CN101832142A - 一种隧道信息化跟踪精确注浆方法 - Google Patents
一种隧道信息化跟踪精确注浆方法 Download PDFInfo
- Publication number
- CN101832142A CN101832142A CN 201010162337 CN201010162337A CN101832142A CN 101832142 A CN101832142 A CN 101832142A CN 201010162337 CN201010162337 CN 201010162337 CN 201010162337 A CN201010162337 A CN 201010162337A CN 101832142 A CN101832142 A CN 101832142A
- Authority
- CN
- China
- Prior art keywords
- hole
- grouting
- slip casting
- water
- construction
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Consolidation Of Soil By Introduction Of Solidifying Substances Into Soil (AREA)
Abstract
本发明涉及隧道注浆领域,具体为一种隧道信息化跟踪精确注浆方法,解决现有隧道注浆采用传统的帷幕注浆法,存在加固圈厚、钻眼数量多、施工工期长等问题,包括止浆墙施作,设置孔口管、注浆管,测量钻孔涌水,压水试验,布孔、钻孔作业,注浆作用,布孔和注浆按照超前地质探孔-其余外圈孔-内圈孔-工作面稳定孔-检查孔-管棚孔的顺序,无工作室超前大管棚施工,玻璃纤维锚杆稳定工作面等步骤,打破了传统施工理念,将注浆设计与地质变化紧密结合,采用“堵裂隙、减少水量;固围岩、稳定地层”注浆机理,注浆孔减少30-40%,缩短了施工周期,提高注浆质量,保证安全快速施工,消除了重大突水突泥事件,最大限度的保护周围环境。
Description
技术领域
本发明涉及隧道注浆领域,具体为一种隧道信息化跟踪注浆方法。
背景技术
当今随着工程建设的发展,复杂地区隧道修建技术获得了重大提升,隧道全断面超前注浆作为应对复杂地质的有效施工手段,在岩溶高风险隧道和高压富水断层施工中发挥着越来越重要的作用,实际应用过程中,注浆设计如何与地质紧密结合、合理优化、提高功效、节约投资一直是制约其推广使用的重要因素。
传统全断面超前帷幕注浆是由内向外堵水,设计加固圈厚,全断面布孔,钻眼数量多,施工工期长,一循环注浆施工约需45天,时间长,投入大;该注浆方法没有与地质条件紧密结合,注浆效果评定标准与地质适用性确定难;注浆薄弱区界定与处置困难。导致许多工程由于考虑工程工期、投资,转而采用其它方法,导致工程受阻实例层出不穷。
发明内容
本发明为了解决现有隧道注浆采用传统的帷幕注浆法,存在加固圈厚、钻眼数量多、施工工期长等问题,提供一种隧道信息化跟踪精确注浆方法。
本发明是采用如下技术方案实现的:一种隧道信息化跟踪精确注浆方法,包括以下步骤:
(1)止浆墙施作
(2)设置孔口管、注浆管
(3)测量钻孔涌水
(4)压水试验
(5)布孔、钻孔作业
A、先施作3-5个作为外圈孔的超前地质探孔,分布在拱顶、拱腰及拱脚处,根据超前地质探孔的监测结果探明实际地质情况及水文条件,优化后续布孔设计;B、施作其余外圈孔,为环形布置,注浆加固圈厚度为3.5~5m,相邻外圈孔开孔间距为1.5m,终孔间距为3m;C、施作至少一层内圈孔,在外圈孔内侧呈环形布置,注浆加固圈厚度为1.5~2m,相邻外圈孔开孔间距为1.5m,终孔间距为3m;D、施作工作面稳定孔,在工作面上半断面按照相邻孔之间上下左右间距均为1.5m、且为梅花形的原则布孔;在工作面下半断面按照相邻孔之间上下左右间距均为3.0m、且为梅花形的原则布孔;E、施作检查孔,根据上述外圈孔、内圈孔、工作面稳定孔的涌水量和注浆量分析结果,布置检查孔,主要布置在地质条件差或注浆薄弱区域的异常孔附近,采用一个异常孔周围布置两个检查孔的原则;F、施作管棚孔,在开挖轮廓线外拱部90°~120°范围内布孔,布设间距40~50cm,外插角5°~7°;
上述步骤中,内圈孔的层数根据注浆、堵水效果确定;超前地质探孔兼注浆孔和检查孔,三孔合一,内圈孔兼外圈孔的检查孔,工作面稳定孔兼内圈孔的检查孔,检查孔兼补充注浆孔,管棚孔兼周边补充注浆孔;
(6)注浆作业
A、注浆顺序:注浆过程按照外堵裂隙、内固围岩,由外及内、间隔跳孔(例如对于外圈孔和内圈孔来说,先对序号为1、3、5、7等孔进行注浆,再对2、4、6、8等孔进行注浆,这样,后者可作为前者的检查孔,检查其注浆效果)的约束法进行注浆顺序控制,具体注浆顺序依次为超前地质探孔-其余外圈孔-内圈孔-工作面稳定孔-检查孔-管棚孔,注浆过程中,内层孔作为外层孔的检查孔,相邻孔互为检查孔;B、注浆方式:采用前进式分段注浆,分段长度根据出水量及地层破碎程度进行控制:出水量小于Q<10m3/h时,分段长度小于10m/段;钻孔出水量10m3/h≤Q<30m3/h时,按照3-5m/段长度控制;钻孔出水量Q≥30m3/h时,停止钻进立即进行注浆处理;地层无坍孔,分段长度小于10m/段;地层出现轻微坍孔,分段长度小于或等于5m/段;地层出现严重坍孔,停止钻进注浆;C、注浆材料选择:以硫铝酸盐水泥单液浆、普通水泥单液浆为主,普通水泥-水玻璃双液浆、超细水泥浆为辅,其中硫铝酸盐水泥单液浆水灰比为(0.8~1.2)∶1,普通水泥单液浆水灰比为(0.6~1.2)∶1,普通水泥-水玻璃双液浆水灰比为(0.8~1.2)∶1,体积比为1∶(0.3~1),超细水泥浆水灰比为(0.8~1.2)∶1;
(7)超前大管棚施工
选择围岩较好地段为管棚搭接段落,采用无工作室管棚施工,施工中对搭接段和管棚后段采用小导管加强施作,管棚材料采用Φ76mm-Φ108mm无缝钢管;
