CN102562074A - 大断面隧道上硬下软复合地层的施工方法 - Google Patents

大断面隧道上硬下软复合地层的施工方法 Download PDF

Info

Publication number
CN102562074A
CN102562074A CN2012100236814A CN201210023681A CN102562074A CN 102562074 A CN102562074 A CN 102562074A CN 2012100236814 A CN2012100236814 A CN 2012100236814A CN 201210023681 A CN201210023681 A CN 201210023681A CN 102562074 A CN102562074 A CN 102562074A
Authority
CN
China
Prior art keywords
excavation
construction
arch
thickness
spacing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100236814A
Other languages
English (en)
Inventor
李波
邵建龙
赵飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Second Engineering Co Ltd of CTCE Group
Original Assignee
Second Engineering Co Ltd of CTCE Group
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Second Engineering Co Ltd of CTCE Group filed Critical Second Engineering Co Ltd of CTCE Group
Priority to CN2012100236814A priority Critical patent/CN102562074A/zh
Publication of CN102562074A publication Critical patent/CN102562074A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

本发明公开了一种铁路隧道的施工方法,特别涉及一种大断面隧道上硬下软复合地层的施工方法,该方法包括:开挖施工、初期支护、仰拱及衬砌施工的步骤,其中开挖施工过程中当隧道掌子面上部硬围岩厚度小于2m时,开挖施工方法为三台阶七步法,当隧道掌子面上部硬围岩厚度大于2m时,开挖施工方法为三台阶法。本施工方法具有施工进度快、安全性高,施工经济好的特点。

Description

大断面隧道上硬下软复合地层的施工方法
技术领域
本发明公开了一种隧道的施工方法,特别涉及针对上硬下软复合地层的隧道施工方法。
背景技术
在隧道施工时,会遇到各种异常地质情况,如遇到隧道开挖断面上部为硬岩,围岩级别为Ⅱ级、Ⅲ级,下部为软岩,围岩级别为Ⅳ级、Ⅴ级,如何综合判断围岩级别进行施工就非常重要,而现有技术中,上软下硬地层施工较多,上硬下软地层施工却没有切实可行的施工方法。
我们针对八苏木隧道现场地质条件,进行了技术攻关,研究制定了大断面隧道上硬下软复合地层施工方法,顺利的完成隧道施工,该方法具有施工安全,施工进度较快,经济性好的施工特点。
发明内容
本发明的发明目的是为了克服已有技术的不足,提供一种切实可行的针对上硬下软地层施工的隧道施工方法
本发明的技术方案是:一种大断面隧道上硬下软复合地层的施工方法,该方法包括开挖施工、初期支护、仰拱及衬彻施工的步骤,本方法针对不同的上硬下软复合地层特点,对开挖施工、仰拱及衬砌施工采取如下不同的施工方案进行施工,包括以下施工步骤:
1)、当上部硬岩厚度小于2m时,开挖选择三台阶七步法施工,对拱部120°范围内出现泥岩的位置采用Ф42小导管进行超前支护,长度不小于3.5m,开挖每循环进尺不大于1.6m,中台、下台左右侧开挖采用错开施工,错开距离不小于1m;当上部硬岩厚度大于2m时,开挖选择三台阶法开挖,上台、中台、下台开挖高度控制在3.5m左右,上台中部因高度较高,开挖时设置2m高简易拼装台架,以便于进行开挖作业,隧道每循环开挖进尺寸不大于2.0m,掌子面上部玄武岩开挖采用光面***,周边眼不大于60cm,掌子面下部采用松动***,挖掘机配合;
2)、初期支护及时紧跟,每步开挖完成后,及时进行支护,初期支护采用喷锚构筑法,以拱架、***锚杆、钢筋网、喷射混凝土构成的初期支护为主要受力结构;根据掌子面上部玄武岩厚度采用以下三种不同初期支护方式;当上部硬岩厚度小于3m时,全环设置I18工字钢架,每榀间距0.8m,喷射混凝土厚度25cm,拱部***锚杆长度4.0m,间距1.0m×1.0m;当上部硬岩厚度大于等于3m且小于6m时,拱部采用挂网喷射C25 混凝土支护,钢筋采用φ8,网格间距20×20cm,喷射混凝土厚度15cm,边墙采用I18工字钢架支护,每榀间距1.0m,喷射混凝土厚度25cm,拱部***锚杆长度3.5m,间距1.2m×1.2m;当上部硬岩厚度大于等于6m时,隧道全环均采用挂网喷射C25混凝土支护,钢筋采用φ8,网格间距20×20cm,喷射混凝土厚度12cm,拱部***锚杆长度3.0m,间距1.2m×1.2m;
3)、隧道仰拱下部均为泥岩,遇水易软化,施工前,在开挖仰拱前方设置积水井,将仰拱中积水进行抽排,仰拱每循环开挖不大于5m,开挖成形后,及时喷射混凝土将围岩进行封闭;
仰拱、衬砌采用钢筋混凝土,厚度应不小于40cm,施工时,应严格控制仰拱、衬砌距离掌子面距离,仰拱距离掌子面不宜超出40m,衬砌距离掌子面不宜超出70m。
上述洞内上台、中台的临时排水沟和仰拱积水井距离边墙不少于1m,以免软化基础。
上述拱架基础下部设置纵向钢带,采用20#槽钢,扩大拱脚。
上述初期支护采用型钢拱架支护时,***锚杆尽量与型钢拱架相连,下部锁脚锚杆每处设置不少于2根;如拱部有支护拱架时,在其拱部设置4根锚杆,起悬吊作用,以减小下部拱脚荷载。
本发明的有益效果是:针对不同的上硬下软复合地层特点,对开挖施工、衬砌施工、仰拱及衬砌施工采取不同的施工方案进行施工,是一种切实可行的施工方法,且此施工方法具有施工进度快、安全性高,施工经济好的特点。
附图说明
图1为开挖施工步骤中三台阶七步法施工顺序示意图;
图2为开挖施工步骤中三台阶七步法开挖示意图;
其中:1、上台,2、中台左侧,3、中台右侧,4、中台,5、下台右侧,6、下台左侧,7、下台,8、超前支护,9、仰拱,10、衬彻。
具体实施方式
本施工方法,针对不同的上硬下软复合地层特点,主要根据上硬岩的厚度,围岩的级别,下软岩的稳定性等特点,对开挖施工、衬砌施工、仰拱及衬砌施工采取不同的施工方案进行施工。
本实施例为京包线集宁至包头段增建第二双线八苏木隧道(全长8184m),是京包线集宁至包头段增建第二双线重点控制工程,设计为单洞双线隧道,隧道开挖断面大于130m2,开挖高度达11m,开挖宽度最大达14m。隧道出口施工时,开挖揭示隧道开挖范围内为上硬下软复合地层,掌子面上部为玄武岩,厚度为1-9米,整体性较好,围岩级别能达到Ⅱ级,下部为泥岩,呈胶结状,具有一定自稳性,但遇水易崩解,稳定性差, 围岩级别为Ⅳ级或Ⅴ级。针对这样的上硬下软复合地层特点,如图1和图2所示本施工方法的步骤为:
1、开挖施工
当上部玄武岩厚度小于2m时,开挖选择三台阶七步法施工,对拱部120°范围内出现泥岩的位置采用Ф42小导管进行超前支护(8),开挖每循环进尺不大于1.6m,中台左右侧及下台左右侧开挖采用错开施工,错开距离不小于1m。具体施工顺序如图1所示为上台(1)→中台左侧(2)→中台右侧(3)→中台(4)→下台右侧(5)→下台左侧(6)→下台(7)。 
当上部玄武岩厚度大于2m时,开挖选择三台阶法开挖,上台、中台、下台开挖高度控制在3.5m左右,上台中部因高度较高,开挖时设置2m高自制简易拼装台架,以便于进行开挖作业,隧道每循环开挖进尺寸不大于2.0m,掌子面上部玄武岩开挖采用光面***,周边眼不大于60cm,掌子面下部采用松动***,挖掘机配合。
、初期支护施工
1)支护参数选择
初期支护及时紧跟,每步开挖完成后,及时进行支护,初期支护采用喷锚构筑法,以拱架、***锚杆、钢筋网、喷射混凝土构成的初期支护为主要受力结构。根据掌子面上部玄武岩厚度采用以下三种不同初期支护方式。当上部玄武岩厚度小于3m时,全环设置I18工字钢架,每榀间距0.8m,喷射混凝土厚度25cm,拱部***锚杆长度4.0m,间距1.0m×1.0m;当上部玄武岩厚度大于等于3m且小于6m时,拱部采用挂网喷射C25 混凝土支护,钢筋采用φ8,网格间距20×20cm,喷射混凝土厚度15cm,边墙采用I18工字钢架支护,每榀间距1.0m,喷射混凝土厚度25cm,拱部***锚杆长度3.5m,间距1.2m×1.2m;当上部玄武岩厚度大于等于6m时,隧道全环均采用挂网喷射C25混凝土支护,钢筋采用φ8,网格间距20×20cm,喷射混凝土厚度12cm,拱部***锚杆长度3.0m,间距1.2m×1.2m。
防止初期支护失稳措施
因下部为泥岩,围岩遇水易软化,为防止拱脚下沉,具体采取如下措施:
①   洞内上台、中台临时排水沟和仰拱积水井距离边墙不少于1m,以免软化基础;
②   洞内安排专人进行排水,24小时值班,及时将掌子面的积水进行抽排;
③拱架基础下部设置纵向钢带,采用[20槽钢,扩大拱脚;
④初期支护采用型钢拱架支护时,***锚杆尽量与型钢拱架相连,下部锁脚锚杆每处设置不少于2根;
⑤如拱部有支护拱架时,在其拱部设置4根锚杆,起悬吊作用,以减小下部拱脚荷载;
3、仰拱、衬砌施工
隧道仰拱下部均为泥岩,遇水易软化,施工前,在开挖仰拱(9)前方设置积水井,将仰拱中积水进行抽排,仰拱每循环开挖不大于5m,开挖成形后,及时喷射混凝土将围岩进行封闭。
仰拱(9)、衬砌(10)采用钢筋混凝土,厚度应不小于40cm,施工时,应严格控制仰拱、衬砌距离掌子面距离,仰拱距离掌子面不宜超出40m,衬砌距离掌子面不宜超出70m。
二、施工注意事项
①做好超前地质预报工作,配备有经验的地质工程师,及时了解地质情况变化。
②充分认识水对软弱围岩的破坏作用,及时对围岩渗水及施工废水进行合理排放,杜绝对施工台阶墙脚形成浸泡。
③施工前,对所有参建员工进行上岗前的安全教育。对从事电器、***、高空作业、焊接、机动车驾驶等特殊工种的人员,经过专业培训,获得《安全操作合格证》后,方准持证上岗。
④隧道开挖后必须及时进行支护,尤其是下部的泥岩位置。
⑤加强监控量测工作,信息及时反馈,指导现场施工。量测人员发现量测数据有突变或异变时,应于量测后及时向现场负责人和技术负责人汇报,并立即采取应急措施或通知施工人员暂时撤离危险地段。
本实施例具有施工安全,施工进度较快,经济性好的优点,取得了较好的实施效果。

