CN102545092B - Base and installation rod used for electrified installation device on tower and installation method thereof - Google Patents

Base and installation rod used for electrified installation device on tower and installation method thereof Download PDF

Info

Publication number
CN102545092B
CN102545092B CN201210017425.4A CN201210017425A CN102545092B CN 102545092 B CN102545092 B CN 102545092B CN 201210017425 A CN201210017425 A CN 201210017425A CN 102545092 B CN102545092 B CN 102545092B
Authority
CN
China
Prior art keywords
mounting bar
shaped pedestal
base
peristome
shaft tower
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201210017425.4A
Other languages
Chinese (zh)
Other versions
CN102545092A (en
Inventor
吴天钢
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIAXING SHANNIU ELECTRONIC TECHNOLOGY CO LTD
Original Assignee
JIAXING SHANNIU ELECTRONIC TECHNOLOGY CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIAXING SHANNIU ELECTRONIC TECHNOLOGY CO LTD filed Critical JIAXING SHANNIU ELECTRONIC TECHNOLOGY CO LTD
Priority to CN201210017425.4A priority Critical patent/CN102545092B/en
Publication of CN102545092A publication Critical patent/CN102545092A/en
Application granted granted Critical
Publication of CN102545092B publication Critical patent/CN102545092B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Electric Cable Installation (AREA)

Abstract

The invention discloses a base and an installation method used for an electrified installation device on a tower and an installation method thereof. The base comprises a U-shaped seat body and a bayonet lock device arranged on the lower portion of the opening portion of the U-shaped seat body, a screw hole is arranged at the top of the U-shaped seat body, and a jack is arranged on one side of the U-shaped seat body. The installation rod can be a split installation rod, an integral type installation rod or a single installation rod. The method is that the electrified device is installed on the aerial tower through the base by adopting the split installation rod, the integral type installation rod or the single installation rod. The installation device can be installed with power on, the installation mode is simple, installation speed of various devices on the tower can be effectively improved, and working efficiency is improved.

Description

A kind of base for charged erection unit on shaft tower and mounting bar and installation method
Technical field
The present invention relates to install on a kind of overhead transmission line shaft tower base and the installation method thereof of various kinds of equipment, particularly a kind of base for charged erection unit on shaft tower and mounting bar and installation method.
Background technology
At present, the built on stilts transmission and distribution line line pole tower One's name is legion of each electric pressure, when the shaft tower later stage, need to install all kinds of operations, safeguard additional, in the time of as bird-scaring unit, line supervision instrument, anemometry instrument etc., can only take the mode of power failure installation or artificial live line working to carry out, the reliability of impact power supply, needs to drop into larger human and material resources, and artificial live line working danger is high.Charged erection unit needs special equipment, instrument and installation method.
Summary of the invention
Technical problem to be solved by this invention is to provide a kind of base for charged erection unit on shaft tower and mounting bar and installation method, the installation that can have a power failure, and mounting means is simple, effectively improves the installation rate of various kinds of equipment on shaft tower, increases work efficiency.
The technical scheme that technical solution problem of the present invention adopts is: first aspect, a kind of base for charged erection unit on shaft tower, comprise U-shaped pedestal, lift sub pin device, described lift sub pin device is arranged at the bottom of U-shaped pedestal peristome, the top of described U-shaped pedestal is provided with screwed hole, and a side of described U-shaped pedestal is provided with jack.
Preferably described lift sub pin device comprises circular bayonet lock, circular holder and spring as a kind of, and the cross-arm plane of described circular bayonet lock and shaft tower or draw hole set in iron plane to match is bolted and is connected between described circular holder and U-shaped pedestal.
As further improvement, the top of described U-shaped pedestal peristome is provided with for the installing frame of magnet is installed.
Second aspect, a kind of mounting bar that the floor installation of above-mentioned charged erection unit is used on shaft tower, comprise head and barred body, the top of described barred body is provided with external screw thread, described head comprises and is provided with externally threaded top and establishes female bottom, the hand of spiral of described upper and lower is contrary, and the jack that the external screw thread that described top is set and U-shaped pedestal one side are provided with matches; The set external screw thread of the internal thread that described bottom is set and barred body top matches, and this is split type mounting bar.
The 3rd aspect, a kind of mounting bar that the floor installation of above-mentioned charged erection unit is used on shaft tower, comprise peristome and barred body, described peristome is provided with upper opening and runs through the top screwed hole of opening both sides, and be provided with lower through-hole, the top of described barred body is provided with external screw thread, the set external screw thread of described top screwed hole and barred body top matches, described barred body and lower through-hole are dwindled relevant position diameter is corresponding, and the diameter after described lower through-hole is dwindled is slightly less than barred body diameter, this is Contiuum type mounting bar.
The 4th aspect, the mounting bar that the floor installation of above-mentioned charged erection unit is used on shaft tower, comprises barred body, and described barred body top is provided with one section of through hole, the circular holder of the diameter of described through hole and lift sub pin device matches, and this is single formula mounting bar.
The 5th aspect, a kind of adopt described split type mounting bar by described base the installation method for charged erection unit on shaft tower, comprise the following steps, the first step, is screwed into the connecting bolt of equipment to be installed in the screwed hole at U-shaped pedestal top of base; Second step, is connected the tapped bottom of the barred body of mounting bar and head, and the jack that the externally threaded top of head band is set with U-shaped pedestal one side is connected; The 3rd step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, to cross-arm plane or draw iron plane, makes the bayonet lock of lift sub pin device snap in cross-arm plane or draw in hole set in iron plane on U-shaped pedestal peristome card; The 4th step, slowly screws mounting bar, and the jack on the externally threaded top of mounting bar head band and U-shaped pedestal starts to unscrew, until the externally threaded top of mounting bar head band is separated with jack, installs.
The 6th aspect, adopt described split type mounting bar by described base the installation method for charged erection unit on shaft tower, comprise the following steps the first step, in the installing frame on the U-shaped pedestal peristome top of base, lay a magnet, and with adhesive tape, magnet and U-shaped pedestal are fixed; Second step, is screwed into the connecting bolt of equipment to be installed in the screwed hole at U-shaped pedestal top; The 3rd step, is connected the tapped bottom of the barred body of mounting bar and head, and the jack that the externally threaded top of head band is set with U-shaped pedestal one side is connected; The 4th step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, U-shaped pedestal peristome is snapped in to cross-arm plane or draws iron plane, by magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix; The 5th step, slowly screws mounting bar, and the jack on the externally threaded top of mounting bar head band and U-shaped pedestal starts to unscrew, until the externally threaded top of mounting bar head band is separated with jack, installs.
The 7th aspect, a kind of adopt described Contiuum type mounting bar by described base the installation method for charged erection unit on shaft tower, comprise the following steps, the first step, is screwed into the connecting bolt of equipment to be installed in the screwed hole at U-shaped pedestal top of base; Second step, blocks the set jack of U-shaped pedestal one side by the opening of the peristome of mounting bar head, and turn barred body is threaded to barred body at the top of the peristome of head; The 3rd step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, to cross-arm plane or draw iron plane, makes the bayonet lock of lift sub pin device snap in cross-arm plane or draw in hole set in iron plane on U-shaped pedestal peristome card; The 4th step, slowly unscrews the barred body of mounting bar, until the peristome of mounting bar head can be separated with jack, installs.
The 8th aspect, adopt described Contiuum type mounting bar by described base the installation method for charged erection unit on shaft tower, comprise the following steps the first step, in the installing frame on the U-shaped pedestal peristome top of base, lay a magnet, and with adhesive tape, magnet and U-shaped pedestal are fixed; Second step, is screwed into the connecting bolt of equipment to be installed in the screwed hole at U-shaped pedestal top of base; The 3rd step, blocks the set jack of U-shaped pedestal one side by the opening of the peristome of mounting bar head, and turn barred body is threaded to barred body at the top of the peristome of head; The 4th step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, by U-shaped pedestal peristome card to cross-arm plane or draw iron plane, by magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix; The 5th step, slowly unscrews the barred body of mounting bar, until the peristome of mounting bar head can be separated with jack, installs.
The 9th aspect, a kind of adopt described single formula mounting bar by described base the installation method for charged erection unit on shaft tower, comprise the following steps, the first step, is screwed into the connecting bolt of equipment to be installed in the screwed hole at U-shaped pedestal top of base; Second step, by circular fixed seating in the through hole on mounting bar top; The 3rd step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, to cross-arm plane or draw iron plane, makes the bayonet lock of lift sub pin device snap in cross-arm plane or draw in hole set in iron plane on U-shaped pedestal peristome card; The 4th step, slowly puts down mounting bar, installs.
The tenth aspect, adopt described single formula mounting bar by described base the installation method for charged erection unit on shaft tower, comprise the following steps the first step, in the installing frame on the U-shaped pedestal peristome top of base, lay a magnet, and with adhesive tape, magnet and U-shaped pedestal are fixed; Second step, is screwed into the connecting bolt of equipment to be installed in the screwed hole at U-shaped pedestal top of base; The 3rd step, by circular fixed seating in the through hole on mounting bar top; The 4th step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, by U-shaped pedestal peristome card to cross-arm plane or draw iron plane, by magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix; The 5th step, slowly puts down mounting bar, installs.
Base for charged erection unit on shaft tower provided by the invention, normally enters described circular card pin card the cross-arm plane of shaft tower or draws hole set in iron plane, and described circular holder is fixedly connected with bolt with U-shaped pedestal.But when the cross-arm plane of shaft tower or draw while the hole matching not being installed with lift sub pin device in iron plane, the invention provides preferred version, employing magnet is fixed, a magnet is installed in the installing frame on described U-shaped pedestal peristome top, when U-shaped pedestal peristome snaps in cross-arm plane or draws after iron plane, adopt magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix.The invention provides three kinds of mounting bars that the floor installation of described charged erection unit is used on shaft tower, i.e. split type mounting bar, Contiuum type mounting bar and single formula mounting bar simultaneously; The present invention also provides for different bases, adopts the method for split type mounting bar, Contiuum type mounting bar and single formula mounting bar charged erection unit on built on stilts shaft tower.
The invention has the beneficial effects as follows: the understructure of charged erection unit is simple, can adopt two kinds of mounting bars to install, and can fix by lift sub pin device and/or magnet, easy for installation, fixing reliable, effectively improved the installation rate of various kinds of equipment on shaft tower, shorten the set-up time, reduce loss of outage, alleviate operating pressure, increase work efficiency.
Accompanying drawing explanation
Fig. 1 is that the master of the embodiment of the present invention looks schematic diagram.
Fig. 2 is the stereogram of the embodiment of the present invention.
Fig. 3 is the cross-sectional schematic of the split type mounting bar of the embodiment of the present invention.
Fig. 4 is the cross-sectional schematic of embodiment of the present invention Contiuum type mounting bar.
Fig. 5 is the cross-sectional schematic of the single formula mounting bar of the embodiment of the present invention.
Below in conjunction with accompanying drawing, the present invention will be further described.
Embodiment
Embodiment 1:
As shown in Figure 1 and Figure 2, a kind of base of charged erection unit, comprises U-shaped pedestal 1, lift sub pin device, and lift sub pin device is arranged at the bottom of U-shaped pedestal 1 peristome, at the top of U-shaped pedestal 1, is provided with screwed hole 3, in a side of U-shaped pedestal 1, is provided with jack 4.Lift sub pin device comprises circular bayonet lock 2, circular holder 5 and spring, bayonet lock 2 and spring are arranged in holder 5, the part that bayonet lock 2 exposes holder 5 is an inclined-plane, highest point is 10mm, the cross-arm plane of this bayonet lock 2 and shaft tower or draw hole set in iron plane to match, is fixedly connected with by bolt 9 between holder 5 and U-shaped pedestal 1.
Embodiment 2:
On the top of U-shaped pedestal 1 peristome, be also provided with for the installing frame 8 of magnet is installed.All the other are identical with embodiment 1.
Embodiment 3:
The split type mounting bar that the base of above-mentioned charged erection unit adopts in installation, as shown in Figure 3, comprise head and barred body, head comprises and is provided with externally threaded top 6 and establishes female bottom 7, the hand of spiral of described top 6 and bottom 7 is contrary, is provided with externally threaded top 6 and matches with the jack 4 that U-shaped pedestal 1 one sides are provided with.The set external screw thread of the internal thread that described bottom 7 is set and barred body top matches.
Embodiment 4:
The Contiuum type mounting bar that the base of above-mentioned charged erection unit adopts in installation, as shown in Figure 4, comprise peristome and barred body, described peristome is provided with upper opening and runs through the top screwed hole 10 of opening both sides, and be provided with lower through-hole, and the top of described barred body is provided with external screw thread, and described top screwed hole 10 matches with the set external screw thread in barred body top, described barred body and lower through-hole are dwindled relevant position diameter is corresponding, and the diameter of described lower through-hole after dwindling is slightly less than barred body diameter.
Embodiment 5:
The single formula mounting bar that the base of above-mentioned charged erection unit adopts in installation, as shown in Figure 5, comprises barred body, and described barred body top is provided with one section of through hole 11, and the circular holder 5 of the diameter of described through hole 11 and lift sub pin device matches.
Embodiment 6:
Split type mounting bar described in employing embodiment 3 is a kind of installation method for charged erection unit on shaft tower by the base shown in embodiment 1, and the first step, is screwed into the connecting bolt of equipment to be installed in the screwed hole 3 at U-shaped pedestal 1 top; Second step, the external screw thread that mounting bar head top is set is connected with the jack 4 that U-shaped pedestal 1 one sides are provided with; The 3rd step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, and U-shaped pedestal 1 peristome card to cross-arm plane or draw iron plane, is treated to the bayonet lock of lift sub pin device snaps in cross-arm plane or draws in hole set in iron plane; The 4th step, slowly screws mounting bar, and the jack 4 of the head of mounting bar and U-shaped pedestal 1 starts to unscrew, until mounting bar head is separated with jack 4, installs.
Embodiment 7:
Split type mounting bar described in employing embodiment 3 is a kind of installation method for charged erection unit on shaft tower by the base shown in embodiment 2, comprise the following steps, the first step, in the installing frame 8 on the U-shaped pedestal 1 peristome top of base, lay a magnet, and with adhesive tape, magnet and U-shaped pedestal 1 is fixing; Second step, is screwed into the connecting bolt of equipment to be installed in the screwed hole 3 at U-shaped pedestal 1 top; The 3rd step, is connected the tapped bottom 7 of the barred body of mounting bar and head, and the jack 4 that the externally threaded top 6 of head band is set with U-shaped pedestal 1 one sides is connected; The 4th step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, U-shaped pedestal 1 peristome is snapped in to cross-arm plane or draws iron plane, by magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix; The 5th step, slowly screws mounting bar, and the externally threaded top 6 of mounting bar head band starts to unscrew with the jack 4 on U-shaped pedestal 1, until the externally threaded top 6 of mounting bar head band is separated with jack, installs.
Embodiment 8:
Contiuum type mounting bar described in employing embodiment 4 is a kind of installation method for charged erection unit on shaft tower by the base shown in embodiment 1, comprise the following steps, the first step, is screwed into the connecting bolt of equipment to be installed in the screwed hole 3 at U-shaped pedestal 1 top of base; Second step, blocks the set jack 4 of U-shaped pedestal 1 one sides by the opening of the peristome of mounting bar head, and turn barred body is threaded to barred body at the top of the peristome of head; The 3rd step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, to cross-arm plane or draw iron plane, makes the bayonet lock of lift sub pin device snap in cross-arm plane or draw in hole set in iron plane on U-shaped pedestal 1 peristome card; The 4th step, slowly unscrews the barred body of mounting bar, until the peristome of mounting bar head can be separated with jack 4, installs.
Embodiment 9:
Contiuum type mounting bar described in employing embodiment 4 is a kind of installation method for charged erection unit on shaft tower by the base shown in embodiment 2, comprise the following steps, the first step, in the installing frame 8 on the U-shaped pedestal 1 peristome top of base, lay a magnet, and with adhesive tape, magnet and U-shaped pedestal 1 is fixing; Second step, is screwed into the connecting bolt of equipment to be installed in the screwed hole 3 at U-shaped pedestal 1 top of base; The 3rd step, blocks the set jack 4 of U-shaped pedestal 1 one sides by the opening of the peristome of mounting bar head, and turn barred body is threaded to barred body at the top of the peristome of head; The 4th step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, by U-shaped pedestal 1 peristome card to cross-arm plane or draw iron plane, by magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix; The 5th step, slowly unscrews the barred body of mounting bar, until the peristome of mounting bar head can be separated with jack 4, installs.
Embodiment 10:
Contiuum type mounting bar described in employing embodiment 4 is a kind of installation method for charged erection unit on shaft tower by the base shown in embodiment 2, comprise the following steps, the first step, is screwed into the connecting bolt of equipment to be installed in the screwed hole 3 at U-shaped pedestal 1 top of base; Second step, is placed on circular holder 5 in the through hole 11 on mounting bar top; The 3rd step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, to cross-arm plane or draw iron plane, makes the bayonet lock of lift sub pin device snap in cross-arm plane or draw in hole set in iron plane on U-shaped pedestal 1 peristome card; The 4th step, slowly puts down mounting bar, installs.
Embodiment 11:
Contiuum type mounting bar described in employing embodiment 4 is a kind of installation method for charged erection unit on shaft tower by the base shown in embodiment 2, comprise the following steps, the first step, in the installing frame 8 on the U-shaped pedestal 1 peristome top of base, lay a magnet, and with adhesive tape, magnet and U-shaped pedestal 1 is fixing; Second step, is screwed into the connecting bolt of equipment to be installed in the screwed hole 3 at U-shaped pedestal 1 top of base; The 3rd step, is placed on circular holder 5 in the through hole 11 on mounting bar top; The 4th step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, by U-shaped pedestal 1 peristome card to cross-arm plane or draw iron plane, by magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix; The 5th step, slowly puts down mounting bar, installs.

Claims (10)

1. the base for charged erection unit on shaft tower, it is characterized in that: comprise U-shaped pedestal (1), lift sub pin device, described lift sub pin device is arranged at the bottom of U-shaped pedestal (1) peristome, the top of described U-shaped pedestal (1) is provided with screwed hole (3), and a side of described U-shaped pedestal (1) is provided with jack (4); Described lift sub pin device comprises circular bayonet lock (2), circular holder (5) and spring, the cross-arm plane of described circular bayonet lock (2) and shaft tower or draw hole set in iron plane to match, is fixedly connected with by bolt (9) between described circular holder (5) and U-shaped pedestal (1).
2. the base for charged erection unit on shaft tower as claimed in claim 1, is characterized in that: the top of described U-shaped pedestal (1) peristome is provided with the installing frame (8) for magnet is installed.
3. the mounting bar that the floor installation of charged erection unit as claimed in claim 1 or 2 is used on shaft tower, it is characterized in that: comprise peristome and barred body, described peristome is provided with upper opening and runs through the top screwed hole (10) of opening both sides, and be provided with lower through-hole, the top of described barred body is provided with external screw thread, described top screwed hole (10) matches with the set external screw thread in barred body top, described barred body and lower through-hole are dwindled relevant position diameter is corresponding, and the diameter after described lower through-hole is dwindled is slightly less than barred body diameter, this is Contiuum type mounting bar.
4. the mounting bar that the floor installation of charged erection unit as claimed in claim 1 or 2 is used on shaft tower, it is characterized in that: comprise barred body, described barred body top is provided with one section of through hole (11), the circular holder (5) of the diameter of described through hole (11) and lift sub pin device matches, and this is single formula mounting bar.
5. one kind adopts split type mounting bar base as claimed in claim 1 to be used for to the installation method of charged erection unit on shaft tower, described split type mounting bar comprises head and barred body, the top of described barred body is provided with external screw thread, described head comprises and is provided with externally threaded top (6) and establishes female bottom (7), the hand of spiral of described top (6) and bottom (7) is contrary, and the jack (4) that the external screw thread that described top (6) are set and U-shaped pedestal (1) one side are provided with matches; The set external screw thread of the internal thread that described bottom (7) is set and barred body top matches; It is characterized in that: comprise the following steps, the first step, is screwed into the connecting bolt of equipment to be installed in the screwed hole (3) at U-shaped pedestal (1) top of base; Second step, is connected the tapped bottom of the barred body of mounting bar and head (7), and the jack (4) that the externally threaded top of head band (6) is set with U-shaped pedestal (1) one side is connected; The 3rd step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, to cross-arm plane or draw iron plane, makes the bayonet lock of lift sub pin device snap in cross-arm plane or draw in hole set in iron plane on U-shaped pedestal (1) peristome card; The 4th step, slowly screws mounting bar, and the externally threaded top of mounting bar head band (6) start to unscrew with the jack (4) on U-shaped pedestal (1), until the externally threaded top of mounting bar head band (6) is separated with jack (4), install.
6. one kind adopts split type mounting bar base as claimed in claim 2 to be used for to the installation method of charged erection unit on shaft tower, described split type mounting bar comprises head and barred body, the top of described barred body is provided with external screw thread, described head comprises and is provided with externally threaded top (6) and establishes female bottom (7), the hand of spiral of described top (6) and bottom (7) is contrary, and the jack (4) that the external screw thread that described top (6) are set and U-shaped pedestal (1) one side are provided with matches; The set external screw thread of the internal thread that described bottom (7) is set and barred body top matches; It is characterized in that: comprise the following steps, the first step is laid a magnet in the installing frame (8) on U-shaped pedestal (1) the peristome top of base, and with adhesive tape, magnet and U-shaped pedestal (1) is fixing; Second step, is screwed into the connecting bolt of equipment to be installed in the screwed hole (3) at U-shaped pedestal (1) top; The 3rd step, is connected the tapped bottom of the barred body of mounting bar and head (7), and the jack (4) that the externally threaded top of head band (6) is set with U-shaped pedestal (1) one side is connected; The 4th step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, U-shaped pedestal (1) peristome is snapped in to cross-arm plane or draws iron plane, by magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix; The 5th step, slowly screws mounting bar, and the externally threaded top of mounting bar head band (6) start to unscrew with the jack (4) on U-shaped pedestal (1), until the externally threaded top of mounting bar head band (6) is separated with jack, install.
