CN102063166A - 集装箱式数据中心 - Google Patents
集装箱式数据中心 Download PDFInfo
- Publication number
- CN102063166A CN102063166A CN2010105537151A CN201010553715A CN102063166A CN 102063166 A CN102063166 A CN 102063166A CN 2010105537151 A CN2010105537151 A CN 2010105537151A CN 201010553715 A CN201010553715 A CN 201010553715A CN 102063166 A CN102063166 A CN 102063166A
- Authority
- CN
- China
- Prior art keywords
- data center
- cabin
- chilling units
- water chilling
- handpiece water
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05K—PRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
- H05K7/00—Constructional details common to different types of electric apparatus
- H05K7/14—Mounting supporting structure in casing or on frame or rack
- H05K7/1485—Servers; Data center rooms, e.g. 19-inch computer racks
- H05K7/1497—Rooms for data centers; Shipping containers therefor
-
- H—ELECTRICITY
- H05—ELECTRIC TECHNIQUES NOT OTHERWISE PROVIDED FOR
- H05K—PRINTED CIRCUITS; CASINGS OR CONSTRUCTIONAL DETAILS OF ELECTRIC APPARATUS; MANUFACTURE OF ASSEMBLAGES OF ELECTRICAL COMPONENTS
- H05K7/00—Constructional details common to different types of electric apparatus
- H05K7/20—Modifications to facilitate cooling, ventilating, or heating
- H05K7/20709—Modifications to facilitate cooling, ventilating, or heating for server racks or cabinets; for data centers, e.g. 19-inch computer racks
- H05K7/20763—Liquid cooling without phase change
- H05K7/2079—Liquid cooling without phase change within rooms for removing heat from cabinets
Landscapes
- Engineering & Computer Science (AREA)
- Computer Hardware Design (AREA)
- General Engineering & Computer Science (AREA)
- Microelectronics & Electronic Packaging (AREA)
- Physics & Mathematics (AREA)
- Thermal Sciences (AREA)
- Cooling Or The Like Of Electrical Apparatus (AREA)
Abstract
本发明公开了一种集装箱式数据中心,属于数据中心领域。所述集装箱式数据中心包括:集装箱式箱体,所述箱体内部分为设备舱、供配电舱和冷水机组舱;所述箱体上设置门;所述供配电舱中安装供电设备;所述设备舱中安装电子设备和水冷末端;所述冷水机组舱中安装冷水机组,所述冷水机组与所述水冷末端相连,为所述水冷末端提供冷水。本发明通过在单个箱体内完成设备舱、供配电舱和冷水机组舱的全布局,满足了集装箱式数据中心内部对制冷的需求,而不需要额外部署制冷设备,节省了基础设施建造的时间,使集装箱式数据中心可以即到即用,实现了集装箱式数据中心的快速部署和应急配备。
Description
技术领域
本发明涉及数据中心领域,特别涉及一种集装箱式数据中心。
背景技术
集装箱式数据中心作为一种低成本、高能效、机动灵活和快速部署的数据中心,已经逐渐被各大设备商采用。
现有技术中的箱式数据中心的基础设施包括集装箱式箱体,箱体内部分为设备区和供配电区:设备区安装机柜,机柜内部安装数据设备;供配电区安装供配电设备,该供配电设备包括不间断电源、配电柜及发电机。在设备区和供配电区都装有空调、火灾报警器、消防设施、安全监控设备中的一种或几种。设备区和供配电区之间设有隔板,隔板上有门。
现有技术中的箱式数据中心采用两舱式设计,只是将数据中心必备的设施进行了组合,在箱式数据中心使用普通精密空调进行冷却,空调的制冷量小,无法满足数据中心在大功耗情况下的制冷要求,需要额外部署制冷设备,使该箱式数据中心不能即到即用,无法实现箱式数据中心的快速部署和应急配备。
发明内容
为了实现集装箱式数据中心的快速部署和应急配备,使集装箱式数据中心可以即到即用,而不需要额外部署制冷设备,本发明实施例提供了一种集装箱式数据中心,所述数据中心包括:
集装箱式箱体,所述箱体内部分为设备舱、供配电舱和冷水机组舱;
所述箱体上设置门;
所述供配电舱中安装供电设备;
所述设备舱中安装电子设备和水冷末端;
所述冷水机组舱中安装冷水机组,所述冷水机组与所述水冷末端相连,为所述水冷末端提供冷水。
本发明实施例提供的技术方案,通过在单个箱体内完成设备舱、供配电舱和冷水机组舱的全布局,满足了集装箱式数据中心内部对制冷的需求,而不需要额外部署制冷设备,节省了基础设施建造的时间,使集装箱式数据中心可以即到即用,实现了集装箱式数据中心的快速部署和应急配备。
附图说明
为了更清楚地说明本发明实施例中的技术方案,下面将对实施例描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其他的附图。
图1是本发明实施例一提供的集装箱式数据中心的立体图;
图2是本发明实施例二提供的第一种集装箱式数据中心的俯视图;
图3是本发明实施例二提供的第一种集装箱式数据中心的冷水机组风道示意图;
图4是本发明实施例二提供的第二种集装箱式数据中心的冷水机组风道示意图;
图5是本发明实施例二提供的第三种集装箱式数据中心的冷水机组风道示意图;
图6是本发明实施例二提供的第二种集装箱式数据中心的俯视图;
图7是本发明实施例二提供的第三种集装箱式数据中心的俯视图。
具体实施方式
为使本发明的目的、技术方案和优点更加清楚,下面将结合附图对本发明实施方式作进一步地详细描述。
实施例一
本发明实施例提供了一种集装箱式数据中心,参见图1,包括:
集装箱式箱体1,该箱体1内部分为设备舱11、供配电舱12和冷水机组舱13,且该箱体1上设置门111、门112、门121和门131;设备舱11中安装电子设备113和水冷末端114;供配电舱12中安装供电设备122;冷水机组舱13中安装冷水机组132,该冷水机组132与水冷末端114相连,为水冷末端114提供冷水。
本发明实施例提供的集装箱式数据中心,通过在单个箱体内完成设备舱、供配电舱和冷水机组舱的全布局,满足了集装箱式数据中心内部对制冷的需求,而不需要额外部署制冷设备,节省了基础设施建造的时间,使集装箱式数据中心可以即到即用,实现了集装箱式数据中心的快速部署和应急配备。
实施例二
本发明实施例提供了一种集装箱式数据中心,请同时参见图1和图2,包括:
集装箱式箱体1,该箱体1内部分为设备舱11、供配电舱12和冷水机组舱13,其中,供配电舱12居于箱体1的中间,设备舱11居于供配电舱12的右侧,冷水机组舱13居于供配电舱12的左侧。箱体1中的设备舱11、供配电舱12和冷水机组舱13上分别设置门111、门112、门121和门131供出入,每个舱既可以设置一个门,如,供配电舱12设置门121,冷水机组舱13设置门131,也可以设置多个门供出入,如,设备舱11可以在每两排电子机架115之间、电子机架115与舱壁之间都设有门,见图1中的门111和门112。
其中,设备舱11中安装电子设备113和水冷末端114。该电子设备113安装在电子机架115上,该电子机架115垂直于箱体1的长边且平行设置;该电子机架115的宽度为500毫米-600毫米,本发明实施例仅以电子机架115的宽度为550毫米为例进行说明,但对此不作具体限定。水冷末端114置于设备舱11的底部、或顶部、或电子机架115侧部,用于为设备舱11制冷,降低设备舱11内的温度。
供配电舱12中安装供电设备122,用于为设备舱11和冷水机组舱13提供不间断的供电。该供电设备122包括UPS(Uninterruptible Power Supply,不间断电源)122a和电池122b,还可以包括其它供电设备,本发明实施例对此不作具体限定。供配电舱12中还可以安装水冷末端123,置于供配电舱12的底部、或顶部、或供电设备122侧部,用于为供配电舱12制冷,降低供配电舱12内的温度,也可以不安装水冷末端123,本发明实施例仅以安装水冷末端123为例进行说明,但不限定于此。
冷水机组舱13中安装冷水机组132,本发明实施例不对冷水机组132的种类进行具体限定,可以采用风冷式冷水机组或水冷式冷水机组等。该冷水机组132与设备舱11中的水冷末端114和供配电舱12中的水冷末端123相连,用于制冷,为水冷末端114和水冷末端123提供冷水,并对水冷末端114和水冷末端123流回的水进行降温。结合图3,为冷水机组132的风道示意图,该冷水机组132的风道采用下壁设置进风口、上壁设置出风口的风道结构进行通风,为冷水机组132进行降温,其不含通风口的箱壁密封,可以隔离噪声。参见图4和图5,本发明实施例不对冷水机组132风道结构进行具体限定,还可采用侧壁设置进风口、上壁设置出风口和侧壁设置进风口、侧壁设置出风口等风道结构。
具体地,集装箱式箱体1内部的设备舱11、供配电舱12和冷水机组舱13三者的位置可以任意排列,本发明实施例对此不作具体限定。既可以如图2所示,采用供配电舱12居中、设备舱11和冷水机组舱13居于两侧;也可以如图6所示,采用设备舱11居中、供配电舱12和冷水机组舱13居于两侧;还可以如图7所示,采用冷水机组舱13居中、设备舱11和供配电舱12居于两侧。其中,供配电舱12为设备舱11和冷水机组舱13提供不间断的电源,冷水机组舱13为设备舱11和供配电舱12制冷。
进一步地,设备舱11、供配电舱12和冷水机组舱13之间相邻的各舱体之间用隔板14隔开,隔板14上有门或无门。本发明实施例仅以隔板14上无门为例进行说明,但不限定于此。
另外,设备舱11、供配电舱12和冷水机组舱13中还可以设置火灾报警器、消防设施和安全监控设备中的一种或几种。
综上所述,本发明实施例提供的集装箱式数据中心,通过在单个箱体内完成设备舱、供配电舱和冷水机组舱的全布局,满足了集装箱式数据中心内部对制冷的需求,而不需要额外部署制冷设备,节省了基础设施建造的时间,使集装箱式数据中心可以即到即用,实现了集装箱式数据中心的快速部署和应急配备;另外,当采用550毫米宽的电子机架,且垂直于设备舱的长边平行设置,使电子机架的排列密度更高,从而使可安装的电子设备更多,对集装箱式数据中心的空间利用更充分。
以上所述仅为本发明的较佳实施例,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。
Claims (11)
1.一种集装箱式数据中心,其特征在于,所述数据中心包括:
集装箱式箱体,所述箱体内部分为设备舱、供配电舱和冷水机组舱;
所述箱体上设置门;
所述供配电舱中安装供电设备;
所述设备舱中安装电子设备和水冷末端;
所述冷水机组舱中安装冷水机组,所述冷水机组与所述水冷末端相连,为所述水冷末端提供冷水。
2.根据权利要求1所述的数据中心,其特征在于,所述箱体上设置门,具体包括:
所述设备舱、所述供配电舱和所述冷水机组舱有各自的门供出入,且每个舱至少设置一个门。
3.根据权利要求1所述的数据中心,其特征在于,所述电子设备安装在电子机架上。
4.根据权利要求3所述的数据中心,其特征在于,所述电子机架垂直于所述箱体的长边且平行设置。
5.根据权利要求3所述的数据中心,其特征在于,所述电子机架的宽度为500毫米-600毫米。
6.根据权利要求1所述的数据中心,其特征在于,所述水冷末端置于所述设备舱的底部、或顶部、或所述电子机架侧部。
7.根据权利要求1所述的数据中心,其特征在于,所述供电设备包括不间断电源和电池。
8.根据权利要求1所述的数据中心,其特征在于,所述供配电舱中还安装水冷末端,所述水冷末端与所述冷水机组相连,置于所述供配电舱的底部、或顶部、或所述供电设备侧部。
9.根据权利要求1所述的数据中心,其特征在于,所述冷水机组不含通风口的箱壁密封,采用下壁设置进风口、上壁设置出风口,侧壁设置进风口、上壁设置出风口和侧壁设置进风口、侧壁设置出风口中的任意一种风道结构。
10.根据权利要求1所述的数据中心,其特征在于,所述设备舱、所述供配电舱和所述冷水机组舱三者的位置任意排列,采用供配电舱居中其它舱设于两侧、设备舱居中其它舱设于两侧和冷水机组舱居中其它舱设于两侧中的任意一种,且相邻的各舱体之间用隔板隔开,所述隔板上有门或无门。
11.根据权利要求1所述的数据中心,其特征在于,所述设备舱、所述供配电舱和所述冷水机组舱中,还包括:
火灾报警器、消防设施和安全监控设备中的一种或几种。
Priority Applications (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010105537151A CN102063166A (zh) | 2010-11-17 | 2010-11-17 | 集装箱式数据中心 |
PCT/CN2011/074158 WO2011137774A1 (zh) | 2010-11-17 | 2011-05-17 | 集装箱式数据中心 |
US13/337,545 US8755184B2 (en) | 2010-11-17 | 2011-12-27 | Container data center |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010105537151A CN102063166A (zh) | 2010-11-17 | 2010-11-17 | 集装箱式数据中心 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN102063166A true CN102063166A (zh) | 2011-05-18 |
Family
ID=43998472
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010105537151A Pending CN102063166A (zh) | 2010-11-17 | 2010-11-17 | 集装箱式数据中心 |
Country Status (3)
Country | Link |
---|---|
US (1) | US8755184B2 (zh) |
CN (1) | CN102063166A (zh) |
WO (1) | WO2011137774A1 (zh) |
Cited By (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102403778A (zh) * | 2011-11-04 | 2012-04-04 | 浪潮电子信息产业股份有限公司 | 一种集装箱数据中心的供电方法 |
CN102427705A (zh) * | 2011-11-02 | 2012-04-25 | 方正国际软件有限公司 | 集装箱数据中心节能水冷装置 |
CN102438924A (zh) * | 2011-06-22 | 2012-05-02 | 华为技术有限公司 | 一种集装箱式制冷*** |
CN102854961A (zh) * | 2012-09-12 | 2013-01-02 | 中金数据***有限公司 | 一种集装箱式数据中心 |
CN103771046A (zh) * | 2014-01-09 | 2014-05-07 | 中国人民解放军总后勤部军需装备研究所 | 一种速冻冷藏方舱 |
WO2017157204A1 (zh) * | 2016-03-17 | 2017-09-21 | 韩磊 | 集装箱式数据中心的防御电磁脉冲攻击*** |
CN107302832A (zh) * | 2016-04-15 | 2017-10-27 | 腾讯科技(深圳)有限公司 | 一种数据中心 |
CN107771015A (zh) * | 2017-11-29 | 2018-03-06 | 郑州云海信息技术有限公司 | 一种数据中心 |
WO2022246717A1 (zh) * | 2021-05-27 | 2022-12-01 | 华为数字能源技术有限公司 | 储能集装箱 |
Families Citing this family (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US8116080B2 (en) * | 2009-12-28 | 2012-02-14 | International Business Machines Corporation | Container-based data center having greater rack density |
US8554390B2 (en) * | 2010-11-16 | 2013-10-08 | International Business Machines Corporation | Free cooling solution for a containerized data center |
WO2014130891A1 (en) * | 2013-02-22 | 2014-08-28 | Green Revolution Cooling, Inc. | Liquid cooled modular data center |
WO2014174607A1 (ja) * | 2013-04-24 | 2014-10-30 | 株式会社日立システムズ | 空調設備を備えたコンテナ型データセンター |
JP5762646B2 (ja) * | 2013-04-24 | 2015-08-12 | 株式会社日立システムズ | コンテナ型データセンター |
US9784460B2 (en) * | 2013-08-01 | 2017-10-10 | Nautilus Data Technologies, Inc. | Data center facility and process that utilizes a closed-looped heat management system |
MX2014009795A (es) * | 2014-08-13 | 2014-12-09 | Sixsigma Networks Mexico S A De C V | Centro de procesamiento de datos movil. |
AU2016258540A1 (en) | 2015-05-01 | 2017-11-02 | Baselayer Technology, Llc | Side-cooled modular data center |
WO2017040575A1 (en) * | 2015-09-02 | 2017-03-09 | Revolver 26 Investment Corporation | Integrated high density server vault with hvac ups backup |
WO2018145201A1 (en) | 2017-02-08 | 2018-08-16 | Upstream Data Inc. | Blockchain mine at oil or gas facility |
US10756542B2 (en) | 2018-01-26 | 2020-08-25 | Smart Wires Inc. | Agile deployment of optimized power flow control system on the grid |
US10396533B1 (en) | 2018-02-22 | 2019-08-27 | Smart Wires Inc. | Containerized power flow control systems |
US10314206B1 (en) | 2018-04-25 | 2019-06-04 | Dell Products, L.P. | Modulating AHU VS RAM air cooling, based on vehicular velocity |
US10440863B1 (en) | 2018-04-25 | 2019-10-08 | Dell Products, L.P. | System and method to enable large-scale data computation during transportation |
US11036265B2 (en) | 2018-04-25 | 2021-06-15 | Dell Products, L.P. | Velocity-based power capping for a server cooled by air flow induced from a moving vehicle |
US10368469B1 (en) * | 2018-04-25 | 2019-07-30 | Dell Products, L.P. | Pre-heating supply air for IT equipment by utilizing transport vehicle residual heat |
US10499533B1 (en) | 2018-08-01 | 2019-12-03 | Fujitsu Limited | Container cabling systems and methods |
CA3183109A1 (en) | 2019-05-15 | 2020-11-19 | Upstream Data Inc. | Portable blockchain mining system and methods of use |
US11946269B2 (en) * | 2022-03-21 | 2024-04-02 | Nautilus True, Llc | Modular integrated system modules |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2548392Y (zh) * | 2002-05-10 | 2003-04-30 | 民盈电讯有限公司 | 集装箱式数据中心 |
US20090225513A1 (en) * | 2008-03-10 | 2009-09-10 | Adrian Correa | Device and methodology for the removal of heat from an equipment rack by means of heat exchangers mounted to a door |
CN101755248A (zh) * | 2007-07-19 | 2010-06-23 | 惠普开发有限公司 | 模块化高密度计算机*** |
Family Cites Families (17)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN1464770A (zh) * | 2002-06-13 | 2003-12-31 | 民盈电讯有限公司 | 箱式数据中心基础设施及其集装箱式数据中心 |
US7046514B2 (en) * | 2003-03-19 | 2006-05-16 | American Power Conversion Corporation | Data center cooling |
WO2007139559A1 (en) * | 2006-06-01 | 2007-12-06 | Exaflop Llc | Controlled warm air capture |
US7551971B2 (en) * | 2006-09-13 | 2009-06-23 | Sun Microsystems, Inc. | Operation ready transportable data center in a shipping container |
US7511960B2 (en) * | 2006-09-13 | 2009-03-31 | Sun Microsystems, Inc. | Balanced chilled fluid cooling system for a data center in a shipping container |
US7297015B1 (en) | 2007-03-19 | 2007-11-20 | International Business Machines Corporation | Apparatus for docking a printed circuit board |
JP2010156467A (ja) * | 2007-04-20 | 2010-07-15 | Alps Electric Co Ltd | 液冷システム |
JP2009031557A (ja) * | 2007-07-27 | 2009-02-12 | Alps Electric Co Ltd | 液冷システム |
US8411439B1 (en) * | 2007-09-28 | 2013-04-02 | Exaflop Llc | Cooling diversity in data centers |
US7961463B2 (en) * | 2008-04-02 | 2011-06-14 | Microsoft Corporation | Power efficient data center |
WO2009137215A2 (en) * | 2008-05-05 | 2009-11-12 | Carrier Corporation | Integrated computer equipment container and cooling unit |
US7852627B2 (en) * | 2008-10-31 | 2010-12-14 | Dell Products L.P. | System and method for high density information handling system enclosure |
US20100141105A1 (en) * | 2008-12-04 | 2010-06-10 | Thermocabinet, Llc | Thermal Management Cabinet for Electronic Equipment |
US7903404B2 (en) * | 2009-04-29 | 2011-03-08 | Hewlett-Packard Development Company, L.P. | Data centers |
US8031468B2 (en) * | 2009-06-03 | 2011-10-04 | American Power Conversion Corporation | Hot aisle containment cooling unit and method for cooling |
GB2467808B (en) * | 2009-06-03 | 2011-01-12 | Moduleco Ltd | Data centre |
CN101844655B (zh) * | 2010-04-01 | 2011-12-28 | 上海海洋大学 | 车载集装箱两用制冷*** |
-
2010
- 2010-11-17 CN CN2010105537151A patent/CN102063166A/zh active Pending
-
2011
- 2011-05-17 WO PCT/CN2011/074158 patent/WO2011137774A1/zh active Application Filing
- 2011-12-27 US US13/337,545 patent/US8755184B2/en active Active
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN2548392Y (zh) * | 2002-05-10 | 2003-04-30 | 民盈电讯有限公司 | 集装箱式数据中心 |
CN101755248A (zh) * | 2007-07-19 | 2010-06-23 | 惠普开发有限公司 | 模块化高密度计算机*** |
US20090225513A1 (en) * | 2008-03-10 | 2009-09-10 | Adrian Correa | Device and methodology for the removal of heat from an equipment rack by means of heat exchangers mounted to a door |
Cited By (14)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102438924A (zh) * | 2011-06-22 | 2012-05-02 | 华为技术有限公司 | 一种集装箱式制冷*** |
WO2012103700A1 (zh) * | 2011-06-22 | 2012-08-09 | 华为技术有限公司 | 集装箱式制冷*** |
US9574813B2 (en) | 2011-06-22 | 2017-02-21 | Huawei Technologies Co., Ltd. | Container-type refrigeration system |
CN102427705A (zh) * | 2011-11-02 | 2012-04-25 | 方正国际软件有限公司 | 集装箱数据中心节能水冷装置 |
CN102403778A (zh) * | 2011-11-04 | 2012-04-04 | 浪潮电子信息产业股份有限公司 | 一种集装箱数据中心的供电方法 |
CN102854961A (zh) * | 2012-09-12 | 2013-01-02 | 中金数据***有限公司 | 一种集装箱式数据中心 |
CN103771046B (zh) * | 2014-01-09 | 2016-08-17 | 中国人民解放军总后勤部军需装备研究所 | 一种速冻冷藏方舱 |
CN103771046A (zh) * | 2014-01-09 | 2014-05-07 | 中国人民解放军总后勤部军需装备研究所 | 一种速冻冷藏方舱 |
WO2017157204A1 (zh) * | 2016-03-17 | 2017-09-21 | 韩磊 | 集装箱式数据中心的防御电磁脉冲攻击*** |
CN107205334A (zh) * | 2016-03-17 | 2017-09-26 | 韩磊 | 集装箱式数据中心的防御电磁脉冲攻击*** |
CN107302832A (zh) * | 2016-04-15 | 2017-10-27 | 腾讯科技(深圳)有限公司 | 一种数据中心 |
CN107771015A (zh) * | 2017-11-29 | 2018-03-06 | 郑州云海信息技术有限公司 | 一种数据中心 |
CN107771015B (zh) * | 2017-11-29 | 2019-09-06 | 郑州云海信息技术有限公司 | 一种数据中心 |
WO2022246717A1 (zh) * | 2021-05-27 | 2022-12-01 | 华为数字能源技术有限公司 | 储能集装箱 |
Also Published As
Publication number | Publication date |
---|---|
US20120134107A1 (en) | 2012-05-31 |
US8755184B2 (en) | 2014-06-17 |
WO2011137774A1 (zh) | 2011-11-10 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102063166A (zh) | 集装箱式数据中心 | |
CN210328316U (zh) | 一种模块化数据中心及大平层布局的数据中心 | |
ES2627107T5 (es) | Método para el funcionamiento de un centro de datos con medios de refrigeración eficientes | |
TWI608333B (zh) | Combined data center and its heat dissipation method | |
CN103369908A (zh) | 一种集装箱式数据*** | |
CN102854961A (zh) | 一种集装箱式数据中心 | |
CN220086214U (zh) | 储能集装箱及储能集装箱*** | |
CN103510728A (zh) | 一种集装箱数据中心和一种集装箱 | |
CN103238381B (zh) | 具有温度控制的自容式ups*** | |
KR101915876B1 (ko) | 친환경 ess | |
CN203452412U (zh) | 一种集装箱数据中心和一种集装箱 | |
CN217426937U (zh) | 储能机柜及模块化储能机组 | |
CN110856427B (zh) | 模块化数据中心 | |
RU126357U1 (ru) | Центр обработки данных | |
CN211481646U (zh) | 机柜和数据中心 | |
CN106285077A (zh) | 可扩展式模块化通信机房 | |
CN218274889U (zh) | 一种电池储能集装箱 | |
CN102495664A (zh) | 模块化集装箱式数据中心 | |
CN107327996B (zh) | 一种模块化数据中心 | |
CN209283590U (zh) | 一种集光交、设备安装及蓄电池功能的复合机柜 | |
CN113991210A (zh) | 一种移动式分布式储能*** | |
CN202838108U (zh) | 一种集装箱式数据中心 | |
CN203238985U (zh) | 一种集装箱数据中心架构 | |
CN220274114U (zh) | 预制化数据中心模块及数据中心 | |
CN220964396U (zh) | 数据中心 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20110518 |