Prior art keywords
information
function
resource
production equipment
moves
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010800010268A
Other languages
Chinese (zh)
Inventor
车硕根
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ADVANCED CONSULTING SERVICES CORP
Original Assignee
ADVANCED CONSULTING SERVICES CORP
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ADVANCED CONSULTING SERVICES CORP filed Critical ADVANCED CONSULTING SERVICES CORP
Publication of CN102239453A publication Critical patent/CN102239453A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G05CONTROLLING; REGULATING
    • G05BCONTROL OR REGULATING SYSTEMS IN GENERAL; FUNCTIONAL ELEMENTS OF SUCH SYSTEMS; MONITORING OR TESTING ARRANGEMENTS FOR SUCH SYSTEMS OR ELEMENTS
    • G05B19/00Programme-control systems
    • G05B19/02Programme-control systems electric
    • G05B19/418Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM]
    • G05B19/41845Total factory control, i.e. centrally controlling a plurality of machines, e.g. direct or distributed numerical control [DNC], flexible manufacturing systems [FMS], integrated manufacturing systems [IMS] or computer integrated manufacturing [CIM] characterised by system universality, reconfigurability, modularity
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Game Theory and Decision Science (AREA)
  • Tourism & Hospitality (AREA)
  • Educational Administration (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Automation & Control Theory (AREA)
  • General Factory Administration (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a resources configuration automation system for relocating production facilities and a method thereof. The system provides convenience to a production manager by allowing automatic resources configuration with the least amount of manual work and enables a prompt software response to changes in hardware when a production facility moves or changes. The resources configuration automation system for moving production facilities of the present invention comprises: an information generator that is installed in a production facility and generates information according to the relocation or the changes of the production facility; a middleware that collects the primitive data generated from the information generator, transforms the data into configured data, and outputs the production information thereof; and a resources reconfiguration server that registers the production information outputted by the middleware, regenerates the 4M mapping information based on the registered production information, and reconfigures and allocates the resources.

