CN102059503A
CN102059503A CN2010105305686A CN201010530568A CN102059503A CN 102059503 A CN102059503 A CN 102059503A CN 2010105305686 A CN2010105305686 A CN 2010105305686A CN 201010530568 A CN201010530568 A CN 201010530568A CN 102059503 A CN102059503 A CN 102059503A
Authority
CN
China
Prior art keywords
welding
cylinder
steam turbine
gap
split
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN2010105305686A
Other languages
Chinese (zh)
Inventor
刘宏伟
李媛
支伟东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HARBIN NORTH ELECTRICITY DEVELOPMENT Co Ltd
Original Assignee
HARBIN NORTH ELECTRICITY DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HARBIN NORTH ELECTRICITY DEVELOPMENT Co Ltd filed Critical HARBIN NORTH ELECTRICITY DEVELOPMENT Co Ltd
Priority to CN2010105305686A priority Critical patent/CN102059503A/en
Publication of CN102059503A publication Critical patent/CN102059503A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Turbine Rotor Nozzle Sealing (AREA)

Abstract

The invention relates to an air leakage repairing method for a casing split of a steam turbine set. For years, an excessive repairing method is adopted to handle the standing problem of air leakage of the casing split, such as coating/plating, spray welding, cushioning, welding up, scraping, going back to a factory for processing and the like, and the method has high cost and long period. The method provided by the invention comprises the following steps: (1) disassembling a cylinder, uncovering an upper cylinder of a steam turbine, measuring a through-flow gap in a free state and recording in details, cleaning the disassembled cylinder to remove the split combination, searching for the leakage part, measuring and recording the flatness of the cylinder flange face with a gradienter, closing the cylinder in a free state, measuring the gap of a sealing surface and determining a repairing area and a repairing amount; (2) determining a zero-point area of the gap of the sealing surface, welding a 20 mm broadband at the inner side of the flange of the air leakage area, and welding a 10 mm broadband at the outer side by taking the zero-point area as a reference point; and (3) roughly grinding after the welding, and performing coloring, flaw detection and inspection. The air leakage repairing method provided by the invention is used for repairing air leakage of the casing split of the steam turbine set.

Description

Steam Turbine casing split gas leakage restorative procedure
Technical field:
The present invention relates to a kind of Steam Turbine casing split gas leakage restorative procedure.
Background technology:
The cylinder of steam turbine is everlasting and is worked under HTHP (530 ℃, the 90ata) condition.Also be connected with admission, steam discharge and regenerative steam pipeline at casing outer wall, require cylinder should have enough strength and stiffness, not only to bear the deadweight of each part and the installation pulling force of pipeline, and the thermal stress that produces of the cylinder inside and outside differential pressure will bear work time the, the temperature difference, and steam when flowing out stator blade to the reaction force of stator part and the active force of the hot state countercylinder of various connecting pipe.This shows and guarantee that cylinder part stable operation is particularly important.
Find in the actual motion for many years that in power plant internal expanding mouth, cylinder arch problem on deformation easily take place unit high-pressure cylinder velocity-compounded stage, cause split seriously to leak vapour.Safety, the economical operation of unit have been influenced greatly.
Mainly there are the reason of design aspect and the reason of operation aspect:
One, design reasons:
1, small-sized unit individual layer cylinder structure.In unit starting, shutdown and varying duty because the vapor (steam) temperature difference of each several part in the cylinder, make casing wall radially, axially and on and the temperature difference appears between lower cylinder body, thereby produce thermal stress and thermal deformation.The horizontal flange width of high pressure cylinder is 4~5 times of cylinder wall thickness, and flange is in unidirectional heated condition in the start-up course, has the big temperature difference and thermal stress between internal and external walls and flange and the casing wall, causes the thermal deformation that the casing split flange rises mouthful and leaks vapour.
2, bolt position on flange face is unreasonable, and quantity is few, the interval is excessive, and bolt pretightening can not fit the casing split flange.
Two, operation reason:
1, second temperature difference is big on the cylinder, and because of lower cylinder half is connected with drain water piping with drawing gas, area of dissipation is big and be unfavorable for insulation.Low top, firing floor temperature bottom height in the machine room, following cylinder makes down the cylinder metal temperature always be lower than the metal temperature of upper cylinder half usually than the easy heat radiation of upper cylinder half, causes doming effect on the cylinder, and make down cylinder bottom portion radially dynamic and static gaps reduce, even bump the mill phenomenon.Therefore, take to improve thickening down the cylinder heat-insulation layer, install baffle plate below the cylinder down, guarantee drain water piping hydrophobic unimpeded, avoid measure such as ponding and control temperature rise speed in the cylinder, can obviously reduce the temperature difference that goes up lower cylinder body.
When 2, merging on the cylinder lower cylinder body, bolt does not often reach the requirement of tight angle of heat and radian when installing, and bolt pretension understrressing, can not make the lower flange faying face reach tight contact, causes leaking vapour.
3, bolt generation stress relaxation phenomenon is promptly behind the long-play: bolt produces strain under the pretightning force effect reduces, and plastic deformation increases, and again under the bolt situation that in time more renews, the part can take place rise mouthful and leak vapour.
Along with high parameter, high power turbine unit constantly develop, in recent years the unit of producing, the measure that its high-pressure cylinder flange is structurally mainly taked is to increase the flange height and reduce width, reducing the diameter of bolt accelerates, and make the bolt center line close as far as possible to the intersection point of the prolongation camber line of cylinder wall thickness center line and split, with rigidity and the sealing of improving flange.But, for operating medium and small unit cylinder, if its expense height of new high pressure cylinder, cycle of change optimal design long, influence economy of power plant benefit etc., still to repair use.
For many years, handle casing split leakage vapour hard nut to crack and adopt too much restorative procedure, as: coating, surfacing, cushioning, soldering, scraping, time factory's processing etc., not only cost height but also cycle are long.
Summary of the invention:
The objective of the invention is provides a kind of Steam Turbine casing split gas leakage restorative procedure at the problem of above-mentioned existence, and this method is simple, and the cycle is short, and expense is low.Actual effect is obvious, even after leaking the serious cylinder reparation of vapour, also can keep two overhaul phases.
Above-mentioned purpose realizes by following technical scheme:
Steam Turbine casing split gas leakage restorative procedure, this method comprises the steps:
(1) takes cylinder apart, open the steam turbine upper cylinder half, measure through-flow gap under the free state and make detail record, the split bond is removed in cleaning after tearing cylinder open, search leak site, with level meter surveying record cylinder flange facial plane degree, free state is closed cylinder, measure the sealing surface gap and determine restoring area, and the reparation amount;
(2) determine the zone at zero point in sealing surface gap, with this as datum mark, in the inboard welding of the flange that leaks vapour zone 20mm broadband, welding 10mm broadband, the outside;
(3) welding back corase grind, and dye penetration inspection.
Described Steam Turbine casing split gas leakage restorative procedure, the A507 welding rod is adopted in the welding described in the step (2), and temperature between key-course≤60 ℃ during welding take 2 welders to be symmetrically welded, reverse segmentation welder skill.
Described Steam Turbine casing split gas leakage restorative procedure, roughly grind after the welding described in the step (3), and dye penetration inspection is smeared red lead powder after being meant welding, employing is to the method for grinding, repeatedly merge empty cylinder body, remove minute faying face in the scraping of high point, to dividing faying face in grinding, reach welding region and just establish zero point on same horizontal plane, last lower cylinder body junction fully contacts, pneumatic grinding wheel is adopted in scraping, from the maximum position of scraping amount, to enlarging all around, every reconditioning once vertically reaches laterally to grinding at faying face with leveling ruler, check the contact situation, and detect cylinder horizontal integration face and Boring mill perpendicularity at any time to faying face, prevent to repair partially, detain empty cylinder when the amount of scraping remains 0.10-0.15mm when repairing, cold tight 1/3 bolt is checked the faying face gap, repeatedly to cold tight 1/3 bolt of high pressure outer shell, measure and check, carry out essence and scrape, till 0.05mm, finally under free state, lower cylinder body in the merging, reaching sealing surface restoring area gap width is 0.05mm, the 0.03mm degree of depth is less than 20mm, after tighting a bolt, measure the faying face gap, check whether the split warping phenomenon takes place, behind the flow passage component of packing into, tight a bolt according to tight radian of bolt heat and angle, fully guarantee seal clearance.
Beneficial effect:
1. the present invention promptly saves cost, time, can thoroughly eliminate Lou vapour phenomenon again.Power plant often leaks gas by forced-stopping machine because of cylinder, not only influences unit safety stable operation, because of reducing generated energy, causes very large economy loss, has had a strong impact on the economic benefit of power plant.The way that whole scraping is repaired to split is all adopted in split gas leakage maintenance in the past, and repair surface is big, and the big workman's technical merit height that requires of technical difficulty, is repaired back work a period of time also can leak gas at repairing efficiency long minimum 20 days of repair time; Repair surface of the present invention is little, and the workman is easy and simple to handle, and repair time is short, and maximum 15 days of repairing efficiency is thoroughly removed a hidden danger after the reparation, guarantees unit safety stable operation, can bring considerable economic to power plant.With the 30MW unit is ten thousand kilowatts/hour of example: 300MW=30, and power plant sells 0.25 yuan/kw.h of electricity price, moves one day unit economic benefit: 30 * 10 4* 24 * 0.25=180 ten thousand.Because thoroughly remove a hidden danger after weak point and the reparation and guarantee that unit can normally move repair time, the loss of shutting down in the middle of can reducing can bring remarkable economic efficiency to power plant.
Description of drawings:
Accompanying drawing 1 is the structural representation of the welded flange of invention, and 1 is outside built-up welding band among the figure, and 2 is the flange split, and 3 is inboard built-up welding band, and 4 is bolt hole.
The specific embodiment:
Embodiment 1:
Steam Turbine casing split gas leakage restorative procedure, this method comprises the steps:
(1) take cylinder apart, open the steam turbine upper cylinder half, check that composition surface coating and cylinder face matrix wash away situation, the place that record and mark steam flow wash away vestige and red rust staining is arranged is paid special attention to penetrability and is washed away vestige, clearly has leakage position.Measure through-flow gap under the free state and make detail record, tear cylinder open after cleaning remove the split bond, with level meter surveying record cylinder flange facial plane degree, free state is closed cylinder, measures the sealing surface gap and determines restoring area, and the reparation amount;
(2) determine the zone at zero point in sealing surface gap, as datum mark, adopt A507 (Cr25Ni20Mo6) welding rod, in the inboard welding of the flange that leaks vapour zone 20mm broadband, welding 10mm broadband, the outside with this.See shown in Figure 1: 1 outside built-up welding band among the figure, 2 flange splits, 3 inboard built-up welding bands, 4 bolts hole.
(3) welding back corase grind, and dye penetration inspection.
Described Steam Turbine casing split gas leakage restorative procedure, the A507 welding rod is adopted in the welding described in the step (2), and temperature between key-course≤60 ℃ during welding take 2 welders to be symmetrically welded, reverse segmentation welder skill.Terminal and the middle minute faying face rounding off of welding uses φ 3.2 welding rods, and welding current is stopped " undercut " phenomenon and taken place between 110-120A.
Described Steam Turbine casing split gas leakage restorative procedure, roughly grind after the welding described in the step (3), and dye penetration inspection is smeared red lead powder after being meant welding, employing is to the method for grinding, repeatedly merge empty cylinder body, remove minute faying face in the scraping of high point, to dividing faying face in grinding, reach welding region and just establish zero point on same horizontal plane, last lower cylinder body junction fully contacts, pneumatic grinding wheel is adopted in scraping, from the maximum position of scraping amount, to enlarging all around, every reconditioning once vertically reaches laterally to grinding at faying face with leveling ruler, check the contact situation, and detect cylinder horizontal integration face and Boring mill perpendicularity at any time to faying face, prevent to repair partially, detain empty cylinder when the amount of scraping remains 0.10-0.15mm when repairing, cold tight 1/3 bolt is checked the faying face gap, repeatedly to cold tight 1/3 bolt of high pressure outer shell, measure and check, carry out essence and scrape, till 0.05mm, finally under free state, lower cylinder body in the merging, reaching sealing surface restoring area gap width is 0.05mm, the 0.03mm degree of depth is less than 20mm, after tighting a bolt, measure the faying face gap, check whether the split warping phenomenon takes place, behind the flow passage component of packing into, tight a bolt according to tight radian of bolt heat and angle, fully guarantee seal clearance.

Claims (3)

1. Steam Turbine casing split gas leakage restorative procedure, it is characterized in that: this method comprises the steps:
(1) takes cylinder apart, open the steam turbine upper cylinder half, measure through-flow gap under the free state and make detail record, the split bond is removed in cleaning after tearing cylinder open, search leak site, with level meter surveying record cylinder flange facial plane degree, free state is closed cylinder, measure the sealing surface gap and determine restoring area, and the reparation amount;
(2) determine the zone at zero point in sealing surface gap, with this as datum mark, in the inboard welding of the flange that leaks vapour zone 20mm broadband, welding 10mm broadband, the outside;
(3) welding back corase grind, and dye penetration inspection.
2. Steam Turbine casing split according to claim 1 gas leakage restorative procedure, it is characterized in that: the A507 welding rod is adopted in the welding described in the step (2), and temperature between key-course≤60 ℃ during welding take 2 welders to be symmetrically welded, reverse segmentation welder skill.
3. Steam Turbine casing split gas leakage restorative procedure according to claim 1 and 2, it is characterized in that: roughly grind after the welding described in the step (3), and dye penetration inspection is smeared red lead powder after being meant welding, employing is to the method for grinding, repeatedly merge empty cylinder body, remove minute faying face in the scraping of high point, to dividing faying face in grinding, reach welding region and just establish zero point on same horizontal plane, last lower cylinder body junction fully contacts, pneumatic grinding wheel is adopted in scraping, from the maximum position of scraping amount, to enlarging all around, every reconditioning once vertically reaches laterally to grinding at faying face with leveling ruler, check the contact situation, and detect cylinder horizontal integration face and Boring mill perpendicularity at any time to faying face, prevent to repair partially, detain empty cylinder when the amount of scraping remains 0.10-0.15mm when repairing, cold tight 1/3 bolt is checked the faying face gap, repeatedly to cold tight 1/3 bolt of high pressure outer shell, measure and check, carry out essence and scrape, till 0.05mm, finally under free state, lower cylinder body in the merging, reaching sealing surface restoring area gap width is 0.05mm, the 0.03mm degree of depth is less than 20mm, after tighting a bolt, measure the faying face gap, check whether the split warping phenomenon takes place, behind the flow passage component of packing into, tight a bolt according to tight radian of bolt heat and angle, fully guarantee seal clearance.
CN2010105305686A 2010-11-04 2010-11-04 Air leakage repairing method for casing split of steam turbine set Pending CN102059503A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105305686A CN102059503A (en) 2010-11-04 2010-11-04 Air leakage repairing method for casing split of steam turbine set

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105305686A CN102059503A (en) 2010-11-04 2010-11-04 Air leakage repairing method for casing split of steam turbine set

Publications (1)

Publication Number Publication Date
CN102059503A true CN102059503A (en) 2011-05-18

Family

ID=43995103

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105305686A Pending CN102059503A (en) 2010-11-04 2010-11-04 Air leakage repairing method for casing split of steam turbine set

Country Status (1)

Country Link
CN (1) CN102059503A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102303205A (en) * 2011-09-05 2012-01-04 广州市天河区金棠表面工程技术有限公司 Split deformation or deflation field spraying repair process for steam turbine cylinder
CN104874973A (en) * 2014-02-28 2015-09-02 中电华元核电工程技术有限公司 Steam turbine cylinder joint surface deformation processing method
CN105269242A (en) * 2015-11-20 2016-01-27 湖南省湘衡盐化有限责任公司 Method for repairing air leakage of turbine air cylinders
CN105345390A (en) * 2015-12-10 2016-02-24 东方电气集团东方汽轮机有限公司 Repairing method for split sealing surface of pressure resistant vessel
CN110421342A (en) * 2019-07-12 2019-11-08 中广核核电运营有限公司 The cold clamping method of bolt on half speed unit high intermediate pressure cylinder split
CN110936098A (en) * 2019-11-07 2020-03-31 江苏特维克科技有限公司 High-medium pressure cylinder body split surface defect repairing process
CN114412590A (en) * 2021-12-01 2022-04-29 上海发电设备成套设计研究院有限责任公司 Online safety monitoring method for flange bisection tightness of nuclear turbine cylinder
CN114412591A (en) * 2021-12-01 2022-04-29 上海发电设备成套设计研究院有限责任公司 Multi-dimensional safety monitoring method and device for nuclear turbine, electronic equipment and storage medium
US11725534B2 (en) 2021-12-01 2023-08-15 Shanghai Power Equipment Research Institute Co., Ltd Method of multi-objective and multi-dimensional online joint monitoring for nuclear turbine

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2374058C2 (en) * 2007-12-11 2009-11-27 Открытое акционерное общество "КАМАЗ-Металлургия" Method to recondition ice cylinder block main bearing seats

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2374058C2 (en) * 2007-12-11 2009-11-27 Открытое акционерное общество "КАМАЗ-Металлургия" Method to recondition ice cylinder block main bearing seats

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
施瑾琼: "高压蒸汽轮机中分面变形泄漏的现场维修方法", 《大氮肥》 *
*** 等: "新比隆EHNK型高压汽轮机中分面泄漏分析及对策", 《大氮肥》 *
段继鹏 等: "汽轮机汽缸中分面法兰漏汽的处理", 《电力安全技术》 *
马云蛟 等: "汽轮机缸体中分面变形的焊接刮研修复工艺", 《第十次全国农机维修学术会议论文集》 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102303205A (en) * 2011-09-05 2012-01-04 广州市天河区金棠表面工程技术有限公司 Split deformation or deflation field spraying repair process for steam turbine cylinder
CN102303205B (en) * 2011-09-05 2013-06-26 广州市天河区金棠表面工程技术有限公司 Split deformation or deflation field spraying repair process for steam turbine cylinder
CN104874973A (en) * 2014-02-28 2015-09-02 中电华元核电工程技术有限公司 Steam turbine cylinder joint surface deformation processing method
CN104874973B (en) * 2014-02-28 2017-09-12 中电华元核电工程技术有限公司 A kind of steam turbine deformation of joint surface processing method
CN105269242A (en) * 2015-11-20 2016-01-27 湖南省湘衡盐化有限责任公司 Method for repairing air leakage of turbine air cylinders
CN105345390A (en) * 2015-12-10 2016-02-24 东方电气集团东方汽轮机有限公司 Repairing method for split sealing surface of pressure resistant vessel
CN105345390B (en) * 2015-12-10 2018-10-16 东方电气集团东方汽轮机有限公司 Point sealing surface repair method in pressure resistant vessel
CN110421342A (en) * 2019-07-12 2019-11-08 中广核核电运营有限公司 The cold clamping method of bolt on half speed unit high intermediate pressure cylinder split
CN110936098A (en) * 2019-11-07 2020-03-31 江苏特维克科技有限公司 High-medium pressure cylinder body split surface defect repairing process
CN114412590A (en) * 2021-12-01 2022-04-29 上海发电设备成套设计研究院有限责任公司 Online safety monitoring method for flange bisection tightness of nuclear turbine cylinder
CN114412591A (en) * 2021-12-01 2022-04-29 上海发电设备成套设计研究院有限责任公司 Multi-dimensional safety monitoring method and device for nuclear turbine, electronic equipment and storage medium
US11725534B2 (en) 2021-12-01 2023-08-15 Shanghai Power Equipment Research Institute Co., Ltd Method of multi-objective and multi-dimensional online joint monitoring for nuclear turbine

Similar Documents

Publication Publication Date Title
CN102059503A (en) Air leakage repairing method for casing split of steam turbine set
CN103939156B (en) Method for installing nuclear power half-speed steam turbine
JP2009041449A (en) Repair method for gas turbine rotor vane
Bhatt et al. Performance enhancement in coal fired thermal power plants. Part II: steam turbines
CN102392699B (en) Steam turbine operation method
CN207454783U (en) A kind of flap valve applied to single crystal growing furnace
CN105345390A (en) Repairing method for split sealing surface of pressure resistant vessel
CN100423885C (en) Detecting tools for combustion turbine transitory section renovation technique and renovation technique thereof
CN109098789A (en) A kind of steam turbine vacuum tightness construction method
CN115219108A (en) Leakage detection device for generator hydrogen cooler and test method
Lisyanskii et al. Practical experience with the introduction of honeycomb shroud seals on 250–800 MW supercritical pressure units
CN100462189C (en) Renovation technique of combustion turbine retaining ring
CN104421473A (en) Valve diffuser for a valve
CN104482262A (en) Lateral steam discharge electromagnetic pressure relief valve structure for electric station main steam system
CN204628668U (en) Power station main steam system side steam discharge electromagnetic relief valve structure
CN202900332U (en) Turbine air cylinder casting assembly
JP2020097893A (en) Method for manufacturing turbine casing
Fukuda et al. 700℃ A-USC Technology Development in Japan
Yin et al. Numerical simulation of abrasive flow machining in multi-angle elbows
CN100503140C (en) Renovation technique of combustion turbine transition section
CN109296493B (en) Mounting method of water drainage cone
CN109955027A (en) Steam turbine faying face gap restorative procedure
CN105750818A (en) Method for restoring large-size hydroelectric generating set top cover
Wang Research on integrated application of deep level energy-saving technology for supercritical 600MW steam turbine
Stepanov et al. Single-Cylinder Steam Turbine for Powers Up to 100 MW with Axial Exhaust Pipe

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C02 Deemed withdrawal of patent application after publication (patent law 2001)
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20110518