CN102535441A - 一种地下连续墙的施工方法 - Google Patents

一种地下连续墙的施工方法 Download PDF

Info

Publication number
CN102535441A
CN102535441A CN2012100722422A CN201210072242A CN102535441A CN 102535441 A CN102535441 A CN 102535441A CN 2012100722422 A CN2012100722422 A CN 2012100722422A CN 201210072242 A CN201210072242 A CN 201210072242A CN 102535441 A CN102535441 A CN 102535441A
Authority
CN
China
Prior art keywords
concrete
wall
diaphragm wall
construction
underground diaphragm
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2012100722422A
Other languages
English (en)
Inventor
马文旭
谭永强
高培恩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGNAN FOUNDATION ENGINEERING Corp OF GUANGZHOU ZHONG-MEI
Original Assignee
JIANGNAN FOUNDATION ENGINEERING Corp OF GUANGZHOU ZHONG-MEI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGNAN FOUNDATION ENGINEERING Corp OF GUANGZHOU ZHONG-MEI filed Critical JIANGNAN FOUNDATION ENGINEERING Corp OF GUANGZHOU ZHONG-MEI
Priority to CN2012100722422A priority Critical patent/CN102535441A/zh
Publication of CN102535441A publication Critical patent/CN102535441A/zh
Pending legal-status Critical Current

Links

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明公开了一种地下连续墙的施工方法,属于支护结构技术领域,其技术要点包括下述步骤:(1)在预定地基上开挖沟槽,放置钢筋笼,浇注混凝土形成地下连接墙段;(2)在已经形成的地下连接墙段的相邻位置开挖沟槽,放置钢筋笼,浇注混凝土形成地下连接墙段,相邻的两幅地下连接墙墙段之间预留合适距离,保证接头能有效搭接;(3)两幅地下连续墙段浇注完成后,混凝土仍未达到凝结时,在两墙幅接头处开孔,在开孔处灌注混凝土,使两幅地下连续墙良好连接,形成连续的整体;本发明旨在提供一种施工简单、止水效果良好的地下连续墙的施工方法;用于地下连续墙的构筑。

Description

一种地下连续墙的施工方法
技术领域
本发明涉及一种支护结构的施工方法,更具体地说,尤其涉及一种地下连接墙的施工方法。 
背景技术
地下连续墙就是预先进行成槽作业,形成一定长度的槽段,在槽段内吊放钢筋笼、浇注砼形成单元墙段,然后将单元墙段连接起来形成一道连续的地下钢筋砼墙。地下连续墙可以在复杂条件下施工,施工深度大,支护构件承载能力大,防渗性能好,是基坑支护中最为可靠的支护方式。尤其在砂层中,要达到止水效果,必需采用地下连续墙才是最为可靠的支护方式。目前,地下连续墙不仅作为临时围护结构挡土和止水,同时还作地下室永久性承重外墙结构的三墙合一的形式。 
地下连续墙是一幅一幅进行施工的,而成槽过程中采用泥浆护壁,墙幅之间接头会附着一部分泥皮。由于泥皮的存在,墙幅之间混凝土就会形成一定的缝隙,在水土压力较大的情况下,接缝由于渗漏。可以说,墙幅接头的止水挡土效果决定了地下连续墙防渗效果。 
地下连续墙接头通常采用的方法为接头管、工字钢、十字钢板等形式。由于墙幅之间接缝的渗漏,通常在墙幅外接头处采用搅拌桩、旋喷桩封堵,或者在墙幅内接头处预埋注浆管注浆封堵。 
但是,接头混凝土先后浇注会在墙幅接缝处形成夹有泥皮的天然缝隙,并且存在两幅墙因垂直度不同而产生开叉,同时在水土压力下墙幅产生的差异变形,使接缝会进一步加大,目前连续墙墙幅接缝措施并没有将以上问题有效解决。在地下连续墙大于一定深度以后,巨大的水压力使外侧的水、砂顺着接缝带入基坑内,给基坑安全带来非常大的风险。同时,作为永久结构的主体侧墙,接头渗漏将会给建筑物的正常使用带来许多不便、同时结构使用耐久性也存在一定隐患。 
发明内容
本发明的目的在于针对上述现有技术存在的不足,提供一种施工简单、止水效果良好的地下连续墙的施工方法。 
本发明的技术方案是这样实现的:一种地下连续墙的施工方法,其中该方法包括下述步骤:(1)在预定地基上开挖沟槽,放置钢筋笼,浇注混凝土形成地下连接墙段;(2)在已经形成的地下连接墙段的相邻位置开挖沟槽,放置钢筋笼,浇注混凝土形成地下连接墙段,相邻的两幅地下连接墙墙段之间预留合适距离,保证接头能有效搭接;(3)两幅地下连续墙段 浇注完成后,混凝土仍未达到凝结时,在两墙幅接头处开孔,在开孔处灌注混凝土,使两幅地下连续墙良好连接,形成连续的整体。 
上述的一种地下连续墙的施工方法中,步骤(1)所采用的混凝土为初凝和终凝时间较长的混凝土; 
上述的一种地下连续墙的施工方法中,步骤(2)所采用的混凝土为普通的混凝土。 
上述的一种地下连续墙的施工方法中,步骤(3)所述的开孔后,还需要在孔内放置钢筋笼,然后再灌注混凝土。 
上述的一种地下连续墙的施工方法中,步骤(3)所述的开孔为采用打桩机成孔。 
本发明采用上述方法后,通过采用始凝和终凝时间较长的混凝土对地下连续墙段进行浇注,以延长墙段的固结时间,从而可以在两墙幅接头处开孔,在开孔处灌注混凝土,使两幅地下连续墙良好连接,形成连续的整体。从而有效地防止渗水,提高地下连续墙接缝抗渗能力。 
具体实施方式
下面结合实施例对本发明作进一步的详细说明,但并不构成对本发明的任何限制。
本发明的一种地下连续墙的施工方法,该方法包括下述步骤:(1)在预定地基上开挖沟槽,放置钢筋笼,浇注初凝和终凝时间较长的混凝土形成地下连接墙段;(2)在已经形成的地下连接墙段的相邻位置开挖沟槽,放置钢筋笼,浇注普通的混凝土形成地下连接墙段,相邻的两幅地下连接墙墙段之间预留合适距离,保证接头能有效搭接,浇注第二段相邻墙段时,视具体情况也可以采用初凝和终凝时间较长的混凝土;(3)两幅地下连续墙段浇注完成后,混凝土仍未达到凝结时,在两墙幅接头处开孔,孔的直径优选大于地下连接墙的厚度,在开孔处灌注混凝土,使两幅地下连续墙良好连接,形成连续的整体。必要时,可以在开孔后,在孔内放置钢筋笼,然后再灌注混凝土,形成具有一定承载能力的刚性接头。 
实施例1 
本发明的一种地下连续墙的施工方法,该方法包括下述步骤:(1)在预定位置开挖6m长、0.6m宽、20m深的沟槽,放置钢筋笼,浇注初凝和终凝时间较长的混凝土形成地下连接墙段;(2)在已经形成的地下连接墙段的相邻位置开挖沟槽,放置钢筋笼,浇注普通的混凝土形成地下连接墙段,相邻的两幅地下连接墙墙段之间预留0.5米的间距,保证接头能有效搭接;(3)两幅地下连续墙段浇注完成后,混凝土仍未达到凝结时,在两墙幅接头处采用直径0.8米的带套筒旋挖桩机成孔,在开孔处灌注混凝土,使两幅地下连续墙良好连接,形成连续的整体。 
实施例2 
本发明的一种地下连续墙的施工方法,该方法包括下述步骤:(1)在预定位置开挖6m长、0.8m宽、25m深的沟槽,放置钢筋笼,浇注初凝和终凝时间较长的混凝土形成地下连接墙段;(2)在已经形成的地下连接墙段的相邻位置开挖沟槽,放置钢筋笼,浇注初凝和终凝时间较长的混凝土形成地下连接墙段,相邻的两幅地下连接墙墙段之间预留0.6米的间距,保证接头能有效搭接;(3)两幅地下连续墙段浇注完成后,混凝土仍未达到凝结时,在两墙幅接头处采用直径1.0米的带套筒旋挖桩机成孔,在孔内放置钢筋笼,然后灌注混凝土,形成具有一定承载能力的刚性接头,使两幅地下连续墙良好连接,形成连续的整体。 
实施例3 
本发明的一种地下连续墙的施工方法,该方法包括下述步骤:(1)在预定位置开挖6m长、1m宽、25m深的沟槽,放置钢筋笼,浇注初凝和终凝时间较长的混凝土形成地下连接墙段;(2)在已经形成的地下连接墙段的相邻位置开挖沟槽,放置钢筋笼,浇注初凝和终凝时间较长的混凝土形成地下连接墙段,相邻的两幅地下连接墙墙段之间预留0.8米的间距,保证接头能有效搭接;(3)两幅地下连续墙段浇注完成后,混凝土仍未达到凝结时,在两墙幅接头处采用直径1.2米的带套筒旋挖桩机成孔,在孔内放置钢筋笼,然后灌注混凝土,形成具有一定承载能力的刚性接头,使两幅地下连续墙良好连接,形成连续的整体。 
上述实施例中,实施例1根据地下连接墙的厚度及深度不同,采用初凝和终凝较长的混凝土和普通混凝土分别对两段地下连接墙段进行浇注,使两幅墙段同时达到相的凝固状态。未采用钢筋笼。实施例2根据地下连接墙的厚度及深度不同,均采用初凝和终凝较长的混凝土分别对两段地下连接墙段进行浇注,使两幅墙段同时达到相的凝固状态。采用钢筋笼形成钢性接头。实施例3根据地下连接墙的厚度及深度不同,均采用初凝和终凝较长的混凝土分别对两段地下连接墙段进行浇注,使两幅墙段同时达到相的凝固状态。采用钢筋笼形成钢性接头。但实施例并不能对本发明进行限定,其它的任何未背离本发明的技术方案而所做的改变或其它等效的置换方式,都包含在本发明的保护范围之内。 

Claims (5)

1.一种地下连续墙的施工方法,其特征在于,该方法包括下述步骤:(1)在预定地基上开挖沟槽,放置钢筋笼,浇注混凝土形成地下连接墙段;(2)在已经形成的地下连接墙段的相邻位置开挖沟槽,放置钢筋笼,浇注混凝土形成地下连接墙段,相邻的两幅地下连接墙墙段之间预留合适距离,保证接头能有效搭接;(3)两幅地下连续墙段浇注完成后,混凝土仍未达到凝结时,在两墙幅接头处开孔,在开孔处灌注混凝土,使两幅地下连续墙良好连接,形成连续的整体。
2.根据权利要求1所述的一种地下连续墙的施工方法,其特征在于,步骤(1)所采用的混凝土为初凝和终凝时间较长的混凝土。
3.根据权利要求1所述的一种地下连续墙的施工方法,其特征在于,步骤(2)所采用的混凝土为普通的混凝土。
4.根据权利要求1所述的一种地下连续墙的施工方法,其特征在于,步骤(3)所述的开孔后,还需要在孔内放置钢筋笼,然后再灌注混凝土。
5.根据权利要求1所述的一种地下连续墙的施工方法,其特征在于,步骤(3)所述的开孔为采用桩机成孔。 
CN2012100722422A 2012-03-16 2012-03-16 一种地下连续墙的施工方法 Pending CN102535441A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2012100722422A CN102535441A (zh) 2012-03-16 2012-03-16 一种地下连续墙的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2012100722422A CN102535441A (zh) 2012-03-16 2012-03-16 一种地下连续墙的施工方法

Publications (1)

Publication Number Publication Date
CN102535441A true CN102535441A (zh) 2012-07-04

Family

ID=46343346

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2012100722422A Pending CN102535441A (zh) 2012-03-16 2012-03-16 一种地下连续墙的施工方法

Country Status (1)

Country Link
CN (1) CN102535441A (zh)

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102797252A (zh) * 2012-09-13 2012-11-28 中铁十二局集团第七工程有限公司 地下连续墙的施工方法
CN102808415A (zh) * 2012-07-25 2012-12-05 江苏华东地质建设集团有限公司 一种地下连续墙的基坑支护结构及其施工方法
CN103015405A (zh) * 2012-12-20 2013-04-03 广西大学 一种地下连续墙防渗漏方法
CN103898900A (zh) * 2014-03-25 2014-07-02 东南大学 带拉杆钢管混凝土组合结构地下连续墙及其施工方法
CN103924581A (zh) * 2014-03-25 2014-07-16 东南大学 预制钢管混凝土组合结构地下连续墙及其施工方法
CN105133621A (zh) * 2015-08-27 2015-12-09 中铁第四勘察设计院集团有限公司 基坑围护***的施工方法及基坑围护***
CN105133574A (zh) * 2015-07-23 2015-12-09 青岛静力工程股份有限公司 挤入式地下连续墙终点封闭成墙装置和使用方法
CN105839676A (zh) * 2016-03-30 2016-08-10 东通岩土科技(杭州)有限公司 渠式水泥土连续墙的冷缝处理方法
CN105862912A (zh) * 2016-04-18 2016-08-17 中冶建工集团有限公司 一种混凝土抗滑桩护壁施工方法
CN105908745A (zh) * 2016-04-13 2016-08-31 中国三冶集团有限公司宁波分公司 一种连续防水墙的密闭施工工具及其施工方法
CN110158662A (zh) * 2019-05-09 2019-08-23 中铁第四勘察设计院集团有限公司 一种地下连续墙接缝防漏水的施工方法及结构
CN111424681A (zh) * 2020-04-27 2020-07-17 中铁上海工程局集团华海工程有限公司 地下连续墙与灌注桩分段应用情况下的防水接头结构及其施工方法
CN111719544A (zh) * 2020-06-18 2020-09-29 中煤江南建设发展有限公司 一种干坞格构式地下连墙结构的施工方法

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1143703A (zh) * 1996-08-02 1997-02-26 北京乾坤基础工程有限公司 三合一地下连续墙及其施工方法
CN201962666U (zh) * 2011-02-22 2011-09-07 陈东曙 现浇混凝土桩体连续墙

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1143703A (zh) * 1996-08-02 1997-02-26 北京乾坤基础工程有限公司 三合一地下连续墙及其施工方法
CN201962666U (zh) * 2011-02-22 2011-09-07 陈东曙 现浇混凝土桩体连续墙

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
胡成都: "共线搅拌桩、钻孔桩在基坑支护中的应用", 《岩土工程界》 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102808415B (zh) * 2012-07-25 2015-05-27 江苏华东地质建设集团有限公司 一种地下连续墙的基坑支护结构及其施工方法
CN102808415A (zh) * 2012-07-25 2012-12-05 江苏华东地质建设集团有限公司 一种地下连续墙的基坑支护结构及其施工方法
CN102797252A (zh) * 2012-09-13 2012-11-28 中铁十二局集团第七工程有限公司 地下连续墙的施工方法
CN103015405A (zh) * 2012-12-20 2013-04-03 广西大学 一种地下连续墙防渗漏方法
CN103898900B (zh) * 2014-03-25 2016-01-06 东南大学 带拉杆钢管混凝土组合结构地下连续墙及其施工方法
CN103924581A (zh) * 2014-03-25 2014-07-16 东南大学 预制钢管混凝土组合结构地下连续墙及其施工方法
CN103898900A (zh) * 2014-03-25 2014-07-02 东南大学 带拉杆钢管混凝土组合结构地下连续墙及其施工方法
CN105133574A (zh) * 2015-07-23 2015-12-09 青岛静力工程股份有限公司 挤入式地下连续墙终点封闭成墙装置和使用方法
CN105133621A (zh) * 2015-08-27 2015-12-09 中铁第四勘察设计院集团有限公司 基坑围护***的施工方法及基坑围护***
CN105839676A (zh) * 2016-03-30 2016-08-10 东通岩土科技(杭州)有限公司 渠式水泥土连续墙的冷缝处理方法
CN105839676B (zh) * 2016-03-30 2017-09-29 东通岩土科技(杭州)有限公司 渠式水泥土连续墙的冷缝处理方法
CN105908745A (zh) * 2016-04-13 2016-08-31 中国三冶集团有限公司宁波分公司 一种连续防水墙的密闭施工工具及其施工方法
CN105862912A (zh) * 2016-04-18 2016-08-17 中冶建工集团有限公司 一种混凝土抗滑桩护壁施工方法
CN105862912B (zh) * 2016-04-18 2018-01-09 中冶建工集团有限公司 一种混凝土抗滑桩护壁施工方法
CN110158662A (zh) * 2019-05-09 2019-08-23 中铁第四勘察设计院集团有限公司 一种地下连续墙接缝防漏水的施工方法及结构
CN111424681A (zh) * 2020-04-27 2020-07-17 中铁上海工程局集团华海工程有限公司 地下连续墙与灌注桩分段应用情况下的防水接头结构及其施工方法
CN111424681B (zh) * 2020-04-27 2024-03-08 中铁上海工程局集团华海工程有限公司 地下连续墙与灌注桩分段应用情况下的防水接头结构及其施工方法
CN111719544A (zh) * 2020-06-18 2020-09-29 中煤江南建设发展有限公司 一种干坞格构式地下连墙结构的施工方法

Similar Documents

Publication Publication Date Title
CN102535441A (zh) 一种地下连续墙的施工方法
CN103981898B (zh) 一种整体明挖节点逆作的地下工程施工方法
CN101429764B (zh) 地下连续墙槽段接缝处渗漏水检测及封堵修复装置及其方法
CN105951711A (zh) 海边电站地下连续墙围护施工方法
CN103015456B (zh) 地下混凝土构筑物基础底板中的坑中坑快速支模法
CN207512745U (zh) 一种沉箱装置及其基坑结构
CN111851597B (zh) 顶管近距离下穿管廊的穿越防护结构及施工方法
CN103321246B (zh) 采用地下连续墙的基坑施工方法
CN100510281C (zh) 超大直径、超埋深度调蓄池的半逆作施工方法
CN202194148U (zh) 一种止水帷幕
CN102535519A (zh) 地下连续墙工字钢接头结构及其施工方法
CN103114609A (zh) 新、旧地下连续墙的连接装置及施工方法
CN106120801A (zh) 富水砂层中管线横穿基坑处的施工方法
CN202787334U (zh) 一种隧道施工中深井管的封闭结构
CN106013265A (zh) 地下室应急抗浮结构及其施工方法
CN202194149U (zh) 一种止水帷幕
US11566390B2 (en) Construction method of reclaiming land from the sea based on basement utilization
CN206467695U (zh) 一种用于沉井式空腹地下连续墙的接头
CN205714215U (zh) 隧道衬砌用减压管片及管片衬砌结构
CN104099946B (zh) 一种新型顶管段间检修井
CN203049630U (zh) 建筑物基础底板防水***
CN201424658Y (zh) 地下连续墙槽段接缝处渗漏水检测及封堵修复装置
CN103882889A (zh) 建筑物基础底板防水***
CN104480945B (zh) 一种基坑逆作施工方法
CN104499489B (zh) 一种基坑施工方法

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120704