CN102383398A - 一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺 - Google Patents

一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺 Download PDF

Info

Publication number
CN102383398A
CN102383398A CN2011103013423A CN201110301342A CN102383398A CN 102383398 A CN102383398 A CN 102383398A CN 2011103013423 A CN2011103013423 A CN 2011103013423A CN 201110301342 A CN201110301342 A CN 201110301342A CN 102383398 A CN102383398 A CN 102383398A
Authority
CN
China
Prior art keywords
exhaust
grouting
ductor
seam
responsible
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011103013423A
Other languages
English (en)
Inventor
蔡云鹏
程俊在
姚栓喜
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
NORTHWEST HYDRO CONSULTING ENGINEERS CHECC
Original Assignee
NORTHWEST HYDRO CONSULTING ENGINEERS CHECC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by NORTHWEST HYDRO CONSULTING ENGINEERS CHECC filed Critical NORTHWEST HYDRO CONSULTING ENGINEERS CHECC
Priority to CN2011103013423A priority Critical patent/CN102383398A/zh
Publication of CN102383398A publication Critical patent/CN102383398A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

本发明涉及一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺,其特征在于:包括排气主管、排气孔、诱导板、排气支管、缩颈弯头)和诱导缝;所述排气主管与排气支管用缩颈弯头连接形成排气***,所述排气主管为等间距造有多组排气孔的直径2英寸的连续镀锌钢管;排气主管和诱导板均设置于诱导缝所在位置,诱导板对称布置于诱导缝两侧,排气主管布设于诱导板中心;排气主管等间隔设置有多组水平向对穿的排气孔,排气孔的位置与诱导板的布设位置相对应,每组排气孔孔间距累计长度小于单块诱导板长度。它可有效地防止在施工过程中扰动造成的碾压混凝土坝排气管路***的堵塞,减少后期接缝灌浆管路堵塞处理工作量,利于保证接缝灌浆质量。

Description

一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺
技术领域
本发明涉及一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺。
背景技术
碾压混凝土坝按温控或结构要求通常需要设置横缝,有的还需设纵缝,缝面通常靠预埋诱导板等方法形成。如果要求坝体整体受力,尤其是拱坝,则必须进行缝面接缝灌浆,才能更好的保证大坝及电站安全运行,接缝灌浆***管路布置由进回浆***和排气***组成。
目前水利水电工程碾压混凝土坝接缝灌浆排气有不同的设计及施工技术,由于碾压混凝土施工对各种管路及预埋件的扰动及其它因素的影响,排气***经常被堵塞,易造成后期接缝灌浆施工中灌区不通,则需要通过从坝外钻孔等其它处理措施进行补救,既带来不便又影响灌浆质量。
发明内容
本发明要解决的技术问题是提供一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺,以克服现有技术中存在的排气***易堵塞缺陷。
本发明的技术方案为:一种碾压混凝土坝诱导缝接缝灌浆排气***,其特征在于:包括排气主管、排气孔、诱导板、排气支管、缩颈弯头)和诱导缝;所述排气主管与排气支管用缩颈弯头连接形成排气***,所述排气主管为等间距造有多组排气孔的直径2英寸的连续镀锌钢管;排气主管和诱导板均设置于诱导缝所在位置,诱导板对称布置于诱导缝两侧,排气主管布设于诱导板中心;排气主管等间隔设置有多组水平向对穿的排气孔,排气孔的位置与诱导板的布设位置相对应,每组排气孔孔间距累计长度小于单块诱导板长度。
碾压混凝土坝诱导缝接缝灌浆排气***的施工工艺,其特征在于,包括如下步骤:
1] 按诱导缝的缝长确定排气主管和排气支管合适的长度;
2] 在排气主管上按诱导板的布设间距要求完成排气孔造孔;
3] 碾压混凝土坝施工至接缝灌浆灌区顶部排气高程时,在诱导缝处布设诱导板和安装已造孔的排气主管,安装时要求每组排气孔与诱导板位置相对应且排气孔在水平向一一对应;
4] 安装排气支管,用缩颈弯头将排气主管两端与排气支管连接,形成排气***;
5] 排气管路***安装结束检查合格后碾压混凝土坝继续施工,到满足允许接缝灌浆施工的条件后,接缝灌浆正常施工。
本发明的技术效果为:
施工简便可行,易操作,可靠性高。首先由于采用了连续的排气主管,并且主管有两侧的诱导板保护,可避免受碾压混凝土施工中剧烈扰动产生错位、变形等影响,保证了管路的整体连续性;其次设置的每组排气孔位置与诱导板布设位置一一对应,并且要求排气孔为水平对穿造孔,每组孔孔间距累计长度小于单块诱导板长度,在施工中可防止碾压混凝土料渣块落入排气孔堵塞排气主管,保证了管路的畅通。由此可有效地防止在施工过程中扰动造成的碾压混凝土坝排气管路***的堵塞,减少后期接缝灌浆管路堵塞处理工作量,利于保证接缝灌浆质量。
附图说明
下面结合实施例附图对本发明做进一步说明:
图1是诱导缝灌区布置图示意图;
图2是诱导缝灌区横剖面图示意图;
图3是排气管造孔纵剖面构造示意图;
图4是排气管造孔横剖面构造示意图。
附图标记如下:
1.排气主管、2.排气孔、3.诱导板、4.排气支管、5.缩颈弯头、6.诱导缝。
具体实施方式
本发明涉及水利水电工程中的一种新型碾压混凝土坝诱导缝接缝灌浆排气技术—排气管造孔排气技术。
本发明所涉及的碾压混凝土坝诱导缝接缝灌浆排气***,包括排气主管1、排气孔2、诱导板3、排气支管4、缩颈弯头5和诱导缝6;排气主管1与排气支管4用缩颈弯头5连接形成排气***,排气主管1为等间距造有排气孔2的直径2英寸的连续镀锌钢管;
排气主管1采用连续钢管,两侧设诱导板3,可起到固定和保护作用,避免碾压混凝土施工时排气管路受碾压混凝土施工中剧烈扰动产生错位、变形等影响,保证了排气管路***的整体连续性,排气主管1和诱导板3均设置于诱导缝6所在位置,其中诱导板3对称布置于诱导缝6两侧;直径2英寸的连续排气主管1上等间隔设置的多组水平向对穿的排气孔2,利于有效排气;排气孔2的位置与诱导板3的布设位置相对应,每块诱导板3所对应的排气孔2孔间距累计长度小于单块诱导板3长度,以使排气孔受到保护,在施工中可防止碾压混凝土料渣块落入排气孔堵塞排气主管,保证管路的畅通。
本发明所涉及的一种建造上述碾压混凝土坝诱导缝接缝灌浆排气***的施工工艺,包括如下步骤:
1] 按诱导缝6的缝长确定排气主管1和排气支管4合适的长度;
2] 在排气主管1上按诱导板3的布设间距要求完成排气孔2造孔;
3] 碾压混凝土坝施工至接缝灌浆灌区顶部排气高程时,在诱导缝6处布设诱导板3和安装已造孔的排气主管1,安装时要求每组排气孔2与诱导板位置相对应且排气孔在水平向一一对应;
4] 安装排气支管4,用缩颈弯头5将排气主管1两端与排气支管4连接,形成排气***;
5] 排气管路***安装结束检查合格后碾压混凝土坝继续施工,到满足允许接缝灌浆施工的条件后,接缝灌浆正常施工。
参见图1至4,本发明中,排气主管1采用连续钢管并按设计诱导缝位置,沿诱导缝6及两侧诱导板3的中心线布设,使排气主管连续而畅通,管路***受到了保护,避免受碾压混凝土施工扰动错动变形;排气孔2设置于排气主管1上,等间隔打多组水平向对穿的排气孔2,且与诱导板3的布设位置相对应,每组孔孔间距累计长度小于单块诱导板3长度,各组孔之间的间隔依据诱导板间距确定,使得排气孔2受到保护,避免碾压混凝土施工时的扰动和混凝土料渣块落入排气孔堵塞主管。形成了连续、畅通的排气***,畅通的排气***保证接缝灌浆施工时能正常排气,保证接缝灌浆施工质量,从而实现本发明的目的。

Claims (2)

1.一种碾压混凝土坝诱导缝接缝灌浆排气***,其特征在于:包括排气主管(1)、排气孔(2)、诱导板(3)、排气支管(4)、缩颈弯头(5)和诱导缝(6);所述排气主管(1)与排气支管(4)用缩颈弯头(5)连接形成排气***,所述排气主管(1)为等间距造有多组排气孔(2)的直径2英寸的连续镀锌钢管;排气主管(1)和诱导板(3)均设置于诱导缝(6)所在位置,诱导板(3)对称布置于诱导缝(6)两侧,排气主管(1)布设于诱导板(3)中心;排气主管(1)等间隔设置有多组水平向对穿的排气孔(2),排气孔(2)的位置与诱导板(3)的布设位置相对应,每组排气孔孔间距累计长度小于单块诱导板(3)长度。
2.一种建造如权利要求1所述碾压混凝土坝诱导缝接缝灌浆排气***的施工工艺,其特征在于,包括如下步骤:
1] 按诱导缝(6)的缝长确定排气主管(1)和排气支管(4)合适的长度;
2] 在排气主管(1)上按诱导板(3)的布设间距要求完成排气孔(2)造孔;
3] 碾压混凝土坝施工至接缝灌浆灌区顶部排气高程时,在诱导缝(6)处布设诱导板(3)和安装已造孔的排气主管(1),安装时要求每组排气孔(2)与诱导板位置相对应且排气孔在水平向一一对应;
4] 安装排气支管(4),用缩颈弯头(5)将排气主管(1)两端与排气支管(4)连接,形成排气***;
5] 排气管路***安装结束检查合格后碾压混凝土坝继续施工,到满足允许接缝灌浆施工的条件后,接缝灌浆正常施工。
CN2011103013423A 2011-10-09 2011-10-09 一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺 Pending CN102383398A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011103013423A CN102383398A (zh) 2011-10-09 2011-10-09 一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011103013423A CN102383398A (zh) 2011-10-09 2011-10-09 一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺

Publications (1)

Publication Number Publication Date
CN102383398A true CN102383398A (zh) 2012-03-21

Family

ID=45823199

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011103013423A Pending CN102383398A (zh) 2011-10-09 2011-10-09 一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺

Country Status (1)

Country Link
CN (1) CN102383398A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677676A (zh) * 2012-06-04 2012-09-19 中国水电顾问集团西北勘测设计研究院 常态混凝土拱坝接缝灌浆槽管结合排气技术
CN103290808A (zh) * 2012-08-31 2013-09-11 中国长江三峡集团公司 接缝灌浆***中排气槽封口的改进新方法
CN106192899A (zh) * 2016-08-11 2016-12-07 中国电建集团贵阳勘测设计研究院有限公司 一种拱坝诱导缝内诱导块的布置方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1535925A1 (ru) * 1988-02-17 1990-01-15 Ленинградское отделение Всесоюзного проектно-изыскательского и научно-исследовательского института "Гидропроект" им.С.Я.Жука Способ формировани деформационных швов центральной части плотины
EP0412913A1 (fr) * 1989-08-11 1991-02-13 Lafarge Nouveaux Materiaux Coulis d'injection pour la consolidation de structures fissurées
CN102108692A (zh) * 2011-01-04 2011-06-29 中国水电顾问集团中南勘测设计研究院 碾压混凝土坝及其成缝方法
CN201908307U (zh) * 2010-12-08 2011-07-27 中国水电顾问集团成都勘测设计研究院 接缝灌浆***
CN202265801U (zh) * 2011-10-09 2012-06-06 中国水电顾问集团西北勘测设计研究院 一种碾压混凝土坝诱导缝接缝灌浆排气***

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU1535925A1 (ru) * 1988-02-17 1990-01-15 Ленинградское отделение Всесоюзного проектно-изыскательского и научно-исследовательского института "Гидропроект" им.С.Я.Жука Способ формировани деформационных швов центральной части плотины
EP0412913A1 (fr) * 1989-08-11 1991-02-13 Lafarge Nouveaux Materiaux Coulis d'injection pour la consolidation de structures fissurées
CN201908307U (zh) * 2010-12-08 2011-07-27 中国水电顾问集团成都勘测设计研究院 接缝灌浆***
CN102108692A (zh) * 2011-01-04 2011-06-29 中国水电顾问集团中南勘测设计研究院 碾压混凝土坝及其成缝方法
CN202265801U (zh) * 2011-10-09 2012-06-06 中国水电顾问集团西北勘测设计研究院 一种碾压混凝土坝诱导缝接缝灌浆排气***

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
蔡云鹏: "蔺河口水电站碾压混凝土拱坝设计", 《水力发电》 *
郑丽红: "蔺河口碾压混凝土拱坝诱导缝重复灌浆施工技术", 《青海水力发电》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677676A (zh) * 2012-06-04 2012-09-19 中国水电顾问集团西北勘测设计研究院 常态混凝土拱坝接缝灌浆槽管结合排气技术
CN102677676B (zh) * 2012-06-04 2014-09-24 中国电建集团西北勘测设计研究院有限公司 常态混凝土拱坝接缝灌浆槽管结合排气方法
CN103290808A (zh) * 2012-08-31 2013-09-11 中国长江三峡集团公司 接缝灌浆***中排气槽封口的改进新方法
CN106192899A (zh) * 2016-08-11 2016-12-07 中国电建集团贵阳勘测设计研究院有限公司 一种拱坝诱导缝内诱导块的布置方法

Similar Documents

Publication Publication Date Title
CN111472358B (zh) 一种大体积混凝土基础内部冷却降温方法
CN102383398A (zh) 一种碾压混凝土坝诱导缝接缝灌浆排气***及施工工艺
CN103742723B (zh) 一种用于固定水下隧道内石油天然气管道的鞍式支座
CN104613233A (zh) 薄壁不锈钢管卡压式连接施工方法
CN202265801U (zh) 一种碾压混凝土坝诱导缝接缝灌浆排气***
CN102677676B (zh) 常态混凝土拱坝接缝灌浆槽管结合排气方法
CN107763372A (zh) 大截面圆形管道保温及外护板的安装施工方法
CN204884580U (zh) 一种安全壳钢结构底板支撑***
CN202220346U (zh) 地下室光纤上线间进线口止水防渗漏墙体
CN210686007U (zh) 一种单线隧道逐窗衬砌混凝土浇筑装置
CN210946894U (zh) 一种电力电缆排管工井
CN111472813A (zh) 一种超大跨度锚喷支护岩石隧道防排水体系及施工方法
CN210002728U (zh) 一种屋面侧排排气孔结构
CN104676185A (zh) 一种具有双重补偿功能的排气管道
CN204647550U (zh) 管道安装的旋转式穿管装置
CN110030005A (zh) 盾构隧道轻型保圆支撑体系及其施工方法
CN101852479B (zh) 管道的分段错序安装方法
CN205013862U (zh) 屋面管道安装支架
CN102877539B (zh) 型钢悬挂式污水管改线结构及其施工方法
CN103994277A (zh) 圆形顶管纠偏调节管
CN209654856U (zh) 一种机械复合管弹性敷设曲率半径限制装置
CN203856141U (zh) 一种屋面找坡层排气施工结构
CN202626994U (zh) 常态混凝土拱坝接缝灌浆槽管结合排气***
CN203703477U (zh) 一种具有双重补偿功能的排气管道
CN210370672U (zh) 一种隧道早强支护***

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120321

C53 Correction of patent of invention or patent application
CB02 Change of applicant information

Address after: 710065 Shaanxi Province, Xi'an City Road eight No. 18

Applicant after: POWERCHINA NORTHWEST ENGINEERING Co.,Ltd.

Address before: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Applicant before: NORTHWEST HYDRO CONSULTING ENGINEERS, CHECC

Address after: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Applicant after: NORTHWEST HYDRO CONSULTING ENGINEERS, CHECC

Address before: 710065 Shaanxi Province, Xi'an City Road eight No. 18 general survey and Design Institute of the Northwest Office

Applicant before: Northwest Hydro Consulting Engineers, CHECC

COR Change of bibliographic data

Free format text: CORRECT: APPLICANT; FROM: NORTHWEST HYDROELECTRIC INVESTIGATION + DESIGN INSTITUTE OF CHINA HYDROPOWER ENGINEERING CONSULTING TO: HYDROCHINA XIBEI ENGINEERING CORPORATION

Free format text: CORRECT: APPLICANT; FROM: HYDROCHINA XIBEI ENGINEERING CORPORATION TO: CHINA ELECTRIC POWER CONSTRUCTION GROUP NORTHWEST INVESTIGATION DESIGN + RESEARCH INSTITUTE CO., LTD.