CN102409623B - Floating bridge removing method - Google Patents

Floating bridge removing method Download PDF

Info

Publication number
CN102409623B
CN102409623B CN 201110260616 CN201110260616A CN102409623B CN 102409623 B CN102409623 B CN 102409623B CN 201110260616 CN201110260616 CN 201110260616 CN 201110260616 A CN201110260616 A CN 201110260616A CN 102409623 B CN102409623 B CN 102409623B
Authority
CN
China
Prior art keywords
barge
bridge
concrete
old bridge
open
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201110260616
Other languages
Chinese (zh)
Other versions
CN102409623A (en
Inventor
马科
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Communications Construction Investment Group Co ltd
Original Assignee
SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd filed Critical SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION CO Ltd
Priority to CN 201110260616 priority Critical patent/CN102409623B/en
Publication of CN102409623A publication Critical patent/CN102409623A/en
Application granted granted Critical
Publication of CN102409623B publication Critical patent/CN102409623B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a floating bridge removing method, which comprises the following steps of: 1, removing an old bridge surface; 2, preparing removal construction of a concrete truss of an old bridge; and 3, removing the concrete truss of the old bridge, namely making the bridge overhead through two barges for the first time, fixing a barge on the east side on a river bank on the east side so as to transversely move the old bridge to the upper part of a reinforced concrete foundation on the west side, filling water in a barge on the west side and sinking the barge. After the first movement is finished, the west end of the concrete truss is rolled through a steel roller on the concrete foundation and the east end of the concrete truss is supported by a barge bracket so as to move by hauling the barge until the barge is moved to the river bank, the barge sinks, the concrete truss is pulled to the river bank through a winch, and a crane assists in moving the bridge on the river bank. The method can be used for removing the old bridge, and because the concrete truss is removed by a barge and track combined monolithic translation method, the construction speed is high, navigation closure time is short, and influence of old bridge removal construction on normal operation of a navigation channel is reduced.

