CN101852008A - Lifting scaffold device - Google Patents
Lifting scaffold device Download PDFInfo
- Publication number
- CN101852008A CN101852008A CN 201010191641 CN201010191641A CN101852008A CN 101852008 A CN101852008 A CN 101852008A CN 201010191641 CN201010191641 CN 201010191641 CN 201010191641 A CN201010191641 A CN 201010191641A CN 101852008 A CN101852008 A CN 101852008A
- Authority
- CN
- China
- Prior art keywords
- lifting
- hanging basket
- scaffold
- outrigger
- rack body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Types And Forms Of Lifts (AREA)
- Movable Scaffolding (AREA)
Abstract
The invention discloses a lifting scaffold device, which comprises a lifting scaffold. A cradle is connected below the lifting scaffold. An external wall can be decorated by using the cradle structure when the main structure of a high-rise building is constructed. The lifting scaffold device has the advantages of saving time, shortening construction period, along with simpleness and convenience.
Description
Technical field
The invention belongs to building and use scaffold field, particularly a kind of lifting scaffold device.
Background technology
At present, the frequent scaffold that uses of high-building construction has two kinds: a class is traditional fixed exterior wall scaffold.Promptly up set up support body from ground, whenever reach a certain height (about 8 layers to 10 layers) do one deck cantilever steel girder, set up the exterior wall scaffold support body again.So circulation, set up the highrise building top layer always after, along with the decoration of exterior wall engineering is successively removed from top layer.Need with a large amount of steel pipes, fastener, girder steel and maintenance network, material therefor roughly is directly proportional with the height of building; Another kind of is nearly more than ten years new technology---building operations attached lift scaffolds of wideling popularize of country.Attached lift scaffold only need be set up certain altitude and be attached on high building project (exterior wall) structure by fastening devicess such as through-wall bolts, rely on self jacking equipment and device, can successively climb with the engineering structures construction, have anti-topple, falling proof device, and can realize the external scaffolding of lift work.Adhering to supporting form has respectively: 1, rail mounted.Promptly guide tracked, angle the rail formula, transfer the rail formula, cover rail formula, anchor rail formula.2, cover frame.3, guide bracket formula.Power form has respectively: 1, manual, adopt the hand draw ring chain block.2, electronic, adopt electronic a chain of cucurbit.3, elevator adopts electronic hoisting equipment.4, hydraulic pressure adopts hydraulic power unit.
But the scaffold system of this structure can only be realized the construction to outer wall body, and the part operation of decoration of exterior wall need be waited until that the exterior wall construction is all finished and adheres to scaffold and climb behind the top layer, successively descend and construct, be that construction construction and the decoration of exterior wall construction of outer wall body can not intersect simultaneously and carries out, institute so that chief engineer's phase prolong.
Summary of the invention
Can't carry out the deficiency of decoration of exterior wall engineering in body of wall construction construction simultaneously at the scaffold that exists in the prior art, the purpose of this invention is to provide a kind of lifting scaffold device.
Technical scheme of the present invention is achieved in that a kind of lifting scaffold device, comprises lifting false work, connects a hanging basket below lifting false work, and hanging basket is used to safeguard the construction of decorative engineerings such as masonry, energy-conserving plate material and surface lining.
Preferably, the hanging basket lifting appliance is installed on the described hanging basket, is used to realize the automatic lifting of hanging basket, when the exterior wall decoration construction, hoisting scaffold that need not be often, the convenient like this height of regulating at any time, make things convenient for workman's operation, the construction of wall construction and decoration of exterior wall is not disturbed mutually.Lifting appliance can be manual or electric block or hoist engine etc.In order to control conveniently, described lifting appliance and control device thereof are mounted on the described hanging basket.
Described scaffold can be the building operations attached lift scaffold of promoting the use of at present, more preferably, described scaffold is arranged on the outside of body of wall, comprise rack body, hoisting mechanism and outrigger, stretch out two outriggers in the body of wall on the adjacent two layers floor respectively, its at the middle and upper levels or the outrigger of lower floor's floor be provided with hoisting mechanism, the rack body both sides are equipped with groove, the outrigger end is inserted groove and is cooperated also and can slide mutually with groove formation convex-concave, and hoisting mechanism is connected in rack body so that rack body is promoted.
