CN102050327A - Guide rail device in clip threading machine - Google Patents

Guide rail device in clip threading machine Download PDF

Info

Publication number
CN102050327A
CN102050327A CN 201010298731 CN201010298731A CN102050327A CN 102050327 A CN102050327 A CN 102050327A CN 201010298731 CN201010298731 CN 201010298731 CN 201010298731 A CN201010298731 A CN 201010298731A CN 102050327 A CN102050327 A CN 102050327A
Authority
CN
China
Prior art keywords
chute
safety pin
guide rail
briquetting
rail body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN 201010298731
Other languages
Chinese (zh)
Inventor
张莉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Cixi Beirun Software Co Ltd
Original Assignee
Cixi Beirun Software Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Cixi Beirun Software Co Ltd filed Critical Cixi Beirun Software Co Ltd
Priority to CN 201010298731 priority Critical patent/CN102050327A/en
Publication of CN102050327A publication Critical patent/CN102050327A/en
Pending legal-status Critical Current

Links

Images

Landscapes

  • Portable Nailing Machines And Staplers (AREA)

Abstract

The embodiment of the invention provides a guide rail device in a clip threading machine, comprising a tipsily or vertically arranged guide rail body. The front of the guide rail body is provided with a chute longitudinally extending along the guide rail body, and the chute is used for a clip to slide downwards therein. The guide rail device also comprises a briquette and a release block which are sequentially and adjacently arranged along the downward sliding direction of the clip in the chute, and the guide rail device also comprises a driving device which is used for driving the briquette to lift up from the chute and driving the release block to abut on the clip arranged in the chute in a first state and also used for driving the briquette to press the clip in the chute and driving the release block to lift up from the inside of the chute so as to release another clip below the clip pressed by the briquette in a second state. The guide rail device provided by the invention can convey clips for other related parts in the clip threading machine.

