CN102733481B - A kind of construction method of asymmetric openings formula integral tension cable-membrane analysis - Google Patents

A kind of construction method of asymmetric openings formula integral tension cable-membrane analysis Download PDF

Info

Publication number
CN102733481B
CN102733481B CN201210200723.7A CN201210200723A CN102733481B CN 102733481 B CN102733481 B CN 102733481B CN 201210200723 A CN201210200723 A CN 201210200723A CN 102733481 B CN102733481 B CN 102733481B
Authority
CN
China
Prior art keywords
cable
tension
strop
construction
tensioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201210200723.7A
Other languages
Chinese (zh)
Other versions
CN102733481A (en
Inventor
王树
张国军
张曼生
葛家琪
王泽强
王文胜
尤德清
刘鑫刚
徐瑞龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Aviation Planning and Design Institute Group Co Ltd
Original Assignee
China Aviation Planning and Design Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Aviation Planning and Design Institute Group Co Ltd filed Critical China Aviation Planning and Design Institute Group Co Ltd
Priority to CN201210200723.7A priority Critical patent/CN102733481B/en
Publication of CN102733481A publication Critical patent/CN102733481A/en
Priority to PCT/CN2013/077380 priority patent/WO2013189275A1/en
Priority to US14/409,395 priority patent/US9892213B2/en
Application granted granted Critical
Publication of CN102733481B publication Critical patent/CN102733481B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)
  • Reinforcement Elements For Buildings (AREA)

Abstract

A kind of construction method of asymmetric openings type rope film integral tension structure, specific steps include:Model is established, obtains the technical parameter for construction;Peripheral each node of steel construction and ring beam is installed from the bottom up;To the accurate blanking of rope;Strop is assembled on ground, and it is pressed from both sides into node by strop strop is connected with hoist cable, valley cable, notochord the inner;Hoist cable outer end is drawn to the corresponding node at the top of peripheral steel construction, strop, notochord and valley cable are subsequently lifted ground;It is sequencing tensioning to hoist cable, notochord, valley cable, it is set to be connected after meeting corresponding criterion with respective nodes, detect strop value, when meeting its criterion and simultaneously hoist cable, notochord, after meeting condition of valley cable, rope film tension structure is formed by tensioning overlay film between notochord, valley cable and film side rope.This method is fast and simple, and work progress structure stress is reasonable.

