CN102322134A - 一种扣件式满堂支撑架与满堂脚手架承载力差别的确定方法 - Google Patents

一种扣件式满堂支撑架与满堂脚手架承载力差别的确定方法 Download PDF

Info

Publication number
CN102322134A
CN102322134A CN201110158699A CN201110158699A CN102322134A CN 102322134 A CN102322134 A CN 102322134A CN 201110158699 A CN201110158699 A CN 201110158699A CN 201110158699 A CN201110158699 A CN 201110158699A CN 102322134 A CN102322134 A CN 102322134A
Authority
CN
China
Prior art keywords
bar
steel tube
full space
scaffold
fastener
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201110158699A
Other languages
English (en)
Other versions
CN102322134B (zh
Inventor
刘群
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HANGZHOU ERJIAN CONSTRUCT CO Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN 201110158699 priority Critical patent/CN102322134B/zh
Publication of CN102322134A publication Critical patent/CN102322134A/zh
Application granted granted Critical
Publication of CN102322134B publication Critical patent/CN102322134B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本发明涉及一种立杆轴心受力扣件式满堂支撑架与立杆偏心受力扣件式满堂脚手架,支架纵、横向4各跨,在其范围内加载;架体步距1.5m,立杆纵、横间距1.25×1.2m,用Φ48×3.2钢管搭设,使用扣件连接。支撑架上部由可调托座托顶双钢管主梁,支撑架上部荷载经主梁、可调托座轴心传入立杆。满堂脚手架上部沿纵向在相邻立杆中部布置一根横向水平杆。顶部荷载经横向水平杆,纵向水平杆、扣件偏心传递给立杆,偏心距54mm。与支撑架相比临界荷载下降36%。本发明的方法,找出了满堂脚手架与满堂支撑架承载力差别,使建筑工程安全、经济的使用脚手架。

Description

一种扣件式满堂支撑架与满堂脚手架承载力差别的确定方法
技术领域
本发明涉及一种建筑工地用的扣件式钢管满堂支撑(立杆轴心受力)架与满堂脚手架(立杆偏心受力)承载力差别的确定方法。
背景技术
目前建筑工地在使用扣件式钢管满堂支撑架与满堂脚手架时,没有系列架体搭设结构一一对应的临界荷载要求,没有确定立杆轴心受力扣件式满堂支撑架与立杆偏心受力的扣件式满堂脚手架承载力差别,现场凭经验搭设,一方面,造成材料浪费成本增加,另一方面,造成安全隐患,有的甚至发生重大安全事故。
发明内容
本发明的目的在于提供一种确定立杆轴心受力扣件式满堂支撑架与立杆偏心受力的扣件式满堂脚手架,并确定其承载力的差别。使建筑工程可以安全、经济的使用脚手架。
本发明是这样来实现上述目的的:
一种立杆轴心受力的扣件式满堂支撑架,包括立杆钢管、纵向水平杆和横向水平杆;节点用可锻铸铁扣件连接;支撑架纵向4跨,横向4跨,加载区为4跨×4跨的范围;立杆步距为1.5m,相邻立杆钢管纵向间距1.25m,相邻立杆钢管横向间距1.2m;架体结构按5个步距搭设,扫地杆高度为0.3m,架体结构高度为7.8m;支撑架上部由可调托座托顶双钢管主梁;可调托座上表面至支架最上横管上皮0.52m,可调托座伸出立杆钢管的长度不大于0.35m;支撑架上部荷载经主梁、可调托座轴心传入立杆钢管;立杆钢管、纵向水平杆、横向水平杆和双钢管主梁均采用Φ48×3.2钢管。
一种立杆偏心受力的扣件式满堂脚手架,包括立杆钢管、纵向水平杆和横向水平杆;节点用可锻铸铁扣件连接;支架纵向4跨,横向4跨;加载区为4跨×4跨的范围;立杆步距为1.5m,相邻立杆钢管纵向间距1.25m,相邻立杆钢管4横向间距1.2m;架体结构按5个步距搭设,扫地杆高度为0.3m,架体结构高度为7.8m;架体上部沿纵向在相邻立杆中部布置一根横向水平杆;顶部荷载经横向水平杆、纵向水平杆、扣件偏心传递给立杆,偏心距54mm;立杆钢管、纵向水平杆、横向水平杆均采用Φ48×3.2钢管;与立杆轴心受力的扣件式满堂支撑架相比,临界荷载下降36%。
本发明确定了扣件式满堂支撑架与满堂脚手架承载力的差别,保证建筑工程安全、经济地使用脚手架。
附图说明
图1是扣件式钢管满堂支撑架主视图;
图2是扣件式钢管满堂支撑架侧视图;
图3是扣件式钢管满堂支撑架载荷试验装配主视图;
图4是扣件式钢管满堂支撑架加载区俯视图;
图5是扣件式钢管满堂支撑架载荷试验装配侧视图;
图6是扣件式钢管满堂脚手架主视图;
图7是扣件式钢管满堂脚手架侧视图;
图8是扣件式钢管满堂脚手架载荷试验装配主视图;
图9是扣件式钢管满堂脚手架加载区俯视图;
图10是扣件式钢管满堂脚手架载荷试验装配侧视图;
图中:1、可调托座;2、双钢管;3、横向水平杆;4、立杆钢管;5、纵向水平杆;6、可锻铸铁扣件;7、反力架;8、固定反力架钢管;9、分配梁;10、工字钢;11、千斤顶;12垫块。
具体实施方式
如图1-5所示,立杆轴心受力扣件式满堂支撑架,包括立杆钢管4、纵向水平杆5和横向水平杆3;节点用可锻铸铁扣件6连接;支架纵向4跨,横向4跨;加载区为4跨×4跨的范围;相邻纵向水平杆或相邻横向水平杆轴线距离,即立杆步距E为1.5m,架体结构高度按5个步距(相邻纵或横向水平杆轴线距离)搭设;立杆钢管横向间距A为1.2m,立杆钢管纵向间距B为1.25m,扫地杆高度D为0.3m,架体结构高度C为7.8m;支撑架上部由可调托座托顶双钢管主梁,可调托座1上表面至支架最上横管上皮距离F为0.52m,可调托座1伸出立杆4长度G不大于0.35m;支撑架上部荷载经主梁、可调托座轴心传入立杆;立杆钢管4、纵向水平杆5、横向水平杆3和双钢管主梁均采用Φ48×3.2钢管。试验如图3~5所示,这种扣件式钢管满堂支撑架与满堂脚手架经千斤顶11加荷,顶反力架7主梁,反力架回顶将荷载传至分配梁9,分配梁9将荷载传至工字钢10,工字钢10将荷载传至支架双钢管2,实现满堂支撑架荷载试验。经荷载试验确定,平均单立杆临界荷载17.8kN。
如图6-10所示,立杆偏心受力的满堂脚手架,包括立杆钢管4、纵向水平杆5和横向水平杆3;节点用可锻铸铁扣件6连接;支架纵向4跨,横向4跨;加载区为4跨×4跨的范围;相邻纵向水平杆或相邻横向水平杆轴线距离,即立杆步距E为1.5m,立杆钢管横向间距A为1.2m,立杆钢管纵向间距B为1.25m,扫地杆高度D为0.3m,架体结构高度C为7.8m;架体顶部沿纵向在相邻立杆中部布置一根横向水平杆;顶部荷载经横向水平杆3、纵向水平杆5、扣件6偏心传递给立杆4,偏心距H为54mm;立杆钢管4、纵向水平杆5、横向水平杆3均采用Φ48×3.2钢管。
试验如图8~10所示,这种扣件式钢管满堂支撑架与满堂脚手架经千斤顶11加荷,顶反力架7主梁,反力架回顶将荷载传至分配梁9,分配梁9将荷载传至工字钢10,工字钢10将荷载传至支架顶部横向水平杆3,实现满堂脚手架荷载试验。经荷载试验确定,平均单立杆临界荷载13.1kN;与支撑架相比,平均单立杆临界荷载下降36%。

Claims (2)

1.一种立杆轴心受力的扣件式满堂支撑架,包括立杆钢管、纵向水平杆和横向水平杆;节点用可锻铸铁扣件连接;其特征在于:支撑架纵向4跨,横向4跨,加载区为4跨×4跨的范围;立杆步距为1.5m,相邻立杆钢管纵向间距1.25m,相邻立杆钢管横向间距1.2m;架体结构按5个步距搭设,扫地杆高度为0.3m,架体结构高度为7.8m;支撑架上部由可调托座托顶双钢管主梁;可调托座上表面至支架最上横管上皮0.52m,可调托座伸出立杆钢管的长度不大于0.35m;支撑架上部荷载经主梁、可调托座轴心传入立杆钢管;立杆钢管、纵向水平杆、横向水平杆和双钢管主梁均采用Φ48×3.2钢管。
2.一种立杆偏心受力的扣件式满堂脚手架,包括立杆钢管、纵向水平杆和横向水平杆;节点用可锻铸铁扣件连接;其特征在于:支架纵向4跨,横向4跨;加载区为4跨×4跨的范围;立杆步距为1.5m,相邻立杆钢管纵向间距1.25m,相邻立杆钢管4横向间距1.2m;架体结构按5个步距搭设,扫地杆高度为0.3m,架体结构高度为7.8m;架体上部沿纵向在相邻立杆中部布置一根横向水平杆;顶部荷载经横向水平杆、纵向水平杆、扣件偏心传递给立杆,偏心距54mm;立杆钢管、纵向水平杆、横向水平杆均采用Φ48×3.2钢管;与立杆轴心受力的扣件式满堂支撑架相比,临界荷载下降36%。
CN 201110158699 2011-06-14 2011-06-14 一种扣件式满堂支撑架与满堂脚手架 Expired - Fee Related CN102322134B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201110158699 CN102322134B (zh) 2011-06-14 2011-06-14 一种扣件式满堂支撑架与满堂脚手架

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201110158699 CN102322134B (zh) 2011-06-14 2011-06-14 一种扣件式满堂支撑架与满堂脚手架

Publications (2)

Publication Number Publication Date
CN102322134A true CN102322134A (zh) 2012-01-18
CN102322134B CN102322134B (zh) 2013-09-11

Family

ID=45449958

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201110158699 Expired - Fee Related CN102322134B (zh) 2011-06-14 2011-06-14 一种扣件式满堂支撑架与满堂脚手架

Country Status (1)

Country Link
CN (1) CN102322134B (zh)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677881A (zh) * 2012-06-07 2012-09-19 刘群 一种减小支撑架顶层悬臂长度提高支撑架承载力方法
CN104878914A (zh) * 2013-07-25 2015-09-02 中冶天工集团有限公司 基于斜交不规则荷载满堂脚手架搭设方法
CN105804379A (zh) * 2016-06-08 2016-07-27 中国二十二冶集团有限公司 扣件式满堂脚手架支撑方法
CN106320677A (zh) * 2016-09-14 2017-01-11 安徽省建筑科学研究设计院 一种用于测量碗扣式钢管支架稳定承载力的仪器
CN109974998A (zh) * 2019-04-25 2019-07-05 北京工业大学 一种直角扣件失效下满堂脚手架稳定性试验方法

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2248290T3 (es) * 2000-03-06 2006-03-16 Reco Holding B.V. Metodo para el montaje de un andamio, andamio y partes del mismo.
JP2007309029A (ja) * 2006-05-22 2007-11-29 Alinco Inc 単管足場
JP2009161934A (ja) * 2007-12-28 2009-07-23 Alinco Inc 単管足場用支柱とこれを用いた単管足場構造
CN201310191Y (zh) * 2008-10-27 2009-09-16 中太建设集团股份有限公司 一种扣件式钢管脚手架模板支架
CN201310182Y (zh) * 2008-10-27 2009-09-16 中太建设集团股份有限公司 一种扣件式钢管满堂脚手架

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
ES2248290T3 (es) * 2000-03-06 2006-03-16 Reco Holding B.V. Metodo para el montaje de un andamio, andamio y partes del mismo.
JP2007309029A (ja) * 2006-05-22 2007-11-29 Alinco Inc 単管足場
JP2009161934A (ja) * 2007-12-28 2009-07-23 Alinco Inc 単管足場用支柱とこれを用いた単管足場構造
CN201310191Y (zh) * 2008-10-27 2009-09-16 中太建设集团股份有限公司 一种扣件式钢管脚手架模板支架
CN201310182Y (zh) * 2008-10-27 2009-09-16 中太建设集团股份有限公司 一种扣件式钢管满堂脚手架

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102677881A (zh) * 2012-06-07 2012-09-19 刘群 一种减小支撑架顶层悬臂长度提高支撑架承载力方法
CN104878914A (zh) * 2013-07-25 2015-09-02 中冶天工集团有限公司 基于斜交不规则荷载满堂脚手架搭设方法
CN105804379A (zh) * 2016-06-08 2016-07-27 中国二十二冶集团有限公司 扣件式满堂脚手架支撑方法
CN106320677A (zh) * 2016-09-14 2017-01-11 安徽省建筑科学研究设计院 一种用于测量碗扣式钢管支架稳定承载力的仪器
CN109974998A (zh) * 2019-04-25 2019-07-05 北京工业大学 一种直角扣件失效下满堂脚手架稳定性试验方法

Also Published As

Publication number Publication date
CN102322134B (zh) 2013-09-11

Similar Documents

Publication Publication Date Title
CN102322134B (zh) 一种扣件式满堂支撑架与满堂脚手架
CN105568853A (zh) 大跨度钢砼组合桁架梁侧位横移、落梁的施工方法
CN205242885U (zh) 轻质混凝土预制楼梯连接结构
CN203383221U (zh) 一种钢筋混凝土与钢结构混合的基坑支撑结构
CN211396814U (zh) 支撑横梁与支撑柱连接稳定的钢架厂房
CN102182300B (zh) 一种增加水平剪刀撑提高并确定支撑架承载力的方法
CN102733599A (zh) 适用于型钢混凝土梁的扣件式钢管脚手架模板支架
CN100554629C (zh) 一种扣件式钢管脚手架模板支架
CN205840316U (zh) 大跨度中庭悬空结构模板支撑体系
CN101560829B (zh) 大高宽比扣件式钢管脚手架模板支架
CN201381637Y (zh) 一种扣件式钢管脚手架模板支架
CN201284559Y (zh) 一种扣件式钢管脚手架模板支架
CN201284550Y (zh) 一种扣件式钢管满堂脚手架
CN102677881A (zh) 一种减小支撑架顶层悬臂长度提高支撑架承载力方法
CN102677882A (zh) 一种减小支撑架高宽比提高支撑架承载力方法
CN101560828B (zh) 剪刀撑扣件式钢管脚手架模板支架
CN205777531U (zh) 楼板施工用张弦梁模板支撑设备
CN102182311B (zh) 一种增加连墙件提高并确定支撑架承载力方法
CN204435833U (zh) 施工平台附墙支座
CN102182310B (zh) 一种增加水平约束提高并确定支撑架承载力方法
CN201381638Y (zh) 一种扣件式钢管脚手架模板支架
CN201310191Y (zh) 一种扣件式钢管脚手架模板支架
CN100540826C (zh) 一种扣件式钢管脚手架模板支架
CN205330033U (zh) 混合结构预制楼梯安装体系
CN201310182Y (zh) 一种扣件式钢管满堂脚手架

Legal Events

Date Code Title Description
DD01 Delivery of document by public notice

Addressee: Liu Qun

Document name: Notification of Passing Preliminary Examination of the Application for Invention

C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: HANGZHOU ERJIAN CONSTRUCT CO., LTD.

Free format text: FORMER OWNER: LIU QUN

Effective date: 20130726

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Zhang Guoqing

Inventor after: Fang Zhongming

Inventor after: Ma Zhaolong

Inventor after: Shen Yongmiao

Inventor after: Liu Qun

Inventor before: Liu Qun

Inventor after: Zhang Guoqing

Inventor after: Fang Zhongming

Inventor after: Ma Zhaolong

Inventor after: Shen Yongmiao

Inventor after: Liu Qun

Inventor before: Liu Qun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: LIU QUN TO: ZHANG GUOQING FANG ZHONGMING MA ZHAOLONG SHEN YONGMIAO LIU QUN

Free format text: CORRECT: ADDRESS; FROM: 065000 LANGFANG, HEBEI PROVINCE TO: 310005 HANGZHOU, ZHEJIANG PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20130726

Address after: Hangzhou City, Zhejiang province 310005 Moganshan Road No. 226

Applicant after: Hangzhou Erjian Construct Co., Ltd.

Address before: Langfang City, Hebei Province, Jinguang road 065000 Guangyang District Sheng Chunli room 6 2-102

Applicant before: Liu Qun

Effective date of registration: 20130726

Address after: Hangzhou City, Zhejiang province 310005 Moganshan Road No. 226

Applicant after: Hangzhou Erjian Construct Co., Ltd.

Address before: Langfang City, Hebei Province, Jinguang road 065000 Guangyang District Sheng Chunli room 6 2-102

Applicant before: Liu Qun

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20130911

Termination date: 20190614

CF01 Termination of patent right due to non-payment of annual fee