Description

Resource distribution automated system and method thereof when production equipment moves
Technical field
The present invention relates to a kind of configuration robotization when production equipment moves in the manufacturing industry production management system, can realize resource distribution automatically when particularly moving (or change) at production equipment, perhaps can realize resource distribution by minimum manual operation, thereby can provide convenience resource distribution automated system and method thereof in the time of to move according to the corresponding rapidly production equipment that changes software of the change of hardware to production manager.
Background technology
Usually, manufacturing industry is made of each aspects such as people, process, technology and information.From the unitized viewpoint of manufacturing information, manufacture process comprises: improve the inside manufacture process that related basic factor constitutes with achievement by put delivery in storage from starting material till; And the external procedure that constitutes by product design, material purchases, product payment, service of goods, plant design and maintenance etc.
Wherein, from the resources of production digitizing angle of production scene, the resources of production of inner manufacture process are made of 4M (worker (Man), production equipment (Machine), material (Material), production stage (Method)).
Even after the production equipment robotization, use for fullest, when equipment moves, still will import the relevant information of this equipment shift position by the supvr, and in order to manage according to the mobile of production equipment, program to change also.Because after the modification information registration of production equipment, could realize the reconstruct of resource.
The business step of production system in the past is that definition 4M information table is after the setting program, the person (Tag Manager) that defines the tag control again carries out cable work and test, the production process change when executive problem takes place and moving, the program that change is provided with, and repeat following steps.
Here, according to the method for the mobile execution resource reconstruct of production equipment is by supvr manually positional information or other relevant information that moves of the mobile production equipment of input, and directly carry out resource distribution and distribution by the supvr, to alter the procedure, the mobile of described production equipment comprises: the hardware that the production equipment that brings because of moving of waiting of the car type on auto production line change (increase, stop production, move), the improvement activity carried out because of retionalization of physical distriibution etc. moves, changes because of process route (routing) moves etc.
As can be known, above-mentioned resource distribution and distribution method in the past, exist the supvr according to the inconvenience of relevant modification information such as input position information one by one of the mobile needs of production equipment, also have the inconvenience that to carry out in person about the change of the program of resource distribution and distribution etc.
For example, on production information chemical industry preface structure, need be when carrying out production information based on the production information structure of " factory-production line-technology ", need various Enterprise Resource configurations and distribute as the operation of core inscape, but can have the inconvenience that must directly finish by the supvr.
And method in the past also exists, and when the configuration production information, lacks the visuality on user's viewpoint, the layout inconvenience of Process configuration, and the also very difficult shortcoming of carrying out situation of grasping technology in the middle of the application after configuration.
And method in the past also exists, and when changes such as the increase deletion that Facility Layout or operation take place, based on the Process configuration of database and be not easy change, is difficult to accept effectively the subordinative shortcoming between the technology.
Summary of the invention
The inconvenience of the reconstruct when for this reason, the present invention carries out production equipment mobile in order to solve in the past supvr, need the inconvenience of direct change softwares (program) and provide according to the inconvenience that the hardware change supvr must carry out resource distribution and distribution in person according to hardware change.
The technical problem to be solved in the present invention is, resource distribution automated system and method thereof when providing a kind of production equipment to move, when moving (change) at production equipment, automatically realize resource distribution, perhaps utilize minimum manual operation to realize resource distribution, thereby provide convenience to production manager.
Another technical matters that the present invention will solve is, resource distribution automated system and method thereof when providing a kind of production equipment to move according to hardware change, can change corresponding software rapidly.
In order to solve the problems of the technologies described above, be according to the characteristics of " the resource distribution automated system when production equipment moves " of preferred implementation of the present invention, comprising:
The source takes place in information, and this information generation source is arranged at production equipment, is used for moving or change generation information according to described production equipment;
Middleware, this middleware are used to collect the raw data that is produced by described information generation source, and collected raw data is converted to configuration data, and configuration data is output as production information; And
Resource reconstruct server, this resource reconstruct server are used to register the production information by described middleware output, upgrade the 4M map information based on the production information of described registration and come reconstruct and Resources allocation.
Above-mentioned production equipment comprises: the simple device that can't generate modification information automatically; And the intelligent information that can generate described modification information automatically.
Above-mentioned production equipment is for carrying out many kinds limited-production, reconfigurable production system (RMS:Reconfigurable Manufacturing System).
Above-mentioned information generation source is to be used to respond to moving of described production equipment, and produces the sensor of mobile message.
Above-mentioned middleware is sent to described resource reconstruct server by communication bus with the production information of described conversion.
Above-mentioned middleware comprises: the function of automatic identification equipment state; Confirm the function of starting rate; The function that when unit exception, gives the alarm; The production information query function; Worker's information management function.
Above-mentioned middleware is used for tagging (Tag) to 4M information, carries out the step that is converted to the 4M data.
Above-mentioned resource reconstruct server comprises ERP server, integrated application server, MES server, gateway server.
Above-mentioned resource reconstruct comprises: operation (process), equipment (Facilities), worker (Worker), logistics (Material), operation and management.
Above-mentioned resource reconstruct server comprises:
The applying template manager, this applying template manager is used to define resource;