Description

Transportation by driving is torn the bridge method open
Technical field
The present invention relates to tear open bridge method.
Background technology
Tradition tears that the method speed of application of bridge is slow open, and the iceound time is long, and is bigger to the normal influence on system operation in navigation channel.The patent No. provides a kind of bridge crane gear of tearing open for 200720070714.5 Chinese utility model, comprise, at least two Bailey truss carrier bars, each root Bailey truss carrier bar comprises many row's Bailey truss, Bailey truss comprises the Bailey truss unit that multi-disc connects from beginning to end, connect by bracing frame between many row's Bailey truss, sleeper is placed on the upside of each Bailey truss carrier bar, many tracks, be laid on the sleeper abreast respectively, many dollies are settled in orbit respectively, can travel in orbit, the hoist engine brace summer, be placed on the dolly, and can move with dolly, and hoist engine, be arranged on the hoist engine brace summer, be used for hanging moving the bridge section of having cut.Adopt this equipment to carry out bridge and remove, can only carry out segmentation to bridge and remove, the engineering time is long.
Summary of the invention
Technical problem to be solved by this invention just provides a kind of transportation by driving and tears the bridge method open, and fast, the iceound time of speed of application is short, reduces the removal of old bridge construction to the influence of the normal operation in navigation channel.
For solving the problems of the technologies described above, the present invention adopts following technical scheme: transportation by driving is torn the bridge method open, it is characterized in that comprising the steps:
Phase I: the old bridge bridge floor is removed the construction stage, tears railing earlier open, cuts the bridge floor shop again, and span concrete beam plate in tearing open is then torn the end bay beam slab at last open;
Second stage: old bridge concrete truss is removed the preparation of construction stage, at old bridge west side excavation and along old bridge concrete truss longitudinal direction construction twice reinforced concrete base is arranged, basis end face pre-embedded steel slab, dragging track usefulness when steel plate is traversing as old bridge, simultaneously, two barges are in place, connect with wire rope between two barges, the freight house left and right sides of barge is set up in parallel two row steel roadbed guidance tapes, sets up shellfish thunder sheet on the described steel roadbed guidance tape, and described barge freight house also is provided with the pump drainage wetting system;
Phase III: old bridge concrete truss is removed, for the first time earlier with two barges with the crane span structure sky, barge draining come-up, keep concrete truss level, the east side barge is fixed on the riverbank, east side earlier, laterally westwards during side shifting, puts stationary rope at barge while moving, barge moves with electronic or bottle gouard moved by hands, make old bridge integral body laterally move to reinforced concrete base top, west side, reinforced concrete base is provided with the steel cylinder, after finishing, west side barge water-filling sinks, keep concrete truss level in this process, behind mobile end first, concrete truss west end is having the concrete basis to adopt the steel rollers roll, the east barge stent support, move with dilatory barge, move to the bank until barge, barge sinks, the concrete truss is pulled on the bank by hoist engine, and the bank adopts crane to assist moving bridge simultaneously.
As preferably, at first to existing road envelope road, in old bridge bottom and two on bridge safety guard net is set in the phase I, adopt air compressor machine manually to cut the old bridge member, tear railing earlier open, cut the bridge floor shop again; Span concrete beam plate in tearing open earlier then, after tear the end bay beam slab open, connecting reinforcement between beam slab and beam slab adopts gas cutting to cut off, get through the interior concrete of strand seam with pneumatic pick, to reduce constraint and the restraint forces between the beam slab, in the span beam slab earlier winches to the abutment position with small-sized bridge formation machine, hang on flat car with crane again and transport, and avris is striden beam slab and is directly hung on flat car with crane and transport.
As preferably, in the second stage, to make shellfish thunder sheet end face be higher than 0.2~0.3m at the bottom of the concrete truss after the barge come-up, to regulate by filling, arrange in the barge ballasting, barge is pressed 1.5 times of water-fillings of capacity value.
As preferably, the shellfish thunder sheet on each row steel roadbed guidance tape is arranged and is trapezoidal, is connected by channel-section steel between shellfish thunder sheet and fixing.
As preferably, be " X " shape connection and fixing by channel-section steel between shellfish thunder sheet on the described two row steel roadbed guidance tapes, and " X " top is connected and fixed by channel-section steel.
The present invention carries and tears bridge method open and can be used for removal of old bridge, because the concrete truss is removed the integral translation method that has adopted barge and track combination, speed of application is fast, and the iceound time is short, is conducive to reduce the removal of old bridge construction to the influence of the normal operation in navigation channel.
Description of drawings
Below in conjunction with the drawings and specific embodiments the present invention is further described:
Fig. 1 is the barge structure schematic diagram;
Fig. 2 is the barge vertical view;
Fig. 3 is preparation of construction schematic diagram during the stage;
Fig. 4 is old bridge concrete truss schematic diagram when traversing.
The specific embodiment
Specify the embodiment that transportation by driving is torn the bridge method open in conjunction with Fig. 1 to Fig. 4, comprise the steps:
Phase I: the old bridge bridge floor is removed the construction stage, tears railing earlier open, cuts the bridge floor shop again, and span concrete beam plate in tearing open is then torn the end bay beam slab at last open; Detailed process to existing road envelope road, arranges safety guard net in old bridge bottom and two on bridge at first, adopts air compressor machine manually to cut the old bridge member, tears railing earlier open, cuts the bridge floor shop again; Span concrete beam plate in tearing open earlier then, after tear the end bay beam slab open, connecting reinforcement between beam slab and beam slab adopts gas cutting to cut off, get through the interior concrete of strand seam with pneumatic pick, to reduce constraint and the restraint forces between the beam slab, in the span beam slab earlier winches to the abutment position with small-sized bridge formation machine, hang on flat car with crane again and transport, and avris is striden beam slab and is directly hung on flat car with crane and transport.
Second stage: old bridge concrete truss is removed the preparation of construction stage, at old bridge west side excavation and along old bridge concrete truss 5 longitudinal directions construction twice reinforced concrete base 7 is arranged, basis end face pre-embedded steel slab 8, dragging track usefulness when steel plate is traversing as old bridge, simultaneously, two barges 1 are in place, connect with wire rope 6 between two barges, freight house 11 left and right sides of barge are set up in parallel two row steel roadbed guidance tapes 2, set up shellfish thunder sheet 3 on the described steel roadbed guidance tape, and described barge freight house also is provided with the pump drainage wetting system;
Phase III: old bridge concrete truss is removed, for the first time earlier with two barges with the crane span structure sky, barge draining come-up, keep concrete truss 5 levels, the east side barge is fixed on the riverbank, east side earlier, laterally westwards during side shifting, puts stationary rope at barge while moving, barge moves with electronic or bottle gouard moved by hands, make old bridge integral body laterally move to reinforced concrete base top, west side, reinforced concrete base is provided with steel cylinder 9, after finishing, west side barge water-filling sinks, keep concrete truss level in this process, behind mobile end first, concrete truss west end is having the concrete basis to adopt the steel rollers roll, the east barge stent support, move with dilatory barge, move to the bank until barge, barge sinks, the concrete truss is pulled on the bank by hoist engine, and the bank adopts crane to assist moving bridge simultaneously.
In the second stage, will make shellfish thunder sheet end face be higher than 0.2~0.3m at the bottom of the concrete truss after the barge come-up, regulate by filling, arrange in the barge ballasting, barge is pressed 1.5 times of water-fillings of capacity value.
In addition, shellfish thunder sheet on each row steel roadbed guidance tape is arranged and is trapezoidal, is connected by channel-section steel 4 between shellfish thunder sheet and fixing.Be " X " shape connection and fixing by channel-section steel between shellfish thunder sheet on the described two row steel roadbed guidance tapes, and " X " top is connected and fixed by channel-section steel.

Claims (5)

1. transportation by driving is torn the bridge method open, it is characterized in that comprising the steps:
Phase I: the old bridge bridge floor is removed the construction stage, tears railing earlier open, cuts the bridge floor shop again, and span concrete beam plate in tearing open is then torn the end bay beam slab at last open;
Second stage: old bridge concrete truss is removed the preparation of construction stage, at old bridge west side excavation and along old bridge concrete truss (5) longitudinal direction construction twice reinforced concrete bases (7) are arranged, basis end face pre-embedded steel slab (8), dragging track was used when steel plate was traversing as old bridge, simultaneously, two barges (1) are in place, connect with wire rope (6) between two barges, the freight house of barge (11) left and right sides is set up in parallel two row steel roadbed guidance tapes (2), set up shellfish thunder sheet (3) on the described steel roadbed guidance tape, described barge freight house also is provided with the pump drainage wetting system;
Phase III: old bridge concrete truss is removed, for the first time earlier with two barges with the crane span structure sky, barge draining come-up, keep concrete truss (5) level, the east side barge is fixed on the riverbank, east side earlier, laterally westwards during side shifting, puts stationary rope at barge while moving, barge moves with electronic or bottle gouard moved by hands, make old bridge integral body laterally move to reinforced concrete base top, west side, reinforced concrete base is provided with steel cylinder (9), after finishing, west side barge water-filling sinks, keep concrete truss level in this process, behind mobile end first, concrete truss west end is having the concrete basis to adopt the steel rollers roll, the east barge stent support, move with dilatory barge, move to the bank until barge, barge sinks, the concrete truss is pulled on the bank by hoist engine, and the bank adopts crane to assist moving bridge simultaneously.
2. transportation by driving according to claim 1 is torn the bridge method open, it is characterized in that: at first to existing road envelope road, in old bridge bottom and two on bridge safety guard net is set in the phase I, adopts air compressor machine manually to cut the old bridge member, tear railing earlier open, cut the bridge floor shop again; Span concrete beam plate in tearing open earlier then, after tear the end bay beam slab open, connecting reinforcement between beam slab and beam slab adopts gas cutting to cut off, get through the interior concrete of strand seam with pneumatic pick, to reduce constraint and the restraint forces between the beam slab, in the span beam slab earlier winches to the abutment position with small-sized bridge formation machine, hang on flat car with crane again and transport, and avris is striden beam slab and is directly hung on flat car with crane and transport.
3. transportation by driving according to claim 2 is torn the bridge method open, it is characterized in that: in the phase III, will make shellfish thunder sheet end face be higher than 0.2~0.3m at the bottom of the concrete truss after the barge come-up, regulate by filling, arrange in the barge ballasting, barge is pressed 1.5 times of water-fillings of capacity value.
4. transportation by driving according to claim 3 is torn the bridge method open, it is characterized in that: shellfish thunder sheet on each row steel roadbed guidance tape is arranged and is trapezoidal, is connected by channel-section steel (4) between shellfish thunder sheet and fixing.
5. transportation by driving according to claim 4 is torn the bridge method open, it is characterized in that: be " X " shape connection and fixing by channel-section steel between shellfish thunder sheet on the described two row steel roadbed guidance tapes, and " X " top is connected and fixed by channel-section steel.
CN 201110260616 2011-09-05 2011-09-05 Floating bridge removing method Expired - Fee Related CN102409623B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110260616 CN102409623B (en) 2011-09-05 2011-09-05 Floating bridge removing method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110260616 CN102409623B (en) 2011-09-05 2011-09-05 Floating bridge removing method

Publications (2)

Publication Number Publication Date
CN102409623A CN102409623A (en) 2012-04-11
CN102409623B true CN102409623B (en) 2013-09-04

Family

ID=45911944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110260616 Expired - Fee Related CN102409623B (en) 2011-09-05 2011-09-05 Floating bridge removing method

Country Status (1)

Country Link
CN (1) CN102409623B (en)

Families Citing this family (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106758888A (en) * 2016-12-02 2017-05-31 中铁上海工程局集团有限公司 A kind of quick method for dismounting for multispan concrete arch-type bridge waterborne
CN107489100A (en) * 2017-08-03 2017-12-19 中铁上海工程局集团有限公司 A kind of long sleeper rail of girder steel open bridge floors synthetic resin and its construction method
CN114032794A (en) * 2021-11-24 2022-02-11 中天交通建设投资集团有限公司 Integral demolition construction process for large-span truss concrete bridge

Family Cites Families (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH10280328A (en) * 1997-04-01 1998-10-20 Nkk Corp Removal and erection method for bridge and pontoon equipment used to the method
JP4308896B2 (en) * 2000-02-18 2009-08-05 ナガタ工業株式会社 Removal method of bridge deck
JP4167149B2 (en) * 2003-08-25 2008-10-15 財団法人鉄道総合技術研究所 Construction method of abutment accompanying bridge reconstruction
JP4727504B2 (en) * 2006-06-01 2011-07-20 三菱重工鉄構エンジニアリング株式会社 Bridge removal method
CN101892632B (en) * 2009-05-19 2012-05-30 上海市基础工程有限公司 Construction method of structural system of river under no-cutoff working condition

Also Published As

Publication number Publication date
CN102409623A (en) 2012-04-11

Similar Documents

Publication Publication Date Title
CN106978784B (en) A kind of Long span highway suspension bridge Demolition Construction method
CN100547225C (en) A kind of tunnel overhead arch mould plate trolley with floating type traffic under carriage
CN104480868B (en) On tear beam method open across the highway bridge of railway in operation
CN201003145Y (en) Upward and self-walking type mobile die carrier
CN108532465A (en) A kind of construction method of Through Steel case arch bridge
CN102650118B (en) Construction device and method for erecting prefabricated beam by slip method
CN107747282B (en) On across both wired old bridge overall pulling down methods
CN105839537B (en) Construction method for hoisting stiffening girder of suspension bridge by adopting girdle-carrying traveling of deck erection gantry
CN2793147Y (en) Steel box suspension beam for multi-span suspension bridge
CN204282185U (en) A kind of armful rail magnetic levitation track traffic bridge
CN106120787A (en) A kind of construction method carrying out pile sinking based on pushing tow travelling platform
CN101831888A (en) 1200 tonner water conservancy aqueduct transportation and erection equipment
CN104594173A (en) Rail holding type electromagnetic suspension track traffic box girder
CN102409623B (en) Floating bridge removing method
CN105544409B (en) Double guide beam bridge erecting machine sets up combination beam and now spells a section girder steel construction technology
CN2921280Y (en) Tunnel invert form trolley with floating running chassis
CN102286931B (en) Deck moving support system (MSS) bridge fabrication machine specially for construction of double-T-shaped bridge
CN113585080A (en) Steel box girder lifting and transporting frame system and construction method thereof
CN112323657A (en) Integrated prefabricated bridge dismantling machine and prefabricated bridge dismantling method
CN105019357A (en) Method for mounting specially-shaped precast bridge decks on open lattice steel beams of arched bridge
CN106400700A (en) Double-line cantilever type bridge formation machine
CN102071641A (en) Integral bridge girder erection machine of distributed landing leg type transportation rack of concrete beam packing bridge crane and bridge girder erection engineering method thereof
CN108004930A (en) The construction method of vertical shift bowstring arch bridge
CN110344334A (en) Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector
CN206128095U (en) A air bag launching device that is used for steel cofferdam of large -scale no end

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20200117

Address after: 441000 No.18, Chunyuan East Road, Fancheng District, Xiangyang City, Hubei Province

Patentee after: Zhongtian Communications Construction Investment Group Co.,Ltd.

Address before: 261400 No. 29 North Haiyang Road, Zhifu District, Shandong, Yantai

Patentee before: SHANDONG ZHONGHONG ROAD AND BRIDGE CONSTRUCTION Co.,Ltd.

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130904

Termination date: 20210905