CN102767175A - Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof - Google Patents
Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof Download PDFInfo
- Publication number
- CN102767175A CN102767175A CN2012102403760A CN201210240376A CN102767175A CN 102767175 A CN102767175 A CN 102767175A CN 2012102403760 A CN2012102403760 A CN 2012102403760A CN 201210240376 A CN201210240376 A CN 201210240376A CN 102767175 A CN102767175 A CN 102767175A
- Authority
- CN
- China
- Prior art keywords
- reinforcing cage
- muscle
- reinforcement
- reinforcement cage
- hole
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (9)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102403760A CN102767175A (en) | 2012-07-11 | 2012-07-11 | Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2012102403760A CN102767175A (en) | 2012-07-11 | 2012-07-11 | Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102767175A true CN102767175A (en) | 2012-11-07 |
Family
ID=47094725
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2012102403760A Pending CN102767175A (en) | 2012-07-11 | 2012-07-11 | Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102767175A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103362123A (en) * | 2013-07-05 | 2013-10-23 | 山东科技大学 | Reverse Y-shaped filling pile and construction method thereof |
CN104179172A (en) * | 2014-08-04 | 2014-12-03 | 河北建设勘察研究院有限公司 | Construction method for orifice connection of bored pile reinforcement cage |
CN107119674A (en) * | 2017-05-03 | 2017-09-01 | 苏州波森特岩土工程有限公司 | A kind of bored concrete pile and its construction method for having a lateral spacing |
CN111926802A (en) * | 2020-07-03 | 2020-11-13 | 顾鑫平 | High-strength precast concrete pile and pouring process thereof |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS637416A (en) * | 1986-06-26 | 1988-01-13 | Kumagai Gumi Ltd | Construction of hollow concrete structure under ground |
CN1598165A (en) * | 2004-08-05 | 2005-03-23 | 陈佳训 | Method for pile foundation construction of geologic structure with flow plastic half-flow plastic and its application apparatus |
JP2007002550A (en) * | 2005-06-24 | 2007-01-11 | Daia Soil Kk | Reinforcement cage for concrete pile |
CN102400460A (en) * | 2011-11-30 | 2012-04-04 | 昆明捷程桩工有限责任公司 | Construction method for preventing pile diameter of concrete pouring pile from being varied |
CN202482886U (en) * | 2011-12-13 | 2012-10-10 | 中国二十冶集团有限公司 | Cast-in-place pile steel reinforcement cage for ultra-thick high compression peat soil layer structure |
-
2012
- 2012-07-11 CN CN2012102403760A patent/CN102767175A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPS637416A (en) * | 1986-06-26 | 1988-01-13 | Kumagai Gumi Ltd | Construction of hollow concrete structure under ground |
CN1598165A (en) * | 2004-08-05 | 2005-03-23 | 陈佳训 | Method for pile foundation construction of geologic structure with flow plastic half-flow plastic and its application apparatus |
JP2007002550A (en) * | 2005-06-24 | 2007-01-11 | Daia Soil Kk | Reinforcement cage for concrete pile |
CN102400460A (en) * | 2011-11-30 | 2012-04-04 | 昆明捷程桩工有限责任公司 | Construction method for preventing pile diameter of concrete pouring pile from being varied |
CN202482886U (en) * | 2011-12-13 | 2012-10-10 | 中国二十冶集团有限公司 | Cast-in-place pile steel reinforcement cage for ultra-thick high compression peat soil layer structure |
Non-Patent Citations (1)
Title |
---|
苏宏阳,郦锁林 等: "《基础工程施工手册》", 30 June 2002, 中国计划出版社, article "灌注桩", pages: 555-559 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN103362123A (en) * | 2013-07-05 | 2013-10-23 | 山东科技大学 | Reverse Y-shaped filling pile and construction method thereof |
CN104179172A (en) * | 2014-08-04 | 2014-12-03 | 河北建设勘察研究院有限公司 | Construction method for orifice connection of bored pile reinforcement cage |
CN104179172B (en) * | 2014-08-04 | 2016-02-24 | 河北建设勘察研究院有限公司 | A kind of filling pile cage of reinforcement aperture connection construction method |
