CN102248116A - Manufacturing process for bolt with high strength of more than phi 30 - Google Patents

Manufacturing process for bolt with high strength of more than phi 30 Download PDF

Info

Publication number
CN102248116A
CN102248116A CN2011100785677A CN201110078567A CN102248116A CN 102248116 A CN102248116 A CN 102248116A CN 2011100785677 A CN2011100785677 A CN 2011100785677A CN 201110078567 A CN201110078567 A CN 201110078567A CN 102248116 A CN102248116 A CN 102248116A
Authority
CN
China
Prior art keywords
heating
manufacturing process
temperature
thermal treatment
zone
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2011100785677A
Other languages
Chinese (zh)
Inventor
苏友份
藤宝贵
周世团
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ZHEJIANG DITE HIGH-STRENGTH BOLT CO LTD
Original Assignee
ZHEJIANG DITE HIGH-STRENGTH BOLT CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG DITE HIGH-STRENGTH BOLT CO LTD filed Critical ZHEJIANG DITE HIGH-STRENGTH BOLT CO LTD
Priority to CN2011100785677A priority Critical patent/CN102248116A/en
Publication of CN102248116A publication Critical patent/CN102248116A/en
Pending legal-status Critical Current

Links

Landscapes

  • Forging (AREA)
  • Heat Treatment Of Articles (AREA)

Abstract

The invention discloses a manufacturing process for a bolt with high strength of more than phi 30. The manufacturing process comprises the following steps of: forging; performing heat treatment and after treatment, wherein the heating forging temperature is between 1,100 and 1,300 DEG C, and the heating forging time is between 2 and 5 minutes; directly feeding workpieces into a mesh belt furnace quickly after forging for high temperature tempering, wherein the mesh belt furnace comprises a preheating area, a first heating area, a second heating area and a heat preservation area; preheating the workpieces through the preheating area after the workpieces are fed into the mesh belt furnace, and heating the workpieces through the first heating area and the second heating area; preserving the heat through the heat preservation area; cooling the workpieces which are subjected to the high temperature tempering; and trimming the cooled workpieces. By the manufacturing process, the workpieces are directly fed into the mesh belt furnace for high temperature tempering after being heated and forged, the excess heat of the forged workpieces is fully used, and time and energy are saved. The workpieces have a tempered sorbite structure after the high temperature tempering, grains are refined, and the phenomena that the grains are coarse and a martensite structure and a raw material structure are blended are prevented.