(8)玻璃纤维锚杆稳定工作面
超前注浆结束后,在工作面上半断面的钻孔内放入中空玻璃纤维锚杆并进行注浆施工,使具高抗拉强度的锚杆通过浆液和软弱地层固结成为整体,形成纵向锚固柱。
上述步骤中,止浆墙施作,设置孔口管、注浆管,测量钻孔涌水,压水试验等工序均和传统施工方法一样。
与传统方法相比,本发明具有以下优点:
1、打破了传统施工理念,将注浆设计与地质变化紧密结合,采用“堵裂隙、减少水量;固围岩、稳定地层”新的注浆机理;坚持“超前地质探孔-其余外圈孔-内圈孔-工作面稳定孔-检查孔(注浆补孔)-管棚孔”顺序施作,环环相扣;“超前地质探孔-注浆孔-检查孔互相利用,三孔合-”的注浆原则,设计思路转化使注浆孔减少30-40%(正洞加固圈厚度由8m优化为4-5m,平导加固圈厚度由8m优化为3-4m);堵大水,堵裂隙水,加固地层,优化帷幕注浆孔数;注浆循环时间由原正洞40-50天提前到25天,平导由原30-40天提前到20天,注浆快速施工能力有突破,而且减少了注浆量,减少了对周围环境的影响;同时注浆质量的提高,保证了安全快速施工,消除了重大突水突泥事件,最大限度的保护周围环境;
2、材料方面,通过采用MC超细水泥浆液,T-C浆液,T浆液施工适用性研究,确定以硫铝酸盐水泥单液浆、普通水泥单液浆为主,普通水泥-水玻璃双液浆、超细水泥浆为辅,的最优组合,普通水泥和硫铝酸盐水泥方便使用,注浆功效高,价格适中,推广前景好;
3、工艺使用方面,对前进式和后退式注浆进行了研究,证明高压富水条件下采用塑料袖阀管和PVC管进行后退式注浆操作难度很大;对注浆步距规律进行了认真研究,一次注浆长度通常选择20-30m,使注浆工艺参数选择有了很大进步;
4、无工作间管棚施工技术,取消管棚工作间,直接顶入不侵限位置(顶入处利用上循环大管棚受力);取消管棚钢筋笼;通过管棚受力监测,一圈管棚受力即能满足要求,优化了原拟定双层管棚加强支护方案,简化了工序,而且对管棚材料进行了优化,从最初的Φ108mm无缝钢管+钢筋笼-Φ108mm无缝钢管-Φ76mm无缝钢管,不仅节约大量的钢材,而且采用Φ76mm管棚比采用Φ108mm管棚施工速度提高2倍以上;
5、施工中首次把注浆法与现有新意法有机结合,基于新意法玻纤锚杆稳定掌子面方法,超前注浆结束后,在工作面上半断面按照相邻孔之间上下左右间距均为1.5m、且为梅花形的原则布孔,成孔后下入中空玻璃纤维锚杆并进行注浆施工,使具高抗拉强度的锚杆通过浆液和软弱地层固结成为整体,形成纵向“锚固柱”,有效提高开挖面稳定性,方便安全开挖加快施工进度;
6、对注浆结束标准进行了深入研究,检查孔单孔每米水量由原标准0.2L/min·m放宽到2L/min·m,开挖验证证明效果评定标准合理,认识理念有了很大提高,减少了注浆量,减少了对周围环境的影响。
本发明所述的施工方法尤其适用于高压富水断层的隧道施工。
附图说明
图1为超前注浆终孔交圈图;
图2为钻孔涌水量时间效应图;
图3为钻孔注浆量时间效应图;
图4为注浆效果评定时浆液固结破碎岩体情况;
图5为注浆效果评定时浆液充填裂隙情况;
图中:1-超前地质探孔;2-外圈孔;3-内圈孔;4-工作面稳定孔;5-管棚孔。
具体实施方式
列举以下工程实例进一步说明本发明所述的注浆方法
一、工程简介,齐岳山隧道全长10528米,最大埋深670米,进出口高差达150米,隧道穿越齐岳山背斜构造,通过15条断层,3条暗河,设计最大涌水量每天为74.3万方,齐岳山隧道是目前国内铁路建设中山区铁路隧道的典型代表,岩溶发育和高压突水、突泥的风险程度及处理难度为国内罕见,被国内隧道专家和同行誉为世界级难题,该隧道主要特点是地质条件差,工程风险大,能否安全顺利贯通控制着宜万铁路全线建设安全和工期。
二、采用本发明所述方法进行该隧道施工,具体步骤如下:
(1)止浆墙施作
止浆墙采用C25混凝土浇筑,平导厚1.5m-2.5m,正洞厚2m-3m,基底嵌入岩层50cm;周边预埋1.5m长的Φ42mm导管,止浆墙浇注完成后,通过导管进行注浆,对止浆墙与初期支护间的空隙进行封堵;
(2)设置孔口管、注浆管
钻到预定深度后,停止钻进,退出钻具,利用钻机或人工顶进孔口管,留30厘米在外;管身焊倒刺以增加(抗冲出的)摩阻力,孔口缠麻丝填胶泥,再灌浆充填管外壁与孔壁间隙,固结孔口管。必须注意在高压涌水和高压力注浆时,孔口管必须用锚杆等固定牢靠,防止高压大水冲出孔口管,或注浆反压射出伤及人员和机械设备。待孔口管固结好后,方可继续钻进,以免钻机震松孔口管。为有效控制突涌水,孔口管前段必须安设高压闸阀。设置孔口管的作用是保护孔壁、导向和防止钻孔突然涌大水。
(3)测量钻孔涌水
测水量,采用孔口管放水容器测量;测水压,采用孔口管安设压力表测量;测涌水位置,采用钻杆米数测量;钻进过程中如果采用水钻,用清水作冲洗液,若钻孔冲出的水量比正常钻进情况下的大、水质异常浑浊或喷射远距离沙石,此时应停止钻进,测定水量、水压和涌水位置,确定处理方案和注浆方式。
(4)压水试验
同时启动两台泵进行注水,先检查混合器是否有串水现象,正常后开始往孔内注水,逐步加大排量,升高压力,当注水压力达到或略大于预定的注水压力,维持2~3分钟,检查注浆***和掌子面有无串漏水现象,如无即可结束注水试验,准备注浆;通过压水试验,检查管路***、孔口装置及止浆岩盘的密封性能,同时测定注浆段围岩的单位吸水量,评定围岩的裂隙发育情况,为确定浆液的配合比和注浆量及注入速度提供依据,同时可冲洗疏通裂隙,利于提高注浆效果。
(5)布孔、钻孔作业,如图1所示,
A、先施作3-5个作为外圈孔的超前地质探孔1,分布在拱顶、拱腰及拱脚处,通常拱顶布一孔,拱腰、拱脚各两个,根据超前地质探孔的监测结果探明实际地质情况及水文条件,优化后续布孔设计;
B、施作其余外圈孔2,为环形布置,注浆加固圈厚度为3.5~5m,相邻外圈孔开孔间距为1.5m,终孔间距为3m;
C、施作一层内圈孔3,在外圈孔内侧呈环形布置,注浆加固圈厚度为1.5~2m,相邻外圈孔开孔间距为1.5m,终孔间距为3m;
D、施作工作面稳定孔4,在工作面上半断面按照相邻孔之间上下左右间距均为1.5m、且为梅花形的原则布孔;在工作面下半断面按照相邻孔之间上下左右间距均为3.0m、且为梅花形的原则布孔;
E、施作检查孔,根据上述外圈孔、内圈孔、工作面稳定孔的涌水量和注浆量分析结果,布置检查孔,主要布置在地质条件差或注浆薄弱区域的异常孔附近,采用一个异常孔周围布置两个检查孔的原则;
F、施作管棚孔5,在开挖轮廓线外拱部90°~120°范围内布孔,布设间距40~50cm,外插角5°~7°;
超前地质探孔兼注浆堵水孔、工作面稳定孔兼注浆孔、管棚孔兼注浆孔、检查孔兼补充注浆孔等互相利用,后续孔验证前序孔注浆效果,逐环稳步优化,减少钻孔、注浆数量,加快循环施工周期。
钻孔是注浆施工的第一道工序,钻孔质量的好坏直接影响注浆质量,钻孔速度的快慢制约注浆工期。所以应严格按照设计的钻孔方向、角度、孔径进行钻进,按钻机的操作规程操作。钻机的定位一般是按照计算好的坐标位置就位的。注浆钻孔在掌子面的位置,预先设定钻机位置(高度、离掌子面的距离、偏中距),然后根据终孔位置、孔长等计算出每个钻孔在掌子面的坐标值和钻孔的倾角、偏角。
(6)注浆作业
A、注浆顺序:注浆过程按照外堵裂隙、内固围岩,由外及内、间隔跳孔的约束法进行注浆顺序控制,具体注浆顺序依次为超前地质探孔-其余外圈孔-内圈孔-工作面稳定孔-检查孔-管棚孔,注浆过程中,内层孔作为外层孔的检查孔,相邻孔互为检查孔;
B、注浆方式:采用前进式分段注浆,分段长度根据出水量及地层破碎程度进行控制:出水量小于Q<10m3/h时,分段长度小于10m/段;钻孔出水量10m3/h≤Q<30m3/h时,按照3-5m/段长度控制;钻孔出水量Q≥30m3/h时,停止钻进立即进行注浆处理;地层无坍孔,分段长度小于10m/段;地层出现轻微坍孔,分段长度小于或等于5m/段;地层出现严重坍孔,停止钻进注浆;
C、注浆材料选择:以硫铝酸盐水泥单液浆、普通水泥单液浆为主,普通水泥-水玻璃双液浆、超细水泥浆为辅,其中硫铝酸盐水泥单液浆水灰比为(0.8~1.2)∶1,普通水泥单液浆水灰比为(0.6~1.2)∶1,普通水泥-水玻璃双液浆水灰比为(0.8~1.2)∶1,体积比为1∶(0.3~1),超细水泥浆水灰比为(0.8~1.2)∶1;
(7)超前大管棚施工
常规洞内大管棚施工,为了满足钻孔设备工作要求,必须沿开挖轮廓线扩大60~80cm(10-15m长采用大钻机时)作为管棚施工工作间,不仅开挖工作量相当大,且在对于软弱地层扩大断面开挖风险性极高。
为了提高施工效率,避免软弱破碎地层开挖工作间的高风险和额外的开挖工程量,施工中通对地层分析,合理优化注浆管棚施工段长,选择围岩较好地段为管棚搭接段落,采用无工作室管棚施工,施工中对搭接段和管棚后段采用小导管加强施作,管棚材料采用Φ76mm-Φ108mm无缝钢管。具体施工步骤如下:
A.管棚加工:大管棚采用直径Φ76mm-Φ108mm、壁厚7mm~9mm无缝钢管加工,每节长6~10m,采用丝扣法或内套钢管焊接连接,每根管棚前端加工成椎形尖端并封闭,便于管棚安设。管壁梅花形布设Φ8mm溢浆孔,孔间距50cm,每根管棚末端一节不布设溢浆孔;
B.管棚施工:沿大管棚导向管调整好钻孔角度,采用Φ90mm~Φ125mm钻头钻进引孔到设计长度。引孔完成后采用清水洗孔排渣后退出钻杆,根据设计长度下入管棚。对管棚侵限段不下入管棚(采用玻纤锚杆代替,受力依靠上循环管棚),通过钻机直接将管棚顶到开挖轮廓线外;
C.管棚安设完成后进行全孔一次性管棚注浆;
D.管棚孔兼注浆孔前期注浆按注浆分段原则操作,注浆完后洗孔,满足注浆效果要求后,下入管棚进行全孔一次性注浆;
(8)玻璃纤维锚杆稳定工作面
传统帷幕注浆和周边超前管棚施工完成后,最大的危险就是防止开挖工作面前方因高水压作用失稳以及防止开挖面临空局部垮塌,因此必须采取有效的措施稳定工作面,本发明在施工中首次把注浆法与现有“新意法”有机结合,超前注浆结束后,在工作面上半断面的钻孔内放入中空玻璃纤维锚杆并进行注浆施工,使具高抗拉强度的锚杆通过浆液和软弱地层固结成为整体,形成纵向锚固柱。有效提高开挖面稳定性,方便安全开挖,加快施工进度。多个循环开挖揭示验证,采用玻璃纤维锚杆加固对稳定掌子面具有明显作用。
按照上述工序,不断循环开挖,注浆,即完成整个隧道的施工。
三、注浆效果评定方法及标准
A、分析法
(1)钻孔涌水量分析
通过对注浆施工段内水量横断面及纵向分布情况的监测,明确出水区域,有针对性的加强注浆施工,注浆方式、工艺依据水量分布进行动态调整,提高堵水率。并作为结束后的重点检查及补充注浆区域,并在开挖施工过程中加强支护和补充注浆。
(2)钻孔涌水量时间效应分析
以施工过程中各钻孔施工顺序及单孔最大涌水量绘制钻孔水量时间效应图和单孔注浆量图进行对比分析,如图2、图3所示。从图中可得出:
①地层吸浆量与涌水量,具有明显的对应关系,符合地层加固堵水机理;
②钻孔水量随着时间有明显的递减效应,说明达到堵水目的;
③地层吸浆量随时间减小,空隙率逐渐减小,地层逐渐密实,达到充填裂隙,固结围岩的目的。
(3)P-Q-T曲线分析
通过注浆施工过程绘制的P-Q-T曲线分析,浆液流量及注浆压力随时间变化符合充填裂隙、封堵涌水的注浆机理,若曲线发生异常变化,应及时分析查找原因,制定对策,保证注浆质量。
(4)注浆堵水率分析
以斜井工区正洞第2循环钻孔注浆施工为例,对施工过程不同阶段钻孔中最大涌水量进行统计分析各阶段的堵水率如表1所示。
表1各阶段注浆堵水率表
施工时间段 | 单孔平均最大水量(m3/h) | 施工注浆孔数(个) | 注浆量(m3) | 堵水率(%) |
初始探测阶段 | 90 | 5 | 86.61 | ------- |
外圈孔阶段 | 50 | 13 | 76.63 | 45% |
