Prior art keywords
phase
line
fault
breaker
current
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN 201110369298
Other languages
Chinese (zh)
Other versions
CN102412568A (en
Inventor
杜宁
郑彬
班连庚
项祖涛
宋瑞华
韩彬
周佩朋
杨大业
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Original Assignee
State Grid Corp of China SGCC
China Electric Power Research Institute Co Ltd CEPRI
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, China Electric Power Research Institute Co Ltd CEPRI filed Critical State Grid Corp of China SGCC
Priority to CN 201110369298 priority Critical patent/CN102412568B/en
Publication of CN102412568A publication Critical patent/CN102412568A/en
Application granted granted Critical
Publication of CN102412568B publication Critical patent/CN102412568B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Driving Mechanisms And Operating Circuits Of Arc-Extinguishing High-Tension Switches (AREA)

Abstract

The invention belongs to the power system field, concretely relating to a method for adjusting current delay zero crossing in a line protection motion sequential solution breaker connection/disconnection process. When carrying out an idle wire connection operation on a line which carries a parallel reactor and has a pre-existing singlephase earth fault, since current direct current bias is large, according to a line protection motion sequential which is generally employed, which means that after detecting a fault, a line breaker is controlled to carry out simultaneous brake disconnection of three phases by a line protection unit, a line breaker open operation fails possibly, and present main counter-measures can not thoroughly solve the above problem. According to the invention, reasonable adjustment is carried out on a line protection motion sequential. If the line has the pre-existing singlephase earth fault, when carrying out three-phase idle wire connection, after the fault is detected by the line protection unit, a fault phase line breaker is controlled to carry out single-phase brake disconnection first, after certain time, normal phase current direct current bias weaken to zero crossing of current, then a normal phase line breaker is controlled to carry out brake disconnection.

