CN102400558B - 苯加氢钢结构安装工程中工艺钢平台钢柱安装方法 - Google Patents
苯加氢钢结构安装工程中工艺钢平台钢柱安装方法 Download PDFInfo
- Publication number
- CN102400558B CN102400558B CN201010279866.2A CN201010279866A CN102400558B CN 102400558 B CN102400558 B CN 102400558B CN 201010279866 A CN201010279866 A CN 201010279866A CN 102400558 B CN102400558 B CN 102400558B
- Authority
- CN
- China
- Prior art keywords
- steel
- platform
- steel column
- column
- girder
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
- Bridges Or Land Bridges (AREA)
- Rod-Shaped Construction Members (AREA)
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
一种苯加氢钢结构安装工程中工艺钢平台钢柱安装方法,其特征在于包括以下步骤:a、吊装钢柱,b、校正钢柱,c、测控多层钢框架安装中的钢柱,d、安装多层工艺钢平台钢梁,e、连接钢柱与框架梁腹板和翼缘,f、安装次梁和平台铺板。本发明的苯加氢钢结构安装工程中工艺钢平台钢柱安装方法具有制作步骤设计合理、操作简单,工程质量安全可靠和降低工程成本的优点。
Description
技术领域
本发明涉及一种主体框架钢结构安装方法,具体地说,是一种苯加氢钢结构安装工程中工艺钢平台钢柱安装方法。
背景技术
苯加氢装置的工艺较特殊,其***复杂,设备多,***本身压力、温度较高,泵设备不允许空转。苯加氢工程主要分为中心控制室及变电所、精制装置、给排水工程、空压站、储运设施(罐区及泵房)、全厂供电及全厂照明、火炬和工程的附属设施,在这些设施的电气安装中有防雷、防火、防爆的特殊要求,其中主体框架钢结构安装是整个电气安装***中的重要环节。目前国内已建或在建苯加氢钢结构安装工程中工艺钢平台钢柱安装尚处于不规范阶段,存在着很多不科学、不合理的地方,制作过程繁杂、制作费用高。
因此已知的苯加氢钢结构安装工程中工艺钢平台钢柱安装方法存在着上述种种不便和问题。
发明内容
本发明的目的,在于提出一种安全可靠的苯加氢钢结构安装工程中工艺钢平台钢柱安装方法。
为实现上述目的,本发明的技术解决方案是:
一种苯加氢钢结构安装工程中工艺钢平台钢柱安装方法,其特征在于包括以下步骤:
a、吊装钢柱,所述钢柱为型钢柱,第一段钢柱吊装就位用地脚螺栓固定,第二段及以上钢柱先装1/2普通螺栓固定,用腹板连接板夹紧,耳板用普通螺栓固定,钢柱调整完毕后再换高强螺栓;
b、校正钢柱,钢柱就位后,使用吊车、钢锲和垫板先调整标高,再调整扭转,最后调整垂直度,形成框架后不再做整体校正;
c、测控多层钢框架安装中的钢柱,多层钢框架安装精度的测控以测控钢柱为主,测控钢柱落位固定垂直度和柱顶轴线,考虑钢梁安装后,柱梁接头现场焊接收缩量,钢柱向外倾斜范围为(平台标高位置)1~2mm;
d、安装多层工艺钢平台钢梁,所述工艺钢平台钢梁为型钢;
e、连接钢柱与框架梁腹板和翼缘,钢柱与框架梁腹板用高强螺栓连接,钢柱与翼缘为焊接固定,施工次序为初拧高强螺栓,再进行焊接,最后终拧高强螺栓;
f、安装次梁和平台铺板,工艺钢平台的平台表面为网格板,安装、焊接次梁和平台铺板后交付土建施工砼平台。
本发明的苯加氢钢结构安装工程中工艺钢平台钢柱安装方法还可以采用以下的技术措施来进一步实现。
前述的方法,其中所述步骤d安装多层工艺钢平台钢梁,多层工艺钢平台钢梁的同一列柱框架梁先从中间跨开始安装,对称向两端扩展,在安装钢梁时,钢柱垂直度一般不会发生变化,用经纬仪跟踪观测;若钢柱垂直度超差,应复查钢梁尺寸且进行必要的处理。
前述的方法,其中所述步骤d安装多层工艺钢平台钢梁,多层工艺钢平台钢梁的同一层平台框架梁吊装就位、复测垂直度、钢梁标高符合质量要求后,用高强螺栓连接、固定钢柱与钢柱、钢柱与平台框架梁腹板。
采用上述技术方案后,本发明的苯加氢钢结构安装工程中工艺钢平台钢柱安装方法具有以下优点:
1、制作步骤设计合理、操作简单;
2、工程质量安全可靠;
3、降低工程成本。
具体实施方式
以下通过具体实施例进一步说明本发明。
实施例1
一种苯加氢钢结构安装工程中工艺钢平台钢柱安装方法,其特征在于包括以下步骤:
a、吊装钢柱,所述钢柱为型钢柱,第一段钢柱吊装就位用地脚螺栓固定,第二段及以上钢柱先装1/2普通螺栓固定,用腹板连接板夹紧,耳板用普通螺栓固定,钢柱调整完毕后再换高强螺栓;
b、校正钢柱,钢柱就位后,使用吊车、钢锲和垫板先调整标高,再调整扭转,最后调整垂直度,形成框架后不再做整体校正;
c、测控多层钢框架安装中的钢柱,多层钢框架安装精度的测控以测控钢柱为主,测控钢柱落位固定垂直度和柱顶轴线,考虑钢梁安装后,柱梁接头现场焊接收缩量,钢柱向外倾斜范围为(平台标高位置)1~2mm;
d、安装多层工艺钢平台钢梁,所述工艺钢平台钢梁为型钢;所述多层工艺钢平台钢梁的同一列柱框架梁先从中间跨开始安装,对称向两端扩展,在安装钢梁时,钢柱垂直度一般不会发生变化,用经纬仪跟踪观测;若钢柱垂直度超差,应复查钢梁尺寸且进行必要的处理;所述多层工艺钢平台钢梁的同一层平台框架梁吊装就位、复测垂直度、钢梁标高符合质量要求后,用高强螺栓连接、固定钢柱与钢柱、钢柱与平台框架梁腹板;
e、连接钢柱与框架梁腹板和翼缘,钢柱与框架梁腹板用高强螺栓连接,钢柱与翼缘为焊接固定,施工次序为初拧高强螺栓,再进行焊接,最后终拧高强螺栓;
f、安装次梁和平台铺板,工艺钢平台的平台表面为网格板,安装、焊接次梁和平台铺板后交付土建施工砼平台。
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变化。因此,所有等同的技术方案也应该属于本发明的范畴,应由各权利要求限定。
Claims (3)
1.一种苯加氢钢结构安装工程中工艺钢平台钢柱安装方法,其特征在于包括以下步骤:
a、吊装钢柱,所述钢柱为型钢柱,第一段钢柱吊装就位用地脚螺栓固定,第二段及以上钢柱先装1/2普通螺栓固定,用腹板连接板夹紧,耳板用普通螺栓固定,钢柱调整完毕后再换高强螺栓;
b、校正钢柱,钢柱就位后,使用吊车、钢锲和垫板先调整标高,再调整扭转,最后调整垂直度,形成框架后不再做整体校正;
c、测控多层钢框架安装中的钢柱,多层钢框架安装精度的测控以测控钢柱为主,测控钢柱落位固定垂直度和柱顶轴线,钢柱向外倾斜范围为1~2mm;
d、安装多层工艺钢平台钢梁,所述工艺钢平台钢梁为型钢;
e、连接钢柱与框架梁腹板和翼缘,钢柱与框架梁腹板用高强螺栓连接,钢柱与翼缘为焊接固定,施工次序为初拧高强螺栓,再进行焊接,最后终拧高强螺栓;
f、安装次梁和平台铺板,工艺钢平台的平台表面为网格板,安装、焊接次梁和平台铺板后交付土建施工砼平台。
2.如权利要求1所述的苯加氢钢结构安装工程中工艺钢平台钢柱安装方法,其特征在于,所述步骤d安装多层工艺钢平台钢梁,多层工艺钢平台钢梁的同一列柱框架梁先从中间跨开始安装,对称向两端扩展,用经纬仪跟踪观测;若钢柱垂直度超差,应复查钢梁尺寸。
3.如权利要求1所述的苯加氢钢结构安装工程中工艺钢平台钢柱安装方法,其特征在于,所述步骤d安装多层工艺钢平台钢梁,多层工艺钢平台钢梁的同一层平台框架梁吊装就位、复测垂直度、钢梁标高符合质量要求后,用高强螺栓连接固定钢柱与钢柱、钢柱与平台框架梁腹板。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010279866.2A CN102400558B (zh) | 2010-09-13 | 2010-09-13 | 苯加氢钢结构安装工程中工艺钢平台钢柱安装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010279866.2A CN102400558B (zh) | 2010-09-13 | 2010-09-13 | 苯加氢钢结构安装工程中工艺钢平台钢柱安装方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102400558A CN102400558A (zh) | 2012-04-04 |
CN102400558B true CN102400558B (zh) | 2016-01-27 |
Family
ID=45883167
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201010279866.2A Active CN102400558B (zh) | 2010-09-13 | 2010-09-13 | 苯加氢钢结构安装工程中工艺钢平台钢柱安装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102400558B (zh) |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN105569351A (zh) * | 2015-12-20 | 2016-05-11 | 安徽伟宏钢结构集团股份有限公司 | 一种钢结构钢柱的安装施工工艺 |
CN105672667A (zh) * | 2016-04-12 | 2016-06-15 | 中交一航局安装工程有限公司 | 电煤码头筛分***安装工艺 |
CN106193625B (zh) * | 2016-07-15 | 2018-05-04 | 沈阳建筑大学 | 一种圆石柱的运输及吊装方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201128956Y (zh) * | 2007-09-30 | 2008-10-08 | 贵州喀斯特钢结构有限公司 | 装配整体式平板型或曲面型钢空腹网格结构 |
CN101691787A (zh) * | 2009-09-22 | 2010-04-07 | 中铁十二局集团建筑安装工程有限公司 | 中高层钢结构建筑逆向施工工艺 |
JP2010121286A (ja) * | 2008-11-17 | 2010-06-03 | Tekken Constr Co Ltd | 鉄骨構造物の建方工法 |
-
2010
- 2010-09-13 CN CN201010279866.2A patent/CN102400558B/zh active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201128956Y (zh) * | 2007-09-30 | 2008-10-08 | 贵州喀斯特钢结构有限公司 | 装配整体式平板型或曲面型钢空腹网格结构 |
JP2010121286A (ja) * | 2008-11-17 | 2010-06-03 | Tekken Constr Co Ltd | 鉄骨構造物の建方工法 |
CN101691787A (zh) * | 2009-09-22 | 2010-04-07 | 中铁十二局集团建筑安装工程有限公司 | 中高层钢结构建筑逆向施工工艺 |
Non-Patent Citations (2)
Title |
---|
高层建筑结构工程施工技术分析与探讨;杜欣双;《价值工程》;20100808(第22期);第75页 * |
高层建筑钢结构安装关键技术研究;李恩平等;《青岛理工大学学报》;20090615;第30卷(第3期);第151-154页"3关键工序施工技术及质量控制措施"部分 * |
Also Published As
Publication number | Publication date |
---|---|
CN102400558A (zh) | 2012-04-04 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US20190257094A1 (en) | Building based on large-space structure and freestanding external envelope as well as construction method | |
CN103291076B (zh) | 弧形框架内多层次钢桁架分片逆向吊装施工方法 | |
CN102400559A (zh) | 苯加氢工程主体框架钢结构安装中钢柱校正方法 | |
CN103982038B (zh) | 一种用于太阳能独立住宅模块化快速组装施工方法 | |
CN105019573A (zh) | 一种具有保温功能的预制外墙模板结构体系及其施工方法 | |
CN204040464U (zh) | 一种楼板模板支承结构 | |
CN203961276U (zh) | 高层建筑施工钢模板及操作架整体提升平台装置 | |
CN107227870B (zh) | 一种由预制构件拼接的变电站建筑 | |
CN202810173U (zh) | 核电站钢衬里牛腿及环吊轨道梁安装施工平台 | |
CN102400558B (zh) | 苯加氢钢结构安装工程中工艺钢平台钢柱安装方法 | |
CN103615047B (zh) | 凌空安装采光顶钢桁架和幕墙的方法 | |
CN108049666A (zh) | 一种超大平面多层钢桁架电子厂房钢结构的梯次安装方法 | |
CN106930527A (zh) | 三维仿真型钢复合悬挑支模高空大跨度预应力梁施工工艺 | |
CN203471133U (zh) | 钢筋桁架生产线用焊接装置 | |
CN203441069U (zh) | 外墙悬空可翻转工作平台 | |
CN202577580U (zh) | 一种多层大跨度装配整体式空间钢网格建筑结构 | |
CN102465601B (zh) | 苯加氢工程主体框架钢结构安装方法 | |
CN105625732A (zh) | 超高悬挑钢结构桁架无支撑施工方法 | |
CN102758525A (zh) | 苯加氢工程模板安装方法 | |
CN102287050B (zh) | 大跨度钢混屋架施工方法 | |
CN201411926Y (zh) | 弧形梁起重结构 | |
CN203755670U (zh) | 悬挑消防连廊支撑结构 | |
CN101603342B (zh) | 钢构保温防水倒置式上人屋面的施工工法 | |
CN103362222B (zh) | 一种带栓接埋件的sp预应力空心板 | |
CN111851789A (zh) | 一种新型装配式劲性墙及施工工艺 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |