CN102635225A - Equipment hoisting platform and method for super high-rise buildings - Google Patents

Equipment hoisting platform and method for super high-rise buildings Download PDF

Info

Publication number
CN102635225A
CN102635225A CN2012100973524A CN201210097352A CN102635225A CN 102635225 A CN102635225 A CN 102635225A CN 2012100973524 A CN2012100973524 A CN 2012100973524A CN 201210097352 A CN201210097352 A CN 201210097352A CN 102635225 A CN102635225 A CN 102635225A
Authority
CN
China
Prior art keywords
platform
hoisting
equipment
support
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100973524A
Other languages
Chinese (zh)
Inventor
魏成权
张广志
黄伟江
李琦
王恒
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
GUANGDONG INDUSTRIAL EQUIPMENT INSTALLATION Co Ltd
Original Assignee
GUANGDONG INDUSTRIAL EQUIPMENT INSTALLATION Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by GUANGDONG INDUSTRIAL EQUIPMENT INSTALLATION Co Ltd filed Critical GUANGDONG INDUSTRIAL EQUIPMENT INSTALLATION Co Ltd
Priority to CN2012100973524A priority Critical patent/CN102635225A/en
Publication of CN102635225A publication Critical patent/CN102635225A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Movable Scaffolding (AREA)

Abstract

The invention discloses an equipment hoisting platform and method for super high-rise buildings. The equipment hoisting platform is characterized in that a bottom plate of the platform is overhung on the outer side of a wall body of a high-rise building, and the bottom plate of the platform and heavy equipment on the bottom plate of the platform are supported by virtue of main support girders, secondary support girders and small support girders installed at the bottom of the bottom plate of the platform. During the heavy equipment hoisting operation, the heavy equipment is hoisted onto a load car on the bottom plate of the platform by virtue of a tower crane, and then the load car is pulled by a winch to place the heavy equipment in a demanded installation position. Through adoption of the equipment hoisting platform and the equipment hoisting method based the equipment hoisting platform, the labor intensity for hosting the heavy equipment onto the high-rise building can be reduced effectively, and the work efficiency of workers is improved. The equipment hoisting platform and method can be applied to the field of renovation of traditional industries through high and new technologies.