Description

A kind of construction method of asymmetric openings formula integral tension cable-membrane analysis
Technical field
The invention belongs to large-span space structure field, it is related to and a kind of is made up of three layers of radial cable, strop and overlay film Between be open integral tension structure construction method.
Background technology
Tension Foundations of Tensile Cable-membrane Structures is the structural system that a kind of tension force and drag-line by film itself collectively constitutes, structure master To be made up of the membrane material of stretching rope and covering, drag-line is divided into valley cable, notochord or hoist cable and the side rope in film edge again, Membrane material obtains abundant tensioning in this class formation, can bear a constant load.Such structure film unit can serve as structure level it Between contact, while there is good carrying to act on.Because Tension Foundations of Tensile Cable-membrane Structures is handsome in appearance, build is slim and graceful, stock utilization Height, the roof system particularly suitable for longspan structures such as physical culture exhibitions venue, airports.With the progress of computer technology, open Membrane structure has obtained extensive development in Practical Project, and the rope net of the structure passes through film surface as structure main stress system Tensioning makes structure formation, as secondary stress system.Because the presence of rope net, the more general Tension Foundations of Tensile Cable-membrane Structures of such rigidity of structure Greatly, thus can be applied in longspan structure.The prestressing force of this class formation rope and film must be according to certain ratio simultaneously Example applies.Because Tension Foundations of Tensile Cable-membrane Structures span is big, construction is complicated, and rational arrangement and method for construction can not only make structure formation state meet to set Meter requires, while can reduce the difficulty of work progress.Different construction stretching methods may be to the stress shape after shaping structures State has an impact, therefore rational stretching plan is related to the final stress and security performance of structure.
The content of the invention
(1)The technical problem of solution
The present invention proposes a kind of construction method for asymmetric openings type rope film integral tension structural system.The structure System forms the space integral tension cable-membrane analysis of middle opening by three layers of hoist cable, notochord and valley cable radial cable with ring rope, leads to The tensioning film surface crossed between notochord and valley cable forms the vertical load-bearing rigidity of rope film, hoist cable enhancing knot by the discrepancy in elevation of ridge valley cable outer end Structure entirety vertical rigidity.The construction method of the present invention does not have to set scaffold, it is only necessary to using peripheral steel construction as support, is divided Batch lifts synchronous tension, you can realize design into form, and construction overall process configuration state is controllable, construction safety state Controllable, construction method is simple and direct efficiently.
(2)Technical scheme
The construction method of the present invention, to realize the structure formation state of design requirement as target, with cable-membrane analysis integral tension For the basic principle of stretching construction, with the analysis of prestressed cable stretching construction overall process computer simulation for construction instruct according to According to determining the pre-tensile stress б of drag-line by sequential construction analysis0, drag-line cutting length, the maximum deformation value d of strop0And draw The priority tension sequence of rope, the final security, reasonability, succinct high efficiency for realizing construction.
A kind of construction method of asymmetric openings type integral tension cable-membrane analysis system of the present invention, it is characterized in that:Its is pre- The basic skills of stress cable-membrane analysis construction stretching is substep lifting integral tension method.Substep lifting integral tension method refers to According to the shape after shaping structures, drag-line is lifted to the position nearer apart from cable body anchorage node step by step by draw-gear, Drag-line synchronous tension is anchored in place by tensioning equipment again, realizes structure finally into the stretch-draw construction method of form.
The construction method of above-mentioned asymmetric openings type rope film integral tension structural system, the construction of its prestressed cable membrane structure Drawing is to instruct foundation with the analysis of prestressed cable stretching construction overall process computer simulation for construction.Analysis process considers knot Structure system geometrical non-linearity.Analysis uses large-scale general finite element program, preferentially using softwares such as ANSYS, ABAQUS, uses Newton-Raphson nonlinear iterations method solves.
The construction method of above-mentioned asymmetric openings type rope film integral tension structural system, foundation sequential construction analysis conclusion, Its prestressed cable membrane structure construction stretching is priority tension sequence with tensioning hoist cable, tensioning notochord, tensioning valley cable, tensioning overlay film, Strop need not carry out tensioning, ultimately form space integral tension cable-membrane analysis.
The construction method of above-mentioned asymmetric openings type rope film integral tension structural system, it is complete in any tensioning step tensioning Cheng Hou, it is both needed to detect the drag-line tension б that tensioning is completedS, and with 0.95 б0≤бS≤1.05б0, allow construction to draw for drag-line Stress criterion.After the completion of all final tensioning of drag-line, the maximum deformation value d of strop need to be detectedS, and with 0.90 d0≤dS≤ 1.10 d0Allow construction Deformation criterion for strop.After the completion of all final tensioning of drag-line, the tension of strop need to be detected бHS, and with 0.90 бH0≤бHS≤1.10 бH0Allow tension criterion of constructing for strop, wherein, d0To pass through overall process The maximum deformation value for the drag-line that sequential construction analysis determines, б0The drawing of drag-line to be determined by overall process sequential construction analysis should Power, бH0For the tension of the strop determined by overall process sequential construction analysis.
For convenience of statement, the strop being connected with valley cable and hoist cable folder node definition is that the first strop presss from both sides node by the present invention, It is that the second strop presss from both sides node by the strop being connected with notochord folder node definition.
A kind of construction method of asymmetric openings type rope film integral tension structural system of the present invention, it is comprised the following steps that:
To realize the structure formation state of design requirement as target, using cable-membrane analysis integral tension as the basic of stretching construction Principle, overall structure computation model is established by computer, and input dependency structure parameter, carry out prestressed cable stretching construction Overall process computer simulation is analyzed.Try to achieve the skills such as the priority tension sequence of the prestressing force of drag-line, cutting length and drag-line Art parameter is used for stretching construction, and analysis process considers structural system geometrical non-linearity.Analysis uses large-scale general finite element program, Preferentially using softwares such as ANSYS, ABAQUS, solved using Newton-Raphson nonlinear iterations method.
Peripheral steel construction is first installed from the bottom up, and ring beam-valley cable node, ring beam-notochord node, ring truss are installed Or ring beam-hoist cable node;
Draw the cutting length of each rope according to sequential construction analysis result of calculation, carry out the accurate of strop and each radial cable Blanking;
Strop is assembled on ground, and strop is connected with hoist cable the inner and valley cable the inner by the first cord clip node, Strop is connected with notochord the inner by the second cord clip node;
Each hoist cable outer end is drawn to corresponding ring truss or ring at the top of peripheral steel construction by lazy halyard Beam-hoist cable node certain distance, the distance take 0.4m to 1.5m, and now strop is subsequently lifted ground together with notochord and valley cable;
Tensioning tooling is made into by traction frock, according to sequential construction analysis result of calculation, hoist cable outer end is carried out and synchronously opens Draw, and detect the tension б for the hoist cable that tensioning is completedDS, with 0.95 бD0≤бDS≤1.05бD0Allow tension of constructing for hoist cable Criterion, if being unsatisfactory for requiring, need to carry out tension regulation using loosening or the mode such as tense to the hoist cable of tensioning, directly To criterion is met, after the tensioning of hoist cable outer end is in place, it is connected with top ring truss or ring beam-hoist cable node;Wherein, бD0For The pre-tensile stress of the hoist cable determined by sequential construction analysis;
Notochord outer end is drawn close to corresponding middle level ring beam-notochord node by lazy halyard, then changes tensioning tooling into, According to sequential construction analysis result of calculation, notochord outer end synchronous tension is carried out, and detect the tension for the notochord that tensioning is completed бJS, with 0.95 бJ0≤бJS≤1.05бJ0Allow tension criterion of constructing for notochord, if being unsatisfactory for requiring, need to having opened The notochord of drawing carries out tension regulation using loosening or the mode such as tenses, and up to meeting criterion, the tensioning of notochord outer end is in place Afterwards, to ring beam-notochord node location, and it is connected with ring beam-notochord node;Wherein, бJ0Determined by sequential construction analysis The pre-tensile stress of notochord;
Valley cable outer end is drawn close to corresponding ring beam-valley cable node by lazy halyard, then changes tensioning tooling into, according to Sequential construction analysis result of calculation, valley cable outer end synchronous tension is carried out, and detect the tension б for the valley cable that tensioning is completedGS, with 0.95бG0≤бGS≤1.05бG0Allow tension criterion of constructing for valley cable, if being unsatisfactory for requiring, need the paddy to tensioning Suo Caiyong loosens or tensed etc. mode and carries out tension regulation, until meeting criterion, after the tensioning of valley cable outer end is in place, to ring Beam-valley cable node location, and be connected with ring beam-valley cable node;Wherein, бG0For the pre- of the valley cable that is determined by sequential construction analysis Tension;
Detect the maximum deformation value d of stropS, and with 0.90 d0≤dS≤1.10 d0Construction Deformation is allowed to differentiate for strop Condition;Detect the tension б of stropHS, and with 0.90 бH0≤бHS≤1.10 бH0, allow tension differentiation bar of constructing for strop Part, wherein, бH0For the tension of the strop determined by overall process sequential construction analysis;If being unsatisfactory for requiring, need to adjust again Hoist cable, notochord, the tension of valley cable are saved, until meeting that strop allows construction Deformation criterion and allows tension differentiation of constructing Condition, at the same be required to meet hoist cable, notochord, valley cable allow construct tension criterion;
According to sequential construction analysis result of calculation, pass through tensioning overlay film shape between adjacent notochord, valley cable and film side rope Into rope film tension structure.
Above-mentioned construction method can also be improved, by above-mentioned steps-Replaced with following steps:
Strop is assembled on ground, and node is pressed from both sides by the first strop and is connected with hoist cable the inner, while the second strop is pressed from both sides Node is connected to strop;
Each hoist cable outer end is drawn to corresponding ring truss or ring beam at the top of peripheral steel construction by lazy halyard Hoist cable-node certain distance, the distance take 0.4m to 1.5m, and now strop is subsequently lifted ground;
Node is pressed from both sides by the first strop with valley cable the inner to be connected, press from both sides node by the second strop is connected with notochord the inner Connect.
(3)Beneficial effect
Present invention employs substep to lift cable-membrane analysis integral tension construction method, and complete with prestressed cable stretching construction The analysis of process computer analogue simulation instructs foundation for construction, it is ensured that the structural form after the completion of actual stretching construction meets Design structure into form requirement, it is simple and direct efficiently to realize the asymmetric saddle of large-span stadium roof open-type integral tension cable-membrane analysis The architectural image of shape, construction overall process structural stress state is controllable, and construction safety state can control, the simple and direct height of construction method Effect.
Brief description of the drawings
Fig. 1 is integral tension cable-membrane analysis profile,
Fig. 2 is integral tension cable-membrane analysis graphics,
Fig. 3 is integral tension cable-membrane analysis partial 3 d figure,
Fig. 4 is integral tension cable-membrane analysis part sectioned view,
Fig. 5 is the strop folder node being connected with valley cable and hoist cable,
Fig. 6 is the strop folder node being connected with notochord,
Fig. 7 is ring truss or ring beam hoist cable node,
Fig. 8 is ring beam-notochord node,
Fig. 9 is ring beam-valley cable node,
Figure 10 is construction process figure of the present invention.
In each accompanying drawing:1 hoist cable, 2 notochords, 3 valley cables, 4 strops, 5 overlay films, 6 ring truss or ring beam-hoist cable node, 7 peripheries Strop folder node i.e. the first strop that steel construction, 8 ring beams-notochord node, 9 ring beams-valley cable node, 10 are connected with valley cable and hoist cable Strop folder node i.e. the second strop folder node, the 12 film side ropes that folder node, 11 are connected with notochord.
Embodiment
Embodiment 1
By taking certain stadium project as an example, to illustrate applying for asymmetric openings formula integral tension cable-membrane analysis of the present invention Work method, it comprises the following steps:
To realize the structure formation state of design requirement as target, using cable-membrane analysis integral tension as the basic of stretching construction Principle, overall structure computation model is established by computer, and input dependency structure parameter, carry out prestressed cable stretching construction Overall process computer simulation is analyzed.Try to achieve the skills such as the priority tension sequence of the prestressing force of drag-line, cutting length and drag-line Art parameter is used for stretching construction, and analysis process considers structural system geometrical non-linearity.Analysis uses ANSYS softwares, uses Newton-Raphson nonlinear iterations method solves.
First peripheral steel construction 7 is installed from the bottom up, and install ring beam-valley cable node 9, ring beam-notochord node 8, ring beam- Hoist cable node 6 etc.;
The cutting length of each rope is drawn according to sequential construction analysis result of calculation, carrying out strop 4 and each radial cable includes The accurate blanking of hoist cable 1, notochord 2, valley cable 3;
Strop 4 is assembled on ground, and node 10 is pressed from both sides by the first strop and is connected with the inner of hoist cable 1 and the inner of valley cable 3, Node 11 is pressed from both sides by the second strop with the inner of notochord 2 to be connected;
Each outer end of hoist cable 1 is drawn to corresponding apart from the peripheral top ring truss of steel construction 7 or ring beam 6 by lazy halyard Connecting node certain distance, the distance take 0.4m to 1.5m, and now notochord 2 and valley cable 3 are subsequently lifted ground with strop 4;
Tensioning tooling is made into by traction frock, according to sequential construction analysis result of calculation, the outer end of hoist cable 1 is carried out and synchronously opens Draw, and detect the tension б for the hoist cable 1 that tensioning is completedDS, with 0.95 бD0≤бDS≤1.05бD0Allowing construction to draw for hoist cable 1 should Power criterion, if being unsatisfactory for requiring, need to carry out tension tune using loosening or the mode such as tense to the hoist cable 1 of tensioning Section, until meeting criterion, after the outer end tensioning of hoist cable 1 is in place, it is connected with top ring truss or ring beam-hoist cable node 6;
The outer end of notochord 2 is drawn close to corresponding middle level ring beam-notochord node 8 by lazy halyard, then changes tensioning work into Dress, according to sequential construction analysis result of calculation, the outer end synchronous tension of notochord 2 is carried out, and detect the drawing for the notochord 2 that tensioning is completed Stress бJS, with 0.95 бJ0≤бJS≤1.05бJ0Allow tension criterion of constructing, if being unsatisfactory for requiring, need pair for notochord 2 The notochord 2 of tensioning carries out tension regulation using loosening or the mode such as tenses, until meeting criterion, the outer end of notochord 2 is opened After drawing in place, it is connected to ring beam-position of notochord node 8, and with ring beam-notochord node 8;
According to sequential construction analysis result of calculation, the outer end synchronous tension of valley cable 3 is carried out, and detects the paddy that tensioning is completed The tension б of rope 3GS, with 0.95 бG0≤бGS≤1.05бG0Allow tension criterion of constructing for valley cable 3, will if being unsatisfactory for Ask, then need to carry out tension regulation using loosening or the mode such as tenses to the valley cable 3 of tensioning, up to meeting criterion, paddy After the outer end tensioning of rope 3 is in place, it is connected to ring beam-position of valley cable node 9, and with ring beam-valley cable node 9;
