect auxiliary through adding or reducing according to the practical implementation situation, form more excellent draw bail.
With reference to Fig. 1~Fig. 2; The reinforcing cage of using in a kind of soft foundation punching cast-in-place pile concrete pouring procedure; It comprises inside spin muscle 1 and the axial main muscle 2 of Duo Gen, and said inside spin muscle 1 has the axis, and said many axial main muscle 2 are circumference array around said axis; And connect with inside spin muscle 1, form reinforcement cage skeleton thus; Said reinforcement cage skeleton is provided with current limiting net 3.
Further as preferred embodiment, said current limiting net 3 is an electrowelding net, and its colligation is on the surface of reinforcement cage skeleton.
Further as preferred embodiment, on the external surface of said reinforcement cage skeleton, coiling has external spiral stirrup 4.This shows that above-mentioned current limiting net 3 colligations are not that the outermost layer that refers to reinforcing cage itself is current limiting net 3, and are meant that current limiting net 3 is positioned near the abutment surface, fix through the coupling colligation then on the surface of reinforcement cage skeleton.Preferably, be employed in the method for outermost layer coiling external spiral stirrup 4, come further to strengthen the steadiness of current limiting net 3, and can protect current limiting net 3, it is difficult for because of concrete impacts excessive large tracts of land drawing crack, keep whole complete.
Further as preferred embodiment, said reinforcement cage skeleton is provided with a plurality of ear muscle 5, and said ear muscle 5 is " several " glyph shape, and two ends connect with axial main muscle 2, and external spiral stirrup 4 connects with ear muscle 5.Through ear muscle 5, can be effectively with the ectonexine reinforcing bar, promptly axial main muscle 2 links up with external spiral stirrup 4, forms a firm reinforcement cage skeleton.
Further as preferred embodiment, the specification of said electrowelding net is: silk footpath Ф 0.899mm, hole 10.6mm * 10.6mm.
Further as preferred embodiment, the height of said ear muscle 5 is greater than 30mm, and it is provided with density and is: whenever along the reinforcement cage skeleton axis establish together at a distance from 0.5m, each road is along 4 of circumference; External spiral stirrup 4 connects with 5 spot welding of ear muscle.
Further as preferred embodiment, current limiting net 3 adopts the colligation of #20 galvanized wire to the surface of reinforcement cage skeleton.
After producing above-mentioned reinforcing cage, just can carry out the concrete pouring of soft foundation punching castinplace pile.
Soft foundation punching cast-in-place pile concrete pouring procedure may further comprise the steps:
A), on soft foundation impact holing, obtain a hole, and to stake Kong Qingkong;
B), according to stake hole hole depth, confirm to have the length of the reinforcing cage of axial main muscle 2, said reinforcing cage comprises and is wrapped in its peripheral current limiting net 3;
C), insert the reinforcing cage in the step b) in the hole, when the reinforcing cage quantity in the step b) surpasses one section, need segmentation to install toward stake;
D), concrete perfusion is until design elevation.
Further as preferred embodiment, the reinforcing cage segmentation in the said step c) is installed, and may further comprise the steps:
C1), in the stake hole, lift one section reinforcing cage and fixing;
C2), lifting hypomere reinforcing cage, through the overlap welding between the axial main muscle 2, the bottom of this section reinforcing cage is connected with reinforcing cage in the hole; Particularly, every section reinforcing cage lap joint adopts the arc welding welding, lap length one side welding 10d or double welding 5d, and same cross section top connection quantity must not be greater than 50%, and adjacent spacing is 35d and is not less than 500mm;
C3), linkage section colligation current limiting net 3 and fixing; Particularly, during colligation, pass mesh with galvanized wire and be connected with ear muscle 5 or inside spin muscle 1; The overlap joint wide cut of electrowelding net should satisfy level and be no less than 20 road steel wires to lap length, vertically is no less than 40 road steel wires to lap length; Prick silk colligation spacing and be not more than 15 road silks, lap-joint's bundle silk spacing should be encrypted to and be not more than 10 road steel wires; Certainly, when making the single hop reinforcing cage separately, also adopt this colligation rule, to guarantee integral uniform property;
C4), will pass through step c3) assembly of the reinforcing cage that comes of made continues to transfer;
C5), repeat c2)~c4) step, all be linked to be same section until all reinforcing cages, satisfy the dark requirement of stake.This shows, if the stake hole is darker, can adopt to transfer one section-another section of slinging-connections-integral body and transfer-another section of slinging again-form of construction work of connection again.
More than be that preferred embodiments of the present invention is specified; But the invention is not limited to said embodiment; Those of ordinary skill in the art also can make all equivalent modifications or replacement under the prerequisite of spirit of the present invention, modification that these are equal to or replacement all are included in the application's claim institute restricted portion.

Claims (9)

1. soft foundation punching cast-in-place pile concrete pouring procedure is characterized in that: may further comprise the steps:
A), on soft foundation impact holing, obtain a hole, and to stake Kong Qingkong;
B), according to stake hole hole depth, confirm to have the length of the reinforcing cage of axial main muscle, said reinforcing cage comprises and is wrapped in its peripheral current limiting net;
C), insert the reinforcing cage in the step b) in the hole, when the reinforcing cage quantity in the step b) surpasses one section, need segmentation to install toward stake;
D), concrete perfusion is until design elevation.
2. soft foundation punching cast-in-place pile concrete pouring procedure according to claim 1 is characterized in that: the reinforcing cage segmentation in the said step c) is installed, and may further comprise the steps:
C1), in the stake hole, lift one section reinforcing cage and fixing;
C2), lifting hypomere reinforcing cage, through the overlap welding between the axial main muscle, the bottom of this section reinforcing cage is connected with reinforcing cage in the hole;
C3), linkage section colligation current limiting net and fixing;
C4), will pass through step c3) assembly of the reinforcing cage that comes out of made continues to transfer;
C5), repeat c2)~c4) step, all be linked to be same section until all reinforcing cages, satisfy the dark requirement of stake.
3. the reinforcing cage of using in the claim 1 or 2; It is characterized in that: comprise the axial main muscle of inside spin muscle and Duo Gen, said inside spin muscle has the axis, and said many axial main muscle are circumference array around said axis; And connect with the inside spin muscle, form reinforcement cage skeleton thus; Said reinforcement cage skeleton is provided with current limiting net.
4. reinforcing cage according to claim 3 is characterized in that: said current limiting net is an electrowelding net, and its colligation is on the surface of reinforcement cage skeleton.
5. reinforcing cage according to claim 4 is characterized in that: on the external surface of said reinforcement cage skeleton, coiling has the external spiral stirrup.
6. reinforcing cage according to claim 5 is characterized in that: said reinforcement cage skeleton is provided with a plurality of ear muscle, and said ear muscle is " several " glyph shape, and two ends connect with axial main muscle, and the external spiral stirrup connects with the ear muscle.
7. according to claim 4,5 or 6 described reinforcing cages, it is characterized in that: the specification of said electrowelding net is: silk footpath Ф 0.899mm, hole 10.6mm * 10.6mm.
8. reinforcing cage according to claim 6 is characterized in that: the height of said ear muscle is greater than 30mm, and it is provided with density and is: whenever along the reinforcement cage skeleton axis establish together at a distance from 0.5m, each road is along 4 of circumference; The external spiral stirrup connects with the spot welding of ear muscle.
9. reinforcing cage according to claim 4 is characterized in that: current limiting net adopts the colligation of #20 galvanized wire to the surface of reinforcement cage skeleton.
CN2012102403760A 2012-07-11 2012-07-11 Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof Pending CN102767175A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012102403760A CN102767175A (en) 2012-07-11 2012-07-11 Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012102403760A CN102767175A (en) 2012-07-11 2012-07-11 Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof

Publications (1)

Publication Number Publication Date
CN102767175A true CN102767175A (en) 2012-11-07

Family

ID=47094725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012102403760A Pending CN102767175A (en) 2012-07-11 2012-07-11 Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof

Country Status (1)

Country Link
CN (1) CN102767175A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362123A (en) * 2013-07-05 2013-10-23 山东科技大学 Reverse Y-shaped filling pile and construction method thereof
CN104179172A (en) * 2014-08-04 2014-12-03 河北建设勘察研究院有限公司 Construction method for orifice connection of bored pile reinforcement cage
CN107119674A (en) * 2017-05-03 2017-09-01 苏州波森特岩土工程有限公司 A kind of bored concrete pile and its construction method for having a lateral spacing
CN111926802A (en) * 2020-07-03 2020-11-13 顾鑫平 High-strength precast concrete pile and pouring process thereof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS637416A (en) * 1986-06-26 1988-01-13 Kumagai Gumi Ltd Construction of hollow concrete structure under ground
CN1598165A (en) * 2004-08-05 2005-03-23 陈佳训 Method for pile foundation construction of geologic structure with flow plastic half-flow plastic and its application apparatus
JP2007002550A (en) * 2005-06-24 2007-01-11 Daia Soil Kk Reinforcement cage for concrete pile
CN102400460A (en) * 2011-11-30 2012-04-04 昆明捷程桩工有限责任公司 Construction method for preventing pile diameter of concrete pouring pile from being varied
CN202482886U (en) * 2011-12-13 2012-10-10 中国二十冶集团有限公司 Cast-in-place pile steel reinforcement cage for ultra-thick high compression peat soil layer structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS637416A (en) * 1986-06-26 1988-01-13 Kumagai Gumi Ltd Construction of hollow concrete structure under ground
CN1598165A (en) * 2004-08-05 2005-03-23 陈佳训 Method for pile foundation construction of geologic structure with flow plastic half-flow plastic and its application apparatus
JP2007002550A (en) * 2005-06-24 2007-01-11 Daia Soil Kk Reinforcement cage for concrete pile
CN102400460A (en) * 2011-11-30 2012-04-04 昆明捷程桩工有限责任公司 Construction method for preventing pile diameter of concrete pouring pile from being varied
CN202482886U (en) * 2011-12-13 2012-10-10 中国二十冶集团有限公司 Cast-in-place pile steel reinforcement cage for ultra-thick high compression peat soil layer structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
苏宏阳,郦锁林 等: "《基础工程施工手册》", 30 June 2002, 中国计划出版社, article "灌注桩", pages: 555-559 *

