CN102320519A - 一种钢管套管组对用抱卡装置及其施工方法 - Google Patents

一种钢管套管组对用抱卡装置及其施工方法 Download PDF

Info

Publication number
CN102320519A
CN102320519A CN201110144348A CN201110144348A CN102320519A CN 102320519 A CN102320519 A CN 102320519A CN 201110144348 A CN201110144348 A CN 201110144348A CN 201110144348 A CN201110144348 A CN 201110144348A CN 102320519 A CN102320519 A CN 102320519A
Authority
CN
China
Prior art keywords
pipe
card
embraced
outer tube
hoist
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201110144348A
Other languages
English (en)
Inventor
王五奇
靳宏伟
王同生
魏肖琦
王登武
靳小英
屈国庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Bureau Installation Engineering Co Ltd filed Critical China Construction Seventh Engineering Bureau Installation Engineering Co Ltd
Priority to CN201110144348A priority Critical patent/CN102320519A/zh
Publication of CN102320519A publication Critical patent/CN102320519A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Earth Drilling (AREA)

Abstract

本发明公开了一种钢管套管组对用抱卡装置,包括内管抱卡和外管抱卡,内管抱卡通过紧固螺栓Ⅰ固定,外管抱卡通过紧固螺栓Ⅱ固定,内管抱卡上设有两个对称的吊装孔Ⅰ,外管抱卡上设有两个对称的吊装孔Ⅱ,吊装孔Ⅰ和吊装孔Ⅱ上安装有升降装置。本发明装置简单,使用方便,使用升降装置可以将钢管套管的内管依次安装在外套管内,施工投入机械少,内管拖拉进外套管过程中速度均匀,且内管受力方向与管道中心线一直,不会破坏内管上的支撑支架。

Description

一种钢管套管组对用抱卡装置及其施工方法
技术领域
本发明涉及一种钢管套管组对用抱卡装置及施工方法。
背景技术
目前在现场组对钢套钢管一般用装载机或拖拉机带动钢丝绳将内管拖进外套管内。施工时在钢丝绳两端分别安装一个挂钩,钢丝绳一端挂在装载机上,一端挂在内管口上,开动装载机或拖拉机将内管拖进外套管内。采用此方法施工由于装载机或拖拉机发动时加速度不均匀,有时拖拉过程中速度变化也较大,方向也有变化,拖拉时容易将内套管上的部分支撑支架破坏。
发明内容
本发明要解决的技术问题是安装钢套钢管时,在拖拉过程中速度不均容易将内套管上的部分支撑支架破坏,提供一种钢管套管组对用抱卡装置及施工方法。
本发明的技术方案是:一种钢管套管组对用抱卡装置,包括内管抱卡和外管抱卡,内管抱卡通过紧固螺栓Ⅰ固定,外管抱卡通过紧固螺栓Ⅱ固定,内管抱卡上设有两个对称的吊装孔Ⅰ,外管抱卡上设有两个对称的吊装孔Ⅱ,吊装孔Ⅰ和吊装孔Ⅱ上安装有升降装置。
所述升降装置为电葫芦或手动葫芦或采用滑轮组。
所述的钢管套管组对用抱卡装置的施工方法,它的步骤如下:
(1)将两个阀门井之间的外套管安装完毕,之后把外管抱卡紧固安装在外套管上,升降装置的一端安装在外管抱卡的吊装孔Ⅱ上;
(2)将第一节内管依次装配上支撑支架、保温材料、内管抱卡;
(3)将装配好的第一节内管一端放进外套管一端内,升降装置的另一端安装在内管抱卡的吊装孔Ⅰ上,然后控制升降装置,将第一节内管逐步拉进外套管内;
(4)第二节内管与第一节内管对口焊接、探伤,将第一节内管上的内管抱卡拆除后安装在第二节内管上,升降装置的另一端安装在内管抱卡的吊装孔Ⅰ上,然后控制升降装置,将第二节内管逐步拉进外套管内;
(5)第三节内管及后续的内管依次进行安装。
本发明的有益效果是:本发明装置简单,使用方便,使用升降装置可以将钢管套管的内管依次安装在外套管内,施工投入机械少,内管拖拉进外套管过程中速度均匀,且内管受力方向与管道中心线一直,不会破坏内管上的支撑支架。
附图说明
图1为本发明的示意图;
图2为图1的A-A示意图。
具体实施方式
一种钢管套管组对用抱卡装置,包括内管抱卡4和外管抱卡8,内管抱卡4通过紧固螺栓Ⅰ5固定,外管抱卡8通过紧固螺栓Ⅱ7固定,内管抱卡4上设有两个对称的吊装孔Ⅰ3,外管抱卡8上设有两个对称的吊装孔Ⅱ9,吊装孔Ⅰ3和吊装孔Ⅱ9上安装有升降装置6。
所述升降装置为电葫芦或手动葫芦或采用滑轮组。
所述的钢管套管组对用抱卡装置的施工方法,它的步骤如下:
(1)将两个阀门井之间的外套管安装完毕,之后把外管抱卡紧固安装在外套管上,升降装置的一端安装在外管抱卡的吊装孔Ⅱ上;
(2)将第一节内管依次装配上支撑支架10、保温材料11、内管抱卡;
(3)将装配好的第一节内管一端放进外套管一端内,升降装置的另一端安装在内管抱卡的吊装孔Ⅰ上,然后控制升降装置,将第一节内管逐步拉进外套管内;
(4)第二节内管与第一节内管对口焊接、探伤,将第一节内管上的内管抱卡拆除后安装在第二节内管上,升降装置的另一端安装在内管抱卡的吊装孔Ⅰ上,然后控制升降装置,将第二节内管逐步拉进外套管内;
(5)第三节内管及后续的内管依次进行安装。

Claims (3)

1.一种安装管套管组对用抱卡装置,其特征在于:包括内管抱卡(4)和外管抱卡(8),内管抱卡(4)通过紧固螺栓Ⅰ(5)固定,外管抱卡(8)通过紧固螺栓Ⅱ(7)固定,内管抱卡(4)上设有两个对称的吊装孔Ⅰ(3),外管抱卡(8)上设有两个对称的吊装孔Ⅱ(9),吊装孔Ⅰ(3)和吊装孔Ⅱ(9)上安装有升降装置(6)。
2.根据权利要求1所述的安装管套管组对用抱卡装置,其特征在于:所述升降装置为电葫芦或手动葫芦或采用滑轮组。
3.如权利要求1或2所述的安装管套管组对用抱卡装置的施工方法,其特征在于,它的步骤如下:
(1)将两个阀门井之间的外套管安装完毕,之后把外管抱卡紧固安装在外套管上,升降装置的一端安装在外管抱卡的吊装孔Ⅱ上;
(2)将第一节内管依次装配上支撑支架、保温材料、内管抱卡;
(3)将装配好的第一节内管一端放进外套管一端内,升降装置的另一端安装在内管抱卡的吊装孔Ⅰ上,然后控制升降装置,将第一节内管逐步拉进外套管内;
(4)第二节内管与第一节内管对口焊接、探伤,将第一节内管上的内管抱卡拆除后安装在第二节内管上,升降装置的另一端安装在内管抱卡的吊装孔Ⅰ上,然后控制升降装置,将第二节内管逐步拉进外套管内;
(5)第三节内管及后续的内管依次进行安装。
CN201110144348A 2011-05-31 2011-05-31 一种钢管套管组对用抱卡装置及其施工方法 Pending CN102320519A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201110144348A CN102320519A (zh) 2011-05-31 2011-05-31 一种钢管套管组对用抱卡装置及其施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201110144348A CN102320519A (zh) 2011-05-31 2011-05-31 一种钢管套管组对用抱卡装置及其施工方法

Publications (1)

Publication Number Publication Date
CN102320519A true CN102320519A (zh) 2012-01-18

Family

ID=45448403

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201110144348A Pending CN102320519A (zh) 2011-05-31 2011-05-31 一种钢管套管组对用抱卡装置及其施工方法

Country Status (1)

Country Link
CN (1) CN102320519A (zh)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103331605A (zh) * 2013-06-07 2013-10-02 江苏新丰电子有限公司 具有内接管选择器的三接管制造机
CN103359308A (zh) * 2012-03-31 2013-10-23 中国一冶集团有限公司 管道套管加固装置及方法
CN104627849A (zh) * 2015-02-03 2015-05-20 中建五局工业设备安装有限公司 一种用于内天井管道吊装的吊装设备及吊装方法
CN106239150A (zh) * 2016-09-30 2016-12-21 常州信息职业技术学院 一种内管与中管的装配专机

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09301673A (ja) * 1996-05-09 1997-11-25 Hitachi Plant Eng & Constr Co Ltd 大径管吊り揚げ金具
GB2359605A (en) * 2000-02-28 2001-08-29 Mentor Subsea Tech Serv Inc Pipe in pipe assemblies
JP2002266590A (ja) * 2001-03-06 2002-09-18 Nkk Corp 既設管の更新方法
CN2550610Y (zh) * 2002-07-18 2003-05-14 上海益能电力工程有限公司 隔热型滚动支架
CN2586034Y (zh) * 2002-11-16 2003-11-12 胜利油田胜利石油化工建设有限责任公司三分公司 预制海底管道芯管穿套管装置
CN201326829Y (zh) * 2008-12-30 2009-10-14 二十三冶建设集团有限公司 用于夹套管组装工艺中的穿管装置

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH09301673A (ja) * 1996-05-09 1997-11-25 Hitachi Plant Eng & Constr Co Ltd 大径管吊り揚げ金具
GB2359605A (en) * 2000-02-28 2001-08-29 Mentor Subsea Tech Serv Inc Pipe in pipe assemblies
JP2002266590A (ja) * 2001-03-06 2002-09-18 Nkk Corp 既設管の更新方法
CN2550610Y (zh) * 2002-07-18 2003-05-14 上海益能电力工程有限公司 隔热型滚动支架
CN2586034Y (zh) * 2002-11-16 2003-11-12 胜利油田胜利石油化工建设有限责任公司三分公司 预制海底管道芯管穿套管装置
CN201326829Y (zh) * 2008-12-30 2009-10-14 二十三冶建设集团有限公司 用于夹套管组装工艺中的穿管装置

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
刘佩璋: "顶管工程内穿钢管的施工方法", 《山西建筑》 *
汪建国: "钢管穿管技术在燃气管道更新修复中的应用", 《上海煤气》 *

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103359308A (zh) * 2012-03-31 2013-10-23 中国一冶集团有限公司 管道套管加固装置及方法
CN103359308B (zh) * 2012-03-31 2015-06-24 中国一冶集团有限公司 管道套管加固装置及方法
CN103331605A (zh) * 2013-06-07 2013-10-02 江苏新丰电子有限公司 具有内接管选择器的三接管制造机
CN103331605B (zh) * 2013-06-07 2015-11-04 江苏新丰电子有限公司 具有内接管选择器的三接管制造机
CN104627849A (zh) * 2015-02-03 2015-05-20 中建五局工业设备安装有限公司 一种用于内天井管道吊装的吊装设备及吊装方法
CN104627849B (zh) * 2015-02-03 2017-05-10 中建五局工业设备安装有限公司 一种用于内天井管道吊装的吊装设备及吊装方法
CN106239150A (zh) * 2016-09-30 2016-12-21 常州信息职业技术学院 一种内管与中管的装配专机

Similar Documents

Publication Publication Date Title
CN102320519A (zh) 一种钢管套管组对用抱卡装置及其施工方法
JP2012162324A5 (zh)
CN204917742U (zh) 一种管道安装用便携式龙门吊
CN203891887U (zh) 一种分体始发盾构机
WO2013019754A3 (en) Method and portable apparatus for forcing a pipeline into or out of a borehole
CN206361268U (zh) 一种卡箍结构
CN104863601B (zh) 盾构机分体始发加长管线悬吊***
CN201487380U (zh) 可行走振动拖管器
CN105672906A (zh) 一种单吊卡起下油管装置及工艺
CN104526324A (zh) 煤矿液压支架拆销装置
CN202988568U (zh) 立式管道吊装用具
CN204343343U (zh) 桩基质量检测管定位快接装置
CN104494804A (zh) 一种船舶轴系分段式尾管装置及其安装方法
CN105135054B (zh) 超长管道的顶管施工方法
CN103879929A (zh) 一种用于大口径电缆线圈运输的辅助装置及其使用方法
CN111115429B (zh) 一种水下管道拔出夹具、拔出装置及拔出方法
CN203887784U (zh) Pccp管道对接辅助安装器
CN203890885U (zh) 一种平拉索桥钢索与拉杆的连接装置
CN204470927U (zh) 煤矿液压支架拆销装置
CN209367153U (zh) 一种管道运输胎具
CN204185169U (zh) 一种塔式起升机构钢丝绳卷绕装置
CN207756583U (zh) 一种水泥库用清灰装置
CN205241747U (zh) “臂”式炉辊吊具
CN201843509U (zh) 动力头快速提升装置及使用该提升装置的车载钻机
CN101914951B (zh) 一种管状构件的螺栓反向安装方法及装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20120118