CN102605718A - Prefabrication and construction method of box girder in-situ pedestal - Google Patents

Prefabrication and construction method of box girder in-situ pedestal Download PDF

Info

Publication number
CN102605718A
CN102605718A CN2012101059747A CN201210105974A CN102605718A CN 102605718 A CN102605718 A CN 102605718A CN 2012101059747 A CN2012101059747 A CN 2012101059747A CN 201210105974 A CN201210105974 A CN 201210105974A CN 102605718 A CN102605718 A CN 102605718A
Authority
CN
China
Prior art keywords
pedestal
side form
scaffold
concrete
box girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012101059747A
Other languages
Chinese (zh)
Inventor
张志军
李建军
梁胜国
李周伟
于剑舟
吕亚杰
祁玺剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 12th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Original Assignee
China Railway 12th Bureau Group Co Ltd
Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 12th Bureau Group Co Ltd, Third Engineering Co Ltd of China Railway 12th Bureau Group Co Ltd filed Critical China Railway 12th Bureau Group Co Ltd
Priority to CN2012101059747A priority Critical patent/CN102605718A/en
Publication of CN102605718A publication Critical patent/CN102605718A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention particularly relates to a prefabrication and construction method of a box girder in-situ pedestal, which solves the problems that cast-in-place box girders are high in cost and slow in progress and engineering construction is affected. The prefabrication and construction method includes: a, surveying lofting, performing replacement and layered compaction, and backfilling and tampering the area around an abutment; b, erecting a formwork to concrete a concrete pedestal serving as a bottom form, reserving pull bar holes on the top of the pedestal, and casting a concrete foundation around the pedestal; c, tying tie bars to fasten the bottoms of the lateral forms, using support bars to adjust the top elevation of the lateral forms, using a cup-lock scaffold to reinforce the lateral forms, and placing adjustable jacks and square timber on the top of the scaffold; d, pre-stressing the lateral forms to eliminate non-elastic deformation of a foundation and the scaffold, and correcting elevation of the foundation and the lateral forms again according to pre-stressing results; and e, sequentially installing bottom web reinforcement, inner membrane forms, top plate reinforcement and embedded parts, and pouring body concrete of the box girder. By the method, the stress effect of the forms can be improved greatly, and the prefabrication and construction method has the advantages of simple structure, reasonable design, simplicity in operation and effectiveness in use.

Description

Case beam original position pedestal precast construction method
Technical field
The present invention relates to the box girder construction method, be specially a kind of case beam original position pedestal precast construction method.
Background technology
Cast-in-place beam is one of important way of crossing in existing road, water channel, has characteristics such as widely applicable, that construction technology is easily understood, and can significantly reduce case beam cost of transportation.The existing cast-in-place method construction cost of case beam is higher, and need set up a bowl buckle scaffold in a large number, and progress is slower, needs a large amount of plant equipment to cooperate simultaneously, and via hole also needs big quantity space and influences the difficult problem of all the other engineering constructions of tunnel.
Summary of the invention
The present invention provides a kind of case beam original position pedestal precast construction method in order to solve the problem that the case beam adopts cast-in-place method to have that cost is high, progress slow and influences engineering construction.
The present invention adopts following technical scheme to realize: case beam original position pedestal precast construction method; Adopt following steps: a, measure setting-out; Confirm box girder body position and ground process range and height, change fill out, layered rolling, and to backfilling compaction around the pier; B, formwork erection concreting pedestal be as bed die, and under the pedestal end face, reserve tie rod hole, concreting basis around the pedestal; C, cross pull bar in pedestal to drawing fixedly the side form bottom, the strut that is connected between side form and the concrete foundation is regulated side form top absolute altitude, and through the bowl fastening type scaffold side form is reinforced, and the scaffold top is provided with the adjustable jacking and the lumps of wood; D, carry out the side form precompressed, eliminate the nonelastic deformation of ground and scaffold, again ground and side form are carried out the absolute altitude correction according to the precompressed result; E, successively end web reinforcement, inner membrance template, top board reinforcing bar and built-in fitting are installed after, build box girder body concrete.
This box girder construction is directly prefabricated on the adjacent bridge pier; The concrete pedestal with box girder body weight evenly distributed load in ground, efficiently solve the support cast-in-place method need set up in a large number the bowl fastening type scaffold cause progress slow, need that a large amount of plant equipment cooperate, via hole needs big quantity space and influence the problem of constructing tunnel.
The present invention replaces bed die through pedestal is set in case beam original position; Improve the stressed effect of template greatly, significantly reduced the quantity of setting up of bowl buckle scaffold, saved the expense of mobile formwork assembling; And the template of this method and bracing reinforcement material can repeatedly have enough to meet the need; Economic benefit is particularly outstanding, has advantage simple in structure, reasonable in design, easy and simple to handle, that result of use is good, is applied to cast-in-place beam construction use under cast-in-place beam construction of squat pier bridge location or the complex environment.
Description of drawings
Fig. 1 is a structural representation of the present invention.
Among the figure: 1-pedestal, 2-tie rod hole, 3-concrete foundation, 4-strut, 5-scaffold.
The specific embodiment
Case beam original position pedestal precast construction method adopts following steps: a, measures setting-out, confirms box girder body position and ground process range and height, change fill out, layered rolling, and to backfilling compaction around the pier; B, formwork erection concreting pedestal 1 be as bed die, and under pedestal 1 end face, reserve tie rod hole 2, concreting basis 3 around the pedestal 1; C, cross pull bar in pedestal 1 to drawing fixedly the side form bottom, the strut 4 that is connected between side form and the concrete foundation 3 is regulated side form top absolute altitude, and reinforces through 5 pairs of side forms of bowl fastening type scaffold, and scaffold 5 tops are provided with the adjustable jacking and the lumps of wood; D, carry out the side form precompressed, eliminate the nonelastic deformation of ground and scaffold 5, again ground and side form are carried out the absolute altitude correction according to the precompressed result; E, successively end web reinforcement, inner membrance template, top board reinforcing bar and built-in fitting are installed after, build box girder body concrete.
In the practical implementation process, change to fill out to adopt and contain the stone amount and change at the sand gravel more than 60% and fill out, after the mechanical equating; And single slope drainage slope and charge for remittance well are set, every layer of loose laying depth is no more than 30cm, carries out layered rolling; Adopt the 37 lime earth backfill around the pier, battering ram is tamped.
Pedestal 1 height 25 ㎝; The pedestal template adopts that [25 channel-section steels, pedestal 1 end face absolute altitude are absolute altitude at the bottom of the beam that is provided with after the camber, and formwork erection must carry out accurate levelling to it; Error must not be greater than 2 ㎜; Return 5 ㎝ places under pedestal 1 end face and reserve the tie rod hole 2 that crosses pedestal, tie rod hole 2 is centered close to by vertical 20 ㎝ places, form joint both sides between side form, and tie rod hole 2 adopts the pvc pipe of Ф 40 ㎜ pre-buried in pedestal 1; Ф 10 steel mesh reinforcements that 40 ㎝ * 40 ㎝ are installed are built the C20 concrete in pedestal, end face is repeatedly received flat the processing, and health in time; Concrete foundation adopts the C20 concrete, and thickness is 10 ㎝, and the end face absolute altitude is control to be lower than pedestal end face 25 ㎝.
Earlier the end side form is positioned, all the other side forms are installed successively again, make that side form bottom pull bar preformed hole is corresponding with 2 positions, pedestal 1 draw-in bar hole and pull bar in time is installed; Pull bar adopts the special fining twisted steel of Ф 32 ㎜; The high-strength nut socket of Ф 32 ㎜ is adopted in pull bar two ends and junction, side form bottom, and the outside strut 4 of side form is anchored in the concrete foundation of the outside through expansion bolt, and side form top absolute altitude can be regulated through strut 4; Scaffold 5 material specifications: vertical, cross bar length is 0.6m; Vertical rod length is 0.6m, 0.3m, and jacking adopts adjustable holder support, and jacking is laid vertical lumps of wood.
Side form precompressed and adjustment; Safety for the check side form; Grasp its distortion after stressed, eliminate the nonelastic deformation of ground nonelastic deformation and scaffold 5, the employing sand pocket loads precompressed to side form; Prefabricating load is pressed box girder body Approximate Equivalent load and is arranged, the precompressed maximum load is got 120% box girder body and added the internal mold deadweight from heavy load; Simulating beam body casting sequence divides level Four symmetry to load during precompressed, during loading according to first web, the order symmetry of base plate, back frange plate loads again.Through precompressed, draw nonelastic deformation value and elastic deformation value; The camber sum of calculating according to the distortion of the amount of deflection of case beam and scaffold 5, as the peak of camber, what be arranged on the case beam strides the footpath mid point; The camber of other each points is peak with the mid point, is the rack elasticity deflection with the both ends of case beam, distributes by second-degree parabola; Again adjust according to the ground and the side form absolute altitude of absolute altitude at the bottom of the case beam that calculates after precompressed.

Claims (1)

1. case beam original position pedestal precast construction method is characterized in that: adopt following steps: a, measure setting-out, confirm box girder body position and ground process range and height, change fill out, layered rolling, and to backfilling compaction around the pier; B, formwork erection concreting pedestal (1) be as bed die, and under pedestal (1) end face, reserve tie rod hole (2), and pedestal (1) is concreting basis (3) on every side; C, cross pull bar in pedestal (1) to drawing fixedly the side form bottom; The strut (4) that is connected between side form and the concrete foundation (3) is regulated side form top absolute altitude; And through bowl fastening type scaffold (5) side form is reinforced, scaffold (5) top is provided with the adjustable jacking and the lumps of wood; D, carry out the side form precompressed, eliminate the nonelastic deformation of ground and scaffold (5), again ground and side form are carried out the absolute altitude correction according to the precompressed result; E, successively end web reinforcement, inner membrance template, top board reinforcing bar and built-in fitting are installed after, build box girder body concrete.
CN2012101059747A 2012-04-12 2012-04-12 Prefabrication and construction method of box girder in-situ pedestal Pending CN102605718A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012101059747A CN102605718A (en) 2012-04-12 2012-04-12 Prefabrication and construction method of box girder in-situ pedestal

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012101059747A CN102605718A (en) 2012-04-12 2012-04-12 Prefabrication and construction method of box girder in-situ pedestal

Publications (1)

Publication Number Publication Date
CN102605718A true CN102605718A (en) 2012-07-25

Family

ID=46523452

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012101059747A Pending CN102605718A (en) 2012-04-12 2012-04-12 Prefabrication and construction method of box girder in-situ pedestal

Country Status (1)

Country Link
CN (1) CN102605718A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106835992A (en) * 2017-03-03 2017-06-13 广州市第二市政工程有限公司 A kind of arcuate structure clear-water concrete construction of cast-in-situ box-beam method
CN110242045A (en) * 2019-06-20 2019-09-17 中国十九冶集团有限公司 cast-in-place beam combined template system and construction method thereof
CN111319118A (en) * 2020-02-27 2020-06-23 中交二公局第四工程有限公司 Prefabrication construction method of box girder in plateau valley bridge construction
CN113774802A (en) * 2021-09-17 2021-12-10 黑龙江省龙建路桥第五工程有限公司 Cast-in-place box girder edge protection structure and construction method

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201132364Y (en) * 2007-10-15 2008-10-15 中铁二局股份有限公司 Beam-making pedestal equipment for pretensioned prestressing concrete box beam
CN201304683Y (en) * 2008-11-13 2009-09-09 中铁二局股份有限公司 Casting beam pedestal device of pre-tension pre-stressed concrete beam
KR20090117592A (en) * 2008-05-09 2009-11-12 (주)삼현피에프 Installation method of rahmen bridge with combined girder of steel girder and concrete with minimized negative moment at ends thereof
CN101713168A (en) * 2008-10-06 2010-05-26 中交第三航务工程局有限公司 Process for mounting template for manufacturing sectional box girders
CN201695341U (en) * 2010-06-28 2011-01-05 中铁二十局集团有限公司 Box girder prefabricated pedestal
CN202090289U (en) * 2011-05-20 2011-12-28 湖南中铁五新钢模有限责任公司 Shared type outer lateral template for straight web box girders with different heights

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201132364Y (en) * 2007-10-15 2008-10-15 中铁二局股份有限公司 Beam-making pedestal equipment for pretensioned prestressing concrete box beam
KR20090117592A (en) * 2008-05-09 2009-11-12 (주)삼현피에프 Installation method of rahmen bridge with combined girder of steel girder and concrete with minimized negative moment at ends thereof
CN101713168A (en) * 2008-10-06 2010-05-26 中交第三航务工程局有限公司 Process for mounting template for manufacturing sectional box girders
CN201304683Y (en) * 2008-11-13 2009-09-09 中铁二局股份有限公司 Casting beam pedestal device of pre-tension pre-stressed concrete beam
CN201695341U (en) * 2010-06-28 2011-01-05 中铁二十局集团有限公司 Box girder prefabricated pedestal
CN202090289U (en) * 2011-05-20 2011-12-28 湖南中铁五新钢模有限责任公司 Shared type outer lateral template for straight web box girders with different heights

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
《天津建设科技》 20040630 张平 "预制预应力桥梁无底模施工技术" 第41-42页 1 , 第3期 *
刘海功等: ""混凝土刚性基础底模工艺在现浇箱梁施工中的应用"", 《城市建设》 *
张平: ""预制预应力桥梁无底模施工技术"", 《天津建设科技》 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106835992A (en) * 2017-03-03 2017-06-13 广州市第二市政工程有限公司 A kind of arcuate structure clear-water concrete construction of cast-in-situ box-beam method
CN106835992B (en) * 2017-03-03 2018-08-24 广州市第二市政工程有限公司 A kind of arcuate structure clear-water concrete construction of cast-in-situ box-beam method
CN110242045A (en) * 2019-06-20 2019-09-17 中国十九冶集团有限公司 cast-in-place beam combined template system and construction method thereof
CN111319118A (en) * 2020-02-27 2020-06-23 中交二公局第四工程有限公司 Prefabrication construction method of box girder in plateau valley bridge construction
CN113774802A (en) * 2021-09-17 2021-12-10 黑龙江省龙建路桥第五工程有限公司 Cast-in-place box girder edge protection structure and construction method

Similar Documents

Publication Publication Date Title
CN109778721A (en) Synchronization of jacking up bridge top and the bottom structure carries out the method that bridge increases transformation
KR100993777B1 (en) Rahmen structure construction method using precast segment
CN107336346B (en) Beam making pedestal
CN110578287B (en) Assembled earthing corrugated steel plate-prestressed concrete combined arch bridge and construction method thereof
CN204899204U (en) Mouthful structure concrete structure's of department a template system fetches earth among reverse construction method
CN112779864A (en) Combined cast-in-place box girder support structure and construction method thereof
CN103603435B (en) A kind of assembly concrete antidetonation beam column frame and construction method thereof
CN102605718A (en) Prefabrication and construction method of box girder in-situ pedestal
CN102797223B (en) Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
CN103046764A (en) Method for reinforcing pre-stressed concrete core unit by using bar-mat reinforcement fine aggregate concrete
CN210684430U (en) Main bridge jacking system of large-span tied arch bridge
CN103510458B (en) Pile type continuous rigid frame bridge and construction method thereof
CN204780635U (en) Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures
CN112176879A (en) Bridge pier foundation underpinning structure and construction method
CN216075208U (en) Ultrahigh large-section steel pipe concrete column
CN115094947A (en) Method for mounting prestressed plate assembled retaining wall
CN111676740B (en) Construction and design method of anti-arching roadbed structure of ballastless track of cutting section
CN213508572U (en) Piping lane supporting construction
CN110424245B (en) Large-span tied arch bridge reconstruction method based on bridge hydraulic jacking system
CN211735010U (en) Assembled earthing corrugated steel plate-prestressed concrete combination arched bridge
CN110700069A (en) Su dyke arched bridge structure
CN215857239U (en) Support combination fixing and erecting structure
CN108086349A (en) A kind of corrugated steel pipe overlaps cross section structure
CN211928904U (en) Force transmission structure for simulating interaction relation between landslide body and bridge structure
CN219973248U (en) Construction structure of profile steel stiff pile retaining wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120725