CN101985826B - Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam - Google Patents

Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam Download PDF

Info

Publication number
CN101985826B
CN101985826B CN201010285591A CN201010285591A CN101985826B CN 101985826 B CN101985826 B CN 101985826B CN 201010285591 A CN201010285591 A CN 201010285591A CN 201010285591 A CN201010285591 A CN 201010285591A CN 101985826 B CN101985826 B CN 101985826B
Authority
CN
China
Prior art keywords
section
beam section
assembled
spliced girder
spliced
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201010285591A
Other languages
Chinese (zh)
Other versions
CN101985826A (en
Inventor
欧阳钢
陈明宪
肖跃文
方联民
丁望星
林立军
刘武
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Road and Bridge Construction Group Co Ltd
Original Assignee
Hunan Road and Bridge Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Road and Bridge Construction Group Co Ltd filed Critical Hunan Road and Bridge Construction Group Co Ltd
Priority to CN201010285591A priority Critical patent/CN101985826B/en
Publication of CN101985826A publication Critical patent/CN101985826A/en
Application granted granted Critical
Publication of CN101985826B publication Critical patent/CN101985826B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of a large concrete box beam, which is characterized by comprising the following steps: 1) erecting a high-pile prefabricated platform; 2) erecting beam moving steel tube supports and steel slide rails between the high-pile prefabricated platform and a pier; 3) pouring a matched beam section on the high-pile prefabricated platform; 4) using the poured matched beam section as the end die at one end of the next new beam section to be poured and pouring the new beam section; 5) after pouring the new beam section, transporting the matched beam section to the design position as the beam section to be assembled and simultaneously moving the new beam section forward as the next matched beam section; 6) longitudinally moving the beam section to be assembled to the matching surface of the end of the assembled beam section as the beam section to be assembled and adjusting the position of the beam section to be assembled to ensure the beam section to be assembled to conform to the requirement of split joint with the assembled beam section on the pier; and 7) carrying out split joint on the beam section to be assembled and the assembled beam section. By section prefabricating and long-time beam storing of the beam sections, the construction method effectively ensures the prefabricated beam sections to complete most contraction deformation of the beam body in free state and eliminates the contraction difference of the adjacent beam sections caused by different ages, thus eliminating cracks.

Description

The empty prefabricate of a kind of large concrete boxes deck-molding, move beam, deposit beam, the job practices of assembly unit
Technical field
The invention belongs to method for bridge construction, be specifically related to the empty prefabricate of a kind of large concrete boxes deck-molding, move beam, deposit beam, the job practices of assembly unit.
Background technology
At present, domestic, in the world the large concrete boxes beam is generally adopted the segmentation cast-in-place construction, yet in work progress, because the effect of contraction that the leading portion concreting shrinks the back segment concreting, thereby it is poor to produce concrete shrinkage, causes the crack to produce.Simultaneously, stride segmentation because concreting is many by whole, single hop beam body volume is excessive, causes the beam section because the effect that self retrains also is easy to produce the free shrink crack.
Domestic, the type bridge requires whole Span Continuous to build, for prevent the case beam in building, treat strong process owing to deformation of timbering causes concrete cracking, domestic many similar bridges propose the requirement of 0 sedimentation and deformation to support.This requirement is unpractical from theoretical and actual.
Summary of the invention
The purpose of this invention is to provide the empty prefabricate of a kind of large concrete boxes deck-molding, move beam, deposit beam, the job practices of assembly unit, with solve long beam section in work progress owing to the contraction of beam body, creep and support sedimentation, distortion produce problem of cracks.
Realize that the technical scheme that goal of the invention adopts is: the empty prefabricate of large concrete boxes deck-molding, move beam, deposit beam, the job practices of assembly unit may further comprise the steps:
1, bridge pull in to shore set up high stake prefabricated platform to a side;
2, between high stake prefabricated platform and bridge pier, set up and move the joist steel pipe holder, the parallel steel slide rail of twice is set moving on the joist steel pipe holder;
3, on high stake prefabricated platform, build the matching beam section;
4, the matching beam section that will build is built new beam section as the end mould of the next one new beam Duan Yiduan to be poured;
5, after new beam section is built, through Beam shifter the matching beam section is transported to design attitude along said steel slide rail and deposits beam as beam section to be assembled and treat by force, simultaneously new beam section is moved forward as next matching beam section;
6, beam section examination assembly unit: the coupling face that beam section to be assembled is vertically moved on to the assembled beam section end is as the spliced girder section, the position of adjustment spliced girder section make its meet with bridge pier on the assembled beam section requirement of splicing;
7, the formal assembly unit of beam section: spliced girder section and assembled beam section are spliced.
In step 2; Said moving on the pile foundation support table that the joist steel pipe holder is located at foundation pile; To with direction across bridge stull, bridging being set, direction across bridge is provided with the distribution girder steel to the steel pipe post that moves the joist steel pipe holder on the joist steel pipe holder moving along bridge, and said steel slide rail is located at and distributes on the girder steel.
In said step 4; Be according to construction requirement; In matching beam section bottom the adjustment that the three-dimensional jack carries out matching beam segment mark height and plan-position is set earlier, the bed die and the side form of new beam section to be poured are installed, should make the longitudinal grade of new beam section to be poured consistent during mounting template with the longitudinal grade of matching beam section; One-tenth bridge to guarantee the later stage assembly unit is linear, builds new beam section again.
Beam shifter in the said step 5 comprises:
Four are arranged under the matching beam section, move the beam slide on the steel slide rail; Move the beam slide and comprise horseback riding type steel seat; The board-like block rubber that contacts with the matching beam section is set at horseback riding type steel seat top; Be provided with horseback riding type steel seat bottom and moving the NGB slide plate that the beam slide rail contacts, the postive stop baffle of horseback riding type steel seat both sides welding;
Be arranged at the reaction frame on the twice steel slide rail, the setting of reaction frame front end moves the beam jack, and every jack front end is provided with a shoulder pole girder, is equipped with two pull bars, and an end of pull bar is connected with horseback riding type steel seat, and the other end links to each other with the shoulder pole girder of jack front end.
In the said step 6; Said beam section examination assembly unit is the position that beam section to be assembled is vertically moved on to the about 10cm of coupling face of assembled beam section end; As the spliced girder section; Strengthen laying the three-dimensional jack below the steel plate at spliced girder section fulcrum, this moment, three-dimensional jack vertical equity stroke leaned on the river side to reserve 10cm, and the side of pulling in to shore is reserved 20cm; Control point to spliced girder section back is observed, and is high according to measurement result and monitored instruction adjustment spliced girder segment mark, after absolute altitude is adjusted to the right place, utilizes the transverse horizontal position of the transverse horizontal jack adjustment spliced girder section on three-dimensional top; After adjusting to the right place, guarantee that the spliced girder segment mark is high, under the situation of transverse horizontal invariant position,, spliced girder section and assembled beam section be close to, absolute altitude, the center line of inspection spliced girder section and mate the face situation the spliced girder section 10cm that vertically moves forward.
In the said step 7; The formal assembly unit of said beam section is to retreat 30cm with the vertical equity jack pushing tow spliced girder section of three-dimensional jack; Connect the longitudinal prestressing strands of spliced girder section upper plate and base plate; Assembled beam section is close in the reach of spliced girder section, the absolute altitude of inspection spliced girder section, center line and coupling face situation; Absolute altitude and plan-position with three-dimensional jack adjustment spliced girder section; After adjusting; The spliced girder section is retreated 30cm; At the bonding surface brushwork epoxy resin cementing agent of spliced girder section and assembled beam section,, the cementing agent between seam is solidified under authorized pressure by designing requirement stretch-draw spliced girder section top top board and baseboard prestress bundle with the vertically reach and assembled beam section splicing of spliced girder section; After the epoxy resin adhesive curing, stretch-draw remains longitudinal prestressing strands, finishes in 24 hours in stretch-draw and in time carries out mud jacking; Become new assembled beam section after the assembly unit of spliced girder section is good; At this moment extract the slide under the new assembled beam section out; Install rigid mount, rigid mount adopts the steel seat cushion to establish and forms according to the new assembled beam section bottom surface and the spacing of orbital plane; After rigid mount was installed, the release of three-dimensional jack was also extracted out and is carried out next beam section assembly unit.
Job practices of the present invention through the beam section prefabricate and deposit beam for a long time, effectively make the precast beam section under free state, accomplish most of shrinkage strain of beam body, it is poor because of the different contractions that produce in the length of time to eliminate the adjacent beams section, thereby the elimination crack.Simultaneously and since the precast beam section to build volume less relatively, on support, deposit and treat when strong; The slide that is provided with under the beam section can be free to slide on slide rail, thereby, under the effect of the shrinkage stress of beam body own; But beam body free shrink moves, and has effectively prevented the appearance in crack own; Owing to adopt segmented prefabricatedly, will longer beam section be divided into short segment and make, prevented that long beam section from producing the crack because of support sedimentation, distortion in work progress.
Pass through conversion into bridge coordinate system to prefabricated linear coordinate system; With watering the beam section as the end mould that newly waters beam Duan Yiduan; Control its linear variation with the relative position of this two beams section; Coupling seam with its formation is guaranteed the adjacent block splicing accuracy, and flowing water is produced the prefabricated case beam sections in the fixed form system on precast pedestal.
Prefabricated beam section is utilized Beam shifter to draw to move beam, slide onto design attitude and treat by force moving on the boom support.After beam section intensity reaches designing requirement and accomplishes most of shrinkage and creep, on support, utilize three-dimensional jack pair beam section to carry out the adjustment of locus, and then smear epoxy resin on the beam section bonding surface, the stretch-draw prestressing force bundle is accomplished assembly unit.
Description of drawings
Fig. 1 is the sketch map of the inventive method.
Fig. 2 is the high stake prefabricated platform elevational schematic view in the inventive method.
Fig. 3 is the high stake prefabricated platform side schematic view in the inventive method.
Fig. 4 is that move joist steel pipe holder structure section and the beam section in the inventive method deposited sketch map moving on the joist steel pipe holder.
Fig. 5, Fig. 6 are the Matching Precast situation sketch mapes of beam section.
Beam shifter sketch map in Fig. 7 the inventive method.
Fig. 8 moves beam slide carriage structure sketch map in the Beam shifter.
Fig. 9 is a Beam shifter traction end sketch map.
The specific embodiment
The inventive method may further comprise the steps, referring to Fig. 1 to Fig. 9:
1, bridge pull in to shore set up high stake prefabricated platform 1 to a side (bank side), high stake prefabricated platform 1 adopts the steel pipe support structure, arranges the required template system of precast beam section, referring to Fig. 1, Fig. 2;
2, move joist steel pipe holder 2 along bridge to setting up between the pier stud 13 of river one side (river side) leaning on of high stake prefabricated platform 1 and bridge, moving joist steel pipe holder 2 is load-carrying members that the beam section moves and deposits; The parallel steel slide rail 5 of twice is set moving on the joist steel pipe holder 2; Move on the pile foundation support table 4 that joist steel pipe holder 2 is located at pile foundation 3, the steel pipe post that moves joist steel pipe holder 2 along bridge to stull, bridging being set, to guarantee the support monolithic stability with direction across bridge; Being provided with and distributing girder steel 6 moving on the joist steel pipe holder 2 direction across bridge, is the support of steel slide rail 5 as the load-bearing girder steel; Suitable bridge as the steel slide rail and main spandrel girder that the beam section moves and deposits, distributes the installation of girder steel 6 and steel slide rail 5 to control its absolute altitude and plan-position by the designing requirement strictness, referring to Fig. 1 to Fig. 4 to the parallel steel slide rail 5 of twice is set on distribution girder steel 6;
3, on high stake prefabricated platform 1, build matching beam section 8, referring to Fig. 3;
4, after matching beam section 8 location, according to construction requirement, survey crew is the survey data during as new beam section 7 end moulds to be poured according to matching beam section 8, and the mutual alignment of matching beam section 8 and 7 of new beam sections to be poured concerns, calculates new beam section to be poured 7 present positions; According to measuring and monitor data, carry out the adjustment of matching beam section 8 absolute altitudes and plan-position through 4 three-dimensional jack under the matching beam section 8; The bed die and the side form of new beam section 7 to be poured are installed then, should be made the longitudinal grade of new beam section 7 to be poured consistent during mounting template with the longitudinal grade of matching beam section 8, linear with the one-tenth bridge of guaranteeing the later stage assembly unit, build new beam section 7 again, referring to Fig. 1, Fig. 3;
5, beam section movement, deposit: the method that the transportation of the beam prefabricated sections of case on steel slide rail (main spandrel girder) 5 adopts Beam shifter 14 tractions to slide and move beam; After new beam section 7 to be poured is built; Through Beam shifter 14 the matching beam section 8 on the high stake prefabricated platform 1 being transported to design attitude as movement beam section 9 along said steel slide rail 5 deposits beam as beam section 10 to be assembled and treats by force; Simultaneously the new beam section 7 ' on the high stake prefabricated platform 1 is moved forward as next matching beam section 8, referring to Fig. 1, Fig. 5, Fig. 6;
Beam shifter 14 is extremely shown in Figure 9 like Fig. 7; Comprise that four are arranged at and move beam slide 141 under the case beam beam section, on the steel slide rail 5; Move beam slide 141 and comprise horseback riding type steel seat 1412, reach board-like block rubber 1411 and the horseback riding type steel seat 1412 that is provided with between horseback riding type steel seat 1412 and the case beam beam section and move the NGB slide plate 1414 that is provided with between the beam slide rail, the postive stop baffle 1413 of horseback riding type steel seat 1412 both sides welding, to guarantee in moving the beam process, moving not offset track of beam slide 1;
Beam shifter 14 also comprises the reaction frame 143 that is arranged on the twice steel slide rail 5, and reaction frame 143 front end settings move beam jack 144; Every jack 144 front ends are provided with a shoulder pole girder 145, are equipped with 2 finish rolling deformed bars and make pull bar 142, and an end of pull bar 142 is connected with horseback riding type steel seat 1412, and the other end links to each other with the shoulder pole girder 145 of jack 144 front ends;
6, beam section examination assembly unit: the position of the about 10cm of coupling face that beam section 10 to be assembled is vertically moved on to assembled beam section 12 ends is as spliced girder section 11; Strengthen laying the three-dimensional jack below the steel plate at spliced girder section 11 fulcrums; This moment, three-dimensional jack vertical equity stroke leaned on the river side to reserve 10cm, and the side of pulling in to shore is reserved 20cm; Control point to spliced girder section 11 backs is observed, and transfers spliced girder section 11 absolute altitudes according to measurement result and monitored instruction, after absolute altitude is adjusted to the right place, utilizes the transverse horizontal position of the transverse horizontal jack adjustment spliced girder section 11 on three-dimensional top; After adjusting to the right place, guarantee under the situation of spliced girder section 11 absolute altitudes, transverse horizontal invariant position, with spliced girder section 11 vertical reach 10cm, spliced girder section 11 and assembled beam section 12 are close to, the absolute altitude of inspection spliced girder section 11, center line and coupling face situation;
7, the formal assembly unit of beam section: the vertical equity jack pushing tow spliced girder section 11 with the three-dimensional jack is retreated 30cm; Connect the longitudinal prestressing strands of spliced girder section upper plate and base plate; Assembled beam section is close in 11 reaches of spliced girder section, the absolute altitude of inspection spliced girder section 11, center line and coupling face situation; Absolute altitude and plan-position with three-dimensional jack adjustment spliced girder section 11; After adjusting; Spliced girder section 11 is retreated 30cm; At the mating face brushwork epoxy resin cementing agent of spliced girder section 11 and assembled beam section 12,, make the cementing agent between seam under authorized pressure, solidify (about 12 hours) by designing requirement stretch-draw spliced girder section top top board and baseboard prestress with vertically reach and assembled beam section 12 splicings of spliced girder section 11; After the epoxy resin adhesive curing, stretch-draw remains longitudinal prestressing strands, finishes in 24 hours in stretch-draw and in time carries out mud jacking; Become new assembled beam section 12 after 11 assembly units of spliced girder section are good; At this moment extract out and move beam slide 141 under the new assembled beam section 12; Install rigid mount, rigid mount adopts the steel seat cushion to establish and forms according to the spacing of new assembled beam section 12 bottom surfaces and orbital plane; After rigid mount was installed, the release of three-dimensional jack was also extracted out and is carried out next beam section assembly unit.

Claims (6)

  1. The empty prefabricate of a large concrete boxes deck-molding, move beam, deposit beam, the job practices of assembly unit, it is characterized in that may further comprise the steps:
    1), bridge pull in to shore set up high stake prefabricated platform to a side;
    2), between high stake prefabricated platform and bridge pier, set up and move the joist steel pipe holder, the parallel steel slide rail of twice is set moving on the joist steel pipe holder;
    3), on high stake prefabricated platform, build the matching beam section;
    4), the matching beam section that will build is as the end mould of the next one new beam Duan Yiduan to be poured, builds new beam section;
    5), after new beam section builds, through Beam shifter the matching beam section is transported to design attitude along said steel slide rail and deposits beam as beam section to be assembled and treat by force, simultaneously new beam section is moved forward as next matching beam section;
    6), beam section examination assembly unit: the coupling face that beam section to be assembled is vertically moved on to the assembled beam section end is as the spliced girder section, the position of adjustment spliced girder section make its meet with bridge pier on the assembled beam section requirement of splicing;
    7), the formal assembly unit of beam section: spliced girder section and assembled beam section are spliced.
  2. 2. the empty prefabricate of large concrete boxes deck-molding according to claim 1, move beam, deposit beam, the job practices of assembly unit; It is characterized in that in step 2) in; Said moving on the pile foundation support table that the joist steel pipe holder is located at foundation pile; To with direction across bridge stull, bridging being set, direction across bridge is provided with the distribution girder steel to the steel pipe post that moves the joist steel pipe holder on the joist steel pipe holder moving along bridge, and said steel slide rail is located at and distributes on the girder steel.
  3. 3. the empty prefabricate of large concrete boxes deck-molding according to claim 1, move beam, deposit beam, the job practices of assembly unit; It is characterized in that in said step 4); Be according to construction requirement; In matching beam section bottom the adjustment that the three-dimensional jack carries out matching beam segment mark height and plan-position is set earlier, the bed die and the side form of new beam section to be poured are installed, should make the longitudinal grade of new beam section to be poured consistent during mounting template with the longitudinal grade of matching beam section; One-tenth bridge to guarantee the later stage assembly unit is linear, builds new beam section again.
  4. 4. the empty prefabricate of large concrete boxes deck-molding according to claim 1, move beam, deposit beam, the job practices of assembly unit, it is characterized in that the Beam shifter in the said step 5) comprises:
    Four are arranged under the matching beam section, move the beam slide on the steel slide rail; Move the beam slide and comprise horseback riding type steel seat; The board-like block rubber that contacts with the matching beam section is set at horseback riding type steel seat top; Be provided with horseback riding type steel seat bottom and moving the NGB slide plate that the beam slide rail contacts, the postive stop baffle of horseback riding type steel seat both sides welding;
    Be arranged at the reaction frame on the twice steel slide rail, the setting of reaction frame front end moves the beam jack, and every jack front end is provided with a shoulder pole girder, is equipped with two pull bars, and an end of pull bar is connected with horseback riding type steel seat, and the other end links to each other with the shoulder pole girder of jack front end.
  5. 5. the empty prefabricate of large concrete boxes deck-molding according to claim 1, move beam, deposit beam, the job practices of assembly unit; It is characterized in that in the said step 6); Said beam section examination assembly unit is the position that beam section to be assembled is vertically moved on to the about 10cm of coupling face of assembled beam section end, as the spliced girder section, strengthens laying the three-dimensional jack below the steel plate at spliced girder section fulcrum; This moment, three-dimensional jack vertical equity stroke leaned on the river side to reserve 10cm, and the side of pulling in to shore is reserved 20cm; Control point to spliced girder section back is observed, and is high according to measurement result and monitored instruction adjustment spliced girder segment mark, after absolute altitude is adjusted to the right place, utilizes the transverse horizontal position of the transverse horizontal jack adjustment spliced girder section on three-dimensional top; After adjusting to the right place, guarantee that the spliced girder segment mark is high, under the situation of transverse horizontal invariant position,, spliced girder section and assembled beam section be close to, absolute altitude, the center line of inspection spliced girder section and mate the face situation the spliced girder section 10cm that vertically moves forward.
  6. 6. the empty prefabricate of large concrete boxes deck-molding according to claim 1, move beam, deposit beam, the job practices of assembly unit; It is characterized in that in the said step 7); The formal assembly unit of said beam section is to retreat 30cm with the vertical equity jack pushing tow spliced girder section of three-dimensional jack; Connect the longitudinal prestressing strands of spliced girder section upper plate and base plate, assembled beam section is close in the reach of spliced girder section, the absolute altitude of inspection spliced girder section, center line and coupling face situation; Absolute altitude and plan-position with three-dimensional jack adjustment spliced girder section; After adjusting; The spliced girder section is retreated 30cm; At the bonding surface brushwork epoxy resin cementing agent of spliced girder section and assembled beam section,, the cementing agent between seam is solidified under authorized pressure by designing requirement stretch-draw spliced girder section top top board and baseboard prestress bundle with the vertically reach and assembled beam section splicing of spliced girder section; After the epoxy resin adhesive curing, stretch-draw remains longitudinal prestressing strands, finishes in 24 hours in stretch-draw and in time carries out mud jacking; Become new assembled beam section after the assembly unit of spliced girder section is good; At this moment extract the slide under the new assembled beam section out; Install rigid mount, rigid mount adopts the steel seat cushion to establish and forms according to the new assembled beam section bottom surface and the spacing of orbital plane; After rigid mount was installed, the release of three-dimensional jack was also extracted out and is carried out next beam section assembly unit.
CN201010285591A 2010-09-19 2010-09-19 Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam Active CN101985826B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010285591A CN101985826B (en) 2010-09-19 2010-09-19 Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010285591A CN101985826B (en) 2010-09-19 2010-09-19 Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam

Publications (2)

Publication Number Publication Date
CN101985826A CN101985826A (en) 2011-03-16
CN101985826B true CN101985826B (en) 2012-10-10

Family

ID=43710217

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010285591A Active CN101985826B (en) 2010-09-19 2010-09-19 Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam

Country Status (1)

Country Link
CN (1) CN101985826B (en)

Families Citing this family (16)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102286939A (en) * 2011-08-09 2011-12-21 中铁二十四局集团有限公司 Beam moving and connecting construction method of existing viaducts in urban rail transits
CN103696369B (en) * 2013-11-26 2015-11-18 武汉一冶钢结构有限责任公司 Steel box girder segment four point positioning mounting method
CN103774556B (en) * 2014-01-14 2017-01-04 中建三局集团有限公司 Light-duty bed-jig of assembling pushes away platform integral type device with top pushes away pivot disconnect-type
CN104748732B (en) * 2015-03-26 2017-05-10 广州瀚阳工程咨询有限公司 Measurement method for segmental precast bridge erection field
CN105133500B (en) * 2015-08-28 2016-11-23 中交第二航务工程局有限公司 Without measuring the prefabricated installation method of the prefabricated box-beam sections of tower
CN105442452B (en) * 2015-11-13 2017-12-29 中铁大桥局集团第一工程有限公司 A kind of device and method for assembled double width bridge girder steel
CN105464010A (en) * 2015-11-18 2016-04-06 中泰国际高新技术有限公司 Concrete box culvert construction method and system based on automatic transportation
CN105464011A (en) * 2015-11-18 2016-04-06 中泰国际高新技术有限公司 Construction method and system for transporting, mounting and prefabricating box culverts through box culvert vehicles
CN107059624A (en) * 2016-12-14 2017-08-18 重庆交通大学 Plate segment continuous quick prefabricated-pushing tow in bridge road builds the equipment of combined bridge
CN106927404A (en) * 2017-04-19 2017-07-07 中铁六局集团有限公司 A kind of remote-controlled shifting beam dolly and beam shifting method with hydraulic system
CN108691277A (en) * 2018-08-02 2018-10-23 中铁四局集团有限公司 Three-dimensional adjusting tool for positioning segment prefabricated assembling beam in erection process
CN110629681A (en) * 2019-09-26 2019-12-31 常州市市政建设工程有限公司 Multi-span steel box girder construction process
CN111549678A (en) * 2020-05-25 2020-08-18 河南省第一建筑工程集团有限责任公司 Rapid construction method of prefabricated segmental beam
CN111809523B (en) * 2020-07-07 2021-09-14 中交二航局第四工程有限公司 Measurement and check method based on section box girder short line matching prefabricated pedestal foundation
CN112374359B (en) * 2020-10-30 2023-01-31 上海宝冶冶金工程有限公司 Method for replacing crane beam
CN113529586B (en) * 2021-08-25 2022-11-18 南通路桥工程有限公司 Box girder supporting system and construction method

Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101078198A (en) * 2007-07-04 2007-11-28 湖南省交通规划勘察设计院 Steel box beam erection method for self-anchored suspension bridge

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3114967B2 (en) * 1997-11-13 2000-12-04 株式会社サクラダ Box girder assembling method

Patent Citations (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101078198A (en) * 2007-07-04 2007-11-28 湖南省交通规划勘察设计院 Steel box beam erection method for self-anchored suspension bridge

Also Published As

Publication number Publication date
CN101985826A (en) 2011-03-16

Similar Documents

Publication Publication Date Title
CN101985826B (en) Construction method for high-altitude section prefabricating, beam moving, beam storing and assembling of large concrete box beam
CN104100092B (en) The track-type facilities of a kind of pitched roof pouring construction and method
CN101787678B (en) Large-span section assembling bridge manufacturing machine and assembling construction process thereof
CN107905114B (en) A kind of construction method of large span Successive interference cancellation
CN106522096A (en) Curved incremental launching construction technology for 48m-long-span railway simply-supported box girders and high piers
CN104480810B (en) Low circuit continuous frame formula support rail girder construction and the construction method thereof of putting of middle low speed magnetic suspension
CN109629439B (en) Construction method of single-tower cable-stayed bridge
CN217104732U (en) Sectional type crossbeam construction structures of strideing across existing railway line gate-type pier
CN103556817A (en) Side wall concrete construction method employing side wall trolley
CN102797223B (en) Construction method for cast-in-place of continuous beam at turnout junction for passenger transport line in seawall area by false work method
CN110158487A (en) It is glued assembling construction engineering method in single-track railway simple supported box beam segment
CN101324054B (en) Incremental launching positioning construction method of bridge subsection girder temporary pier
CN105568870A (en) Triangle hanging basket suspended casting device used for overpass bridge construction and construction method thereof
CN111455852A (en) Assembling method of movable formwork for bridge construction
CN112900282A (en) Bidirectional quick pushing equipment system for large-span main beam and construction method
CN102587282A (en) Large-section simply-supported box girder precasting and assembly process under conditions of strong wind and high altitude
CN110593114A (en) Box girder construction method based on large-span box girder multi-hoop truss support bailey bracket
CN104831632A (en) Upper transverse beam and lower transverse beam construction method for bridge cable bent tower
CN205242278U (en) A triangle string basket method is hanged and is watered device for deck bridge construction
CN101476290B (en) Cast-in-place construction method for bridge curtain board
CN106948267B (en) A kind of memorial archway bar formula bridge cable tower king-post method for synchronously constructing
CN102493349B (en) Method for prefabricating and erecting box girders by using bailey beam
CN110983992A (en) Cantilever assembling construction process for double-U-box type composite variable-section assembled continuous beam bridge
CN103806374A (en) Assembled road steel bridge overall track erection and push system and process
CN111042003A (en) Construction method of cable-stayed bridge concrete beam combined hanging basket

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C56 Change in the name or address of the patentee
CP01 Change in the name or title of a patent holder

Address after: 410004 Hunan province Changsha Yuhua District of Shaoshan City Road No. 239

Patentee after: Hunan Road & Bridge Construction Group Co., Ltd.

Address before: 410004 Hunan province Changsha Yuhua District of Shaoshan City Road No. 239

Patentee before: Hunan Road & Bridge Construction Group Corp.