Description

A kind of safety pin installs the track-type facilities in the machine
Technical field
The present invention relates to the safety pin processing technique field, relate in particular to a kind of safety pin and install track-type facilities in the machine.
Background technology
At present, existing safety pin has multiple, purposes is also different, wherein a kind of structure of more common safety pin as shown in fig. 1, this safety pin is made up of the wire needle 1 and the clasp 2 of a bending, wherein, the two ends of wire needle 1 all are arranged in clasp, and an end can break away from from clasp 2, and the middle bent of wire needle 1 becomes at least one circle, forms curled portion 11.
After the safety pin among Fig. 1 was completed, transportation for convenience and sale need install safety pin, and the curled portion that is about to a plurality of safety pins is passed a safety pin, a string safety pin of can taking easily like this, and be the scheme of relatively saving the space.At present, finishing the top safety pin process that installs finishes by the people is manual, promptly push away one and take out a safety pin in the safety pin of disorderly and unsystematic placement as installing fixedly safety pin by the people, and install this fixedly that an end of the draw point of safety pin breaks away from from clasp, and then the curled portion of other safety pins penetrated from an above-mentioned end that installs the draw point that fixing safety pin breaks away from, when penetrating into the number that installs the safety pin in the fixing safety pin and reach requirement, this end that installs the draw point that breaks away from the fixing safety pin is pushed in the clasp again, finally finishes the process that installs of safety pin.But this manually to finish the operation that safety pin installs very consuming time, and efficient is very low.
Summary of the invention
In view of this, the object of the present invention is to provide a kind of safety pin to install track-type facilities in the machine, can carry safety pin for the associated components that safety pin installs in the machine.
For achieving the above object, one embodiment of the present of invention provide a kind of safety pin to install track-type facilities in the machine, comprise a guide rail body that tilts or vertically place, the front of described guide rail body is provided with along the chute of the longitudinal extension of guide rail body, described chute is used for safety pin and slides therein, also comprise along safety pin and in chute, slide the direction briquetting and the release piece of adjacent setting successively, also comprise actuating device, described actuating device is used for when first state, drive briquetting and from chute, lift, and driving release piece props up the safety pin that is positioned at chute; Also be used for when second state, drive briquetting and push down safety pin in the chute, and drive and discharge piece and in described chute, lift, thereby discharge a safety pin of the safety pin below of being pushed down by briquetting.
Preferably, described briquetting comprises one first cover plate and is arranged on the compressed part of described first cover plate on the chute of guide rail body one side, and during safety pin in briquetting is pushed down described chute, the compressed part of described briquetting extend in the described chute and pushes down safety pin.
Preferably, described release piece comprises one second cover plate and is arranged on the stop section of described second cover plate on the chute one side of guide rail body, when the release piece blocked the safety pin that is positioned at chute, the stop section of described release piece was positioned at described chute and blocks the safety pin that is positioned at chute.
Preferably, the opening of described chute also is provided with being used for of extending internally and prevents that safety pin is from anti-delinking part that chute comes off.
Preferably, one section of the bottom of described guide rail body is bent to form guide section to the one side that is provided with chute.
Track-type facilities provided by the invention can be carried safety pin for other associated components that safety pin installs in the machine.
Description of drawings
In order to be illustrated more clearly in the embodiment of the invention or technical scheme of the prior art, to do to introduce simply to the accompanying drawing of required use in embodiment or the description of the Prior Art below, apparently, accompanying drawing in describing below is some embodiments of the present invention, for those of ordinary skills, under the prerequisite of not paying creative work, can also obtain other accompanying drawing according to these accompanying drawings.
Fig. 1 is the structure of common a kind of safety pin;
Fig. 2 is the front elevation that a kind of safety pin provided by the invention installs the track-type facilities in the machine;
Fig. 3 is the left view of the track-type facilities among Fig. 2;
Fig. 4 is that the A-A of the track-type facilities among Fig. 2 is to cutaway view;
Fig. 5 is the scheme drawing of a kind of concrete structure of the briquetting in the track-type facilities;
Fig. 6 is the front elevation of the briquetting among Fig. 5;
Fig. 7 is the left view of the briquetting among Fig. 5;
Fig. 8 is the scheme drawing of a kind of concrete structure of the release piece in the track-type facilities;
Fig. 9 is the front elevation of the release piece among Fig. 8;
Figure 10 is the left view of the release piece among Fig. 8;
Figure 11 and Figure 12 are the scheme drawings of the working process of the track-type facilities that provides of the embodiment of the invention;
Figure 13 is a kind of schematic cross-section of optimal way structure of the chute of the track-type facilities in the embodiment of the invention.
The specific embodiment
For the purpose, technical scheme and the advantage that make the embodiment of the invention clearer, below in conjunction with the accompanying drawing in the embodiment of the invention, technical scheme in the embodiment of the invention is clearly and completely described, obviously, described embodiment is the present invention's part embodiment, rather than whole embodiment.Based on the embodiment among the present invention, those of ordinary skills belong to the scope of protection of the invention not making the every other embodiment that is obtained under the creative work prerequisite.
The safety pin machine of installing is used for safety pin is installed on together automatically one by one, in the process that the safety pin machine that installs installs safety pin, need control accurately safety pin, the embodiment of the invention just consider this demand provide a kind of can be to the safety pin accuracy control install in other devices in the machine so that safety pin can accurately be transported to safety pin.
Fig. 2 installs the front elevation of the track-type facilities in the machine for a kind of safety pin provided by the invention, and Fig. 3 is the left view of the track-type facilities among Fig. 2, and Fig. 4 is that the A-A of the track-type facilities among Fig. 2 is to cutaway view.Please be simultaneously referring to Fig. 2 to Fig. 4, track-type facilities 3 provided by the invention comprises a guide rail body 31 that tilts to place or vertically place, the front of this guide rail body 31 is provided with the chute 311 along the longitudinal extension of guide rail body 31.At track-type facilities 3 is that the front of above-mentioned guide rail body 31 is track-type facilities 3 one side up when tilting placement.
Chute 311 has inlet point 311a on the top of track-type facilities 3, has discharging opening 311b in the bottom of track-type facilities 3.The inlet point 311a device consistent with adjusting the safety pin direction links to each other, the device of this adjustment safety pin direction unanimity can be a vibrating grizzly, vibrating grizzly is by vibrating the feasible rambling safety pin travel direction adjustment that is positioned at wherein, and finally the direction of the safety pin of exporting from vibrating grizzly all is consistent.The safety pin of these direction unanimities enters into chute 311 on the guide rail body 31 from inlet point 311a, slides downwards along the bearing of trend of chute 311, and skids off from discharge end 311b, enters into other devices that are connected mutually with the track-type facilities of present embodiment.
If in track-type facilities 3, safety pin is not carried out any restriction, the safety pin that enters into chute 311 from inlet point 311a will be close to one by one directly and skid off from discharging opening 311b, this is very disadvantageous for the whole machine that installs to the accuracy control of safety pin, in order to allow the machine of installing as production-line technique, install, need from track-type facilities 3, slide a safety pin every the preset time section, the preset time section here is by the mode of operation decision of other devices that are connected mutually with track-type facilities 3, for example when being when having the robot device of a plurality of pivot arms with device that track-type facilities 3 is connected mutually, this preset time section should be the time difference that adjacent two pivot arms rotate to the position of matching with track-type facilities 3.
Consideration based on the accuracy control that safety pin is slided, the safety pin that present embodiment provides install track-type facilities 3 in the machine also comprise along safety pin in chute, slide direction successively adjacent setting briquetting 32 and discharge piece 33, therefore, when guide rail body 31 is vertically placed, briquetting 32 be positioned at discharge piece 33 directly over, when guide rail body 31 tilted to place, briquetting 32 was positioned at the oblique upper that discharges piece 33.Briquetting 32 and discharge one side that piece 33 and guide rail body 31 be provided with chute 311 over against.Briquetting 32 optionally moves and pushes down a safety pin that is positioned at chute 311 to chute 311, also can lift and discharge the safety pin of being pushed down by briquetting 32 from chute 311.Release piece 33 optionally moves in chute 311 and props up the safety pin that is positioned at chute 311, also can lift and discharge the safety pin that is blocked by this release piece 33 from chute 311.
Also comprise an actuating device (not shown), this actuating device is used for when first state, driving briquetting 32 lifts from chute 311, and thereby driving discharges piece 33 mobile safety pin that props up in the chute 311 in chute 311, the safety pin of the most close discharging opening 311b in the chute 311 was blocked in and discharged piece 33 and extend in the zone in the chute 311 this moment, because adjacent safety pin offsets each other end to end, the safety pin in the whole chute 311 is in static state; This actuating device also is used for when second state, drive briquetting 32 and in chute 311, move and push down a safety pin that is positioned at chute 311, driving release piece 33 then lifts from chute 311, before be released the safety pin that piece 33 blocks thereby discharge, this moment, the safety pin of the most close discharge end 311b in chute 311 was just pushed down by briquetting 32 like this, and the safety pin of the most close previous discharge end 311b discharges owing to being released piece 33, so directly skid off from discharge end 311b.
In addition, in order to make track-type facilities to realize better being connected with the device that is adjacent, preferably, (promptly be provided with the end of discharge end 311b) in guide rail body 31 bottoms one section to the one side bending that is provided with chute 311, thereby form guide section 312.The inclination angle of guide section 312 adapts with the plane of the reception safety pin of the device that is connected mutually with track-type facilities 3.
Below describe a kind of concrete structure of briquetting 32 and release piece 33 in detail.
Fig. 5 is the scheme drawing of a kind of concrete structure of the briquetting 32 in the present embodiment, and Fig. 6 is the front elevation of the briquetting among Fig. 5, and Fig. 7 is the left view of the briquetting among Fig. 5.Please be simultaneously referring to Fig. 5 to Fig. 7, this briquetting 32 comprises first cover plate 321 and is arranged on the compressed part 322 of first cover plate 321 on chute 311 one sides of guide rail body 31.During safety pin in briquetting 32 is pushed down chute 311, the compressed part 322 of briquetting 32 extend in the chute 311 and pushes down safety pin.Compressed part 322 the length of chute bearing of trend can be as shown in Fig. 5 to Fig. 7 equal the length of first cover plate 321 at the chute bearing of trend, can certainly less than or greater than the length of first cover plate 321 at the chute bearing of trend.But for the safety pin in the chute 311 more stably being pushed down, the length of the compressed part 322 of this briquetting 32 on the direction that chute 311 extends should equal the length of a safety pin at least.The effect of first cover plate 321 is to make things convenient for actuating device to drive briquetting 32 and moves in chute 311 or lift in chute 311, and the width of first cover plate 321 is greater than the width of chute 311, so with briquetting 32 when chute 311 moves, first cover plate 321 also can serve as the stop block of the distance that restriction briquetting 32 moves to chute 311 simultaneously, therefore the effect that compresses of the size of first cover plate 321 and 32 pairs of safety pins of briquetting does not directly concern, so under the prerequisite of the size that does not change compact heap 322, can dwindle the length of first cover plate 321, thereby save the cost of raw material of track-type facilities at chute 311 bearing of trends.
Fig. 8 is the scheme drawing of a kind of concrete structure of the release piece 33 in the present embodiment, and Fig. 9 is the front elevation of the release piece 33 among Fig. 8, and Figure 10 is the left view of the release piece 33 among Fig. 8.Please be simultaneously referring to Fig. 8 to Figure 10, this release piece 33 comprises second cover plate 331 and is arranged on the stop section 332 of second cover plate 331 on chute 311 one sides of guide rail body 31.When discharging piece 33 move and block safety pin in the chute 311 to chute 311 in, the stop section 332 of release piece 33 is positioned at chute 311 and blocks the safety pin that is positioned at chute 311.
Stop section 332 is positioned at and discharges piece 33 near the end of the discharge end 311b of chute 311, stop section 332 in the length of the direction of extending along chute 311 usually less than the length of second cover plate 331 on this direction, and from the stop section 332 to second cover plates 331 should equal the length of a safety pin at least near the distance of the end of inlet point 311a.The width of stop section 332 should be less than the width of chute 311, so that stop section 332 can extend in the chute 311.
Describe the working process of the track-type facilities that the embodiment of the invention provides in detail below in conjunction with Figure 11 and Figure 12.
Figure 11 is operated in the scheme drawing of first state for the track-type facilities in the present embodiment, this moment guide rail body 31 chute 311 in add the connected head-to-tail safety pin that some is arranged, might as well with this moment the most close discharge end 311b preceding two safety pins be designated as 1a and 1b respectively.Actuating device drives briquetting 32 and lifts from chute 311, making does not have safety pin to be pushed down by briquetting 32 in the chute 311, the release of actuating device driving simultaneously piece 33 moves and props up the safety pin 1a in the chute 311 in chute 311, limit safety pin the position of having only release piece 33 to prop up in whole chute 311, so from discharging piece 33 to there being the connected head-to-tail safety pin that remains static the feed end 311a of chute 311, and in the chute between the discharge end 311b, do not have safety pin discharging piece 33.
Figure 12 is operated in the scheme drawing of second state for the track-type facilities in the present embodiment, actuating device driving this moment briquetting 32 moves to chute 311, thereby push down the safety pin 1b that is arranged in chute 311, actuating device driving release piece 33 lifts from chute 311 then, before be released the safety pin 1a that piece 33 blocks thereby discharge, because the safety pin 1b adjacent with safety pin 1a tightly pushed down by briquetting 32, so only being released the safety pin 1a of piece 33 releases skids off from discharge end 311b along chute, after safety pin 1a skidded off from discharge end 311b, safety pin 1b became the safety pin of the most close discharge end 311b in the chute 311.
Afterwards, track-type facilities is got back to first state once more, promptly under the driving of actuating device, briquetting 32 lifts from chute 311, discharge piece 33 and get back to the state that blocks the safety pin in the chute, all safety pins that be arranged in chute 311 this moment move down, and the safety pin 1b of the most close discharge end 311b offsets with the stop section 332 that discharges piece 33 heretofore; Track-type facilities continues to switch to second state then, makes safety pin 1b skid off from discharge end 311b along chute; Reciprocal according to this, the safety pin that is arranged in chute is skidded off from chute by accuracy control ground one by one.
Need to prove, in order to prevent that safety pin from coming off from chute 311, also overlapped simultaneously in order to prevent that adjacent safety pin from occurring, present embodiment provides a kind of preferred implementation of chute cross section structure, and Figure 13 is near the schematic cross-section of guide rail body briquetting in this preferred implementation.As shown in figure 13, the opening at chute 311 is provided with the anti-delinking part 313 that extends internally.Also to leave opening in the middle of the anti-delinking part 313, so that the stop section 332 of the compressed part 322 of briquetting 32 and release piece 33 can be inserted in the chute 311.
The above only is a preferred implementation of the present invention; should be pointed out that for those skilled in the art, under the prerequisite that does not break away from the principle of the invention; can also make some improvements and modifications, these improvements and modifications also should be considered as protection scope of the present invention.

Claims (5)

1. a safety pin installs the track-type facilities in the machine, it is characterized in that, comprise a guide rail body that tilts or vertically place, the front of described guide rail body is provided with along the chute of the longitudinal extension of guide rail body, described chute is used for safety pin and slides therein, also comprise along safety pin and in chute, slide the direction briquetting and the release piece of adjacent setting successively, also comprise actuating device, described actuating device is used for when first state, drive briquetting and from chute, lift, and driving release piece props up the safety pin that is positioned at chute; Also be used for when second state, drive briquetting and push down safety pin in the chute, and drive and discharge piece and in described chute, lift, thereby discharge a safety pin of the safety pin below of being pushed down by briquetting.
2. device according to claim 1, it is characterized in that, described briquetting comprises one first cover plate and is arranged on the compressed part of described first cover plate on the chute one side of guide rail body, during safety pin in briquetting is pushed down described chute, the compressed part of described briquetting extend in the described chute and pushes down safety pin.
3. device according to claim 1, it is characterized in that, described release piece comprises one second cover plate and is arranged on the stop section of described second cover plate on the chute one side of guide rail body, when the release piece blocked the safety pin that is positioned at chute, the stop section of described release piece was positioned at described chute and blocks the safety pin that is positioned at chute.
4. according to any described device in the claim 1 to 3, it is characterized in that the opening of described chute also is provided with being used for of extending internally and prevents that safety pin is from anti-delinking part that chute comes off.
5. according to any described device in the claim 1 to 3, it is characterized in that one section of the bottom of described guide rail body is bent to form guide section to the one side that is provided with chute.
CN 201010298731 2010-09-28 2010-09-28 Guide rail device in clip threading machine Pending CN102050327A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010298731 CN102050327A (en) 2010-09-28 2010-09-28 Guide rail device in clip threading machine

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010298731 CN102050327A (en) 2010-09-28 2010-09-28 Guide rail device in clip threading machine

Publications (1)

Publication Number Publication Date
CN102050327A true CN102050327A (en) 2011-05-11

Family

ID=43955217

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010298731 Pending CN102050327A (en) 2010-09-28 2010-09-28 Guide rail device in clip threading machine

Country Status (1)

Country Link
CN (1) CN102050327A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102785931A (en) * 2012-09-03 2012-11-21 无锡市欣田机械有限公司 Automatic adding machinery provided with detection device for correction fluid steel bars

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1241524A (en) * 1998-07-03 2000-01-19 株式会社村田制作所 Part-conveying apparatus
CN2728467Y (en) * 2004-08-30 2005-09-28 厉国苗 Cinerary casket made of metal and stone material
US20060151280A1 (en) * 2005-01-10 2006-07-13 Benetech, Inc. Bulk material precision transfer chute apparatus
CN2905712Y (en) * 2006-01-23 2007-05-30 瑞安市华达制药机械厂 Intermittent single granule delivery device for drug capsule
CN201834546U (en) * 2010-09-28 2011-05-18 慈溪市贝瑞软件有限公司 Guide rail device in pin assembling machine

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1241524A (en) * 1998-07-03 2000-01-19 株式会社村田制作所 Part-conveying apparatus
CN2728467Y (en) * 2004-08-30 2005-09-28 厉国苗 Cinerary casket made of metal and stone material
US20060151280A1 (en) * 2005-01-10 2006-07-13 Benetech, Inc. Bulk material precision transfer chute apparatus
CN2905712Y (en) * 2006-01-23 2007-05-30 瑞安市华达制药机械厂 Intermittent single granule delivery device for drug capsule
CN201834546U (en) * 2010-09-28 2011-05-18 慈溪市贝瑞软件有限公司 Guide rail device in pin assembling machine

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102785931A (en) * 2012-09-03 2012-11-21 无锡市欣田机械有限公司 Automatic adding machinery provided with detection device for correction fluid steel bars

Similar Documents

Publication Publication Date Title
CN106593529B (en) The forming method in high inclination-angle high-seam working face equipment returning channel
CN101985887B (en) End supporting, filling and transshipping system of coal face
CN106564775B (en) A kind of band is bulldozed the upset splicing equipment of function
RU2011117361A (en) METHOD AND DEVICE FOR PROCESSING OF FEEDING OF DIVIDED BY LARGE ORE PIECES
CN106271581A (en) A kind of installation equipment of tubing seal
CN105345140A (en) Long-edge edge trimming device for edge trimming saw
CN201834546U (en) Guide rail device in pin assembling machine
CN108285041A (en) A kind of feeder
CN102050327A (en) Guide rail device in clip threading machine
CN205045530U (en) With for brick device complex pile up neatly device
CN102040094B (en) Pin conveying device in pin penetrating machine
CN105846284B (en) A kind of terminal board kludge
KR102264022B1 (en) Bending machine of welded steel mesh
CN103696793A (en) Pseudo-oblique fully-mechanized coal mining hydraulic bracket
CN107098135B (en) Mobile phone color box feeding mechanism
CN101240710B (en) Support moving device
CN205114374U (en) Timber material feeding unit
US20100018044A1 (en) Moving-Positioning Means of Belt-Fastening Apparatus
CN105397720B (en) Automatic pressure spring machine
CN203938112U (en) A kind of feed mechanism
CN211034216U (en) Support mechanism and clamping device
CN112874890A (en) Conveying mechanism of vaccine kit for medical treatment
CN202325651U (en) Filling, loading and transhipping machine
KR20060024668A (en) Auto-constructing equipments of euro form pannel
CN216071729U (en) Telescopic machine convenient to move

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C12 Rejection of a patent application after its publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20110511