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103362123A (en) * 2013-07-05 2013-10-23 山东科技大学 Reverse Y-shaped filling pile and construction method thereof
CN104179172A (en) * 2014-08-04 2014-12-03 河北建设勘察研究院有限公司 Construction method for orifice connection of bored pile reinforcement cage
CN104179172B (en) * 2014-08-04 2016-02-24 河北建设勘察研究院有限公司 A kind of filling pile cage of reinforcement aperture connection construction method
CN107119674A (en) * 2017-05-03 2017-09-01 苏州波森特岩土工程有限公司 A kind of bored concrete pile and its construction method for having a lateral spacing
CN111926802A (en) * 2020-07-03 2020-11-13 顾鑫平 High-strength precast concrete pile and pouring process thereof
CN111926802B (en) * 2020-07-03 2021-09-07 广东港粤建设工程有限公司 High-strength concrete pile and pouring process thereof

Similar Documents

Publication Publication Date Title
CN105544575B (en) A kind of bottom concrete construction method under water of use steel truss reinforcement
CN102767175A (en) Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof
CN110331727A (en) The supporting construction and construction method that bored concrete pile and diaphram wall combine
CN104563147B (en) Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation
CN109989395B (en) Large storage tank filling pile assembled pile cap and construction method thereof
CN114351693A (en) Collapse hole underpinning device for rotary excavating cast-in-place pile and underpinning construction method
JP5919675B2 (en) Composite foundation pile and construction method of composite foundation pile
CN105821771B (en) Overlength case bridge jacking construction technique and its constructing structure under high roadbed city expressway
CN209838429U (en) Back anchor shield constructs lining cutting supporting construction
CN210263026U (en) Anti structure that floats of hole-forming bored concrete pile steel sleeve is protected to mud dado of going out terrace
CN108086307B (en) Steel pipe concrete hole digging and pouring composite miniature pile
CN106759264A (en) One kind grouting pipe network and its construction method
CN108277817B (en) Construction method of high-pile bearing platform tower crane foundation reinforcing structure
CN206706803U (en) Large diameter steel pipe concrete-pile
CN213114605U (en) A steel reinforcement cage that is used for bored concrete pile of karst landform to be under construction
CN210766789U (en) Device for positioning and controlling verticality of reinforcing cage of manual hole digging pile
CN101691753B (en) Pile mould for PCC pile and construction method for overlong PCC pile
CN211113669U (en) Prestressed reinforced concrete breast wall pile
CN103015433A (en) Method for constructing super-large diameter round and square combination deep foundation pit
JP2014109175A (en) Construction method for steel pipe concrete pile and steel pipe pile
CN103184738A (en) Grouting guide pipe restraint ring mounting structure and method for mounting grouting guide pipes by using restraint rings
CN215801568U (en) Bored concrete pile structure for reducing filling coefficient in ultra-deep silt geology
CN209128991U (en) A kind of filling pile cage of reinforcement structure
CN208456595U (en) A kind of toughness shaft wall structure under the high Explosive impact country rock of high pressure
CN208251078U (en) A kind of bottom-expanding sinking-pipe pilework

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Cheng Zhihui

Inventor after: Zeng Jia

Inventor after: Zhao Ziliang

Inventor after: Su Jianliang

Inventor after: Li Huiying

Inventor after: Wu Honghong

Inventor before: Cheng Zhihui

Inventor before: Zeng Jia

Inventor before: Zhao Ziliang

Inventor before: Su Jianliang

Inventor before: Li Huiying

Inventor before: Zhou Hanzhang

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: CHENG ZHIHUI CENG JIA ZHAO ZILIANG SU JIANLIANG LI HUIYING ZHOU HANZHANG TO: CHENG ZHIHUI CENG JIA ZHAO ZILIANG SU JIANLIANG LI HUIYING WU HONGHONG