7. one kind adopts mounting bar claimed in claim 3 base as claimed in claim 1 to be used for to the installation method of charged erection unit on shaft tower, it is characterized in that: comprise the following steps, the first step, is screwed into the connecting bolt of equipment to be installed in the screwed hole (3) at U-shaped pedestal (1) top of base; Second step, blocks the set jack (4) of U-shaped pedestal (1) one side by the opening of the peristome of mounting bar head, and turn barred body is threaded to barred body at the top of the peristome of head; The 3rd step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, to cross-arm plane or draw iron plane, makes the bayonet lock of lift sub pin device snap in cross-arm plane or draw in hole set in iron plane on U-shaped pedestal (1) peristome card; The 4th step, slowly unscrews the barred body of mounting bar, until the peristome of mounting bar head can be separated with jack (4), installs.
8. one kind adopts mounting bar claimed in claim 3 base as claimed in claim 2 to be used for to the installation method of charged erection unit on shaft tower, it is characterized in that: comprise the following steps, the first step, in the installing frame (8) on U-shaped pedestal (1) the peristome top of base, lay a magnet, and with adhesive tape, magnet and U-shaped pedestal (1) is fixing; Second step, is screwed into the connecting bolt of equipment to be installed in the screwed hole (3) at U-shaped pedestal (1) top of base; The 3rd step, blocks the set jack (4) of U-shaped pedestal (1) one side by the opening of the peristome of mounting bar head, and turn barred body is threaded to barred body at the top of the peristome of head; The 4th step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, by U-shaped pedestal (1) peristome card to cross-arm plane or draw iron plane, by magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix; The 5th step, slowly unscrews the barred body of mounting bar, until the peristome of mounting bar head can be separated with jack (4), installs.
9. one kind adopts mounting bar claimed in claim 4 base as claimed in claim 1 to be used for to the installation method of charged erection unit on shaft tower, it is characterized in that: comprise the following steps, the first step, is screwed into the connecting bolt of equipment to be installed in the screwed hole (3) at U-shaped pedestal (1) top of base; Second step, is placed on circular holder (5) in the through hole (11) on mounting bar top; The 3rd step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, to cross-arm plane or draw iron plane, makes the bayonet lock of lift sub pin device snap in cross-arm plane or draw in hole set in iron plane on U-shaped pedestal (1) peristome card; The 4th step, slowly puts down mounting bar, installs.
10. one kind adopts mounting bar claimed in claim 4 base as claimed in claim 2 to be used for to the installation method of charged erection unit on shaft tower, it is characterized in that: comprise the following steps, the first step, in the installing frame (8) on U-shaped pedestal (1) the peristome top of base, lay a magnet, and with adhesive tape, magnet and U-shaped pedestal (1) is fixing; Second step, is screwed into the connecting bolt of equipment to be installed in the screwed hole (3) at U-shaped pedestal (1) top of base; The 3rd step, is placed on circular holder (5) in the through hole (11) on mounting bar top; The 4th step, moves to shaft tower place to be installed by mounting bar by equipment to be installed and base, by U-shaped pedestal (1) peristome card to cross-arm plane or draw iron plane, by magnet by the cross-arm plane of base and shaft tower or draw iron plane to fix; The 5th step, slowly puts down mounting bar, installs.
CN201210017425.4A 2012-01-20 2012-01-20 Base and installation rod used for electrified installation device on tower and installation method thereof Expired - Fee Related CN102545092B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201210017425.4A CN102545092B (en) 2012-01-20 2012-01-20 Base and installation rod used for electrified installation device on tower and installation method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201210017425.4A CN102545092B (en) 2012-01-20 2012-01-20 Base and installation rod used for electrified installation device on tower and installation method thereof

Publications (2)

Publication Number Publication Date
CN102545092A CN102545092A (en) 2012-07-04
CN102545092B true CN102545092B (en) 2014-09-03

Family

ID=46351328

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201210017425.4A Expired - Fee Related CN102545092B (en) 2012-01-20 2012-01-20 Base and installation rod used for electrified installation device on tower and installation method thereof

Country Status (1)

Country Link
CN (1) CN102545092B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105490232A (en) * 2015-12-04 2016-04-13 国家电网公司 Bird repeller fixing installation structure
CN105633857B (en) * 2016-03-30 2018-05-08 国网山东省电力公司商河县供电公司 A kind of charged for replacement bird-scaring unit specific purpose tool
CN107781281A (en) * 2016-08-31 2018-03-09 天津市津宝乐器有限公司 Traveling Tabor papoose carrier attachment means

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2932777Y (en) * 2006-05-22 2007-08-08 卢义福 An insulating rod with removable working head
CN201528140U (en) * 2009-11-04 2010-07-14 河南省电力公司平顶山供电公司 Operating stick for power distribution work
CN201562913U (en) * 2009-11-03 2010-08-25 华北电网有限公司廊坊供电公司 Tool for live-line installing of bird dispeller equipped with single-bolt seat
CN201590620U (en) * 2009-12-05 2010-09-22 山东电力集团公司临沂供电公司 Power transmission line wind deflection preventive fixing clip
CN201877757U (en) * 2010-09-08 2011-06-22 华北电网有限公司廊坊供电公司 Mounting device for installing bird expeller in electrified way

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2932777Y (en) * 2006-05-22 2007-08-08 卢义福 An insulating rod with removable working head
CN201562913U (en) * 2009-11-03 2010-08-25 华北电网有限公司廊坊供电公司 Tool for live-line installing of bird dispeller equipped with single-bolt seat
CN201528140U (en) * 2009-11-04 2010-07-14 河南省电力公司平顶山供电公司 Operating stick for power distribution work
CN201590620U (en) * 2009-12-05 2010-09-22 山东电力集团公司临沂供电公司 Power transmission line wind deflection preventive fixing clip
CN201877757U (en) * 2010-09-08 2011-06-22 华北电网有限公司廊坊供电公司 Mounting device for installing bird expeller in electrified way

Also Published As

Publication number Publication date
CN102545092A (en) 2012-07-04

Similar Documents

Publication Publication Date Title
CN204103316U (en) For the charged insulation eagle's beak pliers action bars disconnected of isolated circuit breaker
CN102420401A (en) Triangular insulating hanging fulcrum bar
CN102545092B (en) Base and installation rod used for electrified installation device on tower and installation method thereof
CN202004372U (en) Tool for live-line replacing large disc diameter and deadweight dead end insulator string
CN202260249U (en) High-voltage transmission line raiser in live working
CN203103882U (en) Insulation bracing frame for live 10kV cable lead disconnection and connection operation
CN203932808U (en) Replacing insulator under electrified wire lifting device
CN203396829U (en) Indoor high voltage charged display
CN202353100U (en) Triangular insulation lifting strut
CN102340114A (en) High-voltage power transmission line lifter for live working
CN206441991U (en) A kind of electric pole lightning protection device
CN201742027U (en) Special tool for replacing insulators in electriferous state for 110kV single tower double circuit
CN205863774U (en) A kind of device of live installation of bird repeller
CN208299219U (en) A kind of electric automatization power distribution cabinet
CN206020766U (en) A kind of power transmission line column draws lower securing member with OPGW insulation
CN201061118Y (en) Intermediate joint of cable
CN206272145U (en) A kind of fast live line changes the device of line feed terminals
CN203850718U (en) 10KV charged bird repeller installation insulation operation rod
CN103996993B (en) 10kV live installation of bird repeller insulating bar
CN209419169U (en) A kind of ground wire vibration abatement component
CN201918652U (en) Wiring insulator of transformer low-voltage switchgear
CN205791271U (en) Fixing sleeve for wire stripper
CN206349542U (en) A kind of regulator cubicle terminal fixer
CN201786336U (en) Adjustable takeoff and landing type non-beam pumping unit bracket
CN202977751U (en) Electric-power line grounding apparatus

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140903

Termination date: 20190120

CF01 Termination of patent right due to non-payment of annual fee