CN102010604B - System and method for preparing rubber-modified asphalt - Google Patents

System and method for preparing rubber-modified asphalt Download PDF

Info

Publication number
CN102010604B
CN102010604B CN2010105348709A CN201010534870A CN102010604B CN 102010604 B CN102010604 B CN 102010604B CN 2010105348709 A CN2010105348709 A CN 2010105348709A CN 201010534870 A CN201010534870 A CN 201010534870A CN 102010604 B CN102010604 B CN 102010604B
Authority
CN
China
Prior art keywords
jar
rubber
modified asphalt
swelling
matrix pitch
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010105348709A
Other languages
Chinese (zh)
Other versions
CN102010604A (en
Inventor
徐培华
陈际江
商博明
王安玲
蔡乾东
贾晓放
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANXI CHAGNDA BOYUAN HIGHWAY MAINTENANCE TECHNOLOGY Co Ltd
Original Assignee
SHANXI CHAGNDA BOYUAN HIGHWAY MAINTENANCE TECHNOLOGY Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANXI CHAGNDA BOYUAN HIGHWAY MAINTENANCE TECHNOLOGY Co Ltd filed Critical SHANXI CHAGNDA BOYUAN HIGHWAY MAINTENANCE TECHNOLOGY Co Ltd
Priority to CN2010105348709A priority Critical patent/CN102010604B/en
Publication of CN102010604A publication Critical patent/CN102010604A/en
Application granted granted Critical
Publication of CN102010604B publication Critical patent/CN102010604B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Compositions Of Macromolecular Compounds (AREA)

Abstract

The invention discloses a system and a method for preparing rubber-modified asphalt. The system comprises a substrate asphalt tank, a first asphalt pump, a primary heating tank, a second asphalt pump, a secondary heating tank, a mixing and swelling tank, a third asphalt pump, a rubber grinder, a development and storage tank, a fourth asphalt pump and a first discharge control valve which are communicated with one another sequentially by a pipeline, wherein the swelling tank is communicated with a feeder by the pipeline. The preparation method comprises the following steps of: (1) heating substrate asphalt to 110 to 130 DEG C, and rising temperature twice to 170 to 200 DEG C in a way that the temperature rising speed of the second time is more than the temperature rising speed of the first time; (2) feeding rubber powder in an amount which is 15 to 25 percent of that of the substrate asphalt by using the feeder; and (3) in the mixing and swelling tank, preserving the heat at 170 to 200 DEG C, performing mixing under stirring for 5 to 10 minutes, introducing the mixture into the development and storage tank by using the rubber grinder, preserving the heat at 170 to 200 DEG C, and performing mixing under stirring for 1 to 3 hours to obtain the rubber-modified asphalt.

Description

A kind of production system of rubber modified asphalt and preparation method
Technical field
The present invention relates to the production field of highway pavement modifying asphalt, particularly a kind of production system of rubber modified asphalt and preparation method.
Background technology
Along with the increase day by day of the rapid economy development and the volume of traffic, the use properties of road is required increasingly high, economize on resources and protect environment; Reduce the traffic noise of road surface driving, prolong service life of road surface, improve the rutting resistance on road surface; Reduce the reaction be full of cracks, increase the anti-slide performance on rainy day road surface, reduce maintenance costs; Improve the driving comfort level, reduce the thickness of paving, these performance requriementss provide direction to the study on the modification of bituminous material.Rubber modified asphalt has performances such as high-temperature stability, low temperature flexibility, resistance to deterioration, fatigue resistence, anti-water damageability, is even more ideal environment-friendly type ground surface material.
At present, the production system of domestic and international existing rubber modified asphalt adopts mostly mixes swelling can and grows the hold-up vessel realization, and adopts the heating of high temperature heat conductive oil pipe.Specifically be adding high temperature matrix pitch and rubber and stirring in mixing swelling can, directly pump into the growth hold-up vessel then and store growth.Its shortcoming is: the speed that (1) matrix pitch adopts heat-conducting oil pipes to heat up separately is slower, and heat utilization efficiency is not high; (2) use the mixing swelling can to need long-time the stirring separately, production efficiency is lower, and the production cycle is long; (3) unidirectional Production Flow Chart causes difficult quality control, and the mass discrepancy of each batch is big, is difficult to guarantee the specification of quality of building the road.Especially the temperature of rubber modified asphalt production requirement matrix pitch high (190 ℃~200 ℃) is mixed the swelling can heating, churning time is longer, and production efficiency is lower, and the matrix pitch easy ageing.
Summary of the invention
One object of the present invention is to provide a kind of production system of rubber modified asphalt, can be through dividing echelon heating matrix pitch, and heat utilization efficiency is high, produces continuous high-efficient, and the control of quality product consistence is easily.
Another object of the present invention is to provide the preparation method based on the rubber modified asphalt of above-mentioned production system, and its constant product quality is produced continuous high-efficient.
In order to reach the foregoing invention purpose, the present invention adopts following technical scheme to be achieved.Technical scheme one:
A kind of production system of rubber modified asphalt; It is characterized in that, comprise the matrix pitch jar that is communicated with successively through pipeline, first bitumenpump, first valve that once heats up jar, second bitumenpump, secondary temperature elevation jar, is rapidly heated jar, mixes swelling can, the 3rd bitumenpump, rubber mill, growth hold-up vessel, the 4th bitumenpump and control discharging; Said swelling can is communicated with feeder through pipeline.
The further improvement and the characteristics of present technique scheme are:
Be provided with circulating line between the inlet of said first valve and the mixing swelling can, circulating line is provided with second valve.
The heating power of said secondary temperature elevation jar is greater than the heating power of the jar that once heats up.
Said feeder adopts the spiral feeder.
Said growth hold-up vessel is at least two.
Said growth hold-up vessel is communicated with the 5th bitumenpump and the surplus material of construction withdrawing can in order through pipeline.
Said growth hold-up vessel adopts horizontal growth storage tank.
In the present technique scheme; Type of heating to matrix pitch adopts two intensification jars, can improve matrix pitch and get into the temperature of mixing swelling can, and the heating power of secondary temperature elevation jar is greater than the heating power of the jar that once heats up; Can improve the temperature of matrix pitch fast; Make of the influence reduction of the rubber powder of the cold conditions that gets into the mixing swelling can, improve swelling efficient, and can prevent the matrix pitch rapid ageing swelling temperature.
In the present technique scheme, at the inlet of first valve with mix between the swelling can and be provided with circulating line, circulating line is provided with second valve; When the modifying asphalt quality of growing hold-up vessel occurs badly, can mix swelling, growth once more to bad product through circulation line, guaranteeing the quality conformance of modifying asphalt, and then satisfy the specification of quality of engineering.
In the present technique scheme, grow hold-up vessel and be communicated with the 5th bitumenpump and the surplus material of construction withdrawing can in order, can conveniently reclaim the waste material in the construction through pipeline; Grow hold-up vessel and be at least two, can switch to use and grow hold-up vessel, carry out continuous production; It is horizontal to grow the hold-up vessel employing, and its body rotation is stirred, and is beneficial to dispersing and mixing.
Technical scheme two
A kind of preparation method of rubber modified asphalt, the production system based on above-mentioned rubber modified asphalt is characterized in that, comprises following concrete steps:
(1), the matrix pitch in the matrix pitch jar is heated to 110~130 ℃ by normal temperature; Pump into the jar that once heats up then; Once be warmed up to 135~165 ℃, pump into the secondary temperature elevation jar again, secondary temperature elevation to 170~200 ℃; Pump into the mixing swelling can at last, wherein secondary temperature elevation speed is greater than a heat-up rate;
(2) the rubber powder input is mixed in the swelling can, the rubber powder input amount is 15%~25% of the matrix pitch amount of pumping into;
(3) in mixing swelling can, matrix pitch and rubber powder mixed 5~10 minutes 170~200 ℃ of insulated and stirred, grew hold-up vessel through feeding behind the rubber mill then, and 170~200 ℃ of insulated and stirred were mixed after 1~3 hour, promptly got.
The further improvement and the characteristics of present technique scheme are:
In the said step (1), matrix pitch was warmed up to 170~200 ℃ total time less than 3 hours, and jar temperature rise rate that wherein once heats up is 1~2 ℃/min, and secondary temperature elevation jar temperature rise rate is 2~3 ℃/min.
Said rubber powder is one or both in interior tire glue powder, the cover rubber powder.
In the present technique scheme; Type of heating to matrix pitch adopts two jars that heat up; Can improve the temperature that matrix pitch get into to mix swelling can, and the heating power of secondary temperature elevation jar is greater than the heating power that once heats up jar, wherein secondary temperature elevation speed can improve the temperature of matrix pitch fast greater than heat-up rate; Make of the influence reduction of the rubber powder of the cold conditions that gets into the mixing swelling can, improve swelling efficient swelling temperature; And matrix pitch was warmed up to 170~200 ℃ total time less than 3 hours, and jar temperature rise rate that wherein once heats up is 1~2 ℃/min, and secondary temperature elevation jar temperature rise rate is 2~3 ℃/min, can prevent the matrix pitch rapid ageing.
Description of drawings
Below in conjunction with description of drawings and embodiment the present invention is explained further details.
Fig. 1 is the structural representation of the production system of employing a kind of rubber modified asphalt of the present invention;
Wherein: P1, first bitumenpump; P2, second bitumenpump; P3, the 3rd bitumenpump; P4, the 4th bitumenpump; P5, the 5th bitumenpump; F1, first valve; F2, second valve; F3, the 3rd valve; F4, the 4th valve; F5, the 5th valve; F6, the 6th valve.
Embodiment
One, the production system of rubber modified asphalt
With reference to accompanying drawing 1, the production system of the rubber modified asphalt in the present embodiment, mainly comprise matrix pitch jar, first bitumenpump, once heat up jar, secondary temperature elevation jar, mix swelling can, 2 growth hold-up vessels, 5 bitumenpumps, 6 valves.
Matrix pitch jar, the first bitumenpump P1, once heat up jar, the second bitumenpump P2, secondary temperature elevation jar, mix swelling can successively through the pipeline connection; Constitute the preheating and the carrying path of matrix pitch; And the heating power of secondary temperature elevation jar is greater than the heating power of the jar that once heats up; Can improve the temperature of matrix pitch fast, make of the influence reduction of the rubber powder of the cold conditions that gets into the mixing swelling can, improve swelling efficient swelling temperature.
Mix swelling can and be communicated with feeder through pipeline, feeder adopts the spiral feeder, is used to realize the quantitative interpolation of rubber powder.The outlet that mixes swelling can is provided with the 3rd bitumenpump P3, and the outlet of the 3rd bitumenpump P3 is communicated with grows hold-up vessel.
In the present embodiment, adopted 2 of parallel connection to grow hold-up vessels, respectively through four pairs of valves (F3, F5), (F4 F6) realizes switching and uses.In addition, because of rubber modified asphalt viscosity is big, adopt horizontal growth hold-up vessel, its body rotates, and is beneficial to mix.
Two parallel connection outlets of growing hold-up vessel connect the 4th bitumenpump P4; The outlet of the 4th bitumenpump P4 is provided with the first valve F1; First valve F1 outlet is as discharge port; Be provided with circulating line between the inlet of the first valve F1 and the mixing swelling can, circulating line is provided with the second valve F2, is used for the switching of Control Circulation pipeline.Simultaneously, construction remains the material withdrawing can, the 5th bitumenpump P5 is communicated to two house stewards that grow hold-up vessels inlet front ends in order, and surplus reusing of expecting is used to construct.
Although more than combine accompanying drawing that embodiment of the present invention are described, the present invention is not limited to above-mentioned specific embodiments, and above-mentioned specific embodiments only is schematic, guiding, rather than restrictive.Those of ordinary skill in the art under the situation that does not break away from the scope that claim of the present invention protects, can also make a variety of forms under the enlightenment of this specification sheets, these all belong to the row of the present invention's protection.
Two, the preparation method of rubber modified asphalt
