CN101886468B - 高位连体结构悬挂式模板支撑施工方法 - Google Patents

高位连体结构悬挂式模板支撑施工方法 Download PDF

Info

Publication number
CN101886468B
CN101886468B CN2010101348150A CN201010134815A CN101886468B CN 101886468 B CN101886468 B CN 101886468B CN 2010101348150 A CN2010101348150 A CN 2010101348150A CN 201010134815 A CN201010134815 A CN 201010134815A CN 101886468 B CN101886468 B CN 101886468B
Authority
CN
China
Prior art keywords
steel
construction
conversion layer
girder
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2010101348150A
Other languages
English (en)
Other versions
CN101886468A (zh
Inventor
仓恒芳
刘亚非
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Dadi Construction Group Co Ltd
Original Assignee
Nanjing Dadi Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Dadi Construction Group Co Ltd filed Critical Nanjing Dadi Construction Group Co Ltd
Priority to CN2010101348150A priority Critical patent/CN101886468B/zh
Publication of CN101886468A publication Critical patent/CN101886468A/zh
Application granted granted Critical
Publication of CN101886468B publication Critical patent/CN101886468B/zh
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

本发明涉及一种高位连体结构悬挂式模板支撑施工方法。本发明采用安装箱型钢吊柱、安装钢梁、压型钢板、焊接抗剪栓钉、绑扎钢筋网片、浇筑楼承板混凝土工序,完成高位连体结构悬挂式模板。本发明解决了传统的承重满堂支撑架、架设高空重型操作平台所存在的支撑材料用量大,搭拆工期长,加固费用高,施工成本大、自重大、施工难度大等缺陷。本发明充分利用转换层钢主梁自身的承载能力,使该层组合楼板在施工阶段作为操作平台搭设模板支撑架,在使用阶段作为超高层建筑的永久性避难层,保证高空作业安全,节省施工费用,又增加了使用面积,该钢主梁作为劲性配筋参与钢骨混凝土连体结构工作,共同承受其上部各层逐渐增加的结构自重和施工荷载。

Description

高位连体结构悬挂式模板支撑施工方法
技术领域
本发明涉及一种高层建筑中高位连体结构,特别涉及一种高位连体结构悬挂式模板支撑施工方法。
背景技术
高层商住楼和办公楼的双塔楼间设置空中连廊或连体结构的建筑越来越多,对于这些建筑的高空连体混凝土结构转换层模板支撑***施工工艺是否合理,将直接影响着工程的安全、质量、工期和施工成本,选择正确的模板支撑施工工艺是该转换层结构施工的关键。在本发明之前,模板支撑施工工艺有:
一是采用传统的承重满堂支撑架。采取措施将裙房屋面加固后,在屋面上搭设高度约100m的满堂式模板支撑架,架体确保稳定并与塔楼实行有效拉结,使其满足连体结构的施工要求。该方案较为稳妥但支撑材料用量大,搭拆工期长,加固费用高,施工成本大。
二是架设高空重型操作平台。在两座塔楼主体混凝土结构施工时,在连体结构转换层设计标高的下方预设埋件,当该部位混凝土达到设计强度后,利用埋件焊接固定型钢支座。型钢支座上安装六四式铁路军用梁组成重型施工操作平台,再搭设连体结构模板支撑架。该施工工艺安全可靠,但临时操作平台自重大,其制作、租赁、安装和拆除的成本也大,且具有一定的施工难度。
因为这种施工方法或工艺均是临时性的,是为了施工二塔楼之间的连体结构而设置的,施工结束后是需要拆除的,所以施工时间及成本,拆除的时间及成本和难度都是必须考虑的。显然,上述二种施工方法均不理想。
发明内容
本发明的目的就在于克服上述缺陷,研制一种高位连体结构悬挂式模板支撑施工方法。
本发明的技术方案是:
高位连体结构悬挂式模板支撑施工方法,其主要技术步骤在于:
(1)安装转换层钢主梁
连体转换层为钢骨混凝土结构,主体施工时两座塔楼均预留了与连体结构相连接的钢牛腿,利用转换层上端相应位置的钢牛腿悬挂滑车组,用双机抬吊的方法将钢主梁逐根提升至设计位置并及时校正和焊接,其余钢次梁用塔吊安装;
(2)悬挂避难层结构施工
利用塔吊安装悬挂避难层的钢吊柱和钢结构楼承板,其施工工序为:
安装箱型钢吊柱→安装钢梁→压型钢板→焊接抗剪栓钉→绑扎钢筋网片→浇筑楼承板混凝土;
(3)在避难层上搭设支模架
在悬挂楼承板上搭设支模架,支承转换层楼板模板,支模架用门式架,也可用碗扣架和扣件、钢管搭设,支模架与两端塔楼主体结构实行有效拉接;
(4)安装转换层主梁、次梁自承重模板
1)在钢主梁腹板两侧的加劲肋处焊接钢筋作为钢拉杆,当梁宽为800mm时,设置一对Φ18的钢筋,当梁宽为800~1200mm时,设置两对Φ20钢筋;
2)在钢拉杆下端设置槽钢横楞,用直螺纹套筒调节固定,槽钢横楞上安装梁底模板,混凝土转换梁自重和全部施工荷载由钢拉杆向上传递给钢主梁;
3)在主梁、次梁两侧安装侧模、背楞及对拉螺栓;
(5)转换层梁板钢筋绑扎、预应力筋安装
混凝土转换梁纵向受力钢筋Φ32与钢柱相互交错布置,对穿过钢柱的纵向钢筋,预先在钢柱腹板上定位钻孔,粗直径钢筋采用套筒冷挤压工艺进行连接;转换层楼板钢筋为双层双向配置,楼板设计采用了无粘结预应力技术;
(6)拆除转换层模板及支模架。
本发明的优点和效果在于充分利用转换层钢主梁自身的承载能力。转换层钢主梁设计为焊接H型钢,截面高2600mm,经复核具有相当大的承载能力,完全可以利用其悬挂操作平台和自身的模板***。设计、建设和施工单位经过多次研究,认为可以在转换层钢主梁下悬挂一层钢结构组合楼板。该层组合楼板在施工阶段作为操作平台搭设模板支撑架,在使用阶段作为超高层建筑的永久性避难层,既保证了高空作业安全,节省了施工费用,又为业主增加了使用面积。
采用焊接H型钢作为混凝土连体结构转换层主梁、次梁的劲性配筋,并在转换层下悬挂一层钢结构楼承板作为施工阶段的操作平台(图1)。充分利用H型钢主梁自身足够大的承载能力,在连体转换层施工阶段,独立承受连体转换层自承重模板和结构自重、梁下悬挂的钢结构避难层自重以及楼板支模架等施工荷载;在连体转换层上部结构施工阶段,该钢主梁作为劲性配筋参与钢骨混凝土连体结构工作,共同承受其上部各层逐渐增加的结构自重和施工荷载。
附图说明
图1--本发明原理结构示意图。
图2--本发明中搭设在悬挂避难层上的支模架结构示意图。
具体实施方式
如图1、图2所示:
钢骨混凝土连体转换层悬挂式模板支撑***由两部分组成:
1)钢骨混凝土连体转换梁3(由钢主梁1和混凝土构成)采用自承重模板(由钢主梁1、钢拉杆5、槽钢9和直螺纹套筒10构成),其混凝土、钢筋和模板重量以及施工活载通过多对均匀分布的钢拉杆5传递至钢主梁1;
2)转换层混凝土楼板4采用常规楼板支模架6,由转换层下部通过数根钢吊柱2悬挂的钢结构避难层7承受楼板支模架6的各项荷载。
1、由钢骨混凝土连体转换层和其下方的悬挂钢结构避难层7组成连体承力结构。悬挂钢结构楼承板8在施工阶段作为临时操作平台,在使用阶段作为高层建筑避难层,完善了使用功能,增加了建筑面积;H型钢主梁1作为连体转换层结构劲性配筋,悬挂钢结构避难层7作为永久性结构,不增加结构用钢量,降低了工程成本;
2、由钢骨混凝土连体转换梁3自承重模板和搭设在悬挂钢结构避难层7上的楼板支模架6,组成悬挂式模板支撑***,共同承受连体结构施工阶段的全部荷载,无需搭设落地超高支模架,无需安装高空重型临时作业平台,无需大型吊装机械设备,减少大量的周转材料、人工和机械设备投入,减轻工人劳动强度,加快施工进度,技术经济效益显著;
3、自承重模板通过焊接在钢主梁1腹板的钢拉杆5,将转换梁3模板(包括钢筋、混凝土自重及施工荷载)向上传递给钢主梁1,充分利用钢主梁1足够大的承载能力承受连体结构自身重量;
4、在悬挂钢结构避难层7上搭设转换层楼板支模架6,避难层7结构自重及全部施工荷载由钢吊柱2向上传递至钢主梁1,传力明确,工艺合理,施工简便;钢结构避难层7悬挂在连体转换层下方,形成连体结构施工阶段的高空作业防护屏障。
效益分析
1、悬挂式模板支撑***施工费用和工期分析
在悬挂钢结构楼承板8上搭设转换层楼板支模架6,层高4.8m,搭设面积570m2,所需门式支架租赁、装拆费用约5万元;转换梁3自承重模板所需的钢拉杆5、槽钢9、直螺纹套筒10等材料及人工费约10万元;合计费用15万元。施工工期1个月。
2、传统的承重满堂支撑架施工费用和工期分析
现有技术中是采用在裙房屋面搭设满堂支撑架进行转换层结构施工,需采取措施加固裙房屋面,然后在屋面上搭设高度约100m、面积570m2、重量约4000t的承重满堂支模架,支撑材料用量大,搭拆工期长,加固费用高,施工成本大。按施工工期4个月考虑,需投入各项费用约270.74万元。
3、经济和社会效益
采用此施工工艺节约施工费用270.74-15=255.74万元。工程主体结构约提前3个月封顶。
作为施工阶段操作平台的悬挂钢结构楼承板8,施工结束无需拆除,使用阶段作为建筑避难层7,为业主增加570m2建筑面积。
4、环保效益
采用本发明节省了超大量的钢管和扣件等周转材料,避免现场周转材料的堆放占用施工用地状况,减少了施工噪声污染,减少了施工活动对周边环境的影响,有利于环境保护,现场施工更加文明。

Claims (1)

1.高位连体结构悬挂式模板支撑施工方法,其步骤在于:
(1)安装转换层钢主梁
连体转换层为钢骨混凝土结构,主体施工时两座塔楼均预留了与连体结构相连接的钢牛腿,利用转换层上端相应位置的钢牛腿悬挂滑车组,用双机抬吊的方法将钢主梁逐根提升至设计位置并及时校正和焊接,其余钢次梁用塔吊安装;
(2)悬挂避难层结构施工
利用塔吊安装悬挂避难层的钢吊柱和钢结构楼承板,其施工工序为:
安装箱型钢吊柱→安装钢梁→压型钢板→焊接抗剪栓钉→绑扎钢筋网片→浇筑楼承板混凝土;
(3)在避难层上搭设支模架
在悬挂楼承板上搭设支模架,支承转换层楼板模板,支模架用门式架,也可用碗扣架和扣件、钢管搭设,支模架与两端塔楼主体结构实行有效拉接;
(4)安装转换层主梁、次梁自承重模板
1)在钢主梁腹板两侧的加劲肋处焊接钢筋作为钢拉杆,当梁宽为800mm时,设置一对Φ18的钢筋,当梁宽大于800小于等于1200mm时,设置两对Φ20钢筋;
2)在钢拉杆下端设置槽钢横楞,用直螺纹套筒调节固定,槽钢横楞上安装梁底模板,混凝土转换梁自重和全部施工荷载由钢拉杆向上传递给钢主梁;
3)在主梁、次梁两侧安装侧模、背楞及对拉螺栓;
(5)转换层梁板钢筋绑扎、预应力筋安装
混凝土转换梁纵向受力钢筋Φ32与钢柱相互交错布置,对穿过钢柱的纵向钢筋,预先在钢柱腹板上定位钻孔,粗直径钢筋采用套筒冷挤压工艺进行连接;转换层楼板钢筋为双层双向配置,楼板设计采用了无粘结预应力技术;
(6)拆除转换层模板及支模架。
CN2010101348150A 2010-03-29 2010-03-29 高位连体结构悬挂式模板支撑施工方法 Expired - Fee Related CN101886468B (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2010101348150A CN101886468B (zh) 2010-03-29 2010-03-29 高位连体结构悬挂式模板支撑施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2010101348150A CN101886468B (zh) 2010-03-29 2010-03-29 高位连体结构悬挂式模板支撑施工方法

Publications (2)

Publication Number Publication Date
CN101886468A CN101886468A (zh) 2010-11-17
CN101886468B true CN101886468B (zh) 2011-08-24

Family

ID=43072541

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2010101348150A Expired - Fee Related CN101886468B (zh) 2010-03-29 2010-03-29 高位连体结构悬挂式模板支撑施工方法

Country Status (1)

Country Link
CN (1) CN101886468B (zh)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108775071A (zh) * 2018-06-29 2018-11-09 聂超 一种预应力悬挂式建筑结构的施工方法

Families Citing this family (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102134907B (zh) * 2010-12-31 2012-07-04 中铁二局股份有限公司 钢筋桁架楼承板施工方法
CN102094391B (zh) * 2011-03-03 2012-08-22 中铁四局集团第一工程有限公司 铁路桥梁承台中顶层钢筋网片的定位施工方法
CN102337784B (zh) * 2011-07-13 2013-07-10 葛加君 高曲塔建筑钢混模架施工方法
CN102400506A (zh) * 2011-09-22 2012-04-04 姚攀峰 一种无模板耗能钢板剪力墙及其施工方法
CN102505635B (zh) * 2011-10-18 2014-01-15 中铁大桥局股份有限公司 桥梁施工用现浇模架
CN102392536B (zh) * 2011-10-28 2013-05-01 山东万鑫建设有限公司 大跨度悬空通廊式模板支撑体系施工方法
CN102767282B (zh) * 2012-08-08 2014-10-29 龙信建设集团有限公司 一种超大异型转换层悬挑梁可装配式高支模施工方法
CN103046743B (zh) * 2012-12-04 2016-05-25 中建三局建设工程股份有限公司 一种超高层转换层型钢混凝土大梁吊挂式模板支撑体系及施工方法
CN103452326B (zh) * 2013-07-25 2015-08-05 浙江精工钢结构集团有限公司 超长吊柱顺做法施工方法及其设备
CN104563503B (zh) * 2013-10-11 2016-06-29 卓越置业集团有限公司 高层与超高层住宅现浇钢筋混凝土高空自动化建造方法
CN104594635B (zh) * 2015-01-26 2017-01-04 贵州新联***工程集团有限公司 一种高层建筑框架结构施工方法
CN104878926B (zh) * 2015-06-16 2017-10-10 中建八局第三建设有限公司 一种悬挂模板体系施工方法及可周转支托
CN105019556A (zh) * 2015-07-24 2015-11-04 安徽富煌钢构股份有限公司 辅助高层钢梁快速吊装的搭接结构及其应用
CN105113542B (zh) * 2015-09-21 2018-06-29 中铁上海工程局集团有限公司 地下车站施工用悬挑***及地下车站施工方法
CN109610834B (zh) * 2019-02-02 2020-12-15 南通职业大学 多层大跨重载混凝土结构的高空施工方法
CN110158934B (zh) * 2019-06-24 2023-07-18 中信国安建工集团有限公司 用于高大空间内悬挂式操作平台的防护***
CN111926911B (zh) * 2020-08-05 2021-11-30 中国三冶集团有限公司 一种超高层空中连廊结构的施工方法
CN114427295B (zh) * 2021-12-31 2022-08-16 中国建筑第二工程局有限公司 一种预埋地锚拉接和抱柱组合超高超限模架体系及其工法

Family Cites Families (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP4172564B2 (ja) * 1999-10-12 2008-10-29 大成建設株式会社 塔状構築物の構築方法
CN1329607C (zh) * 2004-10-11 2007-08-01 上海市第二建筑有限公司 清水混凝土看台板的施工方法
CN100585114C (zh) * 2007-06-29 2010-01-27 浙江宝业建设集团有限公司 夹持式钢支撑与主钢构件紧密安装方法

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108775071A (zh) * 2018-06-29 2018-11-09 聂超 一种预应力悬挂式建筑结构的施工方法

Also Published As

Publication number Publication date
CN101886468A (zh) 2010-11-17

Similar Documents

Publication Publication Date Title
CN101886468B (zh) 高位连体结构悬挂式模板支撑施工方法
CN102444203B (zh) 一种高空大跨度悬挑连廊型钢混凝土结构及施工方法
CN202227476U (zh) 一种高空大跨度悬挑连廊型钢混凝土结构
CN102535845A (zh) 一种连廊结构承重架的施工方法
CN107090925A (zh) 加强型预制钢筋混凝土剪力墙、结构体系及其施工方法
CN100365237C (zh) 一种自升式可变形可拆卸整体提升钢平台***及施工方法
CN103195256A (zh) 吊柱式钢结构胎架法施工工法
CN205012666U (zh) 一种高空钢结构连廊整体提升支座结构
CN103046645A (zh) 一种大跨度预制整浇结构及施工方法
CN108979131B (zh) 一种高层建筑施工钢模板及操作架整体提升平台装置
CN207268073U (zh) 新型柔性支模承重架
CN204781927U (zh) 电梯井支模及电梯井混凝土浇筑操作平台
CN109184190A (zh) 爬升与承载一体化的梁式液压爬升平台及其安装方法
CN103122691A (zh) 塔吊标准节支承高空支模钢平台结构及施工方法
CN106759909B (zh) 一种下挂上承结构体系及其施工方法
CN114134820A (zh) 一种工字组合梁现浇桥面板的模板支撑及施工方法
CN104775363B (zh) 上塔柱钢筋节段的组拼方法
CN203034799U (zh) 塔吊标准节支承高空支模钢平台结构
CN207749417U (zh) 一种混凝土塔柱内模劲性骨架
CN203230165U (zh) 超高悬挑结构模板支撑平台
CN201687083U (zh) 高位连体结构悬挂式模板支撑结构
CN102691267A (zh) 一种外置整体操作平台高墩施工方法
CN102619335A (zh) 大高度小型现浇混凝土梁板的施工方法
CN103482493A (zh) 一种内爬式塔机
CN216042835U (zh) 一种具有轻质墙板的挑高框架结构的加层装置

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110824

CF01 Termination of patent right due to non-payment of annual fee