Claims (4)

1.一种大断面隧道上硬下软复合地层的施工方法,该方法包括开挖施工、初期支护、仰拱及衬彻施工的步骤,其特征在于针对不同的上硬下软复合地层特点,对开挖施工、仰拱及衬砌施工采取如下不同的施工方案进行施工,包括以下施工步骤:
1)、当上部硬岩厚度小于2m时,开挖选择三台阶七步法施工,对拱部120°范围内出现泥岩的位置采用Ф42小导管进行超前支护,长度不小于3.5m,开挖每循环进尺不大于1.6m,中台、下台左右侧开挖采用错开施工,错开距离不小于1m;当上部硬岩厚度大于2m时,开挖选择三台阶法开挖,上台、中台、下台开挖高度控制在3.5m左右,上台中部因高度较高,开挖时设置2m高简易拼装台架,以便于进行开挖作业,隧道每循环开挖进尺寸不大于2.0m,掌子面上部玄武岩开挖采用光面***,周边眼不大于60cm,掌子面下部采用松动***,挖掘机配合;
2)、初期支护及时紧跟,每步开挖完成后,及时进行支护,初期支护采用喷锚构筑法,以拱架、***锚杆、钢筋网、喷射混凝土构成的初期支护为主要受力结构;根据掌子面上部玄武岩厚度采用以下三种不同初期支护方式;当上部硬岩厚度小于3m时,全环设置I18工字钢架,每榀间距0.8m,喷射混凝土厚度25cm,拱部***锚杆长度4.0m,间距1.0m×1.0m;当上部硬岩厚度大于等于3m且小于6m时,拱部采用挂网喷射C25 混凝土支护,钢筋采用φ8,网格间距20×20cm,喷射混凝土厚度15cm,边墙采用I18工字钢架支护,每榀间距1.0m,喷射混凝土厚度25cm,拱部***锚杆长度3.5m,间距1.2m×1.2m;当上部硬岩厚度大于等于6m时,隧道全环均采用挂网喷射C25混凝土支护,钢筋采用φ8,网格间距20×20cm,喷射混凝土厚度12cm,拱部***锚杆长度3.0m,间距1.2m×1.2m;
3)、隧道仰拱下部均为泥岩,遇水易软化,施工前,在开挖仰拱前方设置积水井,将仰拱中积水进行抽排,仰拱每循环开挖不大于5m,开挖成形后,及时喷射混凝土将围岩进行封闭;
仰拱、衬砌采用钢筋混凝土,厚度应不小于40cm,施工时,应严格控制仰拱、衬砌距离掌子面距离,仰拱距离掌子面不宜超出40m,衬砌距离掌子面不宜超出70m。
2.根据权利要求1所述的大断面隧道上硬下软复合地层的施工方法,其特征在于洞内上台、中台的临时排水沟和仰拱积水井距离边墙不少于1m,以免软化基础。
3.根据权利要求1所述的大断面隧道上硬下软复合地层的施工方法,其特征在于拱架基础下部设置纵向钢带,采用20#槽钢,扩大拱脚。
4.根据权利要求1所述的大断面隧道上硬下软复合地层的施工方法,其特征在于初期支护采用型钢拱架支护时,***锚杆尽量与型钢拱架相连,下部锁脚锚杆每处设置不少于2根;如拱部有支护拱架时,在其拱部设置4根锚杆,起悬吊作用,以减小下部拱脚荷载。
CN2012100236814A 2012-02-03 2012-02-03 大断面隧道上硬下软复合地层的施工方法 Pending CN102562074A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100236814A CN102562074A (zh) 2012-02-03 2012-02-03 大断面隧道上硬下软复合地层的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100236814A CN102562074A (zh) 2012-02-03 2012-02-03 大断面隧道上硬下软复合地层的施工方法

Publications (1)

Publication Number Publication Date
CN102562074A true CN102562074A (zh) 2012-07-11

Family

ID=46408508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100236814A Pending CN102562074A (zh) 2012-02-03 2012-02-03 大断面隧道上硬下软复合地层的施工方法

Country Status (1)