Description

The hoisting platform and the hanging method that are used for equipment hoisting on the super highrise building
Technical field
The present invention relates to the equipment hoisting field, particularly relate to a kind of hoisting platform of equipment hoisting and method that lifts through hoisting platform of being used for.
Background technology
Along with the urbanization process step is accelerated, the land resources of large size city inner city is precious, and therefore the development speed of super highrise building is swift and violent in recent years.Super highrise building inside needs for function; Generally all be provided with the multi-layer device layer; Be furnished with large-scale functional apparatus in the mechanical floor, as: air-conditioning unit, water pump, cooling tower, wind cabinet etc., the equipment of central maximum are about 5 meters, wide about 3 meters, high about 3 meters, heavily about 20 tons.
When using traditional hanging method that equipment hoisting is advanced floor, adopt the method for " take by force and hang " usually, promptly tiltedly draw in floor.Operating personnel are in floor, and equipment leans against outside the floor, lean on horizontal force to advance floor to the equipment hard draw.During construction, need the close collaboration of a plurality of skilled heavy industrys, could draw in mechanical floor to main equipment reposefully.The construction speed of this hanging method is very slow, and every main equipment advances floor all needs several hours, and two hours at least, many persons three or four hours, and working security is poor, has the situation of tiltedly hanging, and operating personnel keep away the phenomenon of the local hanging operation of unavoidable existence.
Advance the method for floor during therefore traditional main equipment lifting, have that labour intensity is big, the lifting progress is slow, a shortcoming of lifting poor stability etc.Along with raising, the building operations of building trade construction overall technology level will be implemented " people-oriented " and guarantee construction safety, the lifting of super highrise building main equipment presses for adopts new technology to realize that lifting is safe and reliable, reduce labour intensity, to improve lifting efficient.
Summary of the invention
For addressing the above problem, the present invention provides the hoisting platform of equipment hoisting on a kind of super highrise building that can effectively reduce lifting construction labour intensity and carries out the method for equipment hoisting through this platform.
The technical solution adopted for the present invention to solve the technical problems is:
The hoisting platform that is used for equipment hoisting on a kind of super highrise building; Comprise the platform floor that is arranged at highrise building wall outer side and horizontal positioned and be arranged at the support girder of platform floor two bottom sides; Support on the girder perpendicular to supporting the support secondary beam that girder is provided with some parallel and horizontal positioned; Support between secondary beam and platform floor and be provided with some parallel support girders, be equipped with the diagonal member that is used for auxiliary reinforcing support girder between the support girder of platform floor both sides and building masonry wall.
Further as the improvement of technical scheme of the present invention, platform floor is provided with can be along the load-carrying dolly of platform floor upper surface place planar slide.
Further as the improvement of technical scheme of the present invention, the diagonal member of both sides and building masonry wall and support to be equipped with between girder and be used for the hinge member of hinge-coupled each other.
Further as the improvement of technical scheme of the present invention, support secondary beam and support girder, platform floor and support that fixed form is fixed to one another to be connected through welding between girder.
Further, be provided with guardrail around the platform floor as the improvement of technical scheme of the present invention.
A kind ofly carry out the hanging method of equipment hoisting, it is characterized in that, may further comprise the steps through above-mentioned hoisting platform:
1), connection otic placode or otic placode built-in fitting are installed on the required building masonry wall that lifts;
2), earlier with the support girder of platform floor two bottom sides with is connected otic placode or otic placode built-in fitting and connects, after with diagonal member respectively at connection otic placode or the connection of otic placode built-in fitting;
3), through tower crane with on the load-carrying dolly on the required equipment hoisting horizontalization platform base plate that lifts;
4), connect hoist engine, start hoist engine and drag load-carrying dolly mobile device to the installation site in a side of load-carrying dolly.
Further as the improvement of technical scheme of the present invention, step 2) in diagonal member with connects between otic placode or otic placode built-in fitting through articulated manner realization connection.
Further, through before the tower crane hanging device, on the required equipment that lifts, hoist cable is installed in the step 3) as the improvement of technical scheme of the present invention.
Beneficial effect of the present invention: this hoisting platform is encorbelmented platform floor and is arranged at the highrise building wall outer side; And the support girder through being installed on platform floor bottom, support secondary beam and support girder the jumbo on platform floor and the platform floor is supported; When carrying out the Heavy Equipment-hoisting operation; Earlier through tower crane with after on the load-carrying dolly on Heavy Equipment-hoisting to the platform floor; Through hoist engine pulling load-carrying dolly jumbo is placed required installation site again, this hoisting platform and use the hanging method of this hoisting platform can effectively reduce the labour intensity of Heavy Equipment-hoisting on the highrise building improves workman's efficiency.
Description of drawings
Below in conjunction with accompanying drawing the present invention is described further:
Fig. 1 is that the overall structure of the embodiment of the invention is implemented sketch map;
Fig. 2 is a hoisting platform vertical view in the embodiment of the invention.
The specific embodiment