Description

Adjust the method for line protection motion sequential solution breaker current delay zero crossing
Technical field
The invention belongs to field of power, be specifically related to a kind of method that the route protection action sequence solves current slow zero passage in circuit breaker on/off switch process of adjusting.
Background technology
According to power system operation and test experience, line-breaker is when the circuit closed a floodgate with high-voltage shunt reactor, the circuit breaker current DC component may be larger, the long-time not situation of zero passage of electric current likely appears, if carry out immediately sub-switching operation after closing a floodgate, likely, due to electric current zero passage and can't blow-out not for a long time, cause circuit breaker to damage.In practice, if when there is pre-volt single phase ground fault in circuit, circuit breaker closes ceases to be busy, according to the protection action sequence generally adopted at present, route protection action command circuit breaker three-phase is separating brake immediately, likely there will be this situation.
For the current dc component problem, common braking measure has the installing switching-on resistance, adopts and select phase operating breaker etc., but, according to research, these two kinds of methods all can't be eliminated current DC biasing phenomenon fully.
China's ultra-high/extra-high voltage circuit is usually all with high-voltage shunt reactor.If there is pre-volt single phase ground fault in circuit, circuit breaker is closed the ceases to be busy operation, now due to the single-pole reclosing operation locking, according to the protection action sequence generally adopted at present, close ceases to be busy after the route protection action can order circuit breaker three-phase separating brake immediately.Now flow through the electric current that perfects the phase circuit breaker and larger direct current biasing likely occurs, cause electric current zero passage not for a long time, can't blow-out.Circuit breaker closes in the typical current waveform that has the nonloaded line that lies prostrate in advance single phase ground fault as shown in Figure 1.
As seen from Figure 1, for fault phase, because the fault current alternating current component is very large, electric current still can zero passage; And, for perfecting phase, the circuit breaker current direct current biasing is often very large, zero-crossing timing is very not long to cause electric current, can reach 1s.For SF commonly used in the high-voltage alternating system 6circuit breaker, if electric current zero passage not, can't blow-out.And if the arcing time long (the typical normal arcing time is 20ms) likely causes circuit breaker to damage.
For current DC biasing problem under this operating mode, common braking measure at present comprises:
(1) install switching-on resistance on circuit breaker
Install switching-on resistance on circuit breaker, during combined floodgate, switching-on resistance first drops into, then main contact is closed.Certain inhibitory action is played in the current DC biasing that can produce making process like this.
(2) adopt and select the phase operating breaker
According to research, during crossed belt shunt reactor circuit, the not zero-crossing timing of electric current is relevant with switching-on phase.Fig. 2 is the single-phase typical electric current relation of zero-crossing timing and switching-on phase not while closing ceases to be busy, and wherein, voltage means with cosine function, 0 °, 180 ° corresponding voltage peak values of switching-on phase.As can be seen, when circuit breaker closes a floodgate near voltage peak (0 °, 180 ° phase places), electric current not zero-crossing timing is the shortest, is about the ms magnitude; And while closing a floodgate near voltage zero-cross (90 °, 270 ° phase places), electric current not zero-crossing timing is the longest, can reach several s at zero point.The situation that exists pre-volt single phase ground fault to close ceases to be busy for circuit, due to the impact that is subject to the factors such as Coupling Between Phases, the relation of zero-crossing timing and switching-on phase is not more complex to perfect phase current, typically as shown in Figure 3, while being still in general near the combined floodgate of voltage zero-cross, zero-crossing timing is not longer for electric current, and while closing a floodgate near voltage peak, zero-crossing timing is not shorter for electric current; Even if but just at voltage peak point place, close a floodgate, perfect phase current not zero-crossing timing still have and may reach 0.2s and even surpass 0.4s.
Employing selects the principle of phase operating breaker to be, by controlling circuit breaker, near voltage peak, closes a floodgate, to shorten not zero-crossing timing of electric current.
Above-described current DC biasing braking measure is Shortcomings separately all, can't thoroughly solve the current slow zero passage problem produced in circuit breaker on/off switch process.
1) adopt switching-on resistance
According to domestic and international supergrid operating statistic result, during circuit breaker installing switching-on resistance, the heterogeneous fault that the probability that switching-on resistance itself breaks down is serious higher than some.And, according to operating experience, the probability that the pre-volt of circuit existence single phase ground fault closes ceases to be busy operation appearance is very low.
In addition, using the greatest problem of switching-on resistance is that its required energy is very large, and circuit breaker manufacturer manufacturing capacity is difficult to meet the demands, and its cost is also quite expensive.
According to research conclusion, adopt switching-on resistance also can not eliminate the current DC biasing fully.
2) adopt and select the phase operating breaker
Due to current manufacturing process and Control system resolution, the choosing mutually the operation exist certain random time deviation, its scope be generally ± 30 °.And three phase line is while existing pre-volt single phase ground fault to close ceases to be busy, as Fig. 3, perfect phase current not the relation of zero-crossing timing and switching-on phase also have certain dispersiveness.Owing to having these two enchancement factors, adopting, select the phase operating breaker the long-time not situation of zero passage of electric current still likely to occur, the longest not zero-crossing timing likely surpasses 0.6s, significantly is greater than the normal arcing time of circuit breaker (being typically 20ms).
On the other hand, for suppressing electric current zero passage phenomenon not for a long time, require to select the phase operating breaker to close a floodgate near voltage peak; And, for closing ceases to be busy operation, near voltage peak, can to cause closing the ceases to be busy switching overvoltage high for combined floodgate.Run counter to the requirement of switching-on phase this two aspect.
Summary of the invention
The objective of the invention is; overcome above deficiency, propose a kind of route protection action sequence that passes through to adjust, postpone disjunction and perfect the phase circuit; avoid when existing pre-volt single phase ground fault circuit to close ceases to be busy, because the current slow zero passage causes the method for breaker open operation failure.
According to a kind of method that the route protection action sequence solves current slow zero passage in circuit breaker on/off switch process of adjusting of the present invention; for the transmission line compensated with shunt reactor in electric power system; when being closed the ceases to be busy operation, its single-pole reclosing operation locking.For avoiding owing to existing pre-volt single phase ground fault to cause the failure of line-breaker separating brake on circuit, when closing ceases to be busy, the route protection action sequence is adjusted into and first divides fault phase, divide and perfect phase again.
Above-mentioned route protection action sequence is: if there is pre-volt single phase ground fault on circuit; after the three-phase combination ceases to be busy; at first route protection controls the single-phase separating brake of fault phase; after the time delay through certain hour (typically as 1s left and right or some s); perfect the phase current direct current biasing decay to electric current can zero passage, then control and perfect the phase separating brake.Sequential chart as shown in Figure 4.
Concrete route protection action sequence is as follows:
1) circuit that has pre-volt single phase ground fault is carried out to the operation of three-phase combination ceases to be busy;
2) route protection detects circuit and has single phase ground fault, controls the single-phase separating brake of fault phase line-breaker;
3) after one section time delay (typically as 1s left and right or some s), route protection is controlled and is perfected phase line-breaker separating brake.
The invention has the beneficial effects as follows:
When the adjustment route protection sequential that the present invention proposes is avoided closing ceases to be busy, owing to existing pre-volt single phase ground fault to cause the breaker open operation failure, method is simple, does not also need increase equipment, has good reliability and economy.This method and other protection are compatible, also can not exert an influence to system and equipment safety operation, have good applicability.
The accompanying drawing explanation
Below in conjunction with accompanying drawing, the present invention is further described.
There is pre-volt single phase ground fault in Fig. 1 circuit, during the three-phase combination ceases to be busy, and the typical waveform of switching current;
Fig. 2 is single-phase while closing ceases to be busy electric current is the typical relation of zero-crossing timing and switching-on phase not;
Fig. 3 circuit closes ceases to be busy while having pre-volt single phase ground fault, perfects the not typical relation of zero-crossing timing and switching-on phase of phase current;
The route protection action sequence that Fig. 4 the present invention proposes.
Embodiment
According to the route protection action sequence generally adopted at present, circuit for normal operation, if occur single phase ground fault on circuit, route protection is controlled the single-phase tripping operation of both sides line-breaker, then (be typically about 1s) single-pole reclosing after certain hour, if fault still exists, route protection is controlled both sides circuit breaker three-phase tripping operation; And for the circuit do not put into operation, the single-pole reclosing operation locking, that is, if there is pre-volt single phase ground fault on circuit,, when closing ceases to be busy, route protection is controlled circuit breaker three-phase while separating brake immediately after fault being detected.
The route protection action sequence that the present invention proposes is, if there is pre-volt single phase ground fault on circuit, after the three-phase combination ceases to be busy; at first route protection controls the single-phase separating brake of fault phase; after certain hour, perfect the phase current direct current biasing decay to electric current can zero passage, then control and perfect the phase separating brake.Sequential chart as shown in Figure 4.
Feasibility analysis
(1) for primary cut-out, its three-phase combination separating brake is controlled independent mutually, possesses the operability of first dividing fault phase, perfecting phase in rear minute.
(2) when there is pre-volt single phase ground fault in circuit, after closing ceases to be busy, the alternating current component of fault phase electric current is very large, can be because the current DC biasing causes electric current zero passage not for a long time, as shown in Figure 1a.Therefore, fault phase first divides, and does not have the problem of current slow zero passage.
(3) for perfecting phase, its electric current flow through is far below fault current, and circuit breaker is delayed disjunction can not affect system safety.
(4) perfecting phase retardation 1s left and right can meet the demands usually.For concrete engineering, can be adjusted according to actual parameter.
(5) the first separating brake of fault phase, sound phase is separating brake again, and Inductance on Neutral of Shunt Reactors can flow through larger electric current.According to the result of calculation (perfecting phase retardation 1s separating brake) of certain 500kV project of transmitting and converting electricity, its current peak is about the 100A left and right, and decays to zero in 10s.Can not cause little reactance to damage.
According to specific exemplary embodiment, invention has been described herein.It will be apparent carrying out to one skilled in the art suitable replacement or revise under not departing from the scope of the present invention.Exemplary embodiment is only illustrative, rather than, to the restriction of scope of the present invention, scope of the present invention is by appended claim definition.

