CN102364833A - 一种大型发电机内外定子穿装方法 - Google Patents
一种大型发电机内外定子穿装方法 Download PDFInfo
- Publication number
- CN102364833A CN102364833A CN2011103373791A CN201110337379A CN102364833A CN 102364833 A CN102364833 A CN 102364833A CN 2011103373791 A CN2011103373791 A CN 2011103373791A CN 201110337379 A CN201110337379 A CN 201110337379A CN 102364833 A CN102364833 A CN 102364833A
- Authority
- CN
- China
- Prior art keywords
- stator
- guide rail
- insertion assembly
- external stator
- internal
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Manufacture Of Motors, Generators (AREA)
Abstract
本发明涉及一种大型发电机内外定子穿装方法,其特征在于,步骤为:水平放置外定子并固定,水平缓慢地拉动内定子,使内定子缓慢滑入外定子中,待内定子穿装到位后,通过千斤顶抬升内定子到需要的装配位置,最终将内定子上的弹簧板与外定子的相应支撑结构焊接固定完成整个穿装过程。本发明提供的穿装方法不受穿装工具最大承受重量的限制,穿装中用到的专用工具简单,穿装中无需校调内外定子圆周、同心等,且穿装过程简易,操控性好,穿装完成后整个定子无需翻身。
Description
技术领域
本发明涉及一种大型发电机的内定子与外定子之间的穿装方法。
背景技术
原有汽轮发电机内外定子穿装主要有两种方法:
第一种为内外定子竖直穿装。将发电机定子机座(即外定子)竖直放置于穿装工位上,用吊装工具吊起定子铁心(即内定子)至定子机座上方。待定子铁心稳定后,慢慢放下定子铁心同时调整好定子铁心与定子机座的圆周位置、同心度以及磁中心位置。穿装到位后将定子铁心上的弹簧板与定子机座的相应支撑结构焊接固定,最终完成内外定子穿装。此方法需要专用吊装工具,在穿装过程中需要时刻调整好定子铁心与定子机座的圆周位置、同心度等,且穿装完成后还需对整个定子进行一次翻身,需要另配专用翻身工具,对工具和行车最大吊重要求高。
第二种为内外定子水平穿装-外定子套入内定子。将发电机定子铁心(即内定子)水平放置于穿装工具上,调整定子铁心水平度,吊装定子机座(即外定子)水平缓慢地套入定子铁心,穿装到位后调整定子铁心与定子机座同心,并将定子铁心上的弹簧板与定子机座的相应支撑结构焊接固定,最终完成内外定子穿装。此方法限制于穿装工具的最大承受重量,对于大型发电机穿装具有局限性。
发明内容
本发明的目的是提供一种大型发电机内外定子穿装方法,使大型发电机穿装不受穿装工具等条件的限制,且穿装过程简易、操控性好。
为了达到上述目的,本发明的技术方案是提供了一种大型发电机内外定子穿装方法,其特征在于,步骤为:
步骤1、在内定子的底部及外定子内分别装入第一导轨及第二导轨,将外定子水平放置并固定,在外定子的一侧水平放置支撑架,支撑架紧靠外定子;
步骤2、将内定子架设在支撑架上,将钢丝绳的一端连接在内定子上,另一端穿过定滑轮,拉动钢丝绳使内定子水平缓慢移动,当内定子运动到内时,第一导轨落在第二导轨上,继续拉动钢丝绳,直至内定子穿装到位;
步骤3、通过千斤顶将内定子抬升到需要的装配位置,最后将内定子上的弹簧板与外定子的相应支撑结构焊接固定。
优选地,在所述第一导轨及所述第二导轨上分别涂有润滑剂。
优选地,所述第一导轨与所述第二导轨由不同材料制得。
本发明提供的穿装方法不受穿装工具最大承受重量的限制,穿装中用到的专用工具简单,穿装中无需校调内外定子圆周、同心等,且穿装过程简易,操控性好,穿装完成后整个定子无需翻身。
附图说明
图1为内定子移动过程中示意图;
图2为图1的A-A向剖视图;
图3为内定子到位后示意图。
具体实施方式
为使本发明更明显易懂,兹以一优选实施例,并配合附图作详细说明如下。
本发明提供的一种大型发电机内外定子穿装方法,步骤为:
步骤1、如图2所示,在内定子1的底部及外定子2内分别装入第一导轨6及第二导轨7,在第一导轨6及第二导轨7上分别涂有润滑剂8,第一导轨6与所述第二导轨7由不同材料制得。如图1所示,将外定子2水平放置并固定,在外定子2的一侧水平放置支撑架3,支撑架3紧靠外定子2;
步骤2、如图1所示,将内定子1架设在支撑架3上,将钢丝绳5的一端连接在内定子1上,另一端穿过定滑轮4,拉动钢丝绳5使内定子1水平缓慢移动,当内定子1运动到内时,第一导轨6落在第二导轨7上,继续拉动钢丝绳5,直至内定子1穿装到位;
步骤3、如图3所示,通过千斤顶9将内定子1抬升到需要的装配位置,最后将内定子1上的弹簧板与外定子2的相应支撑结构焊接固定。
Claims (3)
1.一种大型发电机内外定子穿装方法,其特征在于,步骤为:
步骤1、在内定子(1)的底部及外定子(2)内分别装入第一导轨(6)及第二导轨(7),将外定子(2)水平放置并固定,在外定子(2)的一侧水平放置支撑架(3),支撑架(3)紧靠外定子(2);
步骤2、将内定子(1)架设在支撑架(3)上,将钢丝绳(5)的一端连接在内定子(1)上,另一端穿过定滑轮(4),拉动钢丝绳(5)使内定子(1)水平缓慢移动,当内定子(1)运动到内时,第一导轨(6)落在第二导轨(7)上,继续拉动钢丝绳(5),直至内定子(1)穿装到位;
步骤3、通过千斤顶(9)将内定子(1)抬升到需要的装配位置,最后将内定子(1)上的弹簧板与外定子(2)的相应支撑结构焊接固定。
2.如权利要求1所述的一种大型发电机内外定子穿装方法,其特征在于:在所述第一导轨(6)及所述第二导轨(7)上分别涂有润滑剂(8)。
3.如权利要求1所述的一种大型发电机内外定子穿装方法,其特征在于:所述第一导轨(6)与所述第二导轨(7)由不同材料制得。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110337379 CN102364833B (zh) | 2011-10-31 | 2011-10-31 | 一种大型发电机内外定子穿装方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201110337379 CN102364833B (zh) | 2011-10-31 | 2011-10-31 | 一种大型发电机内外定子穿装方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN102364833A true CN102364833A (zh) | 2012-02-29 |
CN102364833B CN102364833B (zh) | 2013-03-06 |
Family
ID=45691387
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201110337379 Active CN102364833B (zh) | 2011-10-31 | 2011-10-31 | 一种大型发电机内外定子穿装方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN102364833B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102764972A (zh) * | 2012-07-18 | 2012-11-07 | 山东电力建设第二工程公司 | 分体式汽轮发电机内定子与外定子穿装方法 |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1212494A (zh) * | 1997-09-19 | 1999-03-31 | 日本胜利株式会社 | 电机和电机定子结构以及定子的组装方法 |
CN102142742A (zh) * | 2011-03-22 | 2011-08-03 | 上海博泽电机有限公司 | 蜗杆压装方法与用于该方法的压装设备 |
-
2011
- 2011-10-31 CN CN 201110337379 patent/CN102364833B/zh active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1212494A (zh) * | 1997-09-19 | 1999-03-31 | 日本胜利株式会社 | 电机和电机定子结构以及定子的组装方法 |
CN102142742A (zh) * | 2011-03-22 | 2011-08-03 | 上海博泽电机有限公司 | 蜗杆压装方法与用于该方法的压装设备 |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102764972A (zh) * | 2012-07-18 | 2012-11-07 | 山东电力建设第二工程公司 | 分体式汽轮发电机内定子与外定子穿装方法 |
Also Published As
Publication number | Publication date |
---|---|
CN102364833B (zh) | 2013-03-06 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN100576696C (zh) | 采用c形梁穿芯吊装大型电机的吊装方法 | |
CN105540424A (zh) | 一种带绕组定子铁芯热套吊运方法及装置 | |
CN105421859A (zh) | 一种电力电网电线杆架设装置及施工方法 | |
CN105591313A (zh) | 一种高压输电线缆的支撑架设备 | |
CN101775911B (zh) | 液压式一体化基站 | |
CN102299587B (zh) | 一种用于发电机装配的定位装置 | |
CN105967093B (zh) | 舾装设备安装方法 | |
CN101320931B (zh) | 发电机定转子套装方法及装置 | |
CN102364833B (zh) | 一种大型发电机内外定子穿装方法 | |
CN205489826U (zh) | 一种光照式无线电能传输*** | |
CN102764972A (zh) | 分体式汽轮发电机内定子与外定子穿装方法 | |
CN211699929U (zh) | 一种电子电力变压器固定支架 | |
CN212991767U (zh) | 一种电气高低压配电柜安装辅助装置 | |
CN201649713U (zh) | 液压式一体化基站 | |
CN209045499U (zh) | 端部焊带移放装置及焊带移放设备 | |
CN202117360U (zh) | 便携式移动基站 | |
CN204173796U (zh) | 一种新型吊具 | |
CN210088781U (zh) | 一种带无人机充电功能的快拆式灯杆 | |
CN209306866U (zh) | 一种适用于特殊地形的变压器吊装装置 | |
CN103051118A (zh) | 一种永磁发电机的转子装配方法 | |
CN202652016U (zh) | 一种大型永磁直驱风力发电机定子用嵌线辅助装置 | |
CN208853773U (zh) | 一种用于加工变压器外箱壳体的钻孔设备 | |
CN202220070U (zh) | 一种核电站用抬轴器 | |
CN210273615U (zh) | 一种新型汽车雨刮电机铁芯片 | |
CN109353952A (zh) | 一种适用于特殊地形的变压器吊装装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |