CN101823546A - Tandem shipbuilding method for chemical tanker - Google Patents

Tandem shipbuilding method for chemical tanker Download PDF

Info

Publication number
CN101823546A
CN101823546A CN201010159697A CN201010159697A CN101823546A CN 101823546 A CN101823546 A CN 101823546A CN 201010159697 A CN201010159697 A CN 201010159697A CN 201010159697 A CN201010159697 A CN 201010159697A CN 101823546 A CN101823546 A CN 101823546A
Authority
CN
China
Prior art keywords
hull
ship
ships
air bag
building berth
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201010159697A
Other languages
Chinese (zh)
Other versions
CN101823546B (en
Inventor
陈佩华
张华斌
刘敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Tian Shi Shipbuilding Co., Ltd
Original Assignee
ZHEJIANG JINGANG SHIPBUILDING CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ZHEJIANG JINGANG SHIPBUILDING CO Ltd filed Critical ZHEJIANG JINGANG SHIPBUILDING CO Ltd
Priority to CN201010159697.9A priority Critical patent/CN101823546B/en
Publication of CN101823546A publication Critical patent/CN101823546A/en
Application granted granted Critical
Publication of CN101823546B publication Critical patent/CN101823546B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Ship Loading And Unloading (AREA)

Abstract

The invention provides a tandem shipbuilding method for a chemical tanker, which belongs to the technical field of ships and solves the problems of low space utilization rate, long shipbuilding period and the like in the traditional chemical tanker building process. The method of the invention comprises the following steps: A, when building No. 1 ship nearby a launching way at the lower end of a shipway, building No. 2 ship or a part of the structure of the No. 2 ship at the upper end of the shipway at the same time; B, after building the No. 1 ship, sliding the ship body to the launching way; C, moving the No. 2 ship to the place, where the No. 1 ship is primarily, at the lower end of the shipway; D, after moving the No. 2 ship to the appointed place, performing secondary positioning on the height and direction of the ship body with a positioning mechanism; and E, after positioning the No. 2 ship, continuously building the No. 2 ship, simultaneously building another ship or a part of the structure of the ship at the place where the No. 2 ship is primarily, and so on. The tandem shipbuilding method for the chemical tanker can simultaneously build more than one ship so that the production efficiency is improved.

Description

A kind of tandem shipbuilding method of chemical carrier
Technical field
The invention belongs to technical field of ships, relate to the tandem shipbuilding method of a kind of tandem shipbuilding method of boats and ships, particularly a kind of chemical carrier.
Background technology
Along with the development of ship building industry, the sectional construction technology reaches its maturity, and is fewer and feweri the quantity that whole ship is divided into segmentation, and segmentation weight is also increasing, and most shipyards adopt large-scale building berth shipbuilding.When shipyard carries out integrated planning at the construction initial stage, can determine the yardstick of building berth according to actual construction ability and the yardstick that can build maximum boats and ships, but the principal dimensions of the usual institute of possible shipyard shipbuilding oceangoing ship has a lot of places at leisure much smaller than the yardstick of building berth in the building berth, form a kind of huge waste.
Large-scale chemical carrier closes up the building berth of place for the band gradient, the construction of considering chemical carrier requires height, cycle is tight, add the place anxiety, for improving the degree of utilization of building berth, enhance productivity, shorten shipbuilding period, so adopting series system builds, promptly build last ship time at the close aquaporin place down of the front end of building berth, build the stern segmentation of a back ship in the building berth rear end, after last launching, again the stern segmentation of already made next ship or whole ship are displaced to front end from the rear end of building berth, and the stern segmentation of on the original position of stern segmentation of second ship, building the 3rd ship, so repeatedly, continuously, carry out ship building in an orderly manner.
Traditional boats and ships displacement method mainly contains mechanical type traction displacement method and floating type displacement method, and the characteristics of two kinds of methods are as follows:
(1) mechanical type traction displacement method
Mechanical type traction displacement method can rely on traction machine, controls the walk rate of stern segmentation (or whole ship) by speed reduction gearing, the stern segmentation is reorientated more accurately.Need the special-purpose shift mechanism of a cover but shortcoming is the method, this shift mechanism comprises traction machine, hawser, roller, sliding machine etc., and needs in the building berth bottom sliding rail is set, and costs an arm and a leg, troublesome poeration.
(2) floating type displacement method
The floating type displacement method mainly is the gate water inlet of opening building berth, utilizes self buoyancy to make stern segmentation or whole ship floating, and relies on the tractor equipment of building berth both sides or utilize other ships traction displacements.The floating type displacement method is simple and convenient, but need to be equipped with the special-purpose lift adjustment of cover mechanism after the displacement second positioning is carried out in the stern segmentation, and water level is also had certain requirement, the too low or very difficult realization in the excessive too fast place of drop at water level.
For now, use relatively manyly at most shipyard mechanical type traction displacement methods and floating type displacement method, corresponding specialized equipment is also many, as patent (application number 01105628.2) disclosed a kind of " secondary positioner of boats and ships stern complete cross section in dock ", what relate to is exactly the localization method of floating type displacement back stern segmentation.This method relates to bow registration device and the stern registration device that is arranged on boats and ships stern complete cross section front and back, the displacement of stern segmentation is carried out in dock, its registration device pedestal links together by fastener and adjusting cushion block and registration device base, pedestal is fastened on the dock bottom, spring conductor rod and spring are contained in the base, the bottom of base is placed with headblock, female mould of stern registration device and the female mould of bow registration device are housed on the base, and stern registration device androtype that contacts with hull bottom and bow registration device androtype cooperate with this with cooresponding female mould respectively regulates adjustable height.
This invention mainly contains two in the purpose that base is provided with spring: the one, and spring has very big elasticity, can absorb lot of energy in the deformation in compression process, plays buffer action, the enormous impact power that hull and dock are subjected to when reducing to locate; The 2nd, spring can keep certain deformation to regulate the height of registration device with the bow stern, the requirement of block telescopic variation when making it to satisfy stern and paragraphing pier, and can make things convenient for the dismounting of bow stern registration device.
Owing to can only adopt laser transit that it is carried out coarse positioning after the displacement of displacement floating type displacement method.If locate inaccurate, deviation appears in line of centers, be that the hull line of centers of benchmark just may depart from the building berth center line far away then with this line of centers, give the lifting of subsequent segment and close up and the measurement of hull principal dimension causes inconvenience, therefore the second positioning of stern segmentation must be determined line of centers and the tram of rib bit line in building berth more exactly, this has just proposed higher requirement to the accurate location of all bigger stern segmentation of quality and volume, is difficult to reach requirement for the general middle-size and small-size shipyard that does not have complete professional equipment.
Summary of the invention
The objective of the invention is the problems referred to above, provide a kind of equipment simple, easy to operate, can make full use of the tandem shipbuilding method of the chemical carrier of building berth, shortening shipbuilding period at the prior art existence.
Purpose of the present invention can realize by following technical proposal: a kind of tandem shipbuilding method of chemical carrier, comprise the building berth of total length greater than the band slope of captain's degree, at the trailer coupling that is provided with the detent mechanism that is used to locate hull, the shift mechanism that is used for mobile hull on the building berth and when hull utilizes the self gravitation displacement, draws, described shift mechanism comprises the air bag and the Air compressor that is used for to above-mentioned airbag aeration that is used to support hull, and this tandem shipbuilding method comprises the steps:
A, build a ship time in the lower end of building berth near aquaporin place down, build the part-structure of No. two ships or No. two ships in the building berth upper end synchronously, a ship and No. two ships are respectively by detent mechanism location hull when building;
B, when ship build finish after, air bag is laid in bottom at a ship, with Air compressor the airbag aeration spreading is supported hull again, originally the detent mechanism that was used to locate this hull is shifted out, oppositely draw hull and slowly release with trailer coupling, a ship deadweight drives air bag and rolls on building berth, makes hull slide to down aquaporin;