Preferably, described hoisting mechanism adopts elevator, and elevator is fixedly mounted on described outrigger or the rack body, elevator and on rope rack body is connected with outrigger.
The invention has the beneficial effects as follows: when carrying out the outer wall body construction, can utilize barrel structure the exterior wall of bottom to be carried out the working procedure of decorative parts, make the construction of top body of wall construction construction and bottom decoration of exterior wall to carry out simultaneously, work progress is simple and convenient, saves time and has shortened the duration.
Description of drawings
Fig. 1 is a structural representation of the present invention;
Fig. 2 is the structural representation of an embodiment of the present invention;
Fig. 3 is Fig. 2 partial structurtes schematic diagrames;
Among the figure: 1 scaffold, 2 lifting appliances, 3 hanging baskets, 4 outriggers, 5 elevators, 6 rack bodies, 7 grooves.
The specific embodiment
The present invention is described further in conjunction with the accompanying drawings:
Embodiment: as shown in Figure 1, be structural representation of the present invention, a kind of lifting scaffold device, comprise lifting false work 1, below lifting false work 1, connect a hanging basket 3, hanging basket 3 two ends directly link to each other with scaffold 1 by rope respectively, or pulley or assembly pulley link to each other hanging basket 3 with lifting false work 1 excessively all, hanging basket 3 is used to safeguard masonry, the construction of decorative engineering such as energy-conserving plate material and surface lining, lifting false work 1 only need be set up certain altitude and be attached on high building project (exterior wall) structure by fastening devicess such as through-wall bolts, rely on self jacking equipment and device, can successively climb with the engineering structures construction, and can realize lift work; Then when the top body of wall was built construction by lifting false work 1, the decoration of exterior wall personnel then can carry out decoration construction to exterior wall by the hanging basket of bottom.
Hanging basket lifting appliance 2 is installed on the hanging basket, be used to realize the lifting of hanging basket 3, hoisting scaffold 1 that need not be often, can freely control lifting by the decoration of exterior wall constructor according to the external wall construction progress, the convenient like this height of regulating at any time makes things convenient for workman's operation, and lifting appliance 2 can be manual or electric block or hoist engine etc., as shown in Figure 1 lifting appliance 2 with and control device be mounted on the hanging basket 3, operate to make things convenient for the external wall construction personnel.
As Fig. 2, show a kind of outrigger formula lifting false work shown in 3, scaffold 1 highly is generally three story heights, be arranged on the outside of body of wall, comprise rack body 6, hoisting mechanism and outrigger 4, stretch out two outriggers 4 in the body of wall on the adjacent two layers floor respectively, one end of outrigger 4 is fixed on the floor in the building engineering structure, the other end of outrigger 4 stretches out floor and inserts the groove 7 of rack body 6 both sides respectively and form convex-concaves with groove 7 and cooperates also and can slide mutually, wherein the outrigger 4 of one deck floor is provided with hoisting mechanism, rack body 6 is promoted, hoisting mechanism adopts elevator 5, the rope of elevator 5 directly or by pulley or assembly pulley links to each other with the bottom of support respectively, rack body connects a hanging basket 36 times, lifting appliance on the hanging basket 3 is an electric winch, the rope at hanging basket 3 two ends links to each other with support by pulley, controller control hoist engine is synchronized with the movement, guarantee that hanging basket 3 is horizontal all the time, make things convenient for workman's operation, when elevator 5 promotes support to certain altitude, basecoat outrigger 4 exposes, these outrigger 4 dismountings are replaced on the top floor, simultaneously also with elevator 5 to bringing Forward, so repeatedly, support finally is thus lifted to the highest point of construction work, removes after construction finishes, like this when major project is finished, the decoration of exterior wall is also finished thereupon, and the time of having saved has shortened the duration.
Claims (7)
1. a lifting scaffold device comprises lifting false work, it is characterized in that: connect a hanging basket below lifting false work.
2. lifting scaffold device according to claim 1 is characterized in that being equipped with on the described hanging basket hanging basket lifting appliance that is used to realize the hanging basket lifting.
3. lifting scaffold device according to claim 2 is characterized in that described lifting appliance is manual or electric block or hoist engine.
4. lifting scaffold device as claimed in claim 3 is characterized in that described lifting appliance and control device thereof are mounted on the described hanging basket.
5. according to described lifting scaffold device one of in the claim 1 to 3, it is characterized in that described scaffold is arranged on the outside of body of wall, comprise rack body, hoisting mechanism and outrigger, stretch out two outriggers in the body of wall on the adjacent two layers floor respectively, its at the middle and upper levels or the outrigger of lower floor's floor be provided with hoisting mechanism, the rack body both sides are equipped with groove, and the outrigger end is inserted groove and cooperated also and can slide mutually with groove formation convex-concave, and hoisting mechanism is connected in rack body so that rack body is promoted.
6. lifting scaffold device according to claim 5 is characterized in that described hoisting mechanism adopts elevator, and elevator is fixedly mounted on described outrigger or the rack body, elevator and on rope rack body is connected with outrigger.
7. according to described lifting scaffold device one of in the claim 1 to 3, it is characterized in that described scaffold is the building operations attached lift scaffold.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010191641 CN101852008A (en) | 2010-06-04 | 2010-06-04 | Lifting scaffold device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 201010191641 CN101852008A (en) | 2010-06-04 | 2010-06-04 | Lifting scaffold device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN101852008A true CN101852008A (en) | 2010-10-06 |
Family
ID=42803676
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 201010191641 Pending CN101852008A (en) | 2010-06-04 | 2010-06-04 | Lifting scaffold device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101852008A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561672A (en) * | 2012-01-06 | 2012-07-11 | 西安理工大学 | Attached scaffold mechanism for high-rise building |
CN104295083A (en) * | 2014-10-11 | 2015-01-21 | 中建八局大连建设工程有限公司 | Guidance and hanging separated cantilever beam composite structure of integrated climbing frame |
CN106193567A (en) * | 2016-07-15 | 2016-12-07 | 中建五局第三建设有限公司 | Variable-section integrated lifting operation platform adduction construction method for ultrahigh building |
CN112012465A (en) * | 2020-07-20 | 2020-12-01 | 中建三局集团有限公司 | Integral hanging basket for decorating outer vertical surface of squat silo and construction method |
Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0486126A2 (en) * | 1990-11-13 | 1992-05-20 | Figgie International Inc. | Mason's scaffold |
CN2120840U (en) * | 1992-04-20 | 1992-11-04 | 李志雄 | Bridging support lift scaffold |
CN2149446Y (en) * | 1993-02-01 | 1993-12-15 | 陈胜坤 | Scoffolds for high building construction |
JPH08199801A (en) * | 1995-01-25 | 1996-08-06 | Nihon Bisoh Co Ltd | Crawler type traveling device for suspending gondola cage |
CN1260434A (en) * | 1999-08-23 | 2000-07-19 | 陈胜坤 | Multiple self-locked elevating scaffold |
CN2435463Y (en) * | 2000-07-25 | 2001-06-20 | 北京市建筑工程研究院 | Integral climbing and split lowering scaffold |
CN2491552Y (en) * | 2001-07-11 | 2002-05-15 | 成军 | Electric mould lifting construction device |
CN2494860Y (en) * | 2001-09-07 | 2002-06-12 | 成军 | Outrigger supporting type lifting scaffold |
CN101200976A (en) * | 2007-11-27 | 2008-06-18 | 吴杰 | Lifting scaffold for construction of chimney and shaft inner wall |
CA2673727A1 (en) * | 2008-07-24 | 2010-01-24 | Roberto Ubaldo Arduino Sani | Multi-point suspended scaffold |
CN101672102A (en) * | 2009-10-19 | 2010-03-17 | 中铁建设集团有限公司 | Steel structural overhead ceiling construction platform |
CN101696598A (en) * | 2009-09-24 | 2010-04-21 | 中冶建工有限公司 | Wholly lifted construction external frame |
-
2010
- 2010-06-04 CN CN 201010191641 patent/CN101852008A/en active Pending
Patent Citations (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
EP0486126A2 (en) * | 1990-11-13 | 1992-05-20 | Figgie International Inc. | Mason's scaffold |
CN2120840U (en) * | 1992-04-20 | 1992-11-04 | 李志雄 | Bridging support lift scaffold |
CN2149446Y (en) * | 1993-02-01 | 1993-12-15 | 陈胜坤 | Scoffolds for high building construction |
JPH08199801A (en) * | 1995-01-25 | 1996-08-06 | Nihon Bisoh Co Ltd | Crawler type traveling device for suspending gondola cage |
CN1260434A (en) * | 1999-08-23 | 2000-07-19 | 陈胜坤 | Multiple self-locked elevating scaffold |
CN2435463Y (en) * | 2000-07-25 | 2001-06-20 | 北京市建筑工程研究院 | Integral climbing and split lowering scaffold |
CN2491552Y (en) * | 2001-07-11 | 2002-05-15 | 成军 | Electric mould lifting construction device |
CN2494860Y (en) * | 2001-09-07 | 2002-06-12 | 成军 | Outrigger supporting type lifting scaffold |
CN101200976A (en) * | 2007-11-27 | 2008-06-18 | 吴杰 | Lifting scaffold for construction of chimney and shaft inner wall |
CA2673727A1 (en) * | 2008-07-24 | 2010-01-24 | Roberto Ubaldo Arduino Sani | Multi-point suspended scaffold |
CN101696598A (en) * | 2009-09-24 | 2010-04-21 | 中冶建工有限公司 | Wholly lifted construction external frame |
CN101672102A (en) * | 2009-10-19 | 2010-03-17 | 中铁建设集团有限公司 | Steel structural overhead ceiling construction platform |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102561672A (en) * | 2012-01-06 | 2012-07-11 | 西安理工大学 | Attached scaffold mechanism for high-rise building |
CN102561672B (en) * | 2012-01-06 | 2014-06-04 | 西安理工大学 | Attached scaffold mechanism for high-rise building |
CN104295083A (en) * | 2014-10-11 | 2015-01-21 | 中建八局大连建设工程有限公司 | Guidance and hanging separated cantilever beam composite structure of integrated climbing frame |
CN106193567A (en) * | 2016-07-15 | 2016-12-07 | 中建五局第三建设有限公司 | Variable-section integrated lifting operation platform adduction construction method for ultrahigh building |
CN106193567B (en) * | 2016-07-15 | 2019-04-02 | 中建五局第三建设有限公司 | Variable-section integrated lifting operation platform adduction construction method for ultrahigh building |
CN112012465A (en) * | 2020-07-20 | 2020-12-01 | 中建三局集团有限公司 | Integral hanging basket for decorating outer vertical surface of squat silo and construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101845883B (en) | Climbing scaffold system and construction method | |
CN103979383B (en) | Building operation multiple layer up-down plateform system | |
CA2713161A1 (en) | Load transportation system | |
CN201826516U (en) | Novel attached lifting scaffold | |
CN201411900Y (en) | Hydraulic die lifter for chimneys | |
CN105692470A (en) | Internal climbing tower crane and operating method thereof | |
CN101566005B (en) | Chimney hydraulic mould lifting device | |
CN101852008A (en) | Lifting scaffold device | |
CN102296808A (en) | Template hoisting system for building | |
CN201826542U (en) | Self-climbing protective screening | |
CN204418657U (en) | Hydraulic formwork for elevator shaft material platform | |
CN201144515Y (en) | Steel structure high altitude construction platform | |
CN102733608A (en) | Construction method for spray head layer of granulation tower | |
CN202441045U (en) | Rail-type electric attached lifting scaffold | |
TW201604119A (en) | Double safety lift cage structure | |
CN203867198U (en) | Slip equipment for high-rise steel structure transfer layer truss | |
CN2853976Y (en) | Jacket auto-lifting radial expansion structural hanging-up for hollow-shaped building construction | |
CN205894715U (en) | Light steel structure is semi -automatic under enclosed construction constructs from hoisting machine that climbs | |
CN206000194U (en) | A kind of elevator hoistways soft or hard safeguard structure | |
CN205892406U (en) | Elevator well structure | |
JP2008196210A (en) | Portable simplified elevator | |
CN205134921U (en) | Building outer wall concrete constructional column hangs construction platform | |
CN203499232U (en) | Attached lifting scaffold | |
CN203654707U (en) | Detachable gantry installation frame | |
CN2435463Y (en) | Integral climbing and split lowering scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C12 | Rejection of a patent application after its publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20101006 |