Embodiment 1:
(1) matrix pitch in the matrix pitch jar is heated to 130 ℃ by normal temperature, makes it become flow state, pump into the jar that once heats up then; Heated up (once heating up) in 30 minutes to 165 ℃; Pump into the secondary temperature elevation jar again, 15 minutes (secondary temperature elevation) pumps into the mixing swelling can at last to 200 ℃;
(2) be that the tyre rubber powder input is mixed in the swelling can in 30 orders~60 purposes with fineness, wherein the rubber powder input amount is 25% of the matrix pitch amount of pumping into;
(3) in mixing swelling can, matrix pitch and rubber powder were mixed 5 minutes 200 ℃ of insulated and stirred, grow hold-up vessel through feeding behind the rubber mill then, 200 ℃ of insulated and stirred were mixed after 1 hour, promptly got rubber modified asphalt.
Embodiment 2:
(1) matrix pitch in the matrix pitch jar is heated to 110 ℃ by normal temperature, pumps into the jar that once heats up then, heat up (once heating up) to 135 ℃, pumped into the secondary temperature elevation jar again in 20 minutes, and 15 minutes (secondary temperature elevation) pumps into the mixing swelling can at last to 170 ℃;
(2) be that 30 orders~60 purpose cover rubber powder inputs are mixed in the swelling can with fineness, wherein the rubber powder input amount is 25% of a matrix pitch amount;
(3) in mixing swelling can, matrix pitch and rubber powder were mixed 10 minutes 170 ℃ of insulated and stirred, grow hold-up vessel through feeding behind the rubber mill then, 170 ℃ of insulated and stirred were mixed after 3 hours, promptly got rubber modified asphalt.
Embodiment 3:
(1) matrix pitch in the matrix pitch jar is heated to 120 ℃ by normal temperature, pumps into the jar that once heats up then, heat up (once heating up) to 150 ℃, pumped into the secondary temperature elevation jar again in 25 minutes, and 13 minutes (secondary temperature elevation) pumps into the mixing swelling can at last to 185 ℃;
(2) be that 30 orders~60 purpose cover rubber powders are that 1: 1 input is mixed in the swelling can with interior tyre rubber powder mass ratio with fineness, wherein the rubber powder input amount is 20% of the matrix pitch amount of pumping into;
(3) in mixing swelling can, matrix pitch and rubber powder were mixed 7 minutes 185 ℃ of insulated and stirred, grow hold-up vessel through feeding behind the rubber mill then, 185 ℃ of insulated and stirred were mixed after 2 hours, promptly got rubber modified asphalt.
Embodiment 4:
(1) matrix pitch in the matrix pitch jar is heated to 125 ℃ by normal temperature, pumps into the jar that once heats up then, heat up (once heating up) to 165 ℃, pumped into the secondary temperature elevation jar again in 30 minutes, and 12 minutes (secondary temperature elevation) pumps into the mixing swelling can at last to 195 ℃;
(2) be that 30 orders~60 purpose cover rubber powders are that 1: 2 rubber powder input is mixed in the swelling can with interior tyre rubber powder mass ratio with fineness, wherein the rubber powder input amount is 18% of the matrix pitch amount of pumping into;
(3) in mixing swelling can, matrix pitch and rubber powder were mixed 6 minutes 195 ℃ of insulated and stirred, grow hold-up vessel through feeding behind the rubber mill then, 195 ℃ of insulated and stirred were mixed after 2 hours, promptly got rubber modified asphalt.
Embodiment 5:
(1) matrix pitch in the matrix pitch jar is heated to 120 ℃, pumps into the jar that once heats up then, heat up (once heating up) to 145 ℃, pumped into the secondary temperature elevation jar again in 23 minutes, and 13 minutes (secondary temperature elevation) pumps into the mixing swelling can at last to 175 ℃;
(2) be that 30 orders~60 purpose cover rubber powders are that 1: 3 rubber powder input is mixed in the swelling can with interior tyre rubber powder mass ratio with fineness, wherein the rubber powder input amount is 20% of a matrix pitch amount;
(3) in mixing swelling can, matrix pitch and rubber powder were mixed 9 minutes 175 ℃ of insulated and stirred, grow hold-up vessel through feeding behind the rubber mill then, 175 ℃ of insulated and stirred were mixed after 2 hours, promptly got rubber modified asphalt.
Embodiment 6:
(1) matrix pitch in the matrix pitch jar is heated to 115 ℃ by normal temperature, pumps into the jar that once heats up then, heat up (once heating up) to 155 ℃, pumped into the secondary temperature elevation jar again in 35 minutes, and 15 minutes (secondary temperature elevation) pumps into the mixing swelling can at last to 190 ℃;
(2) be that 30 orders~60 purpose cover rubber powders are that 1: 4 rubber powder input is mixed in the swelling can with interior tyre rubber powder mass ratio with fineness, wherein the rubber powder input amount is 20% of a matrix pitch amount;
(3) in mixing swelling can, matrix pitch and rubber powder were mixed 6 minutes 190 ℃ of insulated and stirred, grow hold-up vessel through feeding behind the rubber mill then, 190 ℃ of insulated and stirred were mixed after 1 hour, promptly got rubber modified asphalt.
It is as shown in the table that embodiment 1-6 prepares rubber modified asphalt performance index detected result.
Figure BSA00000336612000061
Contrast can be known: the quality index of above-mentioned rubber modified asphalt is superior to The Ministry of Communications's proposed standard.
Although above specific embodiment is described embodiment of the present invention, the present invention is not limited to above-mentioned specific embodiment, and above-mentioned specific embodiment only is schematic, guiding, rather than restrictive.

Claims (9)

1. the production system of a rubber modified asphalt; It is characterized in that, comprise the matrix pitch jar that is communicated with successively through pipeline, first bitumenpump, first valve that once heats up jar, second bitumenpump, secondary temperature elevation jar, mixes swelling can, the 3rd bitumenpump, rubber mill, growth hold-up vessel, the 4th bitumenpump and control discharging; Said swelling can is communicated with feeder through pipeline; The heating power of said secondary temperature elevation jar is greater than the heating power of the jar that once heats up.
2. the production system of rubber modified asphalt according to claim 1 is characterized in that, is provided with circulating line between the inlet of said first valve and the mixing swelling can, and circulating line is provided with second valve.
3. the production system of rubber modified asphalt according to claim 1 is characterized in that, said feeder adopts the spiral feeder.
4. the production system of rubber modified asphalt according to claim 1 is characterized in that, said growth hold-up vessel is at least two.
5. the production system of rubber modified asphalt according to claim 1 is characterized in that, said growth hold-up vessel is communicated with the 5th bitumenpump and the surplus material of construction withdrawing can in order through pipeline.
6. the production system of rubber modified asphalt according to claim 1 is characterized in that, said growth hold-up vessel adopts horizontal growth hold-up vessel.
7. the preparation method of a rubber modified asphalt, the production system based on the described rubber modified asphalt of claim 1 is characterized in that, comprises following concrete steps:
(1), the matrix pitch in the matrix pitch jar is heated to 110~130 ℃ by normal temperature; Pump into the jar that once heats up then; Once be warmed up to 135~165 ℃, pump into the secondary temperature elevation jar again, secondary temperature elevation to 170~200 ℃; Pump into the mixing swelling can at last, wherein secondary temperature elevation speed is greater than a heat-up rate;
(2) the rubber powder input is mixed in the swelling can, the rubber powder input amount is 15%~25% of the matrix pitch amount of pumping into;
(3) in mixing swelling can, matrix pitch and rubber powder mixed 5~10 minutes 170~200 ℃ of insulated and stirred, grew hold-up vessel through feeding behind the rubber mill then, and 170~200 ℃ of insulated and stirred were mixed after 1~3 hour, promptly got.
8. according to the preparation method of the rubber modified asphalt of claim 7; It is characterized in that in the said step (1), matrix pitch was warmed up to 170~200 ℃ total time less than 3 hours; Jar temperature rise rate that wherein once heats up is 1~2 ℃/min, and secondary temperature elevation jar temperature rise rate is 2~3 ℃/min.
9. according to the preparation method of the rubber modified asphalt of claim 7, it is characterized in that said rubber powder is one or both in interior tire glue powder, the cover rubber powder.
CN2010105348709A 2010-11-08 2010-11-08 System and method for preparing rubber-modified asphalt Expired - Fee Related CN102010604B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010105348709A CN102010604B (en) 2010-11-08 2010-11-08 System and method for preparing rubber-modified asphalt

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010105348709A CN102010604B (en) 2010-11-08 2010-11-08 System and method for preparing rubber-modified asphalt

Publications (2)

Publication Number Publication Date
CN102010604A CN102010604A (en) 2011-04-13
CN102010604B true CN102010604B (en) 2012-06-27

Family

ID=43840942

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010105348709A Expired - Fee Related CN102010604B (en) 2010-11-08 2010-11-08 System and method for preparing rubber-modified asphalt

Country Status (1)

Country Link
CN (1) CN102010604B (en)

Families Citing this family (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102691247B (en) * 2012-06-07 2014-12-10 广西国创道路材料有限公司 Asphalt development system
CN104016978B (en) * 2014-06-06 2017-05-03 北京健坤和医药科技有限公司 Palmatine hydrochloride crystal form C as well as preparation method thereof and application thereof in medicament composition or health-care product
CN105062535A (en) * 2015-08-31 2015-11-18 句容宁武科技开发有限公司 Method for continuously producing modified asphalt
CN105233781A (en) * 2015-11-06 2016-01-13 天津海泰环保科技发展有限公司 Preparing experiment platform and method for modifying asphalt through rubber powder
CN106243748B (en) * 2016-08-04 2018-11-30 江西省交通工程集团有限公司 A kind of modified pitch and preparation method thereof
CN106480802A (en) * 2016-12-01 2017-03-08 三汽车制造有限公司 Pitch heating system and asphalt mixing plant
CN106854849A (en) * 2017-03-01 2017-06-16 重庆而为路面材料有限公司 Composable, moveable bitumen concrete production system
CN107268385A (en) * 2017-07-26 2017-10-20 湖北圣通石化有限公司 A kind of modified pitch production line
CN107446607B (en) * 2017-08-01 2023-06-16 东莞东交沥青有限公司 Automatic temperature control heat exchange device for asphalt
CN109554991A (en) * 2018-10-09 2019-04-02 中国石油化工股份有限公司 A kind of cementitious matter preparation system for making colored road surface
CN113211691B (en) * 2021-05-08 2022-05-03 益路恒丰衡水沥青科技有限公司 Rubber asphalt production method based on microwave heating

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200951997Y (en) * 2006-09-29 2007-09-26 上海浦东路桥建设股份有限公司 Rubber powder asphalt producing device
CN101148543A (en) * 2007-08-31 2008-03-26 彭术刚 Device and technique for preparing rubber asphalt by using rubber powder
CN101418078A (en) * 2008-12-11 2009-04-29 山东大山路桥工程有限公司 Rubber powder modified asphalt device
CN101591473A (en) * 2009-06-25 2009-12-02 李滢 A kind of SBS modified asphalt production device and production method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200951997Y (en) * 2006-09-29 2007-09-26 上海浦东路桥建设股份有限公司 Rubber powder asphalt producing device
CN101148543A (en) * 2007-08-31 2008-03-26 彭术刚 Device and technique for preparing rubber asphalt by using rubber powder
CN101418078A (en) * 2008-12-11 2009-04-29 山东大山路桥工程有限公司 Rubber powder modified asphalt device
CN101591473A (en) * 2009-06-25 2009-12-02 李滢 A kind of SBS modified asphalt production device and production method

Also Published As

Publication number Publication date
CN102010604A (en) 2011-04-13

Similar Documents

Publication Publication Date Title
CN102010604B (en) System and method for preparing rubber-modified asphalt
CN101967790B (en) System for producing composite modified asphalt
CN104004271B (en) A kind of low temperature resistant polypropylene dedicated material
CN102977621A (en) SBS (styrene-butadiene-styrene)/scrap rubber powder composite modified asphalt and preparation method thereof
CN104497598B (en) A kind of paste rubber and the preparation method of SBS composite modified asphalt
CN103408953B (en) A kind of bituminous grouting rubber grain properties-correcting agent and preparation method
CN101280114A (en) SBS modified road asphalt, production method and device thereof
CN102532923A (en) Granular modified asphalt and preparation method thereof
CN103360774A (en) Asphaltized rubber modified asphalt and preparation method thereof
CN108099320A (en) Root-resistant puncturing type lignin modified asphalt waterproof roll and its production method
CN105400199A (en) Modified rice hull ash-silicone rubber composite material and preparation method thereof
CN103396669B (en) Microwave desulfurization cracking rubber powder of waste tire composite modified asphalt and preparation method thereof
CN101148543A (en) Device and technique for preparing rubber asphalt by using rubber powder
CN101591473B (en) Device and method for producing SBS modified asphalt
CN106118100B (en) A kind of rubber asphalt stabilizer and the method using its stable modification rubber asphalt
CN205062616U (en) Low temperature modified asphalt concrete construction agitating unit
CN201843046U (en) Production system of composite modified asphalt
CN102311244A (en) Method for recycling PET (polyethylene terephthalate) plastics, early-strength plastic mortar and method for preparing mortar
CN205062617U (en) Low temperature is agitator tank for modified asphalt concrete construction
CN111375324A (en) Continuous blending method for fuel oil
CN202415460U (en) Modified asphalt production line
CN101928368B (en) Method and device for polymerizing polyacrylonitrile spinning stock solution
CN210368522U (en) Mixing arrangement is used in pitch production
CN1928015B (en) Production apparatus of color bitumen
CN203794818U (en) Production system for continuous production of direct-spinning copolymer type antistatic polyester

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
EE01 Entry into force of recordation of patent licensing contract

Application publication date: 20110413

Assignee: Shandong Dashan Road&Bridge Co., Ltd.

Assignor: Shaanxi chagnda Boyuan Highway Maintenance Technology Co Ltd|Chen Jijiang

Contract record no.: 2013370000100

Denomination of invention: System and method for preparing rubber-modified asphalt

Granted publication date: 20120627

License type: Exclusive License

Record date: 20130502

LICC Enforcement, change and cancellation of record of contracts on the licence for exploitation of a patent or utility model
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120627

Termination date: 20191108