Point manager, this manager are used to define Data acquisition, information, finish resource distribution, carry out resource reconstruct, handle monitor message;
The real time data manager, this real time data manager is operably connected to described some manager, is used for incident is notified in the outside, and the state value of storage resources.
Above-mentioned resource reconstruct server comprises: the resource distribution defined function; The 4M middleware is carried out function; Analytic function; The function of reconstruct resource when only the heart moves at work.
Above-mentioned resource distribution defined function is used to the mapping of simulating each layer equipment, definition and Resources allocation, defining BOP (process inventory) mapping, label definition and business procedure.
Above-mentioned 4M middleware is carried out function, is used to define the work centre that comprises worker's terminating machine and measure label, carries out service logic.
Above-mentioned analytic function comprises based on the performance evaluation of KPI and monitoring in real time.
Above-mentioned resource recombination function comprises: the hierarchy editting function that is used to define the hierarchy between 4M and the label; Be used to edit the 4M reference information, generate the 4M reference information editting function of mapping (Map) information between 4M; Be used to extract the label that is registered in a manager, register and edit new label, register and edit label mapping (Mapping) function of the process information of each label; By drawing and abandon the dynamic mapping function of 4M that (drag and drop) upgrades 4M information automatically.
In order to solve the problems of the technologies described above, be according to the characteristics of " the resource distribution automatic mode when production equipment moves " of preferred implementation of the present invention, comprising:
Production information generates step, and the mobile or modification information of the described production equipment that the information generation source that this production information generation step will be installed in described production equipment generates is converted to configuration data and generates production information as source data collection; And
The resource reconstruction step, this resource reconstruction step is registered in middleware with the production information of described generation, upgrades the 4M map information and automatic reconfiguration and Resources allocation based on the production information of described registration.
Above-mentioned middleware comprises: the function of automatic identification equipment state; Confirm the function of starting rate; The function that when unit exception, gives the alarm; The production information query function; Worker's information management function.
Above-mentioned middleware is used for tagging (tag) to 4M information, carries out the step that is converted to the 4M data.
Above-mentioned resource reconstruct comprises: operation (process), equipment, worker, logistics, operation and management.
Above-mentioned resource reconstruction step comprises: the resource distribution defined function; The 4M middleware is carried out function; Analytic function; The function of reconstruct resource when only the heart moves at work.
Above-mentioned resource distribution defined function is used to the mapping of simulating each layer equipment, definition and Resources allocation, defining BOP (process inventory) mapping, label definition and business procedure.
Above-mentioned 4M middleware is carried out function, is used to define the work centre that comprises worker's terminating machine and measure label, carries out service logic.
Above-mentioned resource recombination function comprises: the hierarchy editting function that is used to define the hierarchy between 4M and the label; Be used to edit the 4M reference information, generate the 4M reference information editting function of mapping (Map) information between 4M; Be used to extract the label that is registered in a manager, register and edit new label, register and edit the label mapping function of the process information of each label; By drawing and abandon upgrading automatically the dynamic mapping function of 4M of 4M information.
Description of drawings
The overall schematic of the resource distribution automated system when Fig. 1 moves for production equipment according to the present invention;
Fig. 2 is for being used to illustrate the explanation synoptic diagram of automatic configuration feature in the present invention;
Fig. 3 is in the present invention from the process flow diagram of the automatic configuration of angle of dynamic structure;
Fig. 4 is the structural representation of automatic in the present invention configuration and program;
Fig. 5 is the business step process flow diagram according to goal systems of the present invention;
The process flow diagram of the resource distribution automatic mode when Fig. 6 moves for expression production equipment according to the present invention.
Embodiment
Be elaborated as follows below in conjunction with accompanying drawing to preferred implementation of the present invention.Before the present invention will be described, if think that relevant known function or specifying of structure may influence main points of the present invention, then omits its explanation.
The structural representation of the resource distribution automated system when Fig. 1 moves for the production equipment according to preferred implementation of the present invention comprises that source 111a~115a, middleware 200, resource reconstruct server 300 take place for production equipment 100, information.
Source 111a~115a takes place and is arranged on production equipment (4M) in information, is used to carry out the function according to the mobile generation information of this production equipment.Here, production equipment comprises: controller 111, worker's terminal 112, the timer (Sequencer) (113) that comprises PLC etc., alarm device 114, M2M device 115 etc. can't generate the simple device 110 of modification information automatically; And mobile device 121, bar code 122, RFID 123, OPC 124 etc. can generate the smart machine 120 of above-mentioned modification information automatically.Particularly, production equipment can be to carry out many kinds limited-production, restructural production system (RMS:Reconfigurable Manufacturing System).
Source 111a~115a is taken place in above-mentioned information,, after then being preferably induction and moving trigger pip is generated as the sensor of mobile message if above-mentioned production equipment is a simple device.If above-mentioned production equipment is a smart machine, then be exactly smart machine itself.If when this information generation source was smart machine, then smart machine itself played the effect of wireless sensor node, generate positional information automatically according to moving of self, and offer middleware 200.
Middleware 200 is carried out to collect by above-mentioned information the data that source 111a~115a takes place is taken place, and is converted to configuration data, and is output as the function of production information.
Above-mentioned middleware 200 is sent to above-mentioned resource reconstruct server 300 by communication bus 230 with the production information of above-mentioned conversion, and described middleware 200 comprises: function, production information query function, worker's information management function that the function of automatic identification equipment state, starting rate give the alarm when confirming function, unit exception.Under the preferable case, middleware 200 is carried out above-mentioned 4M information is tagged (Tag), is converted to the function of 4M data.
At this, middleware 200 is divided into: first middleware 210, this first middleware 210 be used for will be arranged at the information of simple device 110 information that source 111a~115a produces takes place is generated as production information; Second middleware 220, this second middleware 220 are used for the wireless messages that smart machine 120 generates is generated as production information.
Resource reconstruct server 300 is used to carry out the production information of registration by above-mentioned middleware 200 outputs, production information based on this registration is upgraded the function that the 4M map information comes reconstruct and Resources allocation, and described resource reconstruct server 300 comprises: ERP server 310, integrated application server 320, MES server 330, gateway server 340.
Hypothesis is carried out resource reconstruct by integrated application server 320 among the present invention.
At this, resource reconstruct comprises: operation (process), equipment, worker, logistics, operation and management information.
Above-mentioned integrated application server 320 as resource reconstruct server 300 comprises: the applying template manager 321 that is used to define resource; Be used to define Data acquisition, information, finish resource distribution, carry out resource reconstruct, and handle the some manager 322 of monitor message; And be operably connected to above-mentioned some manager 322, to the generation of outside notification event, and the real time data manager 323 of the state value of storage resources.
Resource reconstruct server 300 comprises: the function of definition resource distribution; Carry out the function of 4M middleware; Analytic function; Only pass through the function of the mobile reconstruct resource of work centre, the function of described definition resource distribution comprises: simulate the equipment of each layer, and definition and Resources allocation, definition BOP (process inventory) mapping defines the mapping of label and business procedure.
In addition, the function of above-mentioned execution 4M middleware comprises: definition comprises worker's terminating machine and measures the work centre of label, carries out service logic, and above-mentioned analytic function comprises based on the performance evaluation of KPI and implements monitoring.
In addition, above-mentioned resource recombination function comprises: the hierarchy editting function that is used to define hierarchy between 4M and label; Editor 4M reference information, the function of map information between the generation 4M; Extraction is registered in the label of a manager, registers and edit new label, and the label mapping function of registering and editing the technique information of each label; By drawing and abandon upgrading automatically the dynamic mapping function of 4M of 4M information.
Resource distribution automated system when the production equipment among the present invention of said structure moves at often changing the equipment of (moving) according to producing parts, for example, is the RMS that unit constitutes with unit or piece, changes its configuration automatically.
As shown in Figure 1, establishing product equipment 100 can comprise: when move the position or change, can't generate the simple device 110 of modification information automatically, and the smart machine 120 that when move the position or change, can generate modification information automatically.Simple device 110 and smart machine 120 can move in the production scene, just on the problem that can generate modification information automatically, have any different, below, being as the criterion with simple device 110 describes.
When simple device 110 moved, the information generation source 111a~115a that invests this simple device 110 at card generated mobile message, and sends to middleware 200.At this, source 111a~115a takes place and preferably generate trigger pip when equipment changes or is mobile in information, with change of information mode announcement apparatus or mobile sensor.
Equipment is represented the resource of 4M (worker, production equipment, material, production stage), finally the 4M resource should be converted to production information.Here, the worker is worker's terminal, comprise information to harmful content, fault content, production equipment comprises the information about PLC machine performance, relay switch, counter, vibration, position etc., material comprises the information of processed goods, semi-manufacture, substandard products, and production stage comprises bar code, RF-ID/USN, IC-CARD, surveying instrument information.
Along with equipment change or move the information that generates and be communicated to middleware 200, middleware 200 is based on the following function of the information and executing that provides: according to information automatic identification equipments such as device category, feature, version, agreement, DLL, and confirm the function of starting rate; The function that gives the alarm when unusual appears at equipment; The production information query function; Worker's information management function, and the 4M data are converted to configuration data.
At this, as shown in Figure 2, for automatic configuration, middleware 200 is carried out 4M data normalization and synthesization, carries out the labelization (Tag) and the management of 4M data, and carries out the editor and the mapping of 4M data.
Above-mentioned middleware 200 has: the information translation that is used for to source 111a~115a generation to be taken place by the information that is arranged on simple device 110 is first middleware 210 of production information; And second middleware 220 that is used for the wireless messages that smart machine 120 generates is converted to production information.Particularly, in order to ensure the network fiduciary level of wireless sensor network (mash), second middleware, the 220 preferred IPv6 agreements of using.
On the other hand, resource reconstruct server 300, i.e. integrated application server 320 registrations are upgraded the 4M map information by the production information of above-mentioned middleware 200 outputs based on the production information of above-mentioned registration, thereby carry out the function of reconstruct and Resources allocation.
The reconstruct of above-mentioned production information, concerning production equipment, expression is to dropping into quantity, bad number of times, number of run, working time, whether startup/non-startup, the reconstruct of equipment state, concerning material, expression is to the material use amount, the device drives present situation, the energy use amount, production quantity, for Man, expression is to production code member, worker's numbering, action, the non-startup origin of an incident, harmful content, the reconstruct of failure cause, concerning production stage, expression is to production information, quality information, facility information, calendar information, logistics information, the reconstruct of positional information etc.
And the resource reconstruction process step also comprises: operation (process), equipment, worker, logistics and operation and management.
Operation (process) comprising: the reconstruct of the bad data of product data (kind, quantity, turnout (day, month, year, other), operation data (object model is produced in the mixing of cycling time, setup time, each operation), production process figure (pressing the process flow of product/part classification), arrangenent diagram, computer-aided design (CAD) (CAD) file, each operation (type, frequency, reason, other), production designation data (SOP, predetermined period, route, sequence, priority etc.), data in short supply (frequency, concerned process steps, resume).
Equipment comprises: type, quantity, position, function, capacity, mechanical fault data (type (fault, stop), maintain/repair data, the reconstruct of setup time (pressing setup time, instrument, replacing time, load/unload, worker's effect of device).
The worker comprises: the reconstruct of worker's number, work allocation, working range, working time, traveling time, business hours, time of having a rest, holiday etc.
Logistics comprises: (the reconstruct of type, platform number, speed, processing capacity, flow policy (job sharing), logistics processing (preserving (position, capacity, treating apparatus, processing time, processing policy)) etc. of logistics device.
Operation and management comprises: submit management (parts to, product, at goods (WIP)), product is transferred the possession of (frequency, time, treating apparatus (manually, machinery), quantity), flow policy (work allocation, priority), pro-jobs order (pressing the priority of the work of treatment of worker's classification), (bad processing is (discarded in quality management, reprocessing), mechanical fault servicing time), equipment control (the processing scheme of fault machine, indirect processing scheme during mechanical disorder) reconstruct.
Here, the structure of resource reconstruct comprises as shown in Figure 3 and Figure 4: the applying template manager 321 that is used to define resource; Be used to define Data acquisition, information, finish resource distribution, carry out resource reconstruct, and handle the some manager 322 of monitor message; Be operably connected to above-mentioned some manager 322, incident is notified in the outside, and preserve the real time data manager 323 of resource status value.
Obtain the 4M production information at middle layer L0, get in touch by execution level L1 and administration and supervision authorities L2 and plan layer L3 and carry out the 4M middleware.
On the other hand, resource reconstruct server 300 comprises: the function of definition resource distribution, the function of carrying out the 4M middleware, analytic function, the function of the mobile realization resource reconstruct by work centre only.
The function of above-mentioned definition resource distribution is used to simulate each layer equipment, definition and Resources allocation, definition BOP (process inventory) mapping, map tags definition and business procedure.
And the function of above-mentioned execution 4M middleware comprises that definition comprises worker's terminating machine and measures the work centre of label, carries out the function of service logic, and described analytic function is based on KPI and carries out performance evaluation and monitoring in real time.
And above-mentioned resource recombination function comprises: the hierarchy editting function that is used to define the hierarchy between 4M and label; Be used to edit the 4M reference information, generate the 4M reference information editting function of shining upon (Map) information between the 4M; Be used to extract the label that is registered in a manager, register and edit new label, carry out the process information registration of each label and editor's label mapping function; By drawing and abandon upgrading automatically the dynamic mapping function of 4M of 4M information.
Here, the hierarchy editting function is represented, is benchmark with factory-production line-operation, individual other operation factor is defined and is compiled as the function of hierarchy, and the operation factor is carried out modularization with input-processing-output form, with the workflow morphosis and edit the function of operation factor.
4M reference information editting function, expression identification also distributes the resource of 5M (worker, production equipment, material, production stage, measurement (the Measurement)) factor that constitutes operation, and the database information of 5M benchmark is comprehensive and show as the operation benchmark.
Label mapping function, expression are given the also label and the logical mappings relation of management point manager for the measurement of 4M information.
4M dynamically shines upon expression: on the operation structure, with the GUI viewpoint of user's angle, change and manage the change of increase, deletion and the process route information of operation easily; When the process information editor, by drawing and abandon upgrading automatically the related data library information; When being connected, M2M driving arrangement based on general sensor network (USN) discerns automatically from now on, and the automatic generation of operation structural information.
The business step of the resource distribution automated system when Fig. 5 moves for expression production equipment according to the present invention comprises: the 4M table definition; And when workplace and equipment change and mobile service take place, resource distribution is carried out robotization and the business step that is reconstructed.
The mechanism of the resource distribution automatic mode when Fig. 6 moves for expression production equipment according to the present invention, diagram is based on the situation of the automatic reconfiguration of smart machine.
In incipient stage definition resource, function information is carried out in definition, carries out label collection and mapping, and carries out 4M mapping (step S101).
Afterwards, carry out production information generative process (step S110), move (the step S103) of source sensing apparatus takes place by information in this production information generative process, with the mobile message of production equipment as source data collection (step S105) and be converted to configuration data (step S107) and generate production information.
Carry out resource restructuring procedure (step S120) afterwards, this resource restructuring procedure is registered in the production information of above-mentioned generation middleware (step S111), upgrades the 4M map information and reconstruct resource (step S113) and distribute (step S115) based on the production information of above-mentioned registration.
The present invention is not limited to above-mentioned specific preferred implementation; under the situation that does not exceed the claim protection domain; those skilled in the art can carry out various distortion and enforcement to the present invention, and its corresponding change belongs to claim protection domain of the present invention.
Industrial applicibility
Automatic resource configuration when the present invention can realize that production equipment moves (change) or realize resource distribution with minimum manual work, can provide convenience for user (supvr) from the production manager angle, IT knowledge arrangement step that can be minimum, can correspondingly flexibly change, modularization, modularization by management factors minimize complicacy, thereby can improve rig-site utilization.
In addition, the present invention also has by the visuality of the operation flow between the operation is provided, make production manager and worker to grasp in real time and the advantage of analysis procedure situation, also have to make and discern main incident, the required minimized advantage of deferment factor of execution major decision, and the advantage that identification is provided convenience to management factors by providing visual is provided.
In addition, the present invention also has by making clear of the visual of process and measurement project is provided, and makes it possible to discern the advantage of the non-efficiency factor of operation.
In addition, the present invention also has the advantage that can change software according to the rapid correspondence of hardware change.

Claims (26)

1. the resource distribution automated system a when production equipment moves is characterized in that, the resource distribution automated system when this production equipment moves comprises:
The source takes place in information, and this information generation source is arranged in the described production equipment, is used for coming generation information according to the mobile or change of described production equipment;
Middleware, this middleware are used to collect the raw data that is produced by described information generation source, and collected raw data is converted to configuration data, and described configuration data is output as production information; And
Resource reconstruct server, this resource reconstruct server are used to register the production information by described middleware output, and upgrade the 4M map information with reconstruct and Resources allocation based on the production information of being registered.
2. the resource distribution automated system when production equipment according to claim 1 moves is characterized in that, described production equipment comprises: can't generate the simple device of modification information and the smart machine that can generate modification information automatically automatically.
3. the resource distribution automated system when production equipment according to claim 2 moves is characterized in that, described production equipment comprises carries out many kinds limited-production, reconfigurable production system.
4. the resource distribution automated system when production equipment according to claim 1 moves, it is characterized in that described information generation source comprises the sensor that moves and after responding to described moving trigger pip is converted to mobile message that is used to respond to described production equipment.
5. the resource distribution automated system when production equipment according to claim 1 moves is characterized in that, described middleware is sent to described resource reconstruct server by communication bus with the production information of being changed.
6. the resource distribution automated system when production equipment according to claim 5 moves is characterized in that, described middleware comprises: the function of automatic identification equipment state; Confirm the function of device start rate; The function that when described unit exception, gives the alarm; The production information query function; And worker's information management function.
7. the resource distribution automated system when production equipment according to claim 6 moves is characterized in that, described middleware is used for tagging and being the 4M data with described 4M information translation to 4M information.
8. the resource distribution automated system when production equipment according to claim 1 moves, it is characterized in that, described resource reconstruct server comprises ERP server, integrated application server, MES server, NM server, or any server in above-mentioned each server.
9. the resource distribution automated system when production equipment according to claim 1 moves is characterized in that, described resource reconstruct comprises: operation, equipment, worker, logistics, operation and management.
10. the resource distribution automated system when production equipment according to claim 8 moves is characterized in that, described resource reconstruct server comprises:
The applying template manager, this applying template manager is used to define resource;
Point manager, this manager are used to define Data acquisition, information, finish resource distribution, carry out resource reconstruct and handle monitor message; And
The real time data manager, this real time data manager is operably connected to described some manager, is used for incident is notified in the outside, and the state value of storage resources.
11. the resource distribution automated system when production equipment according to claim 10 moves is characterized in that, described resource reconstruct server comprises: the resource distribution defined function; The 4M middleware is carried out function; Analytic function; And the function of the described resource of reconstruct when only the heart moves at work.
The resource distribution automated system when 12. production equipment according to claim 11 moves, it is characterized in that described resource distribution defined function comprises: the mapping of simulating each layer equipment, definition and Resources allocation, the mapping of definition procedure inventory, label definition and business procedure.
13. the resource distribution automated system when production equipment according to claim 11 moves is characterized in that, described 4M middleware is carried out function and comprised: definition comprises worker's terminating machine and measures the work centre of label, and carries out service logic.
14. the resource distribution automated system when production equipment according to claim 11 moves is characterized in that, described analytic function comprises based on the performance evaluation of KPI and monitoring in real time.
15. the resource distribution automated system when production equipment according to claim 11 moves is characterized in that, described resource recombination function comprises: the hierarchy editting function that is used to define the hierarchy between 4M and the label; Be used to edit the 4M reference information, generate the 4M reference information editting function of the map information between 4M; Be used for extracting the label that is registered in a manager, register and edit new label, register and edit the label mapping function of the process information of each label; And by drawing and abandon upgrading automatically the dynamic mapping function of 4M of 4M information.
16. the resource distribution automatic mode a when production equipment moves is characterized in that, the resource distribution automatic mode when this production equipment moves comprises:
Production information generates step, this production information generates step will be installed in moving of described production equipment that the information generation source in the described production equipment generates or modification information as source data collection, and described raw data is converted to configuration data to generate production information; And
The resource reconstruction step, this resource reconstruction step is registered in the production information that is generated in the middleware, and upgrades the 4M map information with automatic reconfiguration and Resources allocation based on the production information of being registered.
17. the resource distribution automatic mode when production equipment according to claim 16 moves is characterized in that, described middleware comprises: the function of automatic identification equipment state; Confirm the function of device start rate; The function that when unit exception, gives the alarm; The production information query function; And worker's information management function.
18. the resource distribution automatic mode when production equipment according to claim 17 moves is characterized in that, described middleware is used for tagging and being the 4M data with described 4M information translation to 4M information.
19. the resource distribution automatic mode when production equipment according to claim 16 moves is characterized in that, described resource reconstruct comprises: operation, equipment, worker, logistics, operation and management.
20. the resource distribution automatic mode when production equipment according to claim 16 moves is characterized in that, described resource reconstruction step comprises: the resource distribution defined function; The 4M middleware is carried out function; Analytic function; And the function of the described resource of reconstruct when only the heart moves at work.
The resource distribution automatic mode when 21. production equipment according to claim 20 moves, it is characterized in that described resource distribution defined function comprises: the mapping of simulating each layer equipment, definition and Resources allocation, the mapping of definition procedure inventory, label definition and business procedure.
22. the resource distribution automatic mode when production equipment according to claim 20 moves is characterized in that, described 4M middleware is carried out function and comprised: definition comprises worker's terminating machine and measures the work centre of label, and carries out service logic.
23. the resource distribution automatic mode when production equipment according to claim 20 moves is characterized in that, described resource recombination function comprises: the hierarchy editting function that is used to define the hierarchy between 4M and the label.
24. the resource distribution automatic mode when production equipment according to claim 23 moves is characterized in that, described resource recombination function also comprises: the 4M reference information editting function that is used to edit the 4M reference information and generates the map information between 4M.
The resource distribution automatic mode when 25. production equipment according to claim 24 moves, it is characterized in that described resource recombination function also comprises: the label mapping function that is used for extracting label, the registration that is registered in a manager and edits new label, registration and edit the process information of each label.
26. the resource distribution automatic mode when production equipment according to claim 25 moves is characterized in that, described resource recombination function also comprises: by drawing and abandon upgrading automatically the dynamic mapping function of 4M of 4M information.
CN2010800010268A 2010-02-25 2010-02-25 Resources configuration automation system for relocation of production facilities and method thereof Pending CN102239453A (en)

Applications Claiming Priority (3)

Application Number Priority Date Filing Date Title
KR1020100017004A KR101057614B1 (en) 2010-02-25 2010-02-25 Resources configuration automation system of moving production facilities and method thereof
PCT/KR2010/001195 WO2011105641A1 (en) 2010-02-25 2010-02-25 Resources configuration automation system for relocation of production facilities and method thereof
KR10-2010-0017004 2010-02-25

Publications (1)

Publication Number Publication Date
CN102239453A true CN102239453A (en) 2011-11-09

Family

ID=44507030

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010800010268A Pending CN102239453A (en) 2010-02-25 2010-02-25 Resources configuration automation system for relocation of production facilities and method thereof

Country Status (4)

Country Link
JP (1) JP2012511221A (en)
KR (1) KR101057614B1 (en)
CN (1) CN102239453A (en)
WO (1) WO2011105641A1 (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107924178A (en) * 2015-12-01 2018-04-17 欧姆龙株式会社 Management system and management program
CN110543158A (en) * 2016-07-25 2019-12-06 锐界全球公司 Parallel manufacturing system and method

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101295731B1 (en) 2012-06-13 2013-08-12 수성대학교 산학협력단 Terminal for automatic recognition apparatus
KR101536350B1 (en) * 2013-04-05 2015-07-14 (주)에이시에스 Self-management system of production resources based wired and wireless sensor network
CN103606060A (en) * 2013-12-04 2014-02-26 国家电网公司 Power equipment service processing method and system
JP6563274B2 (en) 2015-08-20 2019-08-21 三菱重工業株式会社 Production equipment, production equipment design method, and production equipment control method and manufacturing method
KR101716582B1 (en) * 2015-10-26 2017-03-14 현대오토에버 주식회사 Integrated processing system based on data distribution service and operating method thereof
KR102393944B1 (en) 2017-04-21 2022-05-04 한국전자통신연구원 Flexible assembly system for multi-product production and method of reconstructing a production line
KR102442296B1 (en) 2018-12-28 2022-09-15 한국전자통신연구원 Variable reconfiguration flexible assembly system and production line reconstruction method
CN110766374A (en) * 2019-09-04 2020-02-07 华云数据(厦门)网络有限公司 Asset automation control method, device, system, equipment and storage medium
CN112947154A (en) * 2021-01-28 2021-06-11 山西云时代太钢信息自动化技术有限公司 Automatic information acquisition device and printing method in carbon fiber production process
KR102474332B1 (en) * 2021-05-10 2022-12-05 충북대학교 산학협력단 Prediction method of machine health stability in smart factory system, and recording medium thereof
KR102454168B1 (en) * 2022-08-08 2022-10-14 주식회사 와이즈엠시스템즈 Manufacturing performance integrated management system

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050004902A (en) * 2002-05-31 2005-01-12 어드밴스드 마이크로 디바이시즈, 인코포레이티드 Specialization of active software agents in an automated manufacturing environment
KR20060113957A (en) * 2003-11-21 2006-11-03 지멘스 악티엔게젤샤프트 Method for operating industrial installations
KR20080004049A (en) * 2006-07-04 2008-01-09 Stx조선주식회사 A method of managing a production of a ship
CN101308376A (en) * 2008-06-27 2008-11-19 天津市天锻压力机有限公司 Electrode bar product double-station moving device numerical control system
KR20090073463A (en) * 2007-12-31 2009-07-03 주식회사 동부하이텍 Mathod for manufacturing of image sensor

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2005352993A (en) * 2004-06-14 2005-12-22 Tenma Kk Production planning support system and production planning support method
KR100695533B1 (en) * 2006-09-11 2007-03-16 (주)에이시에스 Production Management System base The Ubiquitous
KR100788009B1 (en) 2007-07-13 2007-12-21 (주)에이시에스 Collaborative production system
KR20090073643A (en) * 2007-12-31 2009-07-03 경남도립남해대학 산학협력단 Manufacturing line information serving system and method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20050004902A (en) * 2002-05-31 2005-01-12 어드밴스드 마이크로 디바이시즈, 인코포레이티드 Specialization of active software agents in an automated manufacturing environment
KR20060113957A (en) * 2003-11-21 2006-11-03 지멘스 악티엔게젤샤프트 Method for operating industrial installations
KR20080004049A (en) * 2006-07-04 2008-01-09 Stx조선주식회사 A method of managing a production of a ship
KR20090073463A (en) * 2007-12-31 2009-07-03 주식회사 동부하이텍 Mathod for manufacturing of image sensor
CN101308376A (en) * 2008-06-27 2008-11-19 天津市天锻压力机有限公司 Electrode bar product double-station moving device numerical control system

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107924178A (en) * 2015-12-01 2018-04-17 欧姆龙株式会社 Management system and management program
US10747212B2 (en) 2015-12-01 2020-08-18 Omron Corporation Management system and non-transitory computer-readable recording medium
CN110543158A (en) * 2016-07-25 2019-12-06 锐界全球公司 Parallel manufacturing system and method
CN110543158B (en) * 2016-07-25 2022-08-30 蕾瑞吉公司 Parallel manufacturing system and method

Also Published As

Publication number Publication date
JP2012511221A (en) 2012-05-17
KR101057614B1 (en) 2011-08-19
WO2011105641A1 (en) 2011-09-01

Similar Documents

Publication Publication Date Title
CN102239453A (en) Resources configuration automation system for relocation of production facilities and method thereof
CN106779406B (en) MES system based on RFID
CN107248021B (en) MES system is made to platform-based intelligence
US8190279B2 (en) Production line management system
CN109906467B (en) Information management system
CN108614526B (en) Reconfigurable production process management system
CN103930870B (en) Generate and process the method and engineering system of component application for physical assemblies
CN107844098A (en) A kind of digital factory management system and management method
CN108229782A (en) A kind of visual production management platform based on cloud
CN103164754A (en) Method and manufacturing execution system (MES) framework for production management and control process of clothing industry
CN104091224A (en) System and method for real-time acquisition and analysis of production line data
CN112270612A (en) Dairy product digital factory system
CN102831513A (en) Container logistics field oriented IoT (Internet of Things) application-layer middleware and information fusion integration method
Wang et al. Framework of automated value stream mapping for lean production under the Industry 4.0 paradigm
CN113657730B (en) Integrated execution platform for digital manufacturing
Iglesias et al. Product line engineering of monitoring functionality in industrial cyber-physical systems: a domain analysis
Zhang et al. Coloured Petri net-based active sensing system of real-time and multi-source manufacturing information for smart factory
Wagner et al. Engineering processes for decentralized factory automation systems
CN110930111A (en) APP (application) for unified management of physical assets and mobile operation
CN110516939A (en) Warehouse homework dispatches system
Cupek et al. “Digital Twins” for highly customized electronic devices–Case study on a rework operation
CN101539772A (en) Product lifecycle management method and apparatus
CN102521711B (en) The control method of the data model structure of equipment quality characteristic and device
CN113448693A (en) SAAS cloud platform of digital factory
Leitão et al. Instantiating the PERFORM system architecture for industrial case studies

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20111109