Country Link
CN (1) CN102562074A (zh)

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817621A (zh) * 2012-08-13 2012-12-12 中铁十二局集团有限公司 一种适用于不良地质隧道控制拱墙脚沉降的综合施工方法
CN103344154A (zh) * 2013-07-05 2013-10-09 武汉科技大学 一种碳质片岩隧道***方法及施工方法
CN103628890A (zh) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 软弱千枚岩隧道开挖变形控制方法
CN103628886A (zh) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 富水高地应力条件下软弱围岩隧道的开挖方法
CN103775094A (zh) * 2014-01-22 2014-05-07 安徽水安建设集团股份有限公司 砂砾土地层中型断面输水隧洞两台阶三步开挖施工方法
CN104047623A (zh) * 2014-06-06 2014-09-17 同济大学 一种大跨洞室开挖施工方法
CN104165056A (zh) * 2014-03-11 2014-11-26 中交一公局厦门工程有限公司 一种富水浅埋暗挖隧道的开挖施工方法
CN104314571A (zh) * 2014-08-19 2015-01-28 西安建筑科技大学 一种大断面隧道的三台阶六步超短台阶的施工方法
CN104653187A (zh) * 2014-12-11 2015-05-27 中铁十九局集团有限公司 富水砂层地质大断面隧道开挖方法
CN104879131A (zh) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 上软下硬复合地层的大跨度隧道开挖方法
CN104989410A (zh) * 2015-07-13 2015-10-21 中铁十九局集团第二工程有限公司 浅埋暗挖隧道地表限沉防塌施工方法
CN105909255A (zh) * 2016-05-19 2016-08-31 大连理工大学 一种采用掌子面临时约束超短台阶的大跨软弱围岩隧道施工方法
CN105909256A (zh) * 2016-05-19 2016-08-31 大连理工大学 一种采用掌子面预加固留核心土三台阶临时仰拱技术的大跨软弱围岩隧道施工方法
CN106761778A (zh) * 2017-01-24 2017-05-31 山东大学 一种适用于上软下硬地层的地铁车站暗挖施工工艺
CN107130964A (zh) * 2016-11-11 2017-09-05 新疆北方建设集团有限公司 小型隧洞泥岩开挖施工方法
CN107288652A (zh) * 2017-08-22 2017-10-24 中铁五局集团有限公司 一种小断面软弱围岩隧道三台阶五部开挖施工方法
CN107829748A (zh) * 2017-11-10 2018-03-23 长安大学 一种适用于漂卵石地层大断面隧道的互补循环式开挖方法
CN108131145A (zh) * 2017-12-20 2018-06-08 中铁五局集团有限公司 一种超大跨度隧道开挖支护的施工方法
CN108278115A (zh) * 2017-10-31 2018-07-13 中南大学 一种基于管棚预支护的大拱脚三台阶隧道快速施工方法及结构
CN108301841A (zh) * 2018-02-08 2018-07-20 中建隧道建设有限公司 公路大断面隧道中导超前预留侧边土的施工工法
CN109372517A (zh) * 2018-09-28 2019-02-22 北京交通大学 一种适用于上软下硬复合地层隧道下穿供水管施工方法
CN109723445A (zh) * 2019-02-01 2019-05-07 重庆工商职业学院 平行三台阶隧道全断面整体掘进方法
CN109882185A (zh) * 2019-03-25 2019-06-14 中铁十六局集团第二工程有限公司 一种高地应力条件下岩质软硬不均隧道的施工方法
CN110230504A (zh) * 2019-06-25 2019-09-13 深圳市综合交通设计研究院有限公司 一种上软下硬复合地层全包防水抗水压复合衬砌结构及其施工方法