Detect the maximum deformation value d of strop 4S, and with 0.90 d0≤dS≤1.10 d0Construction Deformation is allowed to sentence for strop 4 Other condition;Detect the tension б of strop 4HS, and with 0.90 бH0≤бHS≤1.10 бH0Allow tension differentiation of constructing for strop 4 Condition.If being unsatisfactory for requiring, need to readjust hoist cable 1, notochord 2, the tension of valley cable 3, until meeting that strop 4 allows to construct Deformation criterion and allow tension criterion of constructing, while be required to meet hoist cable 1, notochord 2, valley cable 3 to allow to construct Tension criterion;
According to sequential construction analysis result of calculation, covered between adjacent notochord 2, valley cable 3 and film side rope 12 by tensioning Film 5 forms rope film tension structure.
Embodiment 2
Illustrate the another of asymmetric openings formula integral tension cable-membrane analysis of the present invention by taking certain stadium project as an example One construction method, it comprises the following steps:
To realize the structure formation state of design requirement as target, using cable-membrane analysis integral tension as the basic of stretching construction Principle, overall structure computation model is established by computer, and input dependency structure parameter, carry out prestressed cable stretching construction Overall process computer simulation is analyzed.Try to achieve the skills such as the priority tension sequence of the prestressing force of drag-line, cutting length and drag-line Art parameter is used for stretching construction, and analysis process considers structural system geometrical non-linearity.Analysis uses ANSYS softwares, uses Newton-Raphson nonlinear iterations method solves.
First peripheral steel construction 7 is installed from the bottom up, and install ring beam-valley cable node 9, ring beam-notochord node 8, ring beam- Hoist cable node 6 etc.;
According to sequential construction analysis result of calculation, the cutting length of each rope is drawn, carrying out strop 4 and each radial cable includes The accurate blanking of hoist cable 1, notochord 2, valley cable 3;
Strop 4 is assembled on ground, and the inner of node 10 and hoist cable 1 is pressed from both sides by the first strop and is connected, while by the second ring Cord clip node 11 is connected to strop 4;
Each outer end of hoist cable 1 is drawn to corresponding apart from the peripheral top ring truss of steel construction 7 or ring beam 6 by lazy halyard Connecting node certain distance, the distance take 0.4m to 1.5m, and now strop 4 is subsequently lifted ground;
Node 10 is pressed from both sides by the first strop with the inner of valley cable 3 to be connected, and is passed through the second strop and is pressed from both sides node and 2 inner phase of notochord Connection;
Tensioning tooling is made into by traction frock, according to sequential construction analysis result of calculation, the outer end of hoist cable 1 is carried out and synchronously opens Draw, and detect the tension б for the hoist cable 1 that tensioning is completedDS, with 0.95 бD0≤бDS≤1.05бD0Allowing construction to draw for hoist cable 1 should Power criterion, if being unsatisfactory for requiring, need to carry out tension tune using loosening or the mode such as tense to the hoist cable 1 of tensioning Section, until meeting criterion, after the outer end tensioning of hoist cable 1 is in place, it is connected with top ring truss or ring beam-hoist cable node 6;
The outer end of notochord 2 is drawn close to corresponding middle level ring beam-notochord node 8 by lazy halyard, then changes tensioning work into Dress, according to sequential construction analysis result of calculation, the outer end synchronous tension of notochord 2 is carried out, and detect the drawing for the notochord 2 that tensioning is completed Stress бJS, with 0.95 бJ0≤бJS≤1.05бJ0Allow tension criterion of constructing, if being unsatisfactory for requiring, need pair for notochord 2 The notochord 2 of tensioning carries out tension regulation using loosening or the mode such as tenses, until meeting criterion, the outer end of notochord 2 is opened After drawing in place, it is connected to ring beam-position of notochord node 8, and with ring beam-notochord node 8;
The outer end of valley cable 3 is drawn close to corresponding ring beam-valley cable node 9 by lazy halyard, then changes tensioning tooling, root into According to sequential construction analysis result of calculation, the outer end synchronous tension of valley cable 3 is carried out, and detect the tension for the valley cable 3 that tensioning is completed бGS, with 0.95 бG0≤бGS≤1.05бG0Allow tension criterion of constructing for valley cable 3, if being unsatisfactory for requiring, need to having opened The valley cable 3 of drawing carries out tension regulation using loosening or the mode such as tenses, and up to meeting criterion, the outer end tensioning of valley cable 3 is just Behind position, it is connected to ring beam-position of valley cable node 9, and with ring beam-valley cable node 9;
Detect the maximum deformation value d of strop 4S, and with 0.90 d0≤dS≤1.10 d0Construction Deformation is allowed to sentence for strop 4 Other condition;Detect the tension б of strop 4HS, and with 0.90 бH0≤бHS≤1.10 бH0Allow tension differentiation of constructing for strop 4 Condition.If being unsatisfactory for requiring, need to readjust hoist cable 1, notochord 2, the tension of valley cable 3, until meeting that strop 4 allows to construct Deformation criterion and allow tension criterion of constructing, while be required to meet hoist cable 1, notochord 2, valley cable 3 to allow to construct Tension criterion;
According to sequential construction analysis result of calculation, covered between adjacent notochord 2, valley cable 3 and film side rope 12 by tensioning Film 5 forms integral tension cable-membrane analysis.

Claims (4)

  1. A kind of 1. construction method of asymmetric openings type rope film integral tension structural system, it is characterised in that:Its prestressed cable film The basic skills of structure construction tensioning is substep lifting integral tension method, and the substep lifting integral tension method is according to structure Shape after shaping, drag-line is lifted to the position nearer apart from cable body anchorage node step by step by draw-gear, then by tensioning Device anchors drag-line synchronous tension in place, realizes structure finally into form;After the completion of any tensioning step tensioning, it is both needed to Detect the drag-line tension б that tensioning is completedS, and with 0.95 б0≤бS≤1.05б0Allow tension differentiation bar of constructing for drag-line Part, б0For the tension of the drag-line determined by overall process sequential construction analysis;After the completion of all final tensioning of drag-line, need to detect The maximum deformation value d of strop (4)S, and with 0.90d0≤dS≤1.10d0Allow construction Deformation criterion, d for strop0To pass through The maximum deformation value for the drag-line that overall process sequential construction analysis determines;After the completion of all final tensioning of drag-line, strop need to be detected Tension бHS, and with 0.90 бH0≤бHS≤1.10бH0Allow tension criterion of constructing, б for stropH0To pass through overall process The tension for the strop (4) that sequential construction analysis determines.
  2. A kind of 2. construction method as claimed in claim 1, it is characterised in that:Prestressed cable membrane structure construction stretching is in advance should The analysis of power cable tension construction overall process computer simulation instructs foundation for construction, and analysis process considers structural system geometry Non-linear, analysis uses large-scale general finite element program, is solved using Newton-Raphson nonlinear iterations method.
  3. A kind of 3. construction method as claimed in claim 2, it is characterised in that:According to sequential construction analysis conclusion, its prestressing force Cable-membrane analysis construction stretching is with tensioning hoist cable (1), notochord (2) and valley cable (3), and tensioning overlay film (5) is priority tension sequence, ring Rope (4) need not carry out tensioning, ultimately form space integral tension cable-membrane analysis.
  4. 4. a kind of construction method as claimed in claim 1, it is comprised the following steps that:
    1. to realize the structure formation state of design requirement as target, using cable-membrane analysis integral tension as the substantially former of stretching construction Then, overall structure computation model is established by computer, and inputs dependency structure parameter, it is complete to carry out prestressed cable stretching construction Process computer analogue simulation is analyzed;Try to achieve the technology of the priority tension sequence of the prestressing force of drag-line, cutting length and drag-line Parameter is used for stretching construction, and analysis process considers structural system geometrical non-linearity;Analysis uses large-scale general finite element program, adopts Solved with Newton-Raphson nonlinear iterations method;
    2. first installing peripheral steel construction (7) from the bottom up, and ring beam-valley cable node (9), ring beam-notochord node (8), ring are installed To truss or ring beam-hoist cable node (6);
    3. the cutting length of each rope is drawn according to sequential construction analysis result of calculation, carry out strop (4) and each radial cable it is accurate Blanking;
    4. in ground assembling strop (4), the strop folder node definition that will be connected with valley cable (3) and hoist cable (1) presss from both sides for the first strop Node (10), the strop folder node definition that will be connected with notochord (2) is that the second strop presss from both sides node (11), is pressed from both sides and saved by the first strop Strop (4) is connected by point (10) with hoist cable (1) the inner and valley cable (3) the inner, and node (11) is pressed from both sides by strop by the second strop (4) it is connected with notochord (2) the inner;
    5. each hoist cable (1) outer end drawn to the corresponding ring truss at the top of the peripheral steel construction (7) by lazy halyard or Ring beam-hoist cable node (6) certain distance, the distance take 0.4m to 1.5m, and now strop (4) is together with notochord (2) and valley cable (3) quilt Lift-off ground;
    6. making tensioning tooling into by traction frock, according to sequential construction analysis result of calculation, carry out hoist cable (1) outer end and synchronously open Draw, and detect the tension б for the hoist cable (1) that tensioning is completedDS, with 0.95 бD0≤бDS≤1.05бD0Allow to construct for hoist cable (1) Tension criterion, бD0For the pre-tensile stress of the hoist cable (1) determined by sequential construction analysis;If being unsatisfactory for requiring, need Tension regulation is carried out by the way of loosening or tensing to the hoist cable (1) of tensioning, until meeting criterion, hoist cable (1) After outer end tensioning is in place, it is connected with top ring truss or ring beam-hoist cable node (6);
    7. drawing notochord (2) outer end close to corresponding middle level ring beam-notochord node (8) by lazy halyard, tensioning work is then changed into Dress, according to sequential construction analysis result of calculation, notochord (2) outer end synchronous tension is carried out, and detect the notochord (2) that tensioning is completed Tension бJS, with 0.95 бJ0≤бJS≤1.05бJ0Allow tension criterion of constructing, б for notochord (2)J0To pass through construction The pre-tensile stress for the notochord that sunykatuib analysis determines;If being unsatisfactory for requiring, need to use the notochord (2) of tensioning and loosen or tense Mode carry out tension regulation, until meet criterion, after notochord (2) outer end tensioning is in place, to ring beam-notochord node (8) position, and be connected with ring beam-notochord node (8);
    8. drawing valley cable (3) outer end close to corresponding ring beam-valley cable node (9) by lazy halyard, tensioning tooling, root are then changed into According to sequential construction analysis result of calculation, valley cable (3) outer end synchronous tension is carried out, and detect the drawing for the valley cable (3) that tensioning is completed Stress бGS, with 0.95 бG0≤бGS≤1.05бG0Allow tension criterion of constructing, б for valley cableG0To pass through construction simulation point Analyse the pre-tensile stress of the valley cable (3) determined;If being unsatisfactory for requiring, need to use what is loosened or tense to the valley cable (3) of tensioning Mode carries out tension regulation, until meeting criterion, after valley cable (3) outer end tensioning is in place, to ring beam-valley cable node (9) Position, and be connected with ring beam-valley cable node (9);
    9. detect the maximum deformation value d of strop (4)S, and with 0.90d0≤dS≤1.10d0Construction Deformation is allowed to differentiate bar for strop Part, d0For the maximum deformation value of the drag-line determined by overall process sequential construction analysis;Detect the tension б of strop (4)HS, and With 0.90 бH0≤бHS≤1.10бH0Allow tension criterion of constructing, б for strop (4)H0To pass through overall process construction simulation point Analyse the tension of the strop (4) determined;If being unsatisfactory for requiring, need to readjust the tension of hoist cable, notochord, valley cable, until Meet strop (4) allow construction Deformation criterion and allow construct tension criterion, while be required to meet hoist cable (1), Notochord (2), valley cable (3) allow construct tension criterion;
    10. according to sequential construction analysis result of calculation, pass through tensioning between adjacent notochord (2), valley cable (3) and film side rope (12) Overlay film (5) forms rope film tension structure.
CN201210200723.7A 2012-06-18 2012-06-18 A kind of construction method of asymmetric openings formula integral tension cable-membrane analysis Active CN102733481B (en)

Priority Applications (3)

Application Number Priority Date Filing Date Title
CN201210200723.7A CN102733481B (en) 2012-06-18 2012-06-18 A kind of construction method of asymmetric openings formula integral tension cable-membrane analysis
PCT/CN2013/077380 WO2013189275A1 (en) 2012-06-18 2013-06-18 Asymmetrical open type integral tension cable membrane structure and method for construction and design therefor
US14/409,395 US9892213B2 (en) 2012-06-18 2013-06-18 Asymmetric cable-membrane tensegrity structure of opening type, method of constructing the same and method of designing the same

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210200723.7A CN102733481B (en) 2012-06-18 2012-06-18 A kind of construction method of asymmetric openings formula integral tension cable-membrane analysis

Publications (2)

Publication Number Publication Date
CN102733481A CN102733481A (en) 2012-10-17
CN102733481B true CN102733481B (en) 2017-11-10

Family

ID=46989730

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210200723.7A Active CN102733481B (en) 2012-06-18 2012-06-18 A kind of construction method of asymmetric openings formula integral tension cable-membrane analysis

Country Status (1)

Country Link
CN (1) CN102733481B (en)

Families Citing this family (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US9892213B2 (en) 2012-06-18 2018-02-13 China Aviation Planning & Construction Development Asymmetric cable-membrane tensegrity structure of opening type, method of constructing the same and method of designing the same
CN103147509A (en) * 2013-04-10 2013-06-12 北京市建筑工程设计有限责任公司 Fully-enclosed assembled string structural system and construction method thereof
CN103397694B (en) * 2013-08-09 2015-05-13 常州工学院 Three-dimensional compression members of tension structure
CN103883125B (en) * 2014-04-08 2015-11-18 北京市建筑工程研究院有限责任公司 Super-span shape of a saddle flexible cable net Tension Forming construction method
CN105822065B (en) * 2016-03-31 2018-08-21 中国一冶集团有限公司 Integral tension formula cable-membrane analysis construction method
CN106968341A (en) * 2017-05-18 2017-07-21 启东建筑集团有限公司 Tubular truss cable-membrane analysis construction method
CN107034994A (en) * 2017-06-16 2017-08-11 中国航空规划设计研究总院有限公司 A kind of open type integral tension cable-membrane analysis and its construction method for having a dorsal funciculus
CN108897943A (en) * 2018-06-26 2018-11-27 北京工业大学 A kind of rung formula Cable Truss Structure digital simulation pre-assembly method based on BIM model
CN110924609B (en) * 2020-02-10 2020-05-15 鲁东大学 Building film traction device and using method thereof
CN111364773B (en) * 2020-03-06 2022-03-29 北京城建集团有限责任公司 Curtain wall stay cable tensioning method and curtain wall mounting structure
CN112081285B (en) * 2020-08-17 2021-10-19 北京市建筑工程研究院有限责任公司 Method for determining length of prestressed stay cable of cable structure
CN112144725B (en) * 2020-09-16 2022-06-03 北京市建筑工程研究院有限责任公司 Method for forming cable dome structure with limited installation space
CN112942582A (en) * 2021-02-05 2021-06-11 浙江精工钢结构集团有限公司 Multi-cable clamp eccentric node suitable for super-large span string structure
CN113417368B (en) * 2021-06-07 2022-12-20 中建深圳装饰有限公司 High-space large-span fold-line-shaped cable membrane structure and construction method thereof
CN115492388B (en) * 2022-09-20 2023-09-29 中建八局第三建设有限公司 Construction method for vertical-surface cable membrane of huge-width outward-inclined cable back-pulling system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002322830A (en) * 2001-04-25 2002-11-08 Takenaka Komuten Co Ltd Cable type roof structure
CN201649393U (en) * 2010-04-27 2010-11-24 上海海事大学 Cable-stayed suspend-dome
CN201649289U (en) * 2010-01-28 2010-11-24 浙江八达建设集团有限公司 Prestress cantilever string structure
CN201660964U (en) * 2010-02-02 2010-12-01 中冶建筑研究总院有限公司 Mast stayed cable truss stretching integral structure

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002322830A (en) * 2001-04-25 2002-11-08 Takenaka Komuten Co Ltd Cable type roof structure
CN201649289U (en) * 2010-01-28 2010-11-24 浙江八达建设集团有限公司 Prestress cantilever string structure
CN201660964U (en) * 2010-02-02 2010-12-01 中冶建筑研究总院有限公司 Mast stayed cable truss stretching integral structure
CN201649393U (en) * 2010-04-27 2010-11-24 上海海事大学 Cable-stayed suspend-dome

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
佛山体育中心新体育场屋盖索膜结构的整体张拉施工全过程模拟;孙文波;《空间结构》;20050630;第11卷(第2期);第50-52页 *

Also Published As

Publication number Publication date
CN102733481A (en) 2012-10-17

Similar Documents

Publication Publication Date Title
CN102733481B (en) A kind of construction method of asymmetric openings formula integral tension cable-membrane analysis
CN107034994A (en) A kind of open type integral tension cable-membrane analysis and its construction method for having a dorsal funciculus
US9892213B2 (en) Asymmetric cable-membrane tensegrity structure of opening type, method of constructing the same and method of designing the same
CN104234433A (en) Tensioning and forming method and tensioning device of spoke type annular cantilever cable support grid structure
CN106065661A (en) Large span unsettled steel corridor construction engineering method
CN105804247B (en) A kind of ridge burr supports cable dome structure
CN103883125A (en) Extra-large-span saddle-shaped flexible network cable tensioning forming construction method
CN108153972B (en) Analysis method for whole process of cable hoisting
CN106013419B (en) Long-span Cantilever abnormity transfinites structural steel corridor construction engineering method
CN103061412B (en) Method for constructing stiff supporting dome structure
CN108412207A (en) A kind of tooling and application method suitable for the double rope synchronous tensions of beam-string structure
CN110565875A (en) hoisting construction method for assembled long-span wooden beam string structure
CN101787732A (en) Cable-stayed multi-layer framework structure and construction control method thereof
CN110807221B (en) Cable force calculation method based on equivalent force displacement method
US20130180184A1 (en) Method for forming a double-curved structure and double-curved structure formed using the same
CN107657138A (en) Application of the Virtual Construction equipment and technology based on BIM in steel crossover engineering
CN105908965A (en) Assembly type concrete wall board, assembly type building and assembly method
CN102425099B (en) Large cantilever wave-purlin combined PC bridge and manufacture method thereof
CN102182251A (en) Bottom chord node fastening device of multi-suspend structure and fastening tension method thereof
CN105484165B (en) Integrated prestress tensioning frame structure and manufacturing and using methods thereof
CN105781126B (en) A kind of beam-string structure passively establishes pre-stressed construction method
CN106013453A (en) Construction method for large-span overhung ultra-limit structure
Mikhaylov et al. Cable roof structure with flexible fabric covering
CN102733525B (en) A kind of being based on carries overall process open type integral tension structure multi-stage design method
CN102433952B (en) Wavy sloping roof structure and preparation method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 100120 Beijing Desheng street, No. 12, Xicheng District

Applicant after: CHINA AVIATION PLANNING AND DESIGN INSTITUTE (GROUP) CO., LTD.

Address before: 100120 Beijing Desheng street, No. 12, Xicheng District

Applicant before: China Aviation Planning and Construction Development Co., Ltd.

COR Change of bibliographic data
GR01 Patent grant
GR01 Patent grant