C, launch a ship for No. one after, remove the place, lay air bag No. two boat bottom, make the airbag aeration spreading support hull with Air compressor, originally the detent mechanism that was used to locate this hull is shifted out, with the oppositely also slowly release of hull of No. two ships of traction of trailer coupling, No. two ships are because deadweight driving air bag rolls on building berth, and air bag drives hull and moves to a former ship position, building berth lower end;
D, after No. two ships slide into the appointed place, on the length direction of hull, finely tune calibration with trailer coupling, arrange detent mechanism again in the bottom of hull, air bag deflation is also removed, with the short transverse second positioning of detent mechanism to hull;
E, No. two ship positionnings are finished after, continue to build No. two ships, build the part-structure of another ship or ship simultaneously synchronously at former No. two ship positions, reciprocal with this.
A ship and No. two ships need to be consistent on short transverse, when closing up, segmental hoisting can guarantee accuracy rate like this, guarantee certain air pressure behind the airbag aeration, air bag is relevant with the air pressure of air bag itself with raising height to the bearing force of hull, friction force was smaller when air bag rolled on building berth, and it is more laborsaving to drag hull with the rolling of air bag.Air bag, trailer coupling and Air compressor are all very common, relatively simple for structure, easy to operate, do not need high cost.
In the tandem shipbuilding method of above-mentioned a kind of chemical carrier, cylindrical behind the described airbag aeration.Columniform air bag is easier at the time ratio of rolling, owing to be relative rolling between hull and the air bag, therefore is not easy to damage the paint of hull bottom in addition.
In the tandem shipbuilding method of above-mentioned a kind of chemical carrier, described No. two ships comprise the stern segmentation.Sometimes the ship total length of Jian Zaoing is long, may not hold two whole ships in the building berth and build simultaneously, so need to build earlier the stern segmentation of No. two ships.
In the tandem shipbuilding method of above-mentioned a kind of chemical carrier, described detent mechanism comprises at the laser transit of hull one side and the steel pier between hull bottom and ground, be placed with the timber wedge piece between part steel pier and the hull, be placed with jack between another part steel pier and the hull, the top of described timber wedge piece and jack leans mutually with hull respectively.
Earlier arrange a plurality of steel piers, measured deviate with laser transit again,, by interpolation on the steel pier or minimizing timber wedge piece steel pier and hull are stablized and contacted with the height of jack adjusting hull in the bottom of hull.
In the tandem shipbuilding method of above-mentioned a kind of chemical carrier, described detent mechanism comprises at the laser transit of hull one side and the steel pier between hull bottom and ground, be provided with the hydraulic pressure buttress that can adjust oneself height between described steel pier and the hull bottom, the two ends of this hydraulic pressure buttress contact with above-mentioned steel pier and hull bottom respectively.
The hydraulic pressure buttress comprises a bearing, has the screw rod of energy lifting on the bearing, and screw rod is driven by a hydraulic efficiency gear, is provided with self-locking structure between screw rod and the bearing.When needs position body section or whole ship, at first the hydraulic pressure buttress is placed on the steel pier, measure the height situation of hull with laser transit, the overhang of adjusting screw(rod) rises hull or descends, after hull height is adjusted, by the height of the locking of the self-locking structure on hydraulic pressure buttress hydraulic pressure buttress.
In the tandem shipbuilding method of above-mentioned a kind of chemical carrier, described jack is the manual type jack.
In the tandem shipbuilding method of above-mentioned a kind of chemical carrier, described trailer coupling comprises a winch that is fixed on the building berth and is positioned at fore the place ahead, is connected with steel rope between winch and the hull.Steel rope one cephalic disc is on winch, and the other end is connected with hull, controls the speed that hull moves by the burst size of control steel rope.
Compared with prior art, the tandem shipbuilding method of this chemical carrier has following advantage:
(1) can build the hull more than simultaneously, improve production efficiency;
(2) shared building berth of all ships of building simultaneously and lifting appliance have improved usage ratio of equipment;
(3) the water mode is simple under the hull, moves the ship just, to the accurate positioning of hull;
(4) involved equipment is not had specific (special) requirements, all equipment installation and convenient disassembly are reliable;
(5) involved device structure is simple, and productive costs is low.
Description of drawings
Fig. 1 is that the chemical carrier series connection is built and the displacement scheme drawing among the embodiment one.
Fig. 2 is the scheme drawing of steel pier among the embodiment one.
Fig. 3 is the scheme drawing of timber wedge piece among the embodiment one.
Fig. 4 is equipped with the steel pier of jack and the scheme drawing between the hull among the embodiment one.
Fig. 5 is equipped with the steel pier of timber wedge piece and the scheme drawing between the hull among the embodiment one.
Among the figure, 1, Air compressor; 2, flexible pipe; 3, air bag; 4, steel pier; 5, timber wedge piece; 6, winch; 7, steel rope; 8, ship; 9, No. two ships; 10, building berth; 11, following aquaporin 11,12, jack; 13, laser transit.
The specific embodiment
Below be specific embodiments of the invention and in conjunction with the accompanying drawings, technical scheme of the present invention is further described, but the present invention be not limited to these embodiment.
Embodiment one:
As shown in Figure 1, the equipment that the present invention relates to comprises that can be held the above building berth that has gradient 10 of a ship, building berth 10 is provided with Air compressor 1 and gantry crane, be provided with the air bag 3, the trailer coupling that are used to be shifted, also be provided with the detent mechanism that is used to locate hull, detent mechanism comprises manual jack 12, steel pier 4, timber wedge piece 5 and laser transit 13.Trailer coupling comprises a winch 6 that is fixed on the building berth 10 and is positioned at fore the place ahead, is connected with steel rope 7 between winch 6 and the hull.Steel rope 7 one cephalic discs are on winch 6, and the other end is connected with hull, control the speed that hull moves by the burst size of control steel rope 7.
At the front end of building berth 10 when aquaporin 11 places build a ship 8 down, the stern segmentation of building No. two ships 9 in building berth 10 rear ends, ship 8 and No. two ships 9 are by the accurate location and with steel pier 4 and timber wedge piece 5 support hulls of laser transit 13.
After ship 8 construction are finished, lay the air bag 3 of some in the bottom of a ship 8, utilize Air compressor 1 that air bag 3 inflