CN102587944A - 松软岩层小断面掘进超前支护工艺 - Google Patents

松软岩层小断面掘进超前支护工艺 Download PDF

Info

Publication number
CN102587944A
CN102587944A CN2012100770515A CN201210077051A CN102587944A CN 102587944 A CN102587944 A CN 102587944A CN 2012100770515 A CN2012100770515 A CN 2012100770515A CN 201210077051 A CN201210077051 A CN 201210077051A CN 102587944 A CN102587944 A CN 102587944A
Authority
CN
China
Prior art keywords
supporting
steel pipe
stratum
soft rock
advance
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN2012100770515A
Other languages
English (en)
Other versions
CN102587944B (zh
Inventor
齐银山
唐宏民
杨振增
齐元国
王磊
刘海波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Hualian Mining Co Ltd
Original Assignee
Shandong Hualian Mining Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Hualian Mining Co Ltd filed Critical Shandong Hualian Mining Co Ltd
Priority to CN201210077051.5A priority Critical patent/CN102587944B/zh
Publication of CN102587944A publication Critical patent/CN102587944A/zh
Application granted granted Critical
Publication of CN102587944B publication Critical patent/CN102587944B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

本发明涉及一种松软岩层小断面掘进超前支护工艺,属于巷道采掘安全技术领域,其特征在于包括以下步骤:准备顶板支护材料、打支护眼孔、将钢管顶入支护眼孔、进行凿岩***、进行出渣作业、进行二次***和进行永久支护作业。松软岩层小断面掘进超前支护工艺的施工顺序是先进行巷道顶板支护在进行凿岩***,***完成后形成顶板预支护空间,提高了人员在工作面下作业的安全性,增大了顶板承压,减小了冒顶的可能,解决了松软岩层掘进中空顶下打钻、出渣顶板危险系数大的问题,方便了永久支护作业,提高了掘进速度。

Description

松软岩层小断面掘进超前支护工艺
技术领域
本发明涉及一种松软岩层小断面掘进超前支护工艺,属于巷道采掘安全技术领域。
背景技术
目前,在松软破碎岩层中进行施工时,传统的***掘进工艺,施工顺序是先进行凿岩***在进行巷道顶板支护,安全系数较低,且存在着在松软岩层掘进中空顶下打钻、出渣顶板危险系数大的问题。
发明内容
根据以上现有技术中的不足,本发明要解决的技术问题是:提供一种解决了上述缺陷的,提高了作业安全系数的松软岩层小断面掘进超前支护工艺。
本发明解决其技术问题所采用的技术方案是:所述的松软岩层小断面掘进超前支护工艺,其特征在于包括以下步骤:
a、准备顶板支护材料,顶板支护材料为钢管;
b、在软岩工作面顶板以上200mm处打支护眼孔,打眼直径与钢管直径相同,打眼深度为5m;
c、打眼完成后,将钢管顶入支护眼孔,钢管尾部外露部分用钢丝连接并悬吊于工作面顶板锚杆上;
d、在工作面进行凿岩***,***后,工作面顶板为钢管组合体形成的预支护空间,在预支护空间内进行出渣作业;
e、出渣作业完成后,进行二次***;
f、二次***完成后,将所有钢管拔出,进行永久支护作业。
打支护眼孔的数量根据岩性破碎程度而定。
预支护空间的钢管两端由基岩与锚杆悬吊,具有较好的承压效果,工人可在其工作面2m的空间内进行出渣作业,相对较为安全。
二次***完成后,钢管组合体承压长度为4m,钢管两端分别埋入基岩1m,且被锚杆悬吊。
永久支护作业完成后,循环重复b~f步骤,直至破碎带施工结束。
所述的a步骤中,顶板支护材料为直径40mm,长度6m的钢管。
所述的c步骤中,采用铁锤或风钻将钢管顶入支护眼孔。
所述的d步骤中,凿岩***的凿岩深度为2m。
本发明所具有的有益效果是:松软岩层小断面掘进超前支护工艺的施工顺序是先进行巷道顶板支护在进行凿岩***,***完成后形成顶板预支护空间,提高了人员在工作面下作业的安全性,增大了顶板承压,减小了冒顶的可能,解决了松软岩层掘进中空顶下打钻、出渣顶板危险系数大的问题,方便了永久支护作业,提高了掘进速度。
具体实施方式
实施例1:
松软岩层小断面掘进超前支护工艺包括以下步骤:
a、准备顶板支护材料,顶板支护材料为直径40mm,长度6m的钢管;
b、在软岩工作面顶板以上200mm处打支护眼孔,打眼直径与钢管直径相同,打眼深度为5m,打支护眼孔的数量根据岩性破碎程度而定;
c、打眼完成后,采用铁锤或风钻将钢管顶入支护眼孔,钢管尾部外露部分用钢丝连接并悬吊于工作面顶板锚杆上;
d、在工作面进行凿岩***,凿岩深度为2m,***后,工作面顶板为钢管组合体形成的预支护空间,在预支护空间内进行出渣作业;
e、出渣作业完成后,进行二次***;
f、二次***完成后,将所有钢管拔出,进行永久支护作业。

Claims (4)

1.一种松软岩层小断面掘进超前支护工艺,其特征在于包括以下步骤:
a、准备顶板支护材料,顶板支护材料为钢管;
b、在软岩工作面顶板以上200mm处打支护眼孔,打眼直径与钢管直径相同,打眼深度为5m;
c、打眼完成后,将钢管顶入支护眼孔,钢管尾部外露部分用钢丝连接并悬吊于工作面顶板锚杆上;
d、在工作面进行凿岩***,***后,工作面顶板为钢管组合体形成的预支护空间,在预支护空间内进行出渣作业;
e、出渣作业完成后,进行二次***;
f、二次***完成后,将所有钢管拔出,进行永久支护作业。
2.根据权利要求1所述的松软岩层小断面掘进超前支护工艺,其特征在于:所述的a步骤中,顶板支护材料为直径40mm,长度6m的钢管。
3.根据权利要求1所述的松软岩层小断面掘进超前支护工艺,其特征在于:所述的c步骤中,采用铁锤或风钻将钢管顶入支护眼孔。
4.根据权利要求1所述的松软岩层小断面掘进超前支护工艺,其特征在于:所述的d步骤中,凿岩***的凿岩深度为2m。
CN201210077051.5A 2012-03-22 2012-03-22 松软岩层小断面掘进超前支护工艺 Active CN102587944B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210077051.5A CN102587944B (zh) 2012-03-22 2012-03-22 松软岩层小断面掘进超前支护工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210077051.5A CN102587944B (zh) 2012-03-22 2012-03-22 松软岩层小断面掘进超前支护工艺

Publications (2)

Publication Number Publication Date
CN102587944A true CN102587944A (zh) 2012-07-18
CN102587944B CN102587944B (zh) 2014-04-16

Family

ID=46477111

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210077051.5A Active CN102587944B (zh) 2012-03-22 2012-03-22 松软岩层小断面掘进超前支护工艺

Country Status (1)

Country Link
CN (1) CN102587944B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042062A (zh) * 2019-12-30 2020-04-21 中国水电基础局有限公司 超深防渗墙成槽方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1240876A (zh) * 1998-07-03 2000-01-12 李景堂 一种在松软围岩中掘进的支护方法
CN1355374A (zh) * 2000-11-27 2002-06-26 山东科技大学资源与环境工程学院 煤矿网格状超前锚固无人工作面开采方法
US20050013672A1 (en) * 2003-07-14 2005-01-20 Slater Bert W. Roof bolt bearing plate and method for an underground mine
CN1580491A (zh) * 2003-08-01 2005-02-16 新汶矿业集团汶南煤矿有限责任公司 采掘工作面破碎顶板超前支护工艺
WO2010092405A2 (en) * 2009-02-12 2010-08-19 Minova International Limited Securing method for horizontal and inclined workings

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1240876A (zh) * 1998-07-03 2000-01-12 李景堂 一种在松软围岩中掘进的支护方法
CN1355374A (zh) * 2000-11-27 2002-06-26 山东科技大学资源与环境工程学院 煤矿网格状超前锚固无人工作面开采方法
US20050013672A1 (en) * 2003-07-14 2005-01-20 Slater Bert W. Roof bolt bearing plate and method for an underground mine
CN1580491A (zh) * 2003-08-01 2005-02-16 新汶矿业集团汶南煤矿有限责任公司 采掘工作面破碎顶板超前支护工艺
WO2010092405A2 (en) * 2009-02-12 2010-08-19 Minova International Limited Securing method for horizontal and inclined workings

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
孙建林: "不良地质条件下隧洞进口开挖、支护施工技术", 《云南水力发电》, vol. 25, no. 3, 31 December 2009 (2009-12-31), pages 73 - 74 *
戴俊: "管棚超前支护隧道掘进周边控制***方法", 《辽宁工程技术大学学报(自然科学版)》, vol. 30, no. 2, 30 April 2011 (2011-04-30), pages 225 - 228 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111042062A (zh) * 2019-12-30 2020-04-21 中国水电基础局有限公司 超深防渗墙成槽方法

Also Published As

Publication number Publication date
CN102587944B (zh) 2014-04-16

Similar Documents

Publication Publication Date Title
CN108894787B (zh) 上覆采空区遗留矿柱应力集中的压裂解除方法
CN101328809B (zh) 无底柱深孔后退式采矿方法
CN104763425A (zh) 一种卸压预裂***沿空留巷无煤柱开采方法
CN103557000B (zh) 利用抽帮充填防治沿空巷道冲击地压的方法
CN104533418A (zh) 一种用于煤矿井下深孔静力破岩法
CN102071940A (zh) 煤矿井筒穿越多层采空区的施工方法
CN103277114A (zh) 地下工程破碎围岩的无喷砼锚网支护方法
CN106014424B (zh) 一种用于浅覆岩浅埋暗挖隧道的***开挖方法
CN104358580B (zh) 一种带筋钢骨架的大头聚能射孔管式注浆锚杆及施工方法
CN105545353A (zh) 一种基于膏体充填的人工假顶构筑方法
CN101967977A (zh) 两头掘进深埋隧洞贯通过程中控制岩柱型岩爆的施工方法
CN104453898A (zh) 一种深孔***与静压注水相结合的煤层弱化方法
CN105401946A (zh) 一种竖井导井的反向***开挖方法
CN102587915A (zh) 人工假顶下诱导崩落采矿方法
CN103114854B (zh) 一种再造人工间柱回采矿柱的方法
CN107165641B (zh) 薄层破碎硬质岩石地层中大倾角扶梯通道反方向暗挖施工方法
CN105953671A (zh) 一种硅质板岩石方边坡开挖施工方法
Yang et al. Application cumulative tensile explosions for roof cutting in Chinese underground coal mines
CN103437770A (zh) 一种激隙泄压软岩巷道支护方法
CN109184752A (zh) 一种煤矿用穿越老窑采空区的支护结构及其支护方法
CN103233739A (zh) 充填体包裹下厚大矿柱开采方法
CN102587944B (zh) 松软岩层小断面掘进超前支护工艺
CN108518223A (zh) 一种垂直深孔球状药包落矿方法
CN104989409B (zh) 一种竖井小断面成孔后全断面开挖方法
Yao et al. Examples of ground support practice in challenging ground conditions at Vale� deep operations in Sudbury

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Advance support technology for small section excavation in soft rock stratum

Effective date of registration: 20211203

Granted publication date: 20140416

Pledgee: YIYUAN JINYUAN MINING Co.,Ltd.

Pledgor: SHANDONG HUALIAN MINING Co.,Ltd.

Registration number: Y2021980014001

PC01 Cancellation of the registration of the contract for pledge of patent right
PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20220713

Granted publication date: 20140416

Pledgee: YIYUAN JINYUAN MINING Co.,Ltd.

Pledgor: SHANDONG HUALIAN MINING Co.,Ltd.

Registration number: Y2021980014001