内圈孔阶段 | 14.8 | 13 | 49.82 | 83.60% |
补充注浆阶段 | 5.4 | 8 | 10.24 | 94.00% |
效果检查阶段 | 2 | 8 | 6.00 | 97.80% |
从表1可以看出,前期5个注浆孔兼超前探孔钻孔施工过程中,平均涌水量达到90m3/h(最大150m3/h),注浆结束后,在外圈孔施工过程中单孔平均最大涌水量为50m3/h,堵水率达到45%;随着由外及内注浆施工的逐渐推进,二圈孔施工完成后堵水率达到83.6%;补充注浆孔后,检查孔施工过程堵水率达到97.8%,达到了预期的堵水效果。
由外及内的施工工序,后续钻孔出水量减小后,有利于快速施工,也达到了约束注浆的目的。
B、检查孔法
(1)检查孔出水量分析
注浆结束后,根据钻孔注浆施工过程出水区域分布及注浆量分布情况,在薄弱区域进行钻孔检查,检查孔出水量是主要的评价标准,现有设计检查孔出水量标准为0.2L/min.m。在平导第一循环试验段钻孔注浆施工过程,注浆结束后经过分析法评定已经满足注浆效果,但检查孔水量均在2L/min.m左右,为设计检查标准的10倍。后经过反复补充注浆,在出水量大的区域共补设注浆孔41个,但注浆量较少,钻孔出水量基本保持不变,后经过采用超细水泥继续进行补充注浆仍未能达到设计要求。
综合以上几种效果检查及评定方法对注浆效果分析:
①通过注浆涌水裂隙得到有效封堵,检查孔水量明显减小,未出现坍孔现象。
②该循环注浆纵向浆液量分布比较均匀,但由于地层裂隙分布的不规则决定浆液在地层中扩散很不均匀,即使反复注浆也难以封堵所有裂隙,因此局部仍然存在细小的渗水裂隙,在高压作用下仍表现为局部渗水,所以检查孔出水量达到0.2L/min·m是比较困难的。
③根据钻孔角度和钻孔深度,大部分出水点在纵向15m后,径向3m外,且结合检查孔及取芯孔钻进速度分析,通过注浆后地层密实度较高,检查孔完成后将进行环向间距30cm的Φ108mm管棚施作并进行管棚注浆,在超前管棚支护及注浆帷幕共同作用下,注浆效果基本满足开挖施工要求,可以进行试验性开挖。
结合类似工程如重庆高速公路方斗山隧道等相似工程,开挖掘进过程中均遭遇到断层破碎带,水量和水压力较大,原设计全断面超前预注浆结束后检查孔评定标准为0.2L/min·m,实际施工中注浆结束后,检查孔出水量均远超过设计评定标准,考虑到断层地质的复杂性质及工期和成本要求,按照在满足开挖要求的前提下,实际施工过程中对注浆标准进行适当调整后,开挖过程中均安全通过断层带。
根据该断层地质情况并结合其它类似工程钻孔注浆效果检查及开挖施工情况类比,提出检查孔出水量建议标准。
①单孔出水量不大于2L/min·m,水质较清。
②检查孔不坍孔,涌泥涌砂。
提高检查孔出水量标准为2L/min.m开挖,经开挖揭示完全满足安全开挖要求。说明2L/min.m的检查孔出水量控制标准是符合高压富水断层破碎带地质特点。
(2)钻孔取芯
通过钻孔取芯,分析浆液对破碎地层的固结程度,为开挖施工提供依据,如图4所示,固结效果较好;
(3)孔内摄像
利用孔内摄像进行注浆效果评定,能够较为直观的对浆液充填度和地层的稳定性质以及出水情况进行分析判识,是一种操作方便实用的方法,如图5所示,成孔情况及浆液充填裂隙情况均达到要求。
Claims (1)
1.一种一种隧道信息化跟踪精确注浆方法,其特征是包括以下步骤:
(1)止浆墙施作
(2)设置孔口管、注浆管
(3)测量钻孔涌水
(4)压水试验
(5)布孔、钻孔作业
A、先施作3-5个作为外圈孔的超前地质探孔(1),分布在拱顶、拱腰及拱脚处,根据超前地质探孔的监测结果探明实际地质情况及水文条件,优化后续布孔设计;
B、施作其余外圈孔(2),为环形布置,注浆加固圈厚度为3.5~5m,相邻外圈孔开孔间距为1.5m,终孔间距为3m;
C、施作至少一层内圈孔(3),在外圈孔内侧呈环形布置,注浆加固圈厚度为1.5~2m,相邻外圈孔开孔间距为1.5m,终孔间距为3m;
D、施作工作面稳定孔(4),在工作面上半断面按照相邻孔之间上下左右间距均为1.5m、且为梅花形的原则布孔;在工作面下半断面按照相邻孔之间上下左右间距均为3.0m、且为梅花形的原则布孔;
E、施作检查孔,根据上述外圈孔、内圈孔、工作面稳定孔的涌水量和注浆量分析结果,布置检查孔,主要布置在地质条件差或注浆薄弱区域的异常孔附近,采用一个异常孔周围布置两个检查孔的原则;
F、施作管棚孔(5),在开挖轮廓线外拱部90°~120°范围内布孔,布设间距40~50cm,外插角5°~7°;
(6)注浆作业
A、注浆顺序:注浆过程按照外堵裂隙、内固围岩,由外及内、间隔跳孔的约束法进行注浆顺序控制,具体注浆顺序依次为超前地质探孔-其余外圈孔-内圈孔-工作面稳定孔-检查孔-管棚孔,注浆过程中,内层孔作为外层孔的检查孔,相邻孔互为检查孔;
B、注浆方式:采用前进式分段注浆,分段长度根据出水量及地层破碎程度进行控制:出水量小于Q<10m3/h时,分段长度小于10m/段;钻孔出水量10m3/h≤Q<30m3/h时,按照3-5m/段长度控制;钻孔出水量Q≥30m3/h时,停止钻进立即进行注浆处理;地层无坍孔,分段长度小于10m/段;地层出现轻微坍孔,分段长度小于或等于5m/段;地层出现严重坍孔,停止钻进注浆;
C、注浆材料选择:以硫铝酸盐水泥单液浆、普通水泥单液浆为主,普通水泥-水玻璃双液浆、超细水泥浆为辅,其中硫铝酸盐水泥单液浆水灰比为(0.8~1.2)∶1,普通水泥单液浆水灰比为(0.6~1.2)∶1,普通水泥-水玻璃双液浆水灰比为(0.8~1.2)∶1,体积比为1∶(0.3~1),超细水泥浆水灰比为(0.8~1.2)∶1;
(7)超前大管棚施工
选择围岩较好地段为管棚搭接段落,采用无工作室管棚施工,施工中对搭接段和管棚后段采用小导管加强施作,管棚材料采用Φ76mm-Φ108mm无缝钢管;
(8)玻璃纤维锚杆稳定工作面
超前注浆结束后,在工作面上半断面的钻孔内放入中空玻璃纤维锚杆并进行注浆施工,使具高抗拉强度的锚杆通过浆液和软弱地层固结成为整体,形成纵向锚固柱。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101623374A CN101832142B (zh) | 2010-02-11 | 2010-04-02 | 一种隧道信息化跟踪精确注浆方法 |
Applications Claiming Priority (3)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201010128163.X | 2010-02-11 | ||
CN201010128163 | 2010-02-11 | ||
CN2010101623374A CN101832142B (zh) | 2010-02-11 | 2010-04-02 | 一种隧道信息化跟踪精确注浆方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101832142A true CN101832142A (zh) | 2010-09-15 |
CN101832142B CN101832142B (zh) | 2011-11-16 |
Family
ID=42716336
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010101623374A Active CN101832142B (zh) | 2010-02-11 | 2010-04-02 | 一种隧道信息化跟踪精确注浆方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101832142B (zh) |
Cited By (34)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101994513A (zh) * | 2010-10-30 | 2011-03-30 | 中铁十二局集团第二工程有限公司 | 上半断面完成全断面帷幕注浆隧道施工方法 |
CN102128038A (zh) * | 2011-01-26 | 2011-07-20 | 北京中铁瑞威基础工程有限公司 | 一种隧道管棚快速施工方法 |
CN102168433A (zh) * | 2011-03-23 | 2011-08-31 | 浙江南湖建设有限公司 | 止水帷幕注浆修复方法 |
CN102278130A (zh) * | 2011-09-05 | 2011-12-14 | 中铁隧道集团有限公司 | 隧道高压富水溶腔加筋注浆工艺方法 |
CN103982201A (zh) * | 2014-05-22 | 2014-08-13 | 北京中铁瑞威工程检测有限责任公司 | 高压富水隧道宽张裂隙超前探测注浆加固开挖方法 |
CN104033165A (zh) * | 2014-05-26 | 2014-09-10 | 江苏鼎泰工程材料有限公司 | 隧道病害修复方法及修复浆料 |
CN104215748A (zh) * | 2014-08-19 | 2014-12-17 | 山东大学 | 一种地下工程破碎围岩注浆加固效果的综合定量检测方法 |
CN104453943A (zh) * | 2014-10-27 | 2015-03-25 | 山东科技大学 | 有效止浆岩盘缺失条件下富水破碎岩体综合注浆控制方法 |
CN104747208A (zh) * | 2015-01-27 | 2015-07-01 | 山东科技大学 | 一种注浆加固浆液扩散调控方法 |
CN105065039A (zh) * | 2015-09-14 | 2015-11-18 | 成都理工大学 | 一种高地温隧道围岩灌浆隔热方法 |
CN105781557A (zh) * | 2016-03-25 | 2016-07-20 | 广东水电二局股份有限公司 | 一种暗挖隧道化学灌浆固结砂层的施工方法 |
CN106049418A (zh) * | 2016-06-22 | 2016-10-26 | 中铁二局集团有限公司 | 一种浅埋穿越断层隧道地表组合注浆加固方法 |
CN107035389A (zh) * | 2017-06-01 | 2017-08-11 | 新疆北新路桥集团股份有限公司 | 一种注浆加固施工方法及地表施工方法 |
CN107762534A (zh) * | 2017-10-19 | 2018-03-06 | 中铁十八局集团有限公司 | 一种全孔一次快速注浆施工方法 |
CN108612546A (zh) * | 2018-05-14 | 2018-10-02 | 姚晓宁 | 一种封闭环境下水平注浆施工方法 |
CN108661650A (zh) * | 2018-04-23 | 2018-10-16 | 中铁隧道局集团有限公司 | 一种富水岩浆岩地区深大竖井井筒施工方法 |
CN108756893A (zh) * | 2018-04-19 | 2018-11-06 | 济南城建集团有限公司 | 一种城区浅埋隧道拱顶土体加固方法 |
CN108798718A (zh) * | 2018-07-09 | 2018-11-13 | 中铁十七局集团第四工程有限公司 | 隧道前承后继注浆方法 |
CN108798717A (zh) * | 2018-07-09 | 2018-11-13 | 山东省煤田地质局第四勘探队 | 一种对城市道路下隧道拱顶围岩注浆加固的钻孔设计方法 |
CN108868788A (zh) * | 2018-06-26 | 2018-11-23 | 李先登 | 一种超长隧道的挖掘方法 |
CN109208579A (zh) * | 2018-08-28 | 2019-01-15 | 北京瑞威世纪铁道工程有限公司 | 集束多段水平袖阀管注浆施工方法 |