Description

A kind of manufacturing process of Φ 30 above high-strength bolts
Technical field
The present invention relates to material and forge and heat treatment technics, be specifically related to the forging and the Technology for Heating Processing of the high-strength bolt of a kind of Φ more than 30.
Background technology
High-strength bolt is used for the connection of bridge, rail, high pressure and extra-high tension unit for imposing the bolt of big pretightning force more.Need very strong bearing capacity when high-strength bolt is used to use, the raw material intensity of employing is very high, therefore processing technology is had relatively high expectations.
The high-strength bolt of Φ more than 30 must adopt heats forged because its specific (special) requirements can not be adopted cold-heading molding, forges the back and can form unnecessary edge at head, need excise.When the heats forged process of high-strength bolt, the heats forged temperature is forged the back product needed long period and is cooled off than higher.Because cool time is long, the head of bolt forms martensite easily and organizes crystal grain thick in respect of the bar portion of position, heating part in advance, owing to have that martensitic structure is easy goes into the bursting apart of head, causes bolt to scrap when cutting edge.On the other hand, when heat treatment because there is the line and staff control of martensitic structure and raw material tissue in bolt, like this when quenching since structural stress inhomogeneous cause bolt to ftracture easily and cause bolt to scrap.
At present, scrap problem at the bolt cracking that causes owing to the appeal reason, people carry out normalized treatment to workpiece after adopting heats forged usually, to reach thinning microstructure, improve the purpose of cutting ability.Because the temperature height is generally about 860 ℃, and temperature retention time is long, the type of cooling is taked the air cooling to this method when normalizing.The holding temperature of this method than higher, heat time heating time is long, will consume many electric energy, cost is higher.The second, this method is owing to adopt normalized treatment, the temperature height, and the type of cooling is an air, the list of bolts face easily forms oxide layer like this, influence the outward appearance and the size of bolt, influences use.In addition, the cooling air mode of this method is generally the open type cooling air mode, and the list of bolts surface temperature is higher, and cooling can be slow, like this at bolt circumferential surface temperature height, like this can be higher in the bolt environment temperature, and cause labor strength also high.
Summary of the invention
The objective of the invention is to:, the invention provides a kind of manufacturing process of Φ 30 above high-strength bolts in order to overcome the deficiencies in the prior art.Manufacturing process of the present invention can effectively reduce the cracking of bolt, has reduced the scrappage of high-strength bolt, simultaneously again can energy saving.
Technical scheme of the present invention: a kind of manufacturing process of Φ 30 above high-strength bolts, this technology may further comprise the steps:
(1) forges: choose the raw material that forge high-strength bolt,, the raw material of choosing are carried out preliminary treatment according to the line footpath requirement of bolt, forge, forging process is a heats forged again, and the heats forged temperature is 1100~1300 ℃, the heats forged time is 2~5 minutes
(2) heat treatment: the workpiece after the heats forged is sent into meshbeltfurnace rapidly carry out high tempering, described meshbeltfurnace comprises the preheating zone, first thermal treatment zone, second thermal treatment zone and heat preservation zone, workpiece carries out preheating through the preheating zone earlier after entering meshbeltfurnace, preheat temperature is 500~550 ℃, be 30~40 minutes preheating time, heat through first thermal treatment zone and second thermal treatment zone again, heating-up temperature is 550~570 ℃, be 30~40 minutes first thermal treatment zone heat time heating time, be 30~40 minutes second heat time heating time), be incubated through heat preservation zone at last, holding temperature is 550~570 ℃, temperature retention time is 60~80 minutes
(3) post processing: the workpiece to high tempering cools off, and cooling back is to the workpiece processing of cutting edge.
As preferably, described raw material are the 42CrMo steel.The 42CrMo steel belongs to unimach, has high strength and toughness, and quenching degree is also better, and higher fatigue limit and anti-repeatedly impact capacity are arranged after the modifier treatment, and low-temperature impact toughness is good, utilizes the 42CrMo forging to make high-strength bolt and has bigger intensity.
As preferred again, the type of cooling in the described step (3) is a water-cooled.Adopt the type of cooling of water-cooled to reduce cool time after high-strength bolt forges, reduced bolt head and the bar portion martensitic formation in position of heating is arranged and organize the thick phenomenon of crystal grain.
As preferred again, the mode of heating that forges in the described step (1) is an eddy-current heating.
As preferred again, preheat temperature is 500~530 ℃ in the described step (2).
As preferred again, the heating-up temperature of first thermal treatment zone and second thermal treatment zone is 550~560 ℃ in the described step (2).
The manufacturing process of Φ 30 above high-strength bolts of the present invention is with stove to carry out high tempering directly into the king after workpiece is carried out heats forged, made full use of and forged the waste heat that the back workpiece still has, the time that reduced has reached purpose of energy saving, after with high tempering, workpiece be organized as tempered sorbite, refinement crystal grain, fully avoided the mixed phenomenons that exist of two kinds in thick phenomenon of crystal grain and martensitic structure and raw material tissue tissue.
The specific embodiment
The manufacturing process of Φ 30 above high-strength bolts of the present invention selects for use the 42CrMo steel as raw material, selects for use the 42CrMo steel can effectively improve indexs such as tensile strength, hardness, yield strength and the elongation after fracture of high-strength bolt and the contraction percentage of area as raw material.
The manufacturing process of Φ 30 above high-strength bolts of the present invention is carried out high tempering will directly sending into meshbeltfurnace through the workpiece after the heats forged, meshbeltfurnace comprises preheating zone, first thermal treatment zone, second thermal treatment zone and heat preservation zone, workpiece enters advanced preheating of crossing the preheating zone behind the meshbeltfurnace, again through the heating of first thermal treatment zone and second thermal treatment zone, enter heat preservation zone again and be incubated, at last the workpiece of high tempering is carried out post processing processing after the water-cooled.
Embodiment 1
Select for use the 42CrMo steel as raw material, line footpath requirement according to bolt, raw material are carried out carrying out heats forged after the preliminary treatment, the heats forged temperature is 1100 ℃, the heats forged time is 5 minutes, the hardness of high-strength bolt head edge of the present invention is HRC45 after the heats forged, metallographic structure is a martensite, to send into meshbeltfurnace rapidly through the workpiece after the heats forged and carry out high tempering, workpiece enters the preheating zone of at first passing through meshbeltfurnace behind the meshbeltfurnace, preheating is 30 minutes under 550 ℃ temperature, enters first thermal treatment zone again, second thermal treatment zone entered behind first thermal treatment zone under 570 ℃ temperature heating 30 minutes, enter second thermal treatment zone then, heating is 30 minutes under 570 ℃ temperature, enters heat preservation zone at last and is incubated, and is incubated 60 minutes down at 570 ℃.
Workpiece behind the high tempering is taken out, and water cools off, and the metallographic structure of workpiece is pearlite and ferrite after the tempering, hardness to workpiece is tested, record that the case hardness of workpiece is HRC32 after the tempering, workpiece is cut edge again, adding up scrappage at last is 0.09%.
Embodiment 2
Select for use the 42CrMo steel as raw material, line footpath requirement according to bolt, raw material are carried out carrying out heats forged after the preliminary treatment, the heats forged temperature is 1200 ℃, the heats forged time is 3 minutes, the hardness of high-strength bolt head edge of the present invention is HRC50 after the heats forged, metallographic structure is a martensite, to send into meshbeltfurnace rapidly through the workpiece after the heats forged and carry out high tempering, workpiece enters the preheating zone of at first passing through meshbeltfurnace behind the meshbeltfurnace, preheating is 30 minutes under 530 ℃ temperature, enters first thermal treatment zone again, second thermal treatment zone entered behind first thermal treatment zone under 560 ℃ temperature heating 35 minutes, enter second thermal treatment zone then, heating is 30 minutes under 560 ℃ temperature, enters heat preservation zone at last and is incubated, and is incubated 70 minutes down at 560 ℃.
Workpiece behind the high tempering is taken out, and water cools off, and the metallographic structure of workpiece is pearlite and ferrite after the tempering, hardness to workpiece is tested, record that the case hardness of workpiece is HRC34 after the tempering, workpiece is cut edge again, adding up scrappage at last is 0.1%.
Embodiment 3
Select for use the 42CrMo steel as raw material, line footpath requirement according to bolt, raw material are carried out carrying out heats forged after the preliminary treatment, the heats forged temperature is 1300 ℃, the heats forged time is 2 minutes, the hardness of high-strength bolt head edge of the present invention is HRC55 after the heats forged, metallographic structure is a martensite, to send into meshbeltfurnace rapidly through the workpiece after the heats forged and carry out high tempering, workpiece enters the preheating zone of at first passing through meshbeltfurnace behind the meshbeltfurnace, preheating is 40 minutes under 500 ℃ temperature, heated 40 minutes under 550 ℃ temperature after entering first thermal treatment zone, enter second thermal treatment zone then, heating is 40 minutes under 550 ℃ temperature, enter heat preservation zone at last and be incubated, be incubated 80 minutes down at 550 ℃.
Workpiece behind the high tempering is taken out, and water cools off, and the metallographic structure of workpiece is pearlite and ferrite after the tempering, hardness to workpiece is tested, record that the case hardness of workpiece is HRC35 after the tempering, workpiece is cut edge again, adding up scrappage at last is 0.11%.
The high-strength bolt hardness of the fabrication process of Φ 30 above high-strength bolts of the present invention is HRC32~35, product rejection rate is about 0.1%, and the high-strength bolt that adopts prior art to produce, i.e. method through directly taking after the heats forged to cut edge, its scrappage is about 5%, and the present invention effectively reduces the scrappage when producing the above high-strength bolt of Φ 30.

Claims (7)

1. the manufacturing process of Φ 30 above high-strength bolts is characterized in that this technology may further comprise the steps:
(1) forges: choose the raw material that forge high-strength bolt,, the raw material of choosing are carried out preliminary treatment according to the line footpath requirement of bolt, forge, forging process is a heats forged again, and the heats forged temperature is 1100~1300 ℃, the heats forged time is 2~5 minutes
(2) heat treatment: the workpiece after the heats forged is sent into meshbeltfurnace rapidly carry out high tempering, described meshbeltfurnace comprises the preheating zone, first thermal treatment zone, second thermal treatment zone and heat preservation zone, workpiece carries out preheating through the preheating zone earlier after entering meshbeltfurnace, preheat temperature is 500~550 ℃, be 30~40 minutes preheating time, heat through first thermal treatment zone and second thermal treatment zone again, heating-up temperature is 550 ℃~570 ℃, be 30~40 minutes first thermal treatment zone heat time heating time, be 30~40 minutes second heat time heating time, is incubated through heat preservation zone at last, and holding temperature is 550 ℃~570 ℃, temperature retention time is 60~80 minutes
(3) post processing: the workpiece to high tempering cools off, and cooling back is to the workpiece processing of cutting edge.
2. the manufacturing process of Φ 30 above high-strength bolts according to claim 1 is characterized in that: described raw material are the 42CrMo steel.
3. the manufacturing process of Φ 30 above high-strength bolts according to claim 1 is characterized in that: the type of cooling in the described step (3) is a water-cooled.
4. the manufacturing process of Φ 30 above high-strength bolts according to claim 1 is characterized in that: the mode of heating that forges in the described step (1) is an eddy-current heating.
5. the manufacturing process of Φ 30 above high-strength bolts according to claim 1 is characterized in that: preheat temperature is 500~530 ℃ in the described step (2).
6. the manufacturing process of Φ 30 above high-strength bolts according to claim 1 is characterized in that: the heating-up temperature of first thermal treatment zone and second thermal treatment zone is 550~560 ℃ in the described step (2).
7. the manufacturing process of Φ 30 above high-strength bolts according to claim 1 is characterized in that: the holding temperature of heat preservation zone is 550~560 ℃ in the described step (2).
CN2011100785677A 2011-03-30 2011-03-30 Manufacturing process for bolt with high strength of more than phi 30 Pending CN102248116A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2011100785677A CN102248116A (en) 2011-03-30 2011-03-30 Manufacturing process for bolt with high strength of more than phi 30

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2011100785677A CN102248116A (en) 2011-03-30 2011-03-30 Manufacturing process for bolt with high strength of more than phi 30

Publications (1)

Publication Number Publication Date
CN102248116A true CN102248116A (en) 2011-11-23

Family

ID=44975891

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2011100785677A Pending CN102248116A (en) 2011-03-30 2011-03-30 Manufacturing process for bolt with high strength of more than phi 30

Country Status (1)

Country Link
CN (1) CN102248116A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102756071A (en) * 2012-08-05 2012-10-31 贵州航天新力铸锻有限责任公司 Forging method for AP1000 type nuclear power station reactor pressure vessel main bolt
CN103240382A (en) * 2013-05-10 2013-08-14 西安航空动力股份有限公司 Post-forging treatment method for TC11 titanium alloy miniature precisely forged blade
CN103436803A (en) * 2013-08-13 2013-12-11 武汉重工铸锻有限责任公司 Processing method for pump head body of five-cylinder plunger pump
CN103526004A (en) * 2013-10-21 2014-01-22 无锡市德力流体科技有限公司 Method for ensuring impact toughness of low-temperature fastener
CN103614530A (en) * 2013-11-20 2014-03-05 大连赛瑞金属制品有限公司 Quenching process in production technology of suspension insulator cryogenic steel foot
CN103982519A (en) * 2014-05-29 2014-08-13 贵州航天精工制造有限公司 Bidirectional orthogonal clamping bolt and preparing method thereof
CN109746360A (en) * 2018-12-28 2019-05-14 江苏海宇机械有限公司 A kind of manufacturing method improving forging part dimensional accuracy
CN109971936A (en) * 2019-04-09 2019-07-05 舞阳钢铁有限责任公司 Reduce 2.25Cr-1Mo-0.3V side edge of steel plate hardness method
CN110695627A (en) * 2019-10-31 2020-01-17 李秋文 Hot heading processing technology for fastener
CN111922266A (en) * 2020-07-29 2020-11-13 陕西建科方圆汽车零部件有限公司 Hot forging bolt processing method

Cited By (13)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102756071A (en) * 2012-08-05 2012-10-31 贵州航天新力铸锻有限责任公司 Forging method for AP1000 type nuclear power station reactor pressure vessel main bolt
CN103240382B (en) * 2013-05-10 2015-04-29 西安航空动力股份有限公司 Post-forging treatment method for TC11 titanium alloy miniature precisely forged blade
CN103240382A (en) * 2013-05-10 2013-08-14 西安航空动力股份有限公司 Post-forging treatment method for TC11 titanium alloy miniature precisely forged blade
CN103436803A (en) * 2013-08-13 2013-12-11 武汉重工铸锻有限责任公司 Processing method for pump head body of five-cylinder plunger pump
CN103526004A (en) * 2013-10-21 2014-01-22 无锡市德力流体科技有限公司 Method for ensuring impact toughness of low-temperature fastener
CN103614530A (en) * 2013-11-20 2014-03-05 大连赛瑞金属制品有限公司 Quenching process in production technology of suspension insulator cryogenic steel foot
CN103614530B (en) * 2013-11-20 2015-09-30 大连赛瑞金属制品有限公司 Quenching technology in the production technique of suspension insulator cryogenic steel foot
CN103982519A (en) * 2014-05-29 2014-08-13 贵州航天精工制造有限公司 Bidirectional orthogonal clamping bolt and preparing method thereof
CN103982519B (en) * 2014-05-29 2016-02-10 贵州航天精工制造有限公司 A kind of orthogonal clamping bolt and preparation method
CN109746360A (en) * 2018-12-28 2019-05-14 江苏海宇机械有限公司 A kind of manufacturing method improving forging part dimensional accuracy
CN109971936A (en) * 2019-04-09 2019-07-05 舞阳钢铁有限责任公司 Reduce 2.25Cr-1Mo-0.3V side edge of steel plate hardness method
CN110695627A (en) * 2019-10-31 2020-01-17 李秋文 Hot heading processing technology for fastener
CN111922266A (en) * 2020-07-29 2020-11-13 陕西建科方圆汽车零部件有限公司 Hot forging bolt processing method

Similar Documents

Publication Publication Date Title
CN102248116A (en) Manufacturing process for bolt with high strength of more than phi 30
CN101549449B (en) Processing technology for high-strength large hexagon head bolt used for steel structure
CN101549448B (en) Processing technology for high-strength bolt used for steel net frame bolt ball node
CN103266212B (en) Thermal treatment technology for improving low-temperature impact toughness of 25Cr2Ni4MoV steel forging
CN101934466A (en) Technology for processing high strength large hexagon-headed bolt used for steel structure
CN107747032A (en) Aviation high-toughness long-life large rotor forged shaft manufacturing process
CN101934467A (en) Machining process of high strength bolt for steel space frame bolted spherical joint
CN103071753B (en) Forging method of ball valve stem
CN103205551A (en) Thermal treatment processing method of thrust wheel
CN105132637A (en) Two-liquid quenching tempering local strengthening heat treatment technology for oil press 5CrMnMo upper die
CN103317319A (en) Production processing method for edge-digging scissors made of Cr12Mo1V1
CN104593573A (en) Combined thermomechanical treatment strengthening method for efficiently improving strength and toughness of non-quenched and tempered steel
CN110684885B (en) Forging control method for uniformly refining grain size of forge piece
CN105063320B (en) A kind of preparation method of high-wind pressure impactor piston
CN114015847A (en) Method for producing 45 steel for direct cutting by controlled rolling and controlled cooling process
CN102181613B (en) Heat treatment method for large-scale Cr12Mov workpiece
US8377235B2 (en) Process for forming steel
CN110551880A (en) softening heat treatment process for small-size 22Si2MnCrNi2MoA steel rolled material
CN113322368B (en) Manufacturing method for eliminating overheating of 35CrNi3MoV large-scale cylinder forging
CN106435404A (en) Low wind speed wind power unit low-carbon alloy steel wind power main shaft manufacturing method
CN101974676A (en) Breaking-preventing knuckle spindle and thermal treatment method thereof
CN107058704A (en) A kind of process of elimination 4Cr13 stainless steel rings rolled piece annealed state net carbon
CN105714027A (en) Heat treatment process for hardening and tempering of 45 steel
CN101745562A (en) Method for machining male mould of flywheel extrusion mould
CN103805764A (en) Hot rolling process for thinning high manganese austenitic steel grains

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20111123