CN102587937B - 复合式水工高压隧洞堵头 - Google Patents
复合式水工高压隧洞堵头 Download PDFInfo
- Publication number
- CN102587937B CN102587937B CN201210060326.4A CN201210060326A CN102587937B CN 102587937 B CN102587937 B CN 102587937B CN 201210060326 A CN201210060326 A CN 201210060326A CN 102587937 B CN102587937 B CN 102587937B
- Authority
- CN
- China
- Prior art keywords
- plug
- steel concrete
- reinforced concrete
- pressure tunnel
- hydraulic high
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 238000010276 construction Methods 0.000 claims abstract description 16
- 239000002131 composite material Substances 0.000 claims abstract description 11
- 239000004927 clay Substances 0.000 claims abstract description 7
- 239000004567 concrete Substances 0.000 claims description 28
- 229910000831 Steel Inorganic materials 0.000 claims description 27
- 239000010959 steel Substances 0.000 claims description 27
- 230000035699 permeability Effects 0.000 abstract description 11
- 239000011150 reinforced concrete Substances 0.000 abstract description 7
- 239000000463 material Substances 0.000 abstract description 3
- 238000007789 sealing Methods 0.000 abstract 1
- 239000011435 rock Substances 0.000 description 13
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 9
- 238000005516 engineering process Methods 0.000 description 8
- 230000000903 blocking effect Effects 0.000 description 5
- 230000000694 effects Effects 0.000 description 4
- 238000000034 method Methods 0.000 description 3
- 239000002689 soil Substances 0.000 description 3
- 238000009412 basement excavation Methods 0.000 description 2
- 238000004880 explosion Methods 0.000 description 2
- 238000005422 blasting Methods 0.000 description 1
- 238000010586 diagram Methods 0.000 description 1
- 238000001035 drying Methods 0.000 description 1
- 230000008595 infiltration Effects 0.000 description 1
- 238000001764 infiltration Methods 0.000 description 1
Images
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
本发明公开了一种复合式水工高压隧洞堵头,在施工支洞(6)内设有钢筋混凝土前堵头(3)和钢筋混凝土后堵头(4),在所述的钢筋混凝土前堵头(3)和所述的钢筋混凝土后堵头(4)之间的所述的施工支洞(6)的内壁上设有刻槽,在所述的钢筋混凝土前堵头(3)和所述的钢筋混凝土后堵头(4)之间设有充填到所述的刻槽内的膨胀性粘土堵头(2)。所述的刻槽为三角形刻槽(1)。本发明是一种刚性和柔性材料相结合的防渗封堵技术方案,是一种渗透性低、密封质量好且结构简单、操作方便的复合式水工高压隧洞堵头。
Description
技术领域
本发明涉及一种隧洞堵头,特别是涉及一种用于水利水电工程、供水工程等领域的复合式水工高压隧洞堵头。
背景技术
现有技术条件下,水工高压引水隧洞施工完毕后,靠近引水隧洞附近一定范围内或高压引水隧洞之间的施工支洞均采用钢筋混凝土材料进行封堵。该技术的不足之处在于:(1)因施工***导致施工支洞围岩出现一定范围的围岩松动圈,导致松动圈范围内的围岩渗透性增加,(2)施工支洞顶部封堵混凝土由于振捣困难和干缩现象,导致钢筋混凝土堵头的上部密封质量不易保证,出现大量渗水。
发明内容
本发明要解决的技术问题是提供一种渗透性低、密封质量好的复合式水工高压隧洞堵头。
为了解决上述技术问题,本发明提供的复合式水工高压隧洞堵头,在施工支洞内设有钢筋混凝土前堵头和钢筋混凝土后堵头4,在所述的钢筋混凝土前堵头和钢筋混凝土后堵头之间的施工支洞的内壁上设有刻槽,在所述的钢筋混凝土前堵头和钢筋混凝土后堵头之间设有充填到所述的刻槽内的膨胀性粘土堵头。
所述的刻槽为三角形刻槽。
采用上述技术方案的复合式水工高压隧洞堵头,利用堵头两端为钢筋混凝土堵头承担高压引水隧洞对堵头产生的水压力;通过钢筋混凝土前堵头和钢筋混凝土后堵头之间的膨胀性粘土堵头达到防渗处理的效果,特别是利用了膨胀土遇水膨胀、渗透性大幅降低的特性;同时三角形刻槽使刻槽部位处于压应力集中状态,使得该部位围岩的裂隙在压应力的作用下闭合,渗透性降低,避免岩体因开挖***导致的围岩松动引起的岩体渗透性增加,进而引起的漏水量增加。该封堵技术设计合理,结构简单,操作方便。
综上所述,本发明利用围岩三角形刻槽降低围岩的渗透性,通过实施柔性膨胀性粘土堵头达到防渗预期效果,而堵头的受力则由两端的钢筋混凝土前堵头和钢筋混凝土后堵头承担,该技术进一步完善了高压引水隧洞防渗封堵技术,是一种刚性和柔性材料相结合的防渗封堵技术方案,是一种渗透性低、密封质量好且结构简单、操作方便的复合式水工高压隧洞堵头。
附图说明
图1为施工支洞堵头纵剖面示意图。
具体实施方式
下面结合附图和具体实施方式对本发明作进一步说明。
参见图1,高压引水隧洞5设有施工支洞6,在施工支洞6内设有钢筋混凝土前堵头3和钢筋混凝土后堵头4,在钢筋混凝土前堵头3和钢筋混凝土后堵头4之间的施工支洞6的内壁上设有三角形刻槽1,在钢筋混凝土前堵头3和钢筋混凝土后堵头4之间设有充填到三角形刻槽1内的膨胀性粘土堵头2,膨胀土在施工填筑过程中严格控制含水量大小,并进行击实处理。
参见图1,采用上述技术方案的复合式水工高压隧洞堵头,利用堵头两端为钢筋混凝土堵头承担高压引水隧洞对堵头产生的水压力;通过钢筋混凝土前堵头3和钢筋混凝土后堵头4之间的膨胀性粘土堵头2达到防渗处理的效果,特别是利用了膨胀土遇水膨胀、渗透性大幅降低的特性;同时三角形刻槽1使刻槽部位处于压应力集中状态,使得该部位围岩的裂隙在压应力的作用下闭合,渗透性降低,避免岩体因开挖***导致的围岩松动引起的岩体渗透性增加,进而引起的漏水量增加。该封堵技术设计合理,结构简单,操作方便。
Claims (2)
1.一种复合式水工高压隧洞堵头,其特征是:在施工支洞(6)内设有钢筋混凝土前堵头(3)和钢筋混凝土后堵头(4),在所述的钢筋混凝土前堵头(3)和所述的钢筋混凝土后堵头(4)之间的所述的施工支洞(6)的内壁上设有刻槽,在所述的钢筋混凝土前堵头(3)和所述的钢筋混凝土后堵头(4)之间设有充填到所述的刻槽内的膨胀性粘土堵头(2)。
2.根据权利要求1所述的复合式水工高压隧洞堵头,其特征是:所述的刻槽为三角形刻槽(1)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210060326.4A CN102587937B (zh) | 2012-03-08 | 2012-03-08 | 复合式水工高压隧洞堵头 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201210060326.4A CN102587937B (zh) | 2012-03-08 | 2012-03-08 | 复合式水工高压隧洞堵头 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102587937A CN102587937A (zh) | 2012-07-18 |
CN102587937B true CN102587937B (zh) | 2014-03-12 |
Family
ID=46477104
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201210060326.4A Expired - Fee Related CN102587937B (zh) | 2012-03-08 | 2012-03-08 | 复合式水工高压隧洞堵头 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102587937B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114045799B (zh) * | 2021-12-21 | 2022-11-29 | 中国电建集团贵阳勘测设计研究院有限公司 | 一种引水隧洞交叉的导流洞封堵结构 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1255949A (en) * | 1967-12-21 | 1971-12-01 | Georg Gautier | Improvements in or relating to sealing of concrete components |
EP0609040A2 (en) * | 1993-01-25 | 1994-08-03 | Amcol International Corporation | Waterproofing article for concrete joints |
EP0716189A1 (en) * | 1994-12-07 | 1996-06-12 | Shigeo Nagahama | A cut-off water process for a concrete underground structure |
CN101949293A (zh) * | 2010-10-09 | 2011-01-19 | 中国水电顾问集团成都勘测设计研究院 | 隧洞堵头的周边止水结构及其设置方法 |
CN202467865U (zh) * | 2012-03-08 | 2012-10-03 | 长沙理工大学 | 复合式水工高压隧洞堵头 |
Family Cites Families (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH06248895A (ja) * | 1993-02-26 | 1994-09-06 | Itsuki Kogyo Kk | グラウト及びグラウト工法 |
JP5033699B2 (ja) * | 2008-04-01 | 2012-09-26 | 前田建設工業株式会社 | 防水シート付着用グラウト材および施工方法 |
-
2012
- 2012-03-08 CN CN201210060326.4A patent/CN102587937B/zh not_active Expired - Fee Related
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1255949A (en) * | 1967-12-21 | 1971-12-01 | Georg Gautier | Improvements in or relating to sealing of concrete components |
EP0609040A2 (en) * | 1993-01-25 | 1994-08-03 | Amcol International Corporation | Waterproofing article for concrete joints |
EP0716189A1 (en) * | 1994-12-07 | 1996-06-12 | Shigeo Nagahama | A cut-off water process for a concrete underground structure |
CN101949293A (zh) * | 2010-10-09 | 2011-01-19 | 中国水电顾问集团成都勘测设计研究院 | 隧洞堵头的周边止水结构及其设置方法 |
CN202467865U (zh) * | 2012-03-08 | 2012-10-03 | 长沙理工大学 | 复合式水工高压隧洞堵头 |
Non-Patent Citations (2)
Title |
---|
吴静等.洞室施工中岩溶及地下水富集区的预测和处理.《云南水力发电》.2007,第23卷(第1期), |
洞室施工中岩溶及地下水富集区的预测和处理;吴静等;《云南水力发电》;20070131;第23卷(第1期);第38-41页 * |
Also Published As
Publication number | Publication date |
---|---|
CN102587937A (zh) | 2012-07-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204456128U (zh) | 一种分层注浆枪 | |
CN103195390B (zh) | 一种本煤层近水平瓦斯抽采钻孔密封方法 | |
CN103603683A (zh) | 袋式注浆锚固装置和锚固方法 | |
CN105888673B (zh) | 松软富水围岩内深孔塑管高压注浆防爆装置的操作方法 | |
CN103397845B (zh) | 一种通过浆液置换控制顶管穿越建筑物引起的沉降的方法 | |
CN103993902B (zh) | 一种瓦斯抽采钻孔两步注浆封孔方法 | |
CN105220687A (zh) | 预应力混凝土管桩后注浆法灌芯补强施工方法 | |
CN208965598U (zh) | 灌浆帷幕与地下洞室相交部位的防渗处理结构 | |
CN105257309B (zh) | 一种砂层中土压平衡盾构机仓内注浆换刀的施工方法 | |
CN202467865U (zh) | 复合式水工高压隧洞堵头 | |
CN102587937B (zh) | 复合式水工高压隧洞堵头 | |
CN103742162A (zh) | 盾尾顶部设置有同步注浆装置的盾构机及同步注浆装置 | |
CN203430466U (zh) | 煤矿瓦斯抽采钻孔封孔装置 | |
CN203769790U (zh) | 盾尾顶部设置有同步注浆装置的盾构机及同步注浆装置 | |
CN203463123U (zh) | 一种中空注浆锚索用推挤膨胀式止浆塞 | |
CN110966011A (zh) | 盾构气压开仓用组合型泥膜制作方法 | |
CN202954360U (zh) | 一种可回收充液式拉力锚杆 | |
CN202577280U (zh) | 土体有压注浆加固用膜袋式封孔器 | |
CN203924150U (zh) | Epr变形缝修补止水结构 | |
CN104141286A (zh) | 施工支洞封堵结构 | |
CN103352702A (zh) | 一种盾构洞内接收施工工法 | |
CN204457781U (zh) | Tbm掘进隧洞断裂滑移型岩爆风险解除结构 | |
CN103161143A (zh) | 一种设置在隐体中的导流洞竖井闸室结构 | |
CN202531092U (zh) | 封孔器 | |
CN204627525U (zh) | 封堵装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20140312 Termination date: 20150308 |
|
EXPY | Termination of patent right or utility model |