CN107119674A (en) * | 2017-05-03 | 2017-09-01 | 苏州波森特岩土工程有限公司 | A kind of bored concrete pile and its construction method for having a lateral spacing |
CN111926802A (en) * | 2020-07-03 | 2020-11-13 | 顾鑫平 | High-strength precast concrete pile and pouring process thereof |
CN111926802B (en) * | 2020-07-03 | 2021-09-07 | 广东港粤建设工程有限公司 | High-strength concrete pile and pouring process thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN105544575B (en) | A kind of bottom concrete construction method under water of use steel truss reinforcement | |
CN102767175A (en) | Concrete-pouring method for soft-soil foundation punched filling pile and used steel-reinforcement cage thereof | |
CN110331727A (en) | The supporting construction and construction method that bored concrete pile and diaphram wall combine | |
CN104563147B (en) | Composite structure pile foundation applied to karst area and construction method of composite structure pile foundation | |
CN109989395B (en) | Large storage tank filling pile assembled pile cap and construction method thereof | |
CN114351693A (en) | Collapse hole underpinning device for rotary excavating cast-in-place pile and underpinning construction method | |
JP5919675B2 (en) | Composite foundation pile and construction method of composite foundation pile | |
CN105821771B (en) | Overlength case bridge jacking construction technique and its constructing structure under high roadbed city expressway | |
CN209838429U (en) | Back anchor shield constructs lining cutting supporting construction | |
CN210263026U (en) | Anti structure that floats of hole-forming bored concrete pile steel sleeve is protected to mud dado of going out terrace | |
CN108086307B (en) | Steel pipe concrete hole digging and pouring composite miniature pile | |
CN106759264A (en) | One kind grouting pipe network and its construction method | |
CN108277817B (en) | Construction method of high-pile bearing platform tower crane foundation reinforcing structure | |
CN206706803U (en) | Large diameter steel pipe concrete-pile | |
CN213114605U (en) | A steel reinforcement cage that is used for bored concrete pile of karst landform to be under construction | |
CN210766789U (en) | Device for positioning and controlling verticality of reinforcing cage of manual hole digging pile | |
CN101691753B (en) | Pile mould for PCC pile and construction method for overlong PCC pile | |
CN211113669U (en) | Prestressed reinforced concrete breast wall pile | |
CN103015433A (en) | Method for constructing super-large diameter round and square combination deep foundation pit | |
JP2014109175A (en) | Construction method for steel pipe concrete pile and steel pipe pile | |
CN103184738A (en) | Grouting guide pipe restraint ring mounting structure and method for mounting grouting guide pipes by using restraint rings | |
CN215801568U (en) | Bored concrete pile structure for reducing filling coefficient in ultra-deep silt geology | |
CN209128991U (en) | A kind of filling pile cage of reinforcement structure | |
CN208456595U (en) | A kind of toughness shaft wall structure under the high Explosive impact country rock of high pressure | |
CN208251078U (en) | A kind of bottom-expanding sinking-pipe pilework |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C53 | Correction of patent of invention or patent application | ||
CB03 | Change of inventor or designer information |
Inventor after: Cheng Zhihui Inventor after: Zeng Jia Inventor after: Zhao Ziliang Inventor after: Su Jianliang Inventor after: Li Huiying Inventor after: Wu Honghong Inventor before: Cheng Zhihui Inventor before: Zeng Jia Inventor before: Zhao Ziliang Inventor before: Su Jianliang Inventor before: Li Huiying Inventor before: Zhou Hanzhang |
|
COR | Change of bibliographic data |
Free format text: CORRECT: INVENTOR; FROM: CHENG ZHIHUI CENG JIA ZHAO ZILIANG SU JIANLIANG LI HUIYING ZHOU HANZHANG TO: CHENG ZHIHUI CENG JIA ZHAO ZILIANG SU JIANLIANG LI HUIYING WU HONGHONG |
|
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20121107 |