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08170484A (ja) * 1994-12-19 1996-07-02 Shimizu Corp 大断面トンネルの構築方法
CN101105131A (zh) * 2007-08-17 2008-01-16 中铁十二局集团有限公司 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN101196116A (zh) * 2007-12-28 2008-06-11 中铁十二局集团有限公司 软弱地质三联拱隧道双侧洞施工方法
CN102226399A (zh) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 软岩四线大跨隧道三台阶以索代撑开挖施工方法

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH08170484A (ja) * 1994-12-19 1996-07-02 Shimizu Corp 大断面トンネルの構築方法
CN101105131A (zh) * 2007-08-17 2008-01-16 中铁十二局集团有限公司 一种适用于铁路大断面ⅳ、ⅴ级围岩隧道的开挖方法
CN101196116A (zh) * 2007-12-28 2008-06-11 中铁十二局集团有限公司 软弱地质三联拱隧道双侧洞施工方法
CN102226399A (zh) * 2011-06-02 2011-10-26 中铁二院工程集团有限责任公司 软岩四线大跨隧道三台阶以索代撑开挖施工方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
***等: "《上软下硬地层浅埋暗挖隧道覆跨比研究》", 《地下空间与工程学报》 *

Cited By (29)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102817621A (zh) * 2012-08-13 2012-12-12 中铁十二局集团有限公司 一种适用于不良地质隧道控制拱墙脚沉降的综合施工方法
CN103344154B (zh) * 2013-07-05 2015-04-08 武汉科技大学 一种碳质片岩隧道***方法及施工方法
CN103344154A (zh) * 2013-07-05 2013-10-09 武汉科技大学 一种碳质片岩隧道***方法及施工方法
CN103628890A (zh) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 软弱千枚岩隧道开挖变形控制方法
CN103628886A (zh) * 2013-11-28 2014-03-12 中铁十三局集团有限公司 富水高地应力条件下软弱围岩隧道的开挖方法
CN103775094A (zh) * 2014-01-22 2014-05-07 安徽水安建设集团股份有限公司 砂砾土地层中型断面输水隧洞两台阶三步开挖施工方法
CN103775094B (zh) * 2014-01-22 2015-12-30 安徽水安建设集团股份有限公司 砂砾土地层中型断面输水隧洞两台阶三步开挖施工方法
CN104165056A (zh) * 2014-03-11 2014-11-26 中交一公局厦门工程有限公司 一种富水浅埋暗挖隧道的开挖施工方法
CN104047623A (zh) * 2014-06-06 2014-09-17 同济大学 一种大跨洞室开挖施工方法
CN104047623B (zh) * 2014-06-06 2016-07-13 同济大学 一种大跨洞室开挖施工方法
CN104314571A (zh) * 2014-08-19 2015-01-28 西安建筑科技大学 一种大断面隧道的三台阶六步超短台阶的施工方法
CN104653187A (zh) * 2014-12-11 2015-05-27 中铁十九局集团有限公司 富水砂层地质大断面隧道开挖方法
CN104879131A (zh) * 2015-05-06 2015-09-02 中国电建集团华东勘测设计研究院有限公司 上软下硬复合地层的大跨度隧道开挖方法
CN104989410A (zh) * 2015-07-13 2015-10-21 中铁十九局集团第二工程有限公司 浅埋暗挖隧道地表限沉防塌施工方法
CN105909255A (zh) * 2016-05-19 2016-08-31 大连理工大学 一种采用掌子面临时约束超短台阶的大跨软弱围岩隧道施工方法
CN105909256A (zh) * 2016-05-19 2016-08-31 大连理工大学 一种采用掌子面预加固留核心土三台阶临时仰拱技术的大跨软弱围岩隧道施工方法
CN107130964A (zh) * 2016-11-11 2017-09-05 新疆北方建设集团有限公司 小型隧洞泥岩开挖施工方法
CN106761778A (zh) * 2017-01-24 2017-05-31 山东大学 一种适用于上软下硬地层的地铁车站暗挖施工工艺
CN106761778B (zh) * 2017-01-24 2018-08-07 山东大学 一种适用于上软下硬地层的地铁车站暗挖施工工艺
CN107288652A (zh) * 2017-08-22 2017-10-24 中铁五局集团有限公司 一种小断面软弱围岩隧道三台阶五部开挖施工方法
CN108278115A (zh) * 2017-10-31 2018-07-13 中南大学 一种基于管棚预支护的大拱脚三台阶隧道快速施工方法及结构
CN107829748A (zh) * 2017-11-10 2018-03-23 长安大学 一种适用于漂卵石地层大断面隧道的互补循环式开挖方法
CN107829748B (zh) * 2017-11-10 2019-07-02 长安大学 一种适用于漂卵石地层大断面隧道的互补循环式开挖方法
CN108131145A (zh) * 2017-12-20 2018-06-08 中铁五局集团有限公司 一种超大跨度隧道开挖支护的施工方法
CN108301841A (zh) * 2018-02-08 2018-07-20 中建隧道建设有限公司 公路大断面隧道中导超前预留侧边土的施工工法
CN109372517A (zh) * 2018-09-28 2019-02-22 北京交通大学 一种适用于上软下硬复合地层隧道下穿供水管施工方法
CN109723445A (zh) * 2019-02-01 2019-05-07 重庆工商职业学院 平行三台阶隧道全断面整体掘进方法
CN109882185A (zh) * 2019-03-25 2019-06-14 中铁十六局集团第二工程有限公司 一种高地应力条件下岩质软硬不均隧道的施工方法
CN110230504A (zh) * 2019-06-25 2019-09-13 深圳市综合交通设计研究院有限公司 一种上软下硬复合地层全包防水抗水压复合衬砌结构及其施工方法

Similar Documents

Publication Publication Date Title
CN102562074A (zh) 大断面隧道上硬下软复合地层的施工方法
CN102587922B (zh) 一种软弱破碎岩层斜交斜井上弧导挑顶施工方法
CN103161480B (zh) 主动支撑巷旁充填沿空留巷的方法
CN102220868B (zh) 城市浅埋大断面隧道五部开挖工法
CN101864963B (zh) 一种大断面黄土隧道施工方法
CN105064397B (zh) 一种在地铁区间盾构隧道基础上扩挖车站的明挖施工方法
CN102536273B (zh) 26m大跨度空间一次成型建造工法
CN102268993B (zh) 一种高液限土中隧道开挖方法
CN201991017U (zh) 基于拱盖法施工成型的地铁大跨度车站主体结构
CN106194196B (zh) 一种横穿隧道洞身的大型溶洞处理与开挖方法
CN102226403A (zh) 地铁大跨度车站主体拱盖法施工方法及车站主体结构
CN103899318B (zh) 中硬地层隧道铣挖及配套机械化施工工法
CN101338678A (zh) 一次扣拱暗挖逆作施工方法
CN106761778A (zh) 一种适用于上软下硬地层的地铁车站暗挖施工工艺
CN201412163Y (zh) 一种敞开式隧道掘进机施工的圆形隧道衬砌结构
CN102373930A (zh) 一种软弱围岩大断面连拱隧道的快速施工方法
CN105089670B (zh) 一种在并行区间盾构隧道基础上扩挖地铁车站施工方法
CN207934910U (zh) 一种新建隧道近距离上跨既有隧道的抗上浮加固体系
CN110529151A (zh) 一种综掘工作面分级分区综合加固过陷落柱方法
CN110486036B (zh) 一种扩大拱脚初支拱盖法施工方法
CN105134269A (zh) 一种锚索穿棚协同承载的巷道围岩控制技术
CN108131145A (zh) 一种超大跨度隧道开挖支护的施工方法
CN109611103A (zh) 一种针对盾构区间上悬孤石群加固处理的方法
CN111425205B (zh) 急倾斜极薄矿体采矿支护方法
CN204590048U (zh) 一种高边坡支护结构

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20120711