CN102704494A - Sequence excavation top ring beam sharing device of adjacent foundation pits - Google Patents

Sequence excavation top ring beam sharing device of adjacent foundation pits Download PDF

Info

Publication number
CN102704494A
CN102704494A CN201210206416XA CN201210206416A CN102704494A CN 102704494 A CN102704494 A CN 102704494A CN 201210206416X A CN201210206416X A CN 201210206416XA CN 201210206416 A CN201210206416 A CN 201210206416A CN 102704494 A CN102704494 A CN 102704494A
Authority
CN
China
Prior art keywords
top beam
reinforcing bar
connector
excavation pit
road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201210206416XA
Other languages
Chinese (zh)
Other versions
CN102704494B (en
Inventor
范卓烨
曹巍
姜春慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 2 Group Co Ltd
Original Assignee
Shanghai Construction No 2 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 2 Group Co Ltd filed Critical Shanghai Construction No 2 Group Co Ltd
Priority to CN201210206416.XA priority Critical patent/CN102704494B/en
Publication of CN102704494A publication Critical patent/CN102704494A/en
Application granted granted Critical
Publication of CN102704494B publication Critical patent/CN102704494B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Road Paving Structures (AREA)
  • Road Repair (AREA)

Abstract

A sequence excavation top ring beam sharing device of adjacent foundation pits is arranged between an earlier excavation pit first support and a later excavation pit first support, is provided with a top ring beam; the top ring beam further includes horizontally arranged top ring beam steel bars and a straight thread steel bar connector arranged inside the top ring beam; one end of the connector is anchored in the top ring beam through steel bars; and the head of the other end of the connector is sealed through a sealing cover, and the connector is connected with second steel bars during the construction of the later excavation pit first support. According to the invention, when the first concrete top ring beam is constructed at the earlier excavation pit first support, the connector for the second steel bars of the later excavation pit first support is pre-buried, and the second steel bars are connected with the connector during the construction of the later excavation pit first support, so that the repeated dismantlement of the top ring beam of a midboard is avoided.

Description

Adjacent foundation ditch successively excavates top beam composite device and job practices
Technical field
The present invention relates to construction engineering technical field, relate in particular to a kind of adjacent foundation ditch and successively excavate top beam composite device and job practices.
Background technology
At present; The development that divides the hole construction along with modern deep big foundation pit according to surrounding enviroment and construction period; The engineering that adjacent foundation ditch successively excavates according to operating mode in foundation pit construction gets more and more; The common wall top beam of adjacent foundation ditch need carry out the top beam secondary construction of adjacent foundation ditch in the engineering after a foundation pit construction completion cuts in the past, caused common wall top beam to repeat construction, increased construction cost and construction period.
So to the problem that prior art exists, this case designer relies on the industry experience for many years of being engaged in, the active research improvement is so there has been the adjacent foundation ditch of invention successively to excavate top beam composite device and job practices and job practices.
Summary of the invention
The present invention be directed in the prior art; The common wall top beam of traditional adjacent foundation ditch need carry out the top beam secondary construction of adjacent foundation ditch after a foundation pit construction completion cuts; Cause common wall top beam to repeat construction, increasing defectives such as construction cost and construction period provides a kind of adjacent foundation ditch successively to excavate the top beam composite device.
The present invention's another purpose is in the prior art; The common wall top beam of traditional adjacent foundation ditch need carry out the top beam secondary construction of adjacent foundation ditch after a foundation pit construction completion cuts; Cause common wall top beam to repeat construction, increase the job practices that defectives such as construction cost and construction period provide a kind of adjacent foundation ditch successively to excavate.
In order to address the above problem, the present invention provides a kind of adjacent foundation ditch successively to excavate the top beam composite device, and said top beam composite device is arranged between first road support of said first excavation pit and the excavation pit first road support of said back; Said top beam composite device has top beam, and said top beam further comprises the top beam reinforcing bar of horizontally set, and is arranged on the straight thread reinforcing bar connector in the said top beam; The first road of said first excavation pit supports and comprises first reinforcing bar, and said first reinforcing bar, one end requires to be arranged in the said top beam according to grappling; The first road of excavation pit, said back supports and comprises second reinforcing bar, and said second reinforcing bar, one end is connected with said connector; Said connector one end is anchored in the said top beam through reinforcing bar, and the said connector other end adopts the seal cover end socket, and when the excavation pit head road support of said back is constructed, is connected with said second reinforcing bar.
Optional, the position of said connector is provided with according to second reinforcing bar position that excavation pit first road in back supports.
For realizing another purpose of the present invention, the job practices that the present invention provides a kind of adjacent foundation ditch successively to excavate, wherein, said job practices comprises:
Execution in step S1: formerly the first road of excavation pit supports when constructing mid-board ground wall bleeding part concrete chisel removal;
Execution in step S2: place the top beam reinforcing bar of said top beam, first reinforcing bar that the first road of first excavation pit is supported requires to be arranged in the said top beam according to anchoring;
Execution in step S3: the second reinforcing bar position setting according to excavation pit first road in back supports is provided with straight thread reinforcing bar connector in said top beam;
Execution in step S4: when treating back excavation pit first road support 3 constructions said connector position topping is chiseled, taken off the seal cover end socket, second reinforcing bar that the first road of excavation, said back is supported is connected with said connector.
Optional, said connector is embedded in the said top beam when building.
In sum; When the present invention constructs first road concrete top beam through excavation pit first road support formerly; The connector of second reinforcing bar that the first road of excavation pit, pre-buried back supports; Said second reinforcing bar connected through connector when excavation pit head road support was constructed in the back, and then had avoided the dismounting that repeats of mid-board top beam to construct.
Description of drawings
The sectional structure sketch map that successively excavates the top beam composite device for the adjacent foundation ditch of the present invention shown in Figure 1;
The job practices flow chart that successively excavates for the adjacent foundation ditch of the present invention shown in Figure 2.
The specific embodiment
By the technology contents, the structural feature that specify the invention, reached purpose and effect, will combine embodiment and conjunction with figs. to specify below.
See also Fig. 1, the structural representation that successively excavates the top beam composite device for the adjacent foundation ditch of the present invention shown in Figure 1.Said top beam composite device 1 is arranged on the first road support 2 of said first excavation pit and the first road of excavation pit, said back supports between 3.Particularly, said top beam composite device 1 has top beam 10, and said top beam 10 further comprises the top beam reinforcing bar 11 of horizontally set, and is arranged on the straight thread reinforcing bar connector 12 in the said top beam 10.The first road of said first excavation pit supports 2 and comprises first reinforcing bar 20.Said first reinforcing bar, 20 1 ends require to be arranged in the said top beam 10 according to grappling.The first road of excavation pit, said back supports 3 and comprises second reinforcing bar (not shown).Said second reinforcing bar, one end is connected with said connector 12.Said connector 12 1 ends are anchored in the said top beam 10 through reinforcing bar 121, and said connector 12 other ends adopt seal cover 122 end sockets, and when said back excavation pit head road support 3 is constructed, are connected with said second reinforcing bar.
Fig. 2 be please continue to consult, and Fig. 1, the job practices flow chart that successively excavates for adjacent foundation ditch shown in Figure 2 combined to consult.The job practices that said adjacent foundation ditch successively excavates may further comprise the steps:
Execution in step S1: when formerly the first road of excavation pit supports 2 constructions with mid-board ground wall bleeding part concrete chisel removal;
Execution in step S2: place the top beam reinforcing bar 11 of said top beam 10, the first road of first excavation pit is supported 2 first reinforcing bar 20 and require to be arranged in the said top beam 10 according to anchoring.
Execution in step S3: support 3 the second reinforcing bar position setting according to the first road of back excavation pit, straight thread reinforcing bar connector 12 is set in said top beam 10.Wherein, an end connecting reinforcement 121 anchorings of said connector 12 are gone in the said top beam 10; The other end of said connector 12 is with seal cover 122 end sockets.Said connector 12 is embedded in the said top beam 10 when building.
Execution in step S4: when excavation pit head supports 3 constructions in the road after treating said connector 12 position toppings are chiseled, taken off seal cover 122 end sockets, second reinforcing bar that said back is excavated first road support 3 is connected with said connector 12.
When the present invention constructs first road concrete top beam through excavation pit first road support formerly 2; The connector 12 of second reinforcing bar of pre-buried back excavation pit first road support 3; Said second reinforcing bar connected through connector 12 when excavation pit head road support 3 was constructed in the back, and then had avoided the dismounting that repeats of mid-board top beam to construct.
In sum; When the present invention constructs first road concrete top beam through excavation pit first road support formerly; The connector of second reinforcing bar that the first road of excavation pit, pre-buried back supports; Said second reinforcing bar connected through connector when excavation pit head road support was constructed in the back, and then had avoided the dismounting that repeats of mid-board top beam to construct.
Those skilled in the art all should be appreciated that, under the situation that does not break away from the spirit or scope of the present invention, can carry out various modifications and modification to the present invention.Thereby, if when any modification or modification fall in the protection domain of appended claims and equivalent, think that the present invention contains these modifications and modification.

Claims (4)

1. an adjacent foundation ditch successively excavates the top beam composite device, it is characterized in that, said top beam composite device is arranged between first road support of said first excavation pit and the excavation pit first road support of said back; Said top beam composite device has top beam, and said top beam further comprises the top beam reinforcing bar of horizontally set, and is arranged on the straight thread reinforcing bar connector in the said top beam; The first road of said first excavation pit supports and comprises first reinforcing bar, and said first reinforcing bar, one end requires to be arranged in the said top beam according to grappling; The first road of excavation pit, said back supports and comprises second reinforcing bar, and said second reinforcing bar, one end is connected with said connector; Said connector one end is anchored in the said top beam through reinforcing bar, and the said connector other end adopts the seal cover end socket, and when the excavation pit head road support of said back is constructed, is connected with said second reinforcing bar.
2. adjacent foundation ditch as claimed in claim 1 successively excavates the top beam composite device, it is characterized in that, the position of said connector is provided with according to second reinforcing bar position that excavation pit first road in back supports.
3. the job practices that adjacent foundation ditch as claimed in claim 1 successively excavates is characterized in that, said job practices comprises:
Execution in step S1: formerly the first road of excavation pit supports when constructing mid-board ground wall bleeding part concrete chisel removal;
Execution in step S2: place the top beam reinforcing bar of said top beam, first reinforcing bar that the first road of first excavation pit is supported requires to be arranged in the said top beam according to anchoring;
Execution in step S3: the second reinforcing bar position setting according to excavation pit first road in back supports is provided with straight thread reinforcing bar connector in said top beam;
Execution in step S4: when treating back excavation pit first road support 3 constructions said connector position topping is chiseled, taken off the seal cover end socket, second reinforcing bar that the first road of excavation, said back is supported is connected with said connector.
4. adjacent foundation ditch as claimed in claim 3 successively excavates top beam composite device and job practices, it is characterized in that, said connector is embedded in the said top beam when building.
CN201210206416.XA 2012-06-20 2012-06-20 Sequence excavation top ring beam sharing device of adjacent foundation pits and its constructing method Active CN102704494B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210206416.XA CN102704494B (en) 2012-06-20 2012-06-20 Sequence excavation top ring beam sharing device of adjacent foundation pits and its constructing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210206416.XA CN102704494B (en) 2012-06-20 2012-06-20 Sequence excavation top ring beam sharing device of adjacent foundation pits and its constructing method

Publications (2)

Publication Number Publication Date
CN102704494A true CN102704494A (en) 2012-10-03
CN102704494B CN102704494B (en) 2014-08-27

Family

ID=46897526

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210206416.XA Active CN102704494B (en) 2012-06-20 2012-06-20 Sequence excavation top ring beam sharing device of adjacent foundation pits and its constructing method

Country Status (1)

Country Link
CN (1) CN102704494B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103741716A (en) * 2013-12-30 2014-04-23 上海建工二建集团有限公司 Method for foundation pit connecting channel construction under semi-reverse construction method and connecting auxiliary structure
CN104264685A (en) * 2014-09-28 2015-01-07 上海建工七建集团有限公司 Construction method for mid-partition wall area structure closure
CN115142469A (en) * 2022-07-13 2022-10-04 上海建工四建集团有限公司 Connecting method and structure of horizontal stressed member and top ring beam

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2830264B1 (en) * 1978-07-10 1979-10-04 Bilfinger Berger Bau Process for the production of a self-supporting concrete wall to be brought directly into the subsoil in alignment with an adjacent building
CN102465534A (en) * 2010-11-11 2012-05-23 上海市第五建筑有限公司 Construction method for adjacent double ditches
CN202767087U (en) * 2012-06-20 2013-03-06 上海建工二建集团有限公司 Top ring beam sharing device for sequential excavation of adjacent foundation pits

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE2830264B1 (en) * 1978-07-10 1979-10-04 Bilfinger Berger Bau Process for the production of a self-supporting concrete wall to be brought directly into the subsoil in alignment with an adjacent building
CN102465534A (en) * 2010-11-11 2012-05-23 上海市第五建筑有限公司 Construction method for adjacent double ditches
CN202767087U (en) * 2012-06-20 2013-03-06 上海建工二建集团有限公司 Top ring beam sharing device for sequential excavation of adjacent foundation pits

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
戴志杰等: "地铁一号线上海南站站改建工程相邻基坑开挖施工技术", 《建筑施工》 *
陈东杰: "上海铁路南站特长相邻基坑平行施工技术", 《施工技术》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103741716A (en) * 2013-12-30 2014-04-23 上海建工二建集团有限公司 Method for foundation pit connecting channel construction under semi-reverse construction method and connecting auxiliary structure
CN103741716B (en) * 2013-12-30 2016-02-10 上海建工二建集团有限公司 Under semi-inverse method between foundation ditch communication channel construction method and be communicated with supplementary structure
CN104264685A (en) * 2014-09-28 2015-01-07 上海建工七建集团有限公司 Construction method for mid-partition wall area structure closure
CN104264685B (en) * 2014-09-28 2016-08-24 上海建工七建集团有限公司 The construction method that a kind of mid-board regional structure is closed up
CN115142469A (en) * 2022-07-13 2022-10-04 上海建工四建集团有限公司 Connecting method and structure of horizontal stressed member and top ring beam

Also Published As

Publication number Publication date
CN102704494B (en) 2014-08-27

Similar Documents

Publication Publication Date Title
CN106522241B (en) The method for supporting deep foundation pit of the high basement structure of super large layer
CN103981898B (en) A kind of inverse underground engineering construction method done of overall open cut node
CN104763433A (en) Underground excavation construction method of large-span subway station in flexible-top and hard-bottom stratum
CN104329095B (en) A kind of existing tunnel Widening Construction method
CN103669369B (en) The supporting and protection structure of foundation ditch and supporting method
CN201679147U (en) Underpinning structure for superstructure shear wall during underground top-down construction of high-rise building
CN104652418A (en) Continuous wall underground pipeline position construction method
JP2017008568A (en) Tunnel joint structure and tunnel construction method
CN102704494A (en) Sequence excavation top ring beam sharing device of adjacent foundation pits
CN204457789U (en) A kind of stake arch wall supports the subway station digging large diameter shield tunnel and build
CN106499199A (en) Close on the interim support replacement of subway ultra-deep foundation pit mid-board and its construction method
CN202577313U (en) Supporting combined system for deep foundation pit
CN202767087U (en) Top ring beam sharing device for sequential excavation of adjacent foundation pits
CN102220764B (en) Construction method of deep foundation pit bracing system
CN102865083A (en) Working well free shield arrival engineering method and structure of existing basement structure
CN104775823B (en) Double-line mining method subway tunnel inclined well entering main tunnel structure and process thereof
CN204282371U (en) A kind of pre-loaded support struts for foundation ditch
CN210201445U (en) Underground pipeline group combination tool type supporting protection system
CN204676569U (en) The Anchor Care of the larger Dangerous Rock Body of a kind of rock side slope combines process structure
JP5252226B2 (en) Building seismic isolation method and seismic isolation building
JP2016199957A (en) Floor preceding method
JP2010209571A (en) Construction method for support pile for constructing structure crossing under railroad track
CN105155867A (en) Underpinning device for tunnel to pass through existing large-diameter pile building
JP2011001784A (en) Method of constructing underground structure
CN104631824A (en) Support-changing construction method of structural slabs at temporary division walls

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Fan Zhuoye

Inventor after: Mao Anji

Inventor after: Cao Wei

Inventor after: Jiang Chunhui

Inventor before: Fan Zhuoye

Inventor before: Cao Wei

Inventor before: Jiang Chunhui

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: FAN ZHUOYE CAO WEI JIANG CHUNHUI TO: FAN ZHUOYE MAO ANJI CAO WEI JIANG CHUNHUI