CN102635359A - Energy-saving rapid construction method for ventilating shafts of tunnels - Google Patents

Energy-saving rapid construction method for ventilating shafts of tunnels Download PDF

Info

Publication number
CN102635359A
CN102635359A CN2012101068197A CN201210106819A CN102635359A CN 102635359 A CN102635359 A CN 102635359A CN 2012101068197 A CN2012101068197 A CN 2012101068197A CN 201210106819 A CN201210106819 A CN 201210106819A CN 102635359 A CN102635359 A CN 102635359A
Authority
CN
China
Prior art keywords
construction
shaft
wall seat
wall
vertical shaft
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012101068197A
Other languages
Chinese (zh)
Other versions
CN102635359B (en
Inventor
王新民
孙修德
曹会芹
邓华军
王�华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 17th Bureau Group Co Ltd
Priority to CN201210106819.7A priority Critical patent/CN102635359B/en
Publication of CN102635359A publication Critical patent/CN102635359A/en
Application granted granted Critical
Publication of CN102635359B publication Critical patent/CN102635359B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention specifically relates to an energy-saving rapid construction method for ventilating shafts of tunnels, which solves the problem that shortcomings exist in the construction on the existing ventilating shafts of tunnels by using a downward driving method. The method comprises the following steps of: a, measuring the position of a positioned shaft; b, carrying out strengthening construction on the geologic status of a shaft mouth, meanwhile, excavating a vertical ballast-discharge hole downwards from the shaft mouth, and carrying out excavation from the front hole of a tunnel to the position of the shaft until the excavating position meets the vertical ballast-discharge hole; c, carrying out shaft excavation by using a drilling and blasting combined method; d, when the shaft is excavated to a certain depth, carrying out secondary lining construction on the upper part of the shaft, wherein the secondary lining construction and the shaft construction are performed synchronously; and e, installing a shaft ventilating device. According to the invention, through adopting a mode of carrying out equidirectional and synchronous operation flow on the shaft excavation construction and the shaft secondary-lining construction, the method has the significant advantages of small safety risk, high construction speed, high working efficiency, energy saving, consumption reduction, easiness in construction drainage in shafts, low comprehensive construction cost, and capabilities of reducing the equipment investment, saving the occupied land and the cost of ecological restoration engineering, and obviously improving the construction work environment.

Description

The energy-conservation rapid constructing method of tunnel ventilation vertical shaft
Technical field
The present invention relates to the construction technology of tunnel ventilation vertical shaft, be specially the energy-conservation rapid constructing method of a kind of tunnel ventilation vertical shaft.
Background technology
Speedway, railway are grown up, and air quality descends obviously in hole operation stage, tunnel, and airshaft is adopted in design, and (diameter is generally changed air in the holes 6~10m), reaches the purpose of improving air quality.
At present, engineering circle adopts positive its sequence of construction of well method to be: bore quick-fried driving, borehole wall temporary lining from top to bottom; Treat that driving to positive hole, carries out the borehole wall and median septum reinforced concrete lining layer from bottom to top again.
At present; The driving method that adopts is mostly: boring pops digs, temporary lining, vertical lifting muck removal, abandon quarrel, setting prevent erosion preventive works, spoil disposal area restore nature greening vegetation engineering nearby, and this method is applicable to that the major diameter tunnel of various geology and other underground construction construct with vertical shaft.
Adopt positive well method construction to have following drawback:
1, bore quick-fried weak effect, driving speed is slow, every cyclic advance is only about 1.0m;
2, all abandon quarrel all needs to be promoted to well head by the shaft bottom, and energy consumption is big, the muck removal time is long;
3, promote muck removal and very easily fall piece, the down-hole constructor is caused the danger side of body;
4, each inter process disturb big, continuous productive process synchronously, long construction period;
5, the flue dust diffusion is slow after the vertical shaft explosion, causes the long-time pause of construction;
6, in the vertical shaft in case meets underground water, the expense of drawing water height, have softening country rock to cause the security risk of caving in;
7, need spoil disposal area be set separately, the afforestation project of soil erosion preventive works and restore vegetation is set, natural environment is had certain influence;
8, the integrated construction cost is high, energy consumption is high, potential safety hazard is many.
Summary of the invention
The present invention adopts positive well method construction to have the problem of above-mentioned weak point in order to solve the existing tunnel airshaft, provides a kind of tunnel ventilation vertical shaft energy-conservation rapid constructing method.
The present invention adopts following technical scheme to realize: the energy-conservation rapid constructing method of tunnel ventilation vertical shaft, and step is following: a, measurement and positioning vertical shaft position; B, pit mouth geology is carried out strengthening construction, meanwhile, from the pit mouth vertical deslagging of excavation hole downwards, and from the tunnel positive hole to vertical shaft position driving to communicating with vertical deslagging hole; C, the method that adopts boring to combine with explosion are carried out shaft sinking; D, after shaft sinking reaches certain depth, two lining constructions are carried out on vertical shaft top, and two lining constructions are carried out with the vertical shaft construction synchronously; E, installation vertical shaft ventilation equipment.
In the work progress, pit mouth geology is reinforced (fore shaft) guarantee that well head is firm, be convenient to installation, the debugging of ground derrick and crane gear,, improved efficiency of construction with the construction synchronization job of vertical deslagging hole; The method that adopts boring to combine with explosion is carried out the vertical shaft construction and has been accelerated construction speed, and the muck removal from vertical deslagging hole is energy-conservation and do not influence vertical shaft top two linings and construct, and has overcome the existing tunnel airshaft and has adopted positive well method to construct to have the problem of above-mentioned weak point.
The concrete steps that two lining constructions are carried out on vertical shaft top are following: a, carry out the cleaning of wall seat through the construction hanging scaffold and reinforce; B, also fixed at the latter half mounting shaft font steel I-beam of wall seat; C, on the groined type steel I-beam of wall seat, bed die is installed, and colligation wall seat the first half and the wall seat top borehole wall two lined steel muscle and median septum reinforcing bar; D, the assembly wall seat top borehole wall and median septum side form, and firm supporting; E, cast wall seat the first half and the borehole wall two lining and median septum concrete and the maintenances of wall seat top; F, remove the groined type steel I-beam and be installed in the latter half of next wall seat and fixed; G, on the groined type steel I-beam of the wall seat of next wall seat, bed die is installed, and the next wall seat of colligation the first half, the wall seat top borehole wall and wall seat the latter half two lined steel muscle and median septum reinforcing bar; H, the next wall seat top borehole wall of installation and median septum side form, and firm supporting; I, the next wall seat the first half of cast, the next wall seat top borehole wall and two lining and median septum concrete and the maintenances of wall seat the latter half; J, the horizontal joint of wall seat the first half, the latter half is prevented that water seal handles the circulation construction.
This two linings job practices stable operation performance is high, and carries out synchronously with the vertical shaft construction, and efficiency of construction significantly promotes when guaranteeing security performance, and energy-saving effect is obvious simultaneously, has simplified working procedure.
Beneficial effect of the present invention is following:
1, adopt rig commonly used such as Churn drill to implement boring, form vertical deslagging hole, quicker, economical than raise boring machine;
2, utilize vertical deslagging hole, solved the deslagging problem, change original vertical lifting muck removal in the positive hole horizontal muck removal, save a large amount of daily energy consumptions and large-scale lifting means and purchase maintenance cost, and improve positive hole, tunnel muck removal utilization rate of equipment and installations;
3, the maintenance cost of purchasing of daily vertical drainage energy consumption and pumping equipment is saved with the vertical drainage function in vertical deslagging hole;
4, thoroughly eliminate the lifting muck removal and fallen potential safety hazards such as piece is hurted sb.'s feelings, ponding immersion country rock borehole well instability;
5, downward muck removal fast shortens the muck removal time, can increase the driving cycle-index, improves efficiency of construction;
6, realize borehole wall concrete lining follow-up, shorten Sidewall Surrounding Rock open-assembly time, can suitably reduce the temporary lining grade, save the temporary lining expense, shorten total time of construction;
7, the vertical deslagging of preboring hole is that the follow-up chambering of vertical shaft provides free face, has improved demolition effect, reduces perforating explosion energy consumption, saves explosive consumption, has alleviated the blasting fume pollution;
8, vertical deslagging hole and positive hole, tunnel connect in advance, for vertical shaft and the smoke evacuation of positive hole provide condition, have improved vertical shaft and positive hole construction environment, have reduced vertical shaft and positive hole construction ventilation cost;
9, needn't spoil disposal area be set specially and the quarrel sidewalk is abandoned in build for vertical shaft, practice thrift in a large number and take up an area of; Save spoil disposal area preventive works and ecological recovery engineering cost;
The present invention tunnels former positive well method and the reverse form of construction work of lining cutting substep changes the shaft sinking construction into and vertical shaft two linings are constructed in the same way, synchronous flow system; Have that security risk is little, speed of application is fast, work efficiency is high, energy-saving and cost-reducing, minimizing equipment input, save spoil disposal area and abandon that the quarrel sidewalk takes up an area of and remarkable advantage such as ecological recovery engineering cost, construction operation environment are obviously improved, construction drainage easily in the vertical shaft, the construction integrated cost is low; Be applicable to that degree of depth 150m is with interior highway tunnel ventilation vertical shaft, railway tunnel airshaft, the construction of water conservancy project diversion tunnel; Also can be applicable to similar the latter half 150m scope construction than deep shaft, two lining technology also can be applicable to the field of the energy-conservation vertical shaft of building air conditioning simultaneously.
The specific embodiment
The energy-conservation rapid constructing method of tunnel ventilation vertical shaft, step is following: a, measurement and positioning vertical shaft position; B, pit mouth geology is carried out strengthening construction, meanwhile, from the pit mouth vertical deslagging of excavation hole downwards, and from the tunnel positive hole to vertical shaft position driving to communicating with vertical deslagging hole; C, the method that adopts boring to combine with explosion are carried out shaft sinking; D, when shaft sinking behind certain depth, two lining constructions are carried out on vertical shaft top, and two lining constructions are carried out with the vertical shaft construction synchronously; E, installation vertical shaft ventilation equipment.
The concrete steps that two lining constructions are carried out on vertical shaft top are following: a, carry out the cleaning of wall seat through the construction hanging scaffold and reinforce; B, also fixed at the latter half mounting shaft font steel I-beam of wall seat; C, on the groined type steel I-beam of wall seat, bed die is installed, and colligation wall seat the first half and the wall seat top borehole wall two lined steel muscle and median septum reinforcing bar; D, the assembly wall seat top borehole wall and median septum side form, and firm supporting; E, cast wall seat the first half and the borehole wall two lining and median septum concrete and the maintenances of wall seat top; F, remove the groined type steel I-beam and be installed in the latter half of next wall seat and fixed; G, on the groined type steel I-beam of the wall seat of next wall seat, bed die is installed, and the next wall seat of colligation the first half, the wall seat top borehole wall and wall seat the latter half two lined steel muscle and median septum reinforcing bar; H, the next wall seat top borehole wall of installation and median septum side form, and firm supporting; I, the next wall seat the first half of cast, the next wall seat top borehole wall and two lining and median septum concrete and the maintenances of wall seat the latter half; J, the horizontal joint of wall seat the first half, the latter half is prevented that water seal handles the circulation construction.
In the practical implementation process; Pit mouth geology is reinforced (fore shaft) construction, after loosening the soil in the face of land that needs the artificial cooperative mechanical of elder generation to excavate certain depth (5-8m), to carrying out reinforced concrete construction around the pit mouth; After concrete reaches certain intensity, the peripheral backfill of pit mouth is closely knit with soil; In the vertical shaft construction, through boring, powder charge, detonate, muck removal, the clear end, wall seat excavation, borehole wall combined bolting and shotcrete step circulate driving downwards.
In that the concrete lining support system is installed, carry out operations such as assembling reinforcement, rigging, fluid concrete, form removal maintenance, joint treatment on the wall seat of driving face certain distance.

Claims (2)

1. energy-conservation rapid constructing method of tunnel ventilation vertical shaft, it is characterized in that: step is following: a, measurement and positioning vertical shaft position; B, pit mouth geology is carried out strengthening construction, meanwhile, from the pit mouth vertical deslagging of excavation hole downwards, and from the tunnel positive hole to vertical shaft position driving to communicating with vertical deslagging hole; C, the method that adopts boring to combine with explosion are carried out shaft sinking; D, when shaft sinking behind certain depth, two lining constructions are carried out on vertical shaft top, and two lining constructions are carried out with the vertical shaft construction synchronously; E, installation vertical shaft ventilation equipment.
2. the energy-conservation rapid constructing method of tunnel ventilation vertical shaft according to claim 1 is characterized in that: the concrete steps that two lining constructions are carried out on vertical shaft top are following: a, carry out the cleaning of wall seat through the construction hanging scaffold and reinforce; B, also fixed at the latter half mounting shaft font steel I-beam of wall seat; C, on the groined type steel I-beam of wall seat, bed die is installed, and colligation wall seat the first half and the wall seat top borehole wall two lined steel muscle and median septum reinforcing bar; D, the assembly wall seat top borehole wall and median septum side form, and firm supporting; E, cast wall seat the first half and the borehole wall two lining and median septum concrete and the maintenances of wall seat top; F, remove the groined type steel I-beam and be installed in the latter half of next wall seat and fixed; G, on the groined type steel I-beam of the wall seat of next wall seat, bed die is installed, and the next wall seat of colligation the first half, the wall seat top borehole wall and wall seat the latter half two lined steel muscle and median septum reinforcing bar; H, the next wall seat top borehole wall of installation and median septum side form, and firm supporting; I, the next wall seat the first half of cast, the next wall seat top borehole wall and two lining and median septum concrete and the maintenances of wall seat the latter half; J, the horizontal joint of wall seat the first half, the latter half is prevented that water seal handles the circulation construction.
CN201210106819.7A 2012-04-13 2012-04-13 Energy-saving rapid construction method for ventilating shafts of tunnels Expired - Fee Related CN102635359B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210106819.7A CN102635359B (en) 2012-04-13 2012-04-13 Energy-saving rapid construction method for ventilating shafts of tunnels

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210106819.7A CN102635359B (en) 2012-04-13 2012-04-13 Energy-saving rapid construction method for ventilating shafts of tunnels

Publications (2)

Publication Number Publication Date
CN102635359A true CN102635359A (en) 2012-08-15
CN102635359B CN102635359B (en) 2014-04-09

Family

ID=46619920

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210106819.7A Expired - Fee Related CN102635359B (en) 2012-04-13 2012-04-13 Energy-saving rapid construction method for ventilating shafts of tunnels

Country Status (1)

Country Link
CN (1) CN102635359B (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900367A (en) * 2012-11-01 2013-01-30 陕西彬长文家坡矿业有限公司 Methods for drilling in cylinder of semi-finished vertical shaft and discharging water from cylinder of gangue-removal vertical shaft
CN104806249A (en) * 2015-04-03 2015-07-29 核工业井巷建设公司 Guiding and tunneling construction method of short silo
CN104989409A (en) * 2015-06-17 2015-10-21 中铁十六局集团第五工程有限公司 Full-face excavation method after vertical shaft small-face pore forming
CN109826654A (en) * 2019-03-12 2019-05-31 四川省交通运输厅公路规划勘察设计研究院 Tunnel ventilation well supporting construction and its construction method
CN112943257A (en) * 2021-01-25 2021-06-11 中铁十四局集团建筑工程有限公司 Method for treating reverse borehole collapse of deep large vertical shaft

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3528278A1 (en) * 1985-08-07 1987-02-19 Gesteins & Tiefbau Gmbh Drilling apparatus for shafts
JPH02304196A (en) * 1989-05-16 1990-12-17 Maeda Corp Shaft excavation construction method
CN101082217A (en) * 2006-06-02 2007-12-05 韩国石油公社 Excavation method of vertical hole
CN101906972A (en) * 2010-07-23 2010-12-08 中铁十七局集团第四工程有限公司 Method for synchronously constructing second shaft wall lining and intermediate baffle of vertical shaft
CN102305075A (en) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 Vertical shaft construction method under unfavorable geological condition

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
DE3528278A1 (en) * 1985-08-07 1987-02-19 Gesteins & Tiefbau Gmbh Drilling apparatus for shafts
JPH02304196A (en) * 1989-05-16 1990-12-17 Maeda Corp Shaft excavation construction method
CN101082217A (en) * 2006-06-02 2007-12-05 韩国石油公社 Excavation method of vertical hole
CN101906972A (en) * 2010-07-23 2010-12-08 中铁十七局集团第四工程有限公司 Method for synchronously constructing second shaft wall lining and intermediate baffle of vertical shaft
CN102305075A (en) * 2011-06-28 2012-01-04 中国水利水电第五工程局有限公司 Vertical shaft construction method under unfavorable geological condition

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102900367A (en) * 2012-11-01 2013-01-30 陕西彬长文家坡矿业有限公司 Methods for drilling in cylinder of semi-finished vertical shaft and discharging water from cylinder of gangue-removal vertical shaft
CN104806249A (en) * 2015-04-03 2015-07-29 核工业井巷建设公司 Guiding and tunneling construction method of short silo
CN104806249B (en) * 2015-04-03 2016-05-04 核工业井巷建设公司 A kind of short vertical shaft pilot shaft tunneling construction method
CN104989409A (en) * 2015-06-17 2015-10-21 中铁十六局集团第五工程有限公司 Full-face excavation method after vertical shaft small-face pore forming
CN109826654A (en) * 2019-03-12 2019-05-31 四川省交通运输厅公路规划勘察设计研究院 Tunnel ventilation well supporting construction and its construction method
CN112943257A (en) * 2021-01-25 2021-06-11 中铁十四局集团建筑工程有限公司 Method for treating reverse borehole collapse of deep large vertical shaft

Also Published As

Publication number Publication date
CN102635359B (en) 2014-04-09

Similar Documents

Publication Publication Date Title
CN110821503B (en) Construction method for main body of ultra-deep shield section air shaft after tunnel advance
CN103835648B (en) One improves rock stratum performance mine shaft rising boring technique by surface grout injection
CN103615250B (en) The full Open stope mining afterwards filling of itemize studding works in coordination with mining codes
CN103835651B (en) A kind of single hole directional drilling local slip casting mine shaft rising boring technique
CN102268993B (en) Method for excavating tunnel in high liquid limit soil
CN103835661B (en) A kind of local excavation pre support mine shaft rising boring technique
CN201982011U (en) Track type drilling trolley
CN104863629A (en) Method for extracting gas from separation layer below overlying strata, draining water and grouting through combined drill hole
CN102635359B (en) Energy-saving rapid construction method for ventilating shafts of tunnels
CN102373930A (en) Rapid construction method of weak surrounding rock large-section multi-arc tunnel
CN104747075A (en) Anti-collapsing drilling method for grout spraying of soft coal seam
CN103835729A (en) Ground pre-grouting strengthening technology for deep long-distance roadway surrounding rock
CN103939135B (en) A kind of fully-mechanized mining working removes frame passage rapid constructing method
CN111075478A (en) Pre-grouting reinforcement process for ground construction of broken belt of excavation working face structure
CN101694159A (en) Technology for rapidly constructing air shaft under chill condition and process for sinking vertical shaft pit shaft
CN102678126A (en) Method for excavating mountain tunnels in weak surrounding rock-fractured zones or shallow covered slope sections
CN103835723A (en) Comprehensive pretreatment method for shaft penetration in mined-out area stratum
CN205638458U (en) Accelerate construction structures of broken system construction speed of underground swift current
CN212985227U (en) Underground shared cavern structure for dismounting TBM
CN104533425A (en) Vertical shaft overall pouring section walling crib and vertical shaft overall pouring section walling crib construction method
CN102606070B (en) Combined drilling technique of vegetable gum diamond coring and downhole hammer casing drilling
CN204002832U (en) A kind of shield tunnel portal structure
CN105545315A (en) Normal pressure tool replacing method for reinforcing excavation face soil layer in shield tunnel construction
CN105545330A (en) Water prevention and control process in construction of metallurgical underground mining ore pass fragmenting system
CN204326963U (en) The anti-well boring device of a kind of vertical shaft

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140409

CF01 Termination of patent right due to non-payment of annual fee