CN102009472B - Thermal stretch processing method of ultra-high molecular weight polyethylene diaphragm - Google Patents

Thermal stretch processing method of ultra-high molecular weight polyethylene diaphragm Download PDF

Info

Publication number
CN102009472B
CN102009472B CN 201010506628 CN201010506628A CN102009472B CN 102009472 B CN102009472 B CN 102009472B CN 201010506628 CN201010506628 CN 201010506628 CN 201010506628 A CN201010506628 A CN 201010506628A CN 102009472 B CN102009472 B CN 102009472B
Authority
CN
China
Prior art keywords
diaphragm
heat
calender
heat tunnel
molecular weight
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN 201010506628
Other languages
Chinese (zh)
Other versions
CN102009472A (en
Inventor
刘阜东
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANDONG DIHAO WEAR-RESISTING PIPE CO., LTD.
Original Assignee
JINAN XIANHE TECHNOLOGY DEVELOPMENT Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JINAN XIANHE TECHNOLOGY DEVELOPMENT Co Ltd filed Critical JINAN XIANHE TECHNOLOGY DEVELOPMENT Co Ltd
Priority to CN 201010506628 priority Critical patent/CN102009472B/en
Publication of CN102009472A publication Critical patent/CN102009472A/en
Application granted granted Critical
Publication of CN102009472B publication Critical patent/CN102009472B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Casting Or Compression Moulding Of Plastics Or The Like (AREA)
  • Extrusion Moulding Of Plastics Or The Like (AREA)

Abstract

The invention discloses a thermal stretch processing method of an ultra-high molecular weight polyethylene diaphragm, comprising the following steps of: (1) taking raw materials of ultra-high molecular weight polyethylene resin, polyethlene wax, a plasticizer and an antioxidant for backup according to the following proportion by weight; (2) after mixing the mixture, putting the mixture into a single screw extruder to extrude a tube; (3) arranging a cutting tool on the lower part of an outlet of a tube mould of the single screw extruder to longitudinally cut the tube; (4) putting the cut tube into a wedge mould, spreading the tube into a plate material; (5) rolling the plate material into a diaphragm blank; (6) stretching the diaphragm blank when passing through a first heating channel; (7) guiding the rolled and stretched diaphragm blank into a second heating channel to heat; (8) guiding the heated diaphragm blank into a fourth calendar to roll and stretch the diaphragm blank rolled by the fourth calendar into a diaphragm product; and (9) forming the diaphragm product by a forming machine, and winding the diaphragm product. The finished product processed by the thermal stretch processing method has low cost and high efficiency, the tensile strength of the finished product can reach above 300MPa, the elasticity modulus can reach above 100g/d, and the like.

Description

Ultra high molecular weight polyethylene films sheet hot-stretch processing method
Technical field
The present invention relates to the High molecular weight polyethylene product, is a kind of ultra high molecular weight polyethylene films sheet hot-stretch processing method.
Background technology
Product with the ultra-high molecular weight polyethylene thin-film material is made has multiple high-quality performances such as high tensile strength, wearability, and therefore, the ultra-high molecular weight polyethylene film product is applied in multiple field gradually.Yet it is the higher technology of a kind of difficulty that superhigh molecular weight polyethylene material is made film.External general slab or the cylinder that the ultra-high molecular weight polyethylene sintering is processed that adopt, unidirectional again or biaxial tension pulls into film with it after the section.The deficiency of this film-forming method is: the quantity-produced thin-film width can not strengthen arbitrarily as required; Process equipment is complicated; Production efficiency is low; Generally about 5 times, the manufacturing cost of film is expensive for draw ratio when producing continuously, and the filter membrane that uses with wine-making industry is example, the film of 0.012 millimeters thick, and price is generally at 180 yuan/m 2The price of this costliness has hindered the expansion of ultra-high molecular weight polyethylene film range of application.
Summary of the invention
The purpose of this invention is to provide a kind of ultra high molecular weight polyethylene films sheet hot-stretch processing method, it adopts and extrudes hot-drawing method manufacturing diaphragm, solves the deficiency that prior art exists.
The present invention is for realizing above-mentioned purpose, and realize through following technical scheme: ultra high molecular weight polyethylene films sheet hot-stretch processing method may further comprise the steps:
1. get raw material for standby by following weight proportion: polyvinyl resin with super-high molecular weight 93kg, Tissuemat E 4.5kg, plasticizer 2kg and anti-oxidant 0.5kg;
2. insert extruding pipe material in the single screw extrusion machine after each raw material being mixed;
3. in the pipe mold of single screw extrusion machine outlet bottom cutting tool is installed, cutting tool along the tubing bottom tube wall tubing is vertically cut open;
4. the tubing after cutting open gets in the wedge shape mould, and tubing is launched to become profile material;
5. profile material is imported and carry out first order calendering in first calender, the roller temperature of first calender is 100 ℃-120 ℃, obtains the diaphragm parison after the calendering;
6. the diaphragm parison is imported in first heat tunnel and heat; Temperature in first heat tunnel is 90 ℃-120 ℃; Be introduced into through the diaphragm parison of first heat tunnel and carry out second level calendering in second calender; When rolled the second level, the speed of the second calender roll was 4 times of the first calender speed of rolls, is stretched when making the diaphragm parison through first heat tunnel;
7. the diaphragm parison that 6. rolls after the stretching through step imports heating in second heat tunnel; The temperature of second heat tunnel is 120 ℃-140 ℃; Import through the diaphragm parison behind second heat tunnel and to carry out third level calendering in the 3rd calender; The 3rd calender roller temperature is 90 ℃-130 ℃, and the speed of the 3rd calender roll is 2-3 times of the second calender speed of rolls;
8. import the 3rd heat tunnel through the diaphragm parison after the third level calendering; Temperature in the 3rd heat tunnel is 120-140 ℃; Diaphragm parison after being heated imports in the 4th calender and rolls; The 4th calender roller temperature is 90-130 ℃, and the speed of the 4th calender roll is 2 times of the 3rd calender speed of rolls, is drawn into the diaphragm finished product through heating of the 3rd heat tunnel and the diaphragm parison after the calendering of the 4th calender;
9. the diaphragm finished product gets into typing back rolling in the forming machine at last;
The structure of first heat tunnel described in the above-mentioned steps, second heat tunnel and the 3rd heat tunnel is all identical, and concrete structure is: heat tunnel upper and lower, left and right wall is interconnected to housing, and the centre is provided with cavity; Cavity middle part walking ultra-high molecular weight polyethylene section bar; Heat-insulation layer is set in the housing, and heat-insulation layer is connected with the reflecting layer, and heater is installed on the reflecting layer; Ultra-high molecular weight polyethylene section bar upper and lower surface is provided with the first heat scatternet and the second heat scatternet respectively; The first heat scatternet is connected with the reflecting layer sidewall respectively with the second heat scatternet, offers port on the front and rear wall of heat tunnel respectively, and the diaphragm parison is passed through.The length of first heat tunnel is 0.95-1.05 rice.The length of the length of second heat tunnel and the 3rd heat tunnel is 0.45-0.55 rice.
Be provided with the herringbone guide plate in the mould of the wedge shape mould described in the step 4; The height of herringbone guide plate by the peak of porch to the exit gradually step-down to become same plane with the exit; Two sidewalls of herringbone guide plate and mould have constituted the first fractal groove and the second fractal groove respectively; Cover plate is placed at the top of mould, and cover plate and herringbone guide plate end face are provided with spacing.
The invention has the advantages that: the present invention adopts method machined diaphragm such as single screw rod is extruded, hot-stretch, and the manufacturing cost of diaphragm is reduced significantly.Adopt method of the present invention can produce the diaphragm of thickness more than 0.01 millimeter, processing method of the present invention all adopts common process equipment to accomplish, and the device fabrication cost is low; In the drawing process environment is not had specific (special) requirements, the whole machining process method is a kind of continuous processing, does not stop; Dishoarding; Do not use solvent, the ultra-high molecular weight polyethylene product is not had any pollution, enlarged the range of application of ultra-high molecular weight polyethylene film and diaphragm.Use the inventive method product processed, cost is low, and production efficiency is high, and the tensile strength of product can reach more than the 300MPa, and elastic modelling quantity reaches 100g/d with first-class.
Description of drawings
Fig. 1 is various device and the process chart that uses in the processing method of the present invention; Fig. 2 is that the A of wedge shape mould 4 among Fig. 1 is to the structure for amplifying sketch map; Fig. 3 is that the B-B of first heat tunnel 6 among Fig. 1 analyses and observe the structure for amplifying sketch map; Fig. 4 is that the C of forming machine 12 among Fig. 1 is to the structure for amplifying sketch map.Fig. 5 is the perspective view of wedge shape mould 4.
Among the figure, the 1st, single screw extrusion machine, the 2nd, pipe mold, the 3rd, cutting tool, the 4th, wedge shape mould; 5 is first calenders, and 6 is first heat tunnels, and 7 is second calenders, and 8 is second heat tunnels, and 9 is the 3rd calenders; 10 is the 3rd heat tunnels, and 11 is the 4th calenders, the 12nd, and forming machine, the 13rd, winder, the 14th, processed ultra-high molecular weight polyethylene section bar; 15 is topping rolls of the 3rd calender 9, the 16th, and the roll of forming machine, the 17th, motor, the 18th, the herringbone guide plate of wedge shape mould 4, the 19th, the first fractal groove of wedge shape mould; The 20th, the second fractal groove of wedge shape mould, the 21st, housing, the 22nd, heater, 23 is first heat scatternets; 24 is second heat scatternets, the 25th, and heat-insulation layer, the 26th, reflecting layer, the 27th, cover plate.
The specific embodiment
The present invention further explains as follows:
Processing method of the present invention is that superhigh molecular weight polyethylene material is carried out the product that heat drawing is produced diaphragm at last, and the thickness of diaphragm is more than 0.01 millimeter, according to the difference of field of employment; The thickness of product diaphragm is different, is adding man-hour, can adjust the thickness of tubing as required; To adapt to the draw ratio in the process, perhaps adjust the length and the temperature of heat tunnel, and adjust the speed of rolls of calender simultaneously; To adapt to the draw ratio in the process, obtain needed different diaphragm thickness, for example: tubing thickness is 8 millimeters; Through after the hot-stretch method of the embodiment of the invention, can obtain the diaphragm of 0.5 millimeters thick.
Ultra high molecular weight polyethylene films sheet hot-stretch processing method of the present invention may further comprise the steps:
1. get raw material for standby by following weight proportion: polyvinyl resin with super-high molecular weight 93kg, Tissuemat E 4.5kg, plasticizer 2kg and anti-oxidant 0.5kg;
2. insert extruding pipe material in the single screw extrusion machine after each raw material being mixed;
3. in the pipe mold of single screw extrusion machine outlet bottom cutting tool is installed, cutting tool along the tubing bottom tube wall tubing is vertically cut open;
4. the tubing after cutting open gets in the wedge shape mould, and tubing is launched to become profile material;
5. profile material is imported and carry out first order calendering in first calender, the roller temperature of first calender is 100 ℃-120 ℃, obtains the diaphragm parison after the calendering;
6. the diaphragm parison is imported in first heat tunnel and heat; Temperature in first heat tunnel is 90 ℃-120 ℃; Be introduced into through the diaphragm parison of first heat tunnel and carry out second level calendering in second calender, during the calendering of the second level, the speed of the second calender roll is 4 times of the first calender speed of rolls; Be stretched when making the diaphragm parison through first heat tunnel, draw ratio is 4 times;
7. the diaphragm parison that 6. rolls after the stretching through step imports heating in second heat tunnel; The temperature of second heat tunnel is 120 ℃-140 ℃; Import through the diaphragm parison behind second heat tunnel and to carry out third level calendering in the 3rd calender; The 3rd calender roller temperature is 90 ℃-130 ℃, and the speed of the 3rd calender roll is 2-3 times of the second calender speed of rolls, and the draw ratio of diaphragm parison is 2-3 times;
8. import the 3rd heat tunnel through the diaphragm parison after the third level calendering; Temperature in the 3rd heat tunnel is 120-140 ℃; Diaphragm parison after being heated imports in the 4th calender and rolls; The 4th calender roller temperature is 90-130 ℃, and the speed of the 4th calender roll is 2 times of the 3rd calender speed of rolls, and being stretched through the 3rd heat tunnel heating and the diaphragm parison after the 4th calender rolls becomes the diaphragm finished product after 2 times;
9. the diaphragm finished product gets into typing back rolling in the forming machine at last.
The structure of first heat tunnel described in the above-mentioned steps, second heat tunnel and the 3rd heat tunnel is all identical, and concrete structure is: heat tunnel upper and lower, left and right wall is interconnected to housing 21, and the centre is provided with cavity; Cavity middle part walking ultra-high molecular weight polyethylene section bar 14, housing 21 is box-like, adopts hinge to connect; Can upper and lower two parts be opened; Heat-insulation layer 25 is set in the housing 21, and heat-insulation layer 25 is connected with reflecting layer 26, and heater 22 is installed on the reflecting layer 26; Ultra-high molecular weight polyethylene section bar 14 upper and lower surfaces are provided with the first heat scatternet 23 and the second heat scatternet 24 respectively; The first heat scatternet 23 is connected with reflecting layer 26 sidewalls respectively with the second heat scatternet 24, offers port on the front and rear wall of heat tunnel respectively, and the diaphragm parison is passed through.
Wedge shape mould described in the step 4 structure as shown in Figure 5; The wedge shape mould base plate is the plane; Be provided with two sidewalls on the base plate, exit width is provided with herringbone guide plate 18 greater than throat width in the mould; The height of herringbone guide plate 18 by the peak of porch to the exit gradually step-down to become same plane with the exit; Herringbone guide plate 18 has constituted the first fractal groove 19 and the second fractal groove 20 respectively with two sidewalls of mould, and cover plate 27 is placed at the top of mould, and cover plate 27 is provided with spacing with herringbone guide plate 18 end faces.The size of this spacing confirms that by the thickness of tubing the tubing after the cutting is imported into wedge shape mould, and the tubing bottom is broken away the inlet entering of back by wedge shape mould, after coming out, becomes profile material.Tubing generate profile material after this wedge shape mould can quick and accurate will be cut open is for the hot-stretch of subsequent processing provides good section bar basis.
The length of first heat tunnel according to the invention is 0.95-1.05 rice, and the length of second heat tunnel and the 3rd heat tunnel is 0.45-0.55 rice.The length of above-mentioned heat tunnel is one of reasonable embodiment in the processing method of the present invention, and certainly, the length of each heat tunnel also can be according to the needs setting of draw ratio, lengthening or shortening.
The concrete structure of the single screw extrusion machine that uses in the inventive method is that disclosed structure is identical in 00215903.1 specification with the patent No..The calender that uses in the inventive method is known calender, and the structure of forming machine 12 described in the inventive method and winder 13 is a known technology.

Claims (4)

1. ultra high molecular weight polyethylene films sheet hot-stretch processing method is characterized in that: may further comprise the steps:
1. get raw material for standby by following weight proportion: polyvinyl resin with super-high molecular weight 93kg, Tissuemat E 4.5kg, plasticizer 2kg and anti-oxidant 0.5kg;
2. insert extruding pipe material in the single screw extrusion machine after each raw material being mixed;
3. in the pipe mold of single screw extrusion machine outlet bottom cutting tool is installed, cutting tool along the tubing bottom tube wall tubing is vertically cut open;
4. the tubing after cutting open gets in the wedge shape mould, and tubing is launched to become profile material;
5. profile material is imported and carry out first order calendering in first calender, the roller temperature of first calender is 100 ℃-120 ℃, obtains the diaphragm parison after the calendering;
6. the diaphragm parison is imported in first heat tunnel and heat; Temperature in first heat tunnel is 90 ℃-120 ℃; Be introduced into through the diaphragm parison of first heat tunnel and carry out second level calendering in second calender; When rolled the second level, the speed of the second calender roll was 4 times of the first calender speed of rolls, is stretched when making the diaphragm parison through first heat tunnel;
7. the diaphragm parison that 6. rolls after the stretching through step imports heating in second heat tunnel; The temperature of second heat tunnel is 120 ℃-140 ℃; Import through the diaphragm parison behind second heat tunnel and to carry out third level calendering in the 3rd calender; The 3rd calender roller temperature is 90 ℃-130 ℃, and the speed of the 3rd calender roll is 2-3 times of the second calender speed of rolls;
8. import the 3rd heat tunnel through the diaphragm parison after the third level calendering; Temperature in the 3rd heat tunnel is 120-140 ℃; Diaphragm parison after being heated imports in the 4th calender and rolls; The 4th calender roller temperature is 90-130 ℃, and the speed of the 4th calender roll is 2 times of the 3rd calender speed of rolls, is drawn into the diaphragm finished product through heating of the 3rd heat tunnel and the diaphragm parison after the calendering of the 4th calender;
9. the diaphragm finished product gets into typing back rolling in the forming machine at last;
The structure of first heat tunnel described in the above-mentioned steps, second heat tunnel and the 3rd heat tunnel is all identical; Concrete structure is: heat tunnel upper and lower, left and right wall is interconnected to housing (21); The centre is provided with cavity, and walking ultra-high molecular weight polyethylene section bar (14) in cavity middle part is provided with heat-insulation layer (25) in the housing (21); Heat-insulation layer (25) is connected with reflecting layer (26); Reflecting layer (26) is gone up heater (22) is installed, and ultra-high molecular weight polyethylene section bar (14) upper and lower surface is provided with the first heat scatternet (23) and the second heat scatternet (24) respectively, and the first heat scatternet (23) is connected with reflecting layer (26) sidewall respectively with the second heat scatternet (24); Offer port on the front and rear wall of heat tunnel respectively, the diaphragm parison is passed through.
2. ultra high molecular weight polyethylene films sheet hot-stretch processing method according to claim 1, it is characterized in that: the length of first heat tunnel is 0.95-1.05 rice.
3. ultra high molecular weight polyethylene films sheet hot-stretch processing method according to claim 1, it is characterized in that: the length of the length of second heat tunnel and the 3rd heat tunnel is 0.45-0.55 rice.
4. ultra high molecular weight polyethylene films sheet hot-stretch processing method according to claim 1; It is characterized in that: be provided with herringbone guide plate (18) in the mould of the wedge shape mould described in the step 4; The height of herringbone guide plate (18) by the peak of porch to the exit gradually step-down to become same plane with the exit; Herringbone guide plate (18) has constituted the first fractal groove (19) and the second fractal groove (20) respectively with two sidewalls of mould; Cover plate (27) is placed at the top of mould, and cover plate (27) is provided with spacing with herringbone guide plate (18) end face.
CN 201010506628 2010-10-14 2010-10-14 Thermal stretch processing method of ultra-high molecular weight polyethylene diaphragm Expired - Fee Related CN102009472B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN 201010506628 CN102009472B (en) 2010-10-14 2010-10-14 Thermal stretch processing method of ultra-high molecular weight polyethylene diaphragm

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN 201010506628 CN102009472B (en) 2010-10-14 2010-10-14 Thermal stretch processing method of ultra-high molecular weight polyethylene diaphragm

Publications (2)

Publication Number Publication Date
CN102009472A CN102009472A (en) 2011-04-13
CN102009472B true CN102009472B (en) 2012-12-05

Family

ID=43839895

Family Applications (1)

Application Number Title Priority Date Filing Date
CN 201010506628 Expired - Fee Related CN102009472B (en) 2010-10-14 2010-10-14 Thermal stretch processing method of ultra-high molecular weight polyethylene diaphragm

Country Status (1)

Country Link
CN (1) CN102009472B (en)

Families Citing this family (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102320137B (en) * 2011-08-04 2014-04-16 山东和谐管业有限公司 Preparation device of ultra-high molecular weight polyethylene sheets and preparation method thereof
CN103009620B (en) * 2011-09-20 2017-11-24 上海华义化工科技有限公司 The heating means and heater of tubular film blank tube
CN102658654A (en) * 2012-05-26 2012-09-12 江苏联冠高新技术有限公司 Manufacture method of ultra-high molecular weight polyethylene plate
CN103072260A (en) * 2012-12-28 2013-05-01 青岛中科昊泰创新技术研究院有限公司 Device for producing plates by ultrahigh molecular weight polyethylene pipes
CN103217445B (en) * 2013-04-08 2015-06-17 中国科学技术大学 Extruding and drawing device for in-situ structure detection in combination with scattering of X rays and experimental method thereof
CN112571708A (en) * 2020-11-17 2021-03-30 中国电子科技集团公司第四十六研究所 Calendering method of ultrathin polytetrafluoroethylene substrate

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101293982A (en) * 2008-06-20 2008-10-29 河南康喜科技有限公司 High-density polyethylene geomembrane and preparing technique thereof
CN101301789A (en) * 2007-05-11 2008-11-12 陈鸣 Method for producing special polyethylene film capable of bonding with metal and non-metal

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101301789A (en) * 2007-05-11 2008-11-12 陈鸣 Method for producing special polyethylene film capable of bonding with metal and non-metal
CN101293982A (en) * 2008-06-20 2008-10-29 河南康喜科技有限公司 High-density polyethylene geomembrane and preparing technique thereof

Also Published As

Publication number Publication date
CN102009472A (en) 2011-04-13

Similar Documents

Publication Publication Date Title
CN102009472B (en) Thermal stretch processing method of ultra-high molecular weight polyethylene diaphragm
US10179427B2 (en) Multi-stage roll type sheet molding apparatus
CN105599266A (en) Production device and method for polypropylene composited and modified extrusion sheet for trolley case
CN102431176A (en) Complete equipment for manufacturing polytetrafluoroethylene oriented films and method thereof
CN110978445A (en) PE pipeline production process and device
CN101962820A (en) Superhigh molecular weight polyethylene monofilament and hot drawing processing method thereof
CN102350780B (en) Apparatus and method for preparing polymer foam material based on differential principle
CN103358518B (en) The manufacturing equipment and its application method of five layers of melting co-extrusion fiber enhanced plastic plate material
Chen et al. Optimization of the coathanger manifold via computer simulation and an orthogonal array method
CN105291444B (en) The plastic honeycomb board continuous producing method and equipment of synergy are rolled based on plastic uptake
CN204505875U (en) On-line curing three-roller calendaring device
CN104191634A (en) Extruded wide film and sheet production line
CN205652909U (en) Pyrocondensation pipe coiling mechanism
CN101274490A (en) Manufacturing system for inside seal of vehicle window
CN215032424U (en) Gradual expansion die structure for continuous extrusion forming of copper and copper alloy plate strip
CN101444965A (en) Method for manufacturing underground flame retardant whole core conveyer belt used in colliery and device thereof
CN214000244U (en) Casting equipment for producing environment-friendly degradable material sheet
CN104723581A (en) Preparation method of fluorine layer-containing polyimide composite material and equipment for method
CN204505666U (en) Online circulation three-roller calendaring device
CN102700108A (en) Coextruded mould of polrvinyl chloride and polymethylmethacrylate
CN202388805U (en) Complete equipment for manufacturing polytetrafluoroethylene oriented film
CN109228220B (en) Melt extrusion-flow/calendaring molding method and device for high-viscosity material
CN205853296U (en) A kind of three-layer co-extruded plastic pipe process units
KR20210027731A (en) Cable sheath extruder
CN105216267A (en) A kind of broadsheet efficient uniform extruder head and extrusion method

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: JI'NAN XIANHE TECHNOLOGY DEVELOPMENT CO., LTD.

Free format text: FORMER OWNER: LIU FUDONG

Effective date: 20120531

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 250002 JINAN, SHANDONG PROVINCE TO: 250108 JINAN, SHANDONG PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20120531

Address after: 250108 Shandong Province, Ji'nan City Industrial Road Licheng District, Zhangmatun Zhang Ma Industrial Park

Applicant after: Jinan Xianhe Technology Development Co., Ltd.

Address before: 250002, No. 2, unit 4, building three, 601 District, sunshine Shun City, Shizhong District, Ji'nan, Shandong

Applicant before: Liu Fudong

C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: SHANDONG XIANHE POLYMER MATERIALS CO., LTD.

Free format text: FORMER OWNER: JI'NAN XIANHE TECHNOLOGY DEVELOPMENT CO., LTD.

Effective date: 20130410

C41 Transfer of patent application or patent right or utility model
COR Change of bibliographic data

Free format text: CORRECT: ADDRESS; FROM: 250108 JINAN, SHANDONG PROVINCE TO: 255000 ZIBO, SHANDONG PROVINCE

TR01 Transfer of patent right

Effective date of registration: 20130410

Address after: 255000, Shandong high tech Zone, Zibo, 51 Tai Chi Avenue, high polymer materials innovation park, block A, room 1110, room 11

Patentee after: Shandong Xianhe Polymer Materials Co., Ltd.

Address before: 250108 Shandong Province, Ji'nan City Industrial Road Licheng District, Zhangmatun Zhang Ma Industrial Park

Patentee before: Jinan Xianhe Technology Development Co., Ltd.

TR01 Transfer of patent right

Effective date of registration: 20171109

Address after: 255084 Shandong high tech Zone in Zibo City, Northridge Road No. 5005

Patentee after: SHANDONG DIHAO WEAR-RESISTING PIPE CO., LTD.

Address before: 255000, Shandong high tech Zone, Zibo, 51 Tai Chi Avenue, high polymer materials innovation park, block A, room 1110, room 11

Patentee before: Shandong Xianhe Polymer Materials Co., Ltd.

TR01 Transfer of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20121205

Termination date: 20201014

CF01 Termination of patent right due to non-payment of annual fee