Claims (2)

1. adjust the method that the route protection action sequence solves current slow zero passage in circuit breaker on/off switch process for one kind, it is characterized in that:
For the transmission line compensated with shunt reactor in electric power system, when being closed the ceases to be busy operation, its single-pole reclosing operation locking, for avoiding owing to existing pre-volt single phase ground fault to cause the failure of line-breaker separating brake on circuit, when closing ceases to be busy, the route protection action sequence is adjusted into and first divides fault phase, divide and perfect phase again;
Above-mentioned route protection action sequence is: if there is pre-volt single phase ground fault on circuit;, after the three-phase combination ceases to be busy, at first route protection controls the single-phase separating brake of fault phase, after the time delay through certain hour; perfect the phase current direct current biasing decay to electric current can zero passage, then control and perfect the phase separating brake.
2. the method for claim 1, is characterized in that, concrete route protection action sequence is as follows:
1) circuit that has pre-volt single phase ground fault is carried out to the operation of three-phase combination ceases to be busy;
2) route protection detects circuit and has single phase ground fault, controls the single-phase separating brake of fault phase line-breaker;
3), after one section time delay, route protection is controlled and is perfected phase line-breaker separating brake.
CN 201110369298 2011-11-18 2011-11-18 Method for adjusting line protection motion sequential solution breaker current delay zero crossing Active CN102412568B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110369298 CN102412568B (en) 2011-11-18 2011-11-18 Method for adjusting line protection motion sequential solution breaker current delay zero crossing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110369298 CN102412568B (en) 2011-11-18 2011-11-18 Method for adjusting line protection motion sequential solution breaker current delay zero crossing

Publications (2)

Publication Number Publication Date
CN102412568A CN102412568A (en) 2012-04-11
CN102412568B true CN102412568B (en) 2013-12-18

Family

ID=45914489

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110369298 Active CN102412568B (en) 2011-11-18 2011-11-18 Method for adjusting line protection motion sequential solution breaker current delay zero crossing

Country Status (1)

Country Link
CN (1) CN102412568B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016066196A1 (en) * 2014-10-30 2016-05-06 Abb Technology Ltd Method in, apparatus for, and interface arrangement between an alternating current power system and a direct current power system
WO2017167744A1 (en) * 2016-04-01 2017-10-05 General Electric Technology Gmbh High voltage direct current switchgear

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106712307B (en) * 2017-03-23 2023-05-23 河北农业大学 Dynamic time delay sequential closing system and method for avoiding damage to circuit breaker by bias current
CN107482599A (en) * 2017-09-14 2017-12-15 南京南瑞继保电气有限公司 Suppress the breaker control method of DC bias current during a kind of line no-load switching
EP3985708A1 (en) * 2020-10-16 2022-04-20 ABB Schweiz AG Current breaker device
CN112134284B (en) * 2020-10-21 2022-05-13 内蒙古电力(集团)有限责任公司内蒙古电力科学研究院分公司 500kV system air-coupled band high-impedance line direct-current bias suppression method

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5543597A (en) * 1993-04-20 1996-08-06 Hitachi, Ltd. Grounding switch gear device
CN1588729A (en) * 2004-10-14 2005-03-02 南京南瑞继保电气有限公司 Re-switch on method for electric tansmission device

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US5543597A (en) * 1993-04-20 1996-08-06 Hitachi, Ltd. Grounding switch gear device
CN1588729A (en) * 2004-10-14 2005-03-02 南京南瑞继保电气有限公司 Re-switch on method for electric tansmission device

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2016066196A1 (en) * 2014-10-30 2016-05-06 Abb Technology Ltd Method in, apparatus for, and interface arrangement between an alternating current power system and a direct current power system
US9812982B2 (en) 2014-10-30 2017-11-07 Abb Schweiz Ag Method in, apparatus for, and interface arrangement between an alternating current power system and a direct current power system
WO2017167744A1 (en) * 2016-04-01 2017-10-05 General Electric Technology Gmbh High voltage direct current switchgear

Also Published As

Publication number Publication date
CN102412568A (en) 2012-04-11

Similar Documents

Publication Publication Date Title
CN102412568B (en) Method for adjusting line protection motion sequential solution breaker current delay zero crossing
US10148080B2 (en) Single-phase-to-earth fault processing device and method for neutral non-effectively grounded distribution network
CN100580835C (en) Breaker synchronous controller and control method thereof
CN104037730A (en) Apparatus and method for inhibiting transformer zero load closing inrush currents
CN103746349A (en) Circuit breaker failure protection mechanism of transformer substation and optimal configuration method for circuit breaker protection
CN201549868U (en) Low-voltage switch intelligent controller
CN203278210U (en) Busbar residual voltage maintaining device
CN203574379U (en) Segregated-phase synchronized switching control device
CN107255774B (en) Line selection method based on trip and closing information of mistakenly selected line
CN112054491B (en) Unified power flow controller closing failure protection method and system based on current discrimination
CN202839447U (en) Intelligent vortex touch high-speed switch
CN102290805A (en) Electric arc grounding overvoltage limiting device applied to medium-voltage distribution system
CN109245068B (en) Neutral point grounding mode conversion device
CN202474870U (en) Intelligent switching device of 10kV reactive-load compensation equipment
CN104600722A (en) Intelligent zero-crossing switching device for high-voltage shunt capacitors
CN102545242A (en) Intelligent switching device for 10kV reactive power compensation equipment
CN209313424U (en) A kind of zero-sequence current protection circuit
CN101217078B (en) A permanent magnetic actuator vacuum circuit breaker assembly with series resistance
CN108448552B (en) ZLB current limiting device based on current judgment
CN201294378Y (en) Switch arc-extinguishing and over-voltage protection
CN112510820A (en) System for automatic splitting of distributed power supply under 10kV feeder line fault
CN105281628A (en) Phase selection control method aimed at zero-load transformer comprising primary side employing star ungrounded connection and calculating influence of residual magnetism of zero-load transformer
CN112186720B (en) High-speed short circuit current limiting device
CN213783271U (en) Switching-on inrush current control device of no-load transformer
CN211266460U (en) Phase selection breaking device and circuit breaker

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: STATE ELECTRIC NET CROP.

Effective date: 20130521

C41 Transfer of patent application or patent right or utility model
TA01 Transfer of patent application right

Effective date of registration: 20130521

Address after: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Applicant after: China Electric Power Research Institute

Applicant after: State Grid Corporation of China

Address before: 100192 Beijing city Haidian District Qinghe small Camp Road No. 15

Applicant before: China Electric Power Research Institute

C14 Grant of patent or utility model