With reference to Fig. 1, Fig. 2; The present invention is for being used for the hoisting platform of equipment hoisting on a kind of super highrise building; Comprise the platform floor 1 that is arranged at highrise building wall outer side and horizontal positioned and be arranged at the support girder 2 of platform floor 1 two bottom sides; Support on the girder 2 perpendicular to supporting the support secondary beam 3 that girder 2 is provided with some parallel and horizontal positioned; Support secondary beam 3 and 1 of platform floor and be provided with some parallel support girders 4, be equipped with the diagonal member 5 that is used for auxiliary reinforcing support girder 2 between the support girder 2 of platform floor 1 both sides and building masonry wall.
As the preferred embodiment of the present invention, platform floor 1 is provided with can be along the load-carrying dolly 6 of platform floor 1 upper surface place planar slide.
A kind ofly carry out the hanging method of equipment hoisting, it is characterized in that, may further comprise the steps through above-mentioned hoisting platform:
1), connection otic placode or otic placode built-in fitting are installed on the required building masonry wall that lifts;
2), earlier with the support girder 2 of platform floor 1 two bottom sides with is connected otic placode or otic placode built-in fitting and connects, after with diagonal member 5 respectively at connection otic placode or the connection of otic placode built-in fitting;
3), through tower crane with on the load-carrying dolly 6 on the required equipment hoisting horizontalization platform base plate 1 that lifts;
4), connect hoist engine, start hoist engine and drag load-carrying dolly 6 mobile devices to the installation site in a side of load-carrying dolly 6.
This hoisting platform is encorbelmented platform floor 1 and is arranged at the highrise building wall outer side; And the support girder 2 through being installed on platform floor 1 bottom, support secondary beam 3 and the jumbo that supports on 4 pairs of platform floors 1 of girder and the platform floor 1 supports; When carrying out the Heavy Equipment-hoisting operation; Earlier through tower crane with after on the load-carrying dolly 6 on Heavy Equipment-hoisting to the platform floor 1; Through hoist engine pulling load-carrying dolly 6 jumbo is placed required installation site again, this hoisting platform and use the hanging method of this hoisting platform can effectively reduce the labour intensity of Heavy Equipment-hoisting on the highrise building improves workman's efficiency.
As the preferred embodiment of the present invention, the diagonal member 5 of both sides and building masonry wall and 2 of girders of support are equipped with and are used for the hinge member of hinge-coupled each other.
As the preferred embodiment of the present invention, support secondary beam 3 and support girder 2, platform floor 1 and support 4 of girders that fixed form is fixed to one another to be connected through welding.
As the preferred embodiment of the present invention, be provided with guardrail 8 around the platform floor 1.
As the preferred embodiment of the present invention, step 2) in diagonal member 5 with connects between otic placode or otic placode built-in fitting through articulated manner realization connection.
As the preferred embodiment of the present invention, through before the tower crane hanging device, on the required equipment that lifts, hoist cable 7 is installed in the step 3).
Carrying out before hoisting platform makes, needing bearing capacity, the main equipment installation site of peripheral headroom size, floor, the appearance and size and the weight of main equipment, choosing the installation site of hoisting platform according to the super highrise building mechanical floor.The installation site of selecting will guarantee that the floor clear space at this place satisfies the requirement that equipment advances floor space; Satisfy the needs that main equipment transports bearing capacity and transport space from the position of platform to the transit route of equipment installation site; Under the situation that satisfies two conditions in front; The equipment transit route can shorten as far as possible, to raise the efficiency.
Simultaneously, need the dimensional parameters of design hoisting platform according to the structure of super highrise building, the appearance and size and the weight of main equipment.In hoisting platform when design, will be carried out checking computations to the structure that all construction loads are loaded into super highrise building, the structural safety of super highrise building when guaranteeing to lift.Hoisting platform is formed by supporting girder 2, support secondary beam 3, support girder 4, platform floor 1 and guardrail 8; Equipment hoisting to the platform floor 1 after; The equipment load is by transmitting by following path: to supporting secondary beam 3, arrive at last and support girder 2 behind platform floor 1 to the support girder 4.The stability of the hoisting platform that is provided with for guaranteeing to encorbelment is provided with two diagonal members 5 in the both sides of hoisting platform, diagonal member 5 two ends are hinged with the support girder 2 of the last layer structure of super highrise building equipment and the steel platform of encorbelmenting respectively.Platform floor 1 is interrupted welding with support girder 4, supports girder 4, supports secondary beam 3, supports the welding of girder 2 total cross-sections, and support girder 2 is hinged with high-strength bolt with super highrise building mechanical floor structure.
After adopting said method to implement, main equipment is no more than ten minutes with regard to bit time on platform floor 1, and traditional upside-down method of hull-section construction of comparing has been practiced thrift main equipment greatly and advanced the time of floor, and reduced labour intensity, more can guarantee construction safety.The employing said method is implemented, and promotes whole project accelerating construction progress the service time of having practiced thrift tower crane in a large number, thereby has created considerable economic more.Therefore the application of this method, the hoisting process safety is higher, operate very simple and efficiently, has reached safety, economy, target efficiently.
Certainly; The invention is not limited to above-mentioned embodiment; Those of ordinary skill in the art also can make equivalent variations or replacement under the prerequisite of spirit of the present invention, modification that these are equal to or replacement all are included in the application's claim institute restricted portion.

Claims (8)

1. the hoisting platform that is used for equipment hoisting on the super highrise building; It is characterized in that: comprise the platform floor (1) that is arranged at highrise building wall outer side and horizontal positioned and be arranged at the support girder (2) of platform floor (1) two bottom sides; Said support girder (2) is gone up perpendicular to supporting the support secondary beam (3) that girder (2) is provided with some parallel and horizontal positioned; Be provided with some parallel support girders (4) between said support secondary beam (3) and platform floor (1), be equipped with the diagonal member (5) that is used for auxiliary reinforcing support girder (2) between the support girder (2) of said platform floor (1) both sides and building masonry wall.
2. be used for the hoisting platform of equipment hoisting on the super highrise building according to claim 1, it is characterized in that: said platform floor (1) is provided with can be along the load-carrying dolly (6) of platform floor (1) upper surface place planar slide.
3. be used for the hoisting platform of equipment hoisting on the super highrise building according to claim 1 and 2, it is characterized in that: diagonal member of said both sides (5) and building masonry wall and support to be equipped with between girder (2) and be used for the hinge member of hinge-coupled each other.
4. be used for the hoisting platform of equipment hoisting on the super highrise building according to claim 1 and 2, it is characterized in that: said support secondary beam (3) with support girder (2), platform floor (1) and support that fixed form is fixed to one another to be connected through welding between girder (4).
5. be used for the hoisting platform of equipment hoisting on the super highrise building according to claim 1 and 2, it is characterized in that: be provided with guardrail (8) around the said platform floor (1).
6. one kind is carried out the hanging method of equipment hoisting through the described hoisting platform of claim 2, it is characterized in that, may further comprise the steps:
1) connection otic placode or otic placode built-in fitting are installed on the required building masonry wall that lifts;
2) earlier with the support girder (2) of said platform floor (1) two bottom sides with is connected otic placode or otic placode built-in fitting and connects, after with diagonal member (5) respectively at connection otic placode or the connection of otic placode built-in fitting;
3) through tower crane the required equipment hoisting that lifts is put on the load-carrying dolly (6) on the said platform floor (1);
4) side at said load-carrying dolly (6) connects hoist engine, starts hoist engine and drags load-carrying dolly (6) mobile device to the installation site.
7. hanging method according to claim 6 is characterized in that: said step 2) diagonal member (5) with connects between otic placode or otic placode built-in fitting through articulated manner realization connection.
8. hanging method according to claim 6 is characterized in that: through before the tower crane hanging device, hoist cable (7) is installed on the required equipment that lifts in the said step 3).
CN2012100973524A 2012-04-05 2012-04-05 Equipment hoisting platform and method for super high-rise buildings Pending CN102635225A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100973524A CN102635225A (en) 2012-04-05 2012-04-05 Equipment hoisting platform and method for super high-rise buildings

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100973524A CN102635225A (en) 2012-04-05 2012-04-05 Equipment hoisting platform and method for super high-rise buildings

Publications (1)

Publication Number Publication Date
CN102635225A true CN102635225A (en) 2012-08-15

Family

ID=46619789

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100973524A Pending CN102635225A (en) 2012-04-05 2012-04-05 Equipment hoisting platform and method for super high-rise buildings

Country Status (1)

Country Link
CN (1) CN102635225A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104030176A (en) * 2014-05-30 2014-09-10 中建七局安装工程有限公司 Balance beam for lifting platform truss and lifting method thereof
CN104818858A (en) * 2015-04-22 2015-08-05 中国十七冶集团有限公司 Indoor heavy electric cabinet lifting method
CN107288353A (en) * 2017-07-11 2017-10-24 中建局集团安装工程有限公司 Equipment hoisting transition support platform and its construction method on a kind of super-high buildings floor
CN107327148A (en) * 2017-06-08 2017-11-07 天津送变电工程公司 A kind of lower jacking ready-package hoisting platform and construction method
CN108004933A (en) * 2017-12-25 2018-05-08 中铁大桥局集团第五工程有限公司 A kind of bridge construction survey platform that can be recycled and application method
CN111456400A (en) * 2020-03-24 2020-07-28 中国五冶集团有限公司 Interim operation platform structure in high altitude
CN111734148A (en) * 2020-06-03 2020-10-02 中国核工业华兴建设有限公司 Alternate hoisting method in semi-hollow U-shaped long and narrow space
WO2023240814A1 (en) * 2022-06-13 2023-12-21 上海建工一建集团有限公司 Construction safety protection platform structure and method for aerial deformation of core tube

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201169904Y (en) * 2008-07-18 2008-12-24 山东金塔建设有限公司 Assembly type suspension supporting discharge platform
CN201276399Y (en) * 2008-09-11 2009-07-22 上海市安装工程有限公司 Apparatus hoisting mechanism for tall building floor non-steel platform
CN101503908A (en) * 2009-03-03 2009-08-12 南通建工集团股份有限公司 Construction method for spacing suspension cable structural template support platform
CN201297036Y (en) * 2008-11-19 2009-08-26 常州第一建筑工程有限公司 Discharging platform
CN201351360Y (en) * 2008-12-12 2009-11-25 广西建工集团第五建筑工程有限责任公司 High-rise building construction assembly unloading platform
JP4504747B2 (en) * 2004-06-25 2010-07-14 三井住友建設株式会社 Building construction method using tower crane
CN201834511U (en) * 2010-08-31 2011-05-18 中建工业设备安装有限公司 Unloading and transferring platform for high-rise special building
CN202017347U (en) * 2011-04-18 2011-10-26 南通长城建筑安装工程有限公司 Externally-hung discharging platform device
CN102367706A (en) * 2011-10-29 2012-03-07 李欣 Prefabricated unloading platform for high-rise building construction

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4504747B2 (en) * 2004-06-25 2010-07-14 三井住友建設株式会社 Building construction method using tower crane
CN201169904Y (en) * 2008-07-18 2008-12-24 山东金塔建设有限公司 Assembly type suspension supporting discharge platform
CN201276399Y (en) * 2008-09-11 2009-07-22 上海市安装工程有限公司 Apparatus hoisting mechanism for tall building floor non-steel platform
CN201297036Y (en) * 2008-11-19 2009-08-26 常州第一建筑工程有限公司 Discharging platform
CN201351360Y (en) * 2008-12-12 2009-11-25 广西建工集团第五建筑工程有限责任公司 High-rise building construction assembly unloading platform
CN101503908A (en) * 2009-03-03 2009-08-12 南通建工集团股份有限公司 Construction method for spacing suspension cable structural template support platform
CN201834511U (en) * 2010-08-31 2011-05-18 中建工业设备安装有限公司 Unloading and transferring platform for high-rise special building
CN202017347U (en) * 2011-04-18 2011-10-26 南通长城建筑安装工程有限公司 Externally-hung discharging platform device
CN102367706A (en) * 2011-10-29 2012-03-07 李欣 Prefabricated unloading platform for high-rise building construction

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN104030176A (en) * 2014-05-30 2014-09-10 中建七局安装工程有限公司 Balance beam for lifting platform truss and lifting method thereof
CN104030176B (en) * 2014-05-30 2016-06-29 中建七局安装工程有限公司 The equalizer bar of hoisting platform truss and hanging method thereof
CN104818858A (en) * 2015-04-22 2015-08-05 中国十七冶集团有限公司 Indoor heavy electric cabinet lifting method
CN107327148A (en) * 2017-06-08 2017-11-07 天津送变电工程公司 A kind of lower jacking ready-package hoisting platform and construction method
CN107288353A (en) * 2017-07-11 2017-10-24 中建局集团安装工程有限公司 Equipment hoisting transition support platform and its construction method on a kind of super-high buildings floor
CN108004933A (en) * 2017-12-25 2018-05-08 中铁大桥局集团第五工程有限公司 A kind of bridge construction survey platform that can be recycled and application method
CN108004933B (en) * 2017-12-25 2024-02-27 中铁大桥局集团第五工程有限公司 Recyclable bridge construction measurement platform and using method
CN111456400A (en) * 2020-03-24 2020-07-28 中国五冶集团有限公司 Interim operation platform structure in high altitude
CN111734148A (en) * 2020-06-03 2020-10-02 中国核工业华兴建设有限公司 Alternate hoisting method in semi-hollow U-shaped long and narrow space
WO2023240814A1 (en) * 2022-06-13 2023-12-21 上海建工一建集团有限公司 Construction safety protection platform structure and method for aerial deformation of core tube

Similar Documents

Publication Publication Date Title
CN102635225A (en) Equipment hoisting platform and method for super high-rise buildings
CN103086279B (en) Vertical transportation construction method for building construction
CN104652298B (en) A kind of whole dismounting system and construction method thereof transferred across box beam supported based on bridge floor
CN205387439U (en) Mast hoisting accessory
CN106006425A (en) Method of hoisting and transporting large-sized equipment arranged in underground machine rooms of super high-rise buildings
CN206859698U (en) A kind of high-rise building air conditioner water vertical shaft Large Diameter Pipeline standpipe inverted construction facility
CN205328487U (en) Dismantlement system of superelevation extra -large -size tower crane
CN202483154U (en) High bearing capacity suspending scaffold
CN204626998U (en) A kind of attached lift scaffold discharging platform
CN103982046A (en) Lifting and installation method of buckling restrained braces
CN104328922B (en) High-altitude multilayer is dangled steel construction against way Hoisting Construction Technology
CN103979442B (en) The method of 6400 tons of Hydraulic double-type crane lifting cost tropsch reactors
CN204001751U (en) Super high steel structure construction overhanging unloading platform
CN203654754U (en) Double-layered overhanging type discharging platform
CN202744175U (en) Sling used for hoisting precast concrete columns
CN204402001U (en) For the mobile operating platform system that structure for steel structure roof inner slab is installed
CN204357138U (en) Simple steel structure lifting upending frame
CN210369846U (en) Operating platform capable of being clamped on elevator shaft shear wall surface and lifted layer by layer
CN202672694U (en) Shaft construction circulation operating platform
CN103291078B (en) A kind of steel girder erection equipment
CN106121254A (en) Heavy component transportation system and construction method after a kind of contrary sequence method dismounting
CN105060124A (en) Intra-frame portal crane system and hoisting use method thereof
CN201952126U (en) Layer-by-layer retreating platform type indoor article lifting system
CN205531262U (en) Steel construction construction platform can rise automatically
CN105155832A (en) Hanging basket device and moving method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120815