CN109441486A (zh) * | 2018-11-30 | 2019-03-08 | 中铁隧道集团二处有限公司 | 用于隧道注浆加固的注浆方法 |
CN109763845A (zh) * | 2019-01-23 | 2019-05-17 | 江西省宜丰万国矿业有限公司 | 一种通过构筑l型注浆截流帷幕防治水的施工方法 |
CN109854275A (zh) * | 2018-12-24 | 2019-06-07 | 龙口矿业集团有限公司 | 富水砂岩巷道过断层破碎带治理方法 |
CN109915071A (zh) * | 2019-05-07 | 2019-06-21 | 义马煤业集团孟津煤矿有限责任公司 | 一种基于三步三速的井下煤层底板注浆加固工艺 |
CN110439579A (zh) * | 2019-09-17 | 2019-11-12 | 中国水利水电第四工程局有限公司 | 一种敞开式tbm富水隧洞超前预注浆方法 |
CN111119940A (zh) * | 2020-01-08 | 2020-05-08 | 中铁隧道集团二处有限公司 | 一种注浆施工处理方法 |
CN112412496A (zh) * | 2020-12-03 | 2021-02-26 | 中铁十二局集团有限公司 | 富水破碎地质带隧道全断面超前帷幕注浆施工方法 |
CN112780314A (zh) * | 2020-12-30 | 2021-05-11 | 中铁十四局集团建筑工程有限公司 | 一种隧道交错穿越岩层破碎带注浆结构及其注浆方法 |
CN112855167A (zh) * | 2021-01-25 | 2021-05-28 | 中铁十四局集团建筑工程有限公司 | 一种超深竖井穿越破碎岩层的注浆阻水方法 |
CN113217030A (zh) * | 2021-05-29 | 2021-08-06 | 贵州铁建工程质量检测咨询有限公司 | 一种泥质板岩隧道注浆加固效果监测的工作方法 |
CN113404517A (zh) * | 2021-08-03 | 2021-09-17 | 福建工程学院 | 一种隧道突泥涌水的施工方法 |
CN113898379A (zh) * | 2021-09-29 | 2022-01-07 | 中铁二局第二工程有限公司 | 一种实测注浆固结地层压力及参数优化的装置及方法 |
CN115726817A (zh) * | 2023-01-09 | 2023-03-03 | 北京城建设计发展集团股份有限公司 | 用于山岭隧道施工的靶向止水方法 |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5645375A (en) * | 1995-06-07 | 1997-07-08 | Stephens; Patrick J. | Method and apparatus for grouting of tunnel liners |
DE19807036C1 (de) * | 1998-02-19 | 1999-12-02 | Schoendorfer Bau Und Umwelttec | Verfahren zur vollflächigen Abdichtung eines mit Tübbingen ausgekleideten Tunnels sowie danach hergestellte Abdichtung |
CN1932243A (zh) * | 2006-09-28 | 2007-03-21 | 上海隧道工程股份有限公司 | 双圆盾构浅覆土施工方法 |
CN101418567A (zh) * | 2007-10-22 | 2009-04-29 | 上海隧道工程股份有限公司 | 一种对隧道管片进行保护性切割的施工方法 |
-
2010
- 2010-04-02 CN CN2010101623374A patent/CN101832142B/zh active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US5645375A (en) * | 1995-06-07 | 1997-07-08 | Stephens; Patrick J. | Method and apparatus for grouting of tunnel liners |
DE19807036C1 (de) * | 1998-02-19 | 1999-12-02 | Schoendorfer Bau Und Umwelttec | Verfahren zur vollflächigen Abdichtung eines mit Tübbingen ausgekleideten Tunnels sowie danach hergestellte Abdichtung |
CN1932243A (zh) * | 2006-09-28 | 2007-03-21 | 上海隧道工程股份有限公司 | 双圆盾构浅覆土施工方法 |
CN101418567A (zh) * | 2007-10-22 | 2009-04-29 | 上海隧道工程股份有限公司 | 一种对隧道管片进行保护性切割的施工方法 |
Cited By (47)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101994513B (zh) * | 2010-10-30 | 2013-01-02 | 中铁十二局集团第二工程有限公司 | 上半断面完成全断面帷幕注浆隧道施工方法 |
CN101994513A (zh) * | 2010-10-30 | 2011-03-30 | 中铁十二局集团第二工程有限公司 | 上半断面完成全断面帷幕注浆隧道施工方法 |
CN102128038A (zh) * | 2011-01-26 | 2011-07-20 | 北京中铁瑞威基础工程有限公司 | 一种隧道管棚快速施工方法 |
CN102128038B (zh) * | 2011-01-26 | 2013-11-13 | 北京中铁瑞威基础工程有限公司 | 一种隧道管棚快速施工方法 |
CN102168433A (zh) * | 2011-03-23 | 2011-08-31 | 浙江南湖建设有限公司 | 止水帷幕注浆修复方法 |
CN102278130A (zh) * | 2011-09-05 | 2011-12-14 | 中铁隧道集团有限公司 | 隧道高压富水溶腔加筋注浆工艺方法 |
CN102278130B (zh) * | 2011-09-05 | 2013-12-04 | 中铁隧道集团有限公司 | 隧道高压富水溶腔加筋注浆工艺方法 |
CN103982201A (zh) * | 2014-05-22 | 2014-08-13 | 北京中铁瑞威工程检测有限责任公司 | 高压富水隧道宽张裂隙超前探测注浆加固开挖方法 |
CN104033165B (zh) * | 2014-05-26 | 2016-08-31 | 江苏鼎泰工程材料有限公司 | 隧道病害修复方法及修复浆料 |
CN104033165A (zh) * | 2014-05-26 | 2014-09-10 | 江苏鼎泰工程材料有限公司 | 隧道病害修复方法及修复浆料 |
CN104215748A (zh) * | 2014-08-19 | 2014-12-17 | 山东大学 | 一种地下工程破碎围岩注浆加固效果的综合定量检测方法 |
CN104453943A (zh) * | 2014-10-27 | 2015-03-25 | 山东科技大学 | 有效止浆岩盘缺失条件下富水破碎岩体综合注浆控制方法 |
CN104747208A (zh) * | 2015-01-27 | 2015-07-01 | 山东科技大学 | 一种注浆加固浆液扩散调控方法 |
CN105065039A (zh) * | 2015-09-14 | 2015-11-18 | 成都理工大学 | 一种高地温隧道围岩灌浆隔热方法 |
CN105065039B (zh) * | 2015-09-14 | 2018-02-13 | 成都理工大学 | 一种高地温隧道围岩灌浆隔热方法 |
CN105781557A (zh) * | 2016-03-25 | 2016-07-20 | 广东水电二局股份有限公司 | 一种暗挖隧道化学灌浆固结砂层的施工方法 |
CN105781557B (zh) * | 2016-03-25 | 2018-10-02 | 广东水电二局股份有限公司 | 一种暗挖隧道化学灌浆固结砂层的施工方法 |
CN106049418A (zh) * | 2016-06-22 | 2016-10-26 | 中铁二局集团有限公司 | 一种浅埋穿越断层隧道地表组合注浆加固方法 |
CN107035389A (zh) * | 2017-06-01 | 2017-08-11 | 新疆北新路桥集团股份有限公司 | 一种注浆加固施工方法及地表施工方法 |
CN107762534A (zh) * | 2017-10-19 | 2018-03-06 | 中铁十八局集团有限公司 | 一种全孔一次快速注浆施工方法 |
CN108756893A (zh) * | 2018-04-19 | 2018-11-06 | 济南城建集团有限公司 | 一种城区浅埋隧道拱顶土体加固方法 |
CN108661650A (zh) * | 2018-04-23 | 2018-10-16 | 中铁隧道局集团有限公司 | 一种富水岩浆岩地区深大竖井井筒施工方法 |
CN108612546A (zh) * | 2018-05-14 | 2018-10-02 | 姚晓宁 | 一种封闭环境下水平注浆施工方法 |
CN108868788A (zh) * | 2018-06-26 | 2018-11-23 | 李先登 | 一种超长隧道的挖掘方法 |
CN108798718A (zh) * | 2018-07-09 | 2018-11-13 | 中铁十七局集团第四工程有限公司 | 隧道前承后继注浆方法 |
CN108798717A (zh) * | 2018-07-09 | 2018-11-13 | 山东省煤田地质局第四勘探队 | 一种对城市道路下隧道拱顶围岩注浆加固的钻孔设计方法 |
CN109208579A (zh) * | 2018-08-28 | 2019-01-15 | 北京瑞威世纪铁道工程有限公司 | 集束多段水平袖阀管注浆施工方法 |
CN109441486A (zh) * | 2018-11-30 | 2019-03-08 | 中铁隧道集团二处有限公司 | 用于隧道注浆加固的注浆方法 |
CN109854275A (zh) * | 2018-12-24 | 2019-06-07 | 龙口矿业集团有限公司 | 富水砂岩巷道过断层破碎带治理方法 |
CN109763845A (zh) * | 2019-01-23 | 2019-05-17 | 江西省宜丰万国矿业有限公司 | 一种通过构筑l型注浆截流帷幕防治水的施工方法 |
CN109915071A (zh) * | 2019-05-07 | 2019-06-21 | 义马煤业集团孟津煤矿有限责任公司 | 一种基于三步三速的井下煤层底板注浆加固工艺 |
CN110439579B (zh) * | 2019-09-17 | 2020-11-24 | 中国水利水电第四工程局有限公司 | 一种敞开式tbm富水隧洞超前预注浆方法 |
CN110439579A (zh) * | 2019-09-17 | 2019-11-12 | 中国水利水电第四工程局有限公司 | 一种敞开式tbm富水隧洞超前预注浆方法 |
CN111119940B (zh) * | 2020-01-08 | 2021-07-06 | 中铁隧道集团二处有限公司 | 一种注浆施工处理方法 |
CN111119940A (zh) * | 2020-01-08 | 2020-05-08 | 中铁隧道集团二处有限公司 | 一种注浆施工处理方法 |
CN112412496A (zh) * | 2020-12-03 | 2021-02-26 | 中铁十二局集团有限公司 | 富水破碎地质带隧道全断面超前帷幕注浆施工方法 |
CN112780314B (zh) * | 2020-12-30 | 2023-02-28 | 中铁十四局集团建筑工程有限公司 | 一种隧道交错穿越岩层破碎带注浆结构 |
CN112780314A (zh) * | 2020-12-30 | 2021-05-11 | 中铁十四局集团建筑工程有限公司 | 一种隧道交错穿越岩层破碎带注浆结构及其注浆方法 |
CN112855167A (zh) * | 2021-01-25 | 2021-05-28 | 中铁十四局集团建筑工程有限公司 | 一种超深竖井穿越破碎岩层的注浆阻水方法 |
CN113217030A (zh) * | 2021-05-29 | 2021-08-06 | 贵州铁建工程质量检测咨询有限公司 | 一种泥质板岩隧道注浆加固效果监测的工作方法 |
CN113217030B (zh) * | 2021-05-29 | 2022-08-09 | 贵州铁建工程质量检测咨询有限公司 | 一种泥质板岩隧道注浆加固效果监测的工作方法 |
CN113404517A (zh) * | 2021-08-03 | 2021-09-17 | 福建工程学院 | 一种隧道突泥涌水的施工方法 |
CN113404517B (zh) * | 2021-08-03 | 2023-09-22 | 福建工程学院 | 一种隧道突泥涌水的施工方法 |
CN113898379A (zh) * | 2021-09-29 | 2022-01-07 | 中铁二局第二工程有限公司 | 一种实测注浆固结地层压力及参数优化的装置及方法 |
CN113898379B (zh) * | 2021-09-29 | 2023-08-11 | 中铁二局第二工程有限公司 | 一种实测注浆固结地层压力及参数优化的装置及方法 |
CN115726817A (zh) * | 2023-01-09 | 2023-03-03 | 北京城建设计发展集团股份有限公司 | 用于山岭隧道施工的靶向止水方法 |
CN115726817B (zh) * | 2023-01-09 | 2023-06-02 | 北京城建设计发展集团股份有限公司 | 用于山岭隧道施工的靶向止水方法 |
Also Published As
Publication number | Publication date |
---|---|
CN101832142B (zh) | 2011-11-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101832142B (zh) | 一种隧道信息化跟踪精确注浆方法 | |
CN101798930B (zh) | 一种隧道高压富水断层带的快速施工方法 | |
CN103334770B (zh) | 一种长大反坡隧道超高水压富水破碎带施工方法 | |
CN108678777B (zh) | 隧道断层破碎带区段的支护方法 | |
CN101994513B (zh) | 上半断面完成全断面帷幕注浆隧道施工方法 | |
CN104790978B (zh) | 小净距立体交叉隧道环形导坑施工方法 | |
CN102877858B (zh) | 用于采煤工作面破碎顶板的加固方法 | |
CN105155550B (zh) | 联合支护开挖大厚度强风化砂岩层深基坑的施工方法 | |
CN106917627B (zh) | 一种富水地层暗挖施工下导洞的超前支护方法 | |
CN107762533A (zh) | 一种高压富水软弱围岩山岭隧道的超前预注浆方法 | |
CN105715296A (zh) | 一种隧道穿越煤矿采空区的吹砂回填注浆施工方法 | |
CN107725056A (zh) | 一种穿越淤泥质地层隧道全环超前快速注浆施工方法 | |
CN108252719A (zh) | 一种城市浅埋隧道下穿软流塑状红黏土层施工方法 | |
CN108457658A (zh) | 一种土质地层隧道单洞双向施工交汇段施工方法 | |
CN104234726A (zh) | 一种穿越富水不整合接触带隧道的洞内降排水施工方法 | |
CN103410522A (zh) | 浅埋暗挖法连续近距离下穿铁路桥的施工方法 | |
CN101793154A (zh) | 利用隧道围岩地质参数和设置分流孔的注浆堵水方法 | |
CN108265706A (zh) | 一种在溶洞地质内的工程桩及成桩工艺 | |
CN108952727B (zh) | 一种大倾角竖直裂隙地层的注浆堵水方法 | |
CN108678753B (zh) | 反坡隧道施工方法 | |
CN115126441B (zh) | 垂直深部钻孔注浆止浆工艺 | |
CN111254933B (zh) | 袖阀管岩溶注浆施工方法 | |
CN109139018A (zh) | 深孔袖阀管注浆与水平旋喷相结合的隧道施工方法及*** | |
CN106437796B (zh) | 一种岩石地层盾构隧道端头加固结构及加固方法 | |
JP2022553449A (ja) | 採掘跡ゾーンにおける削孔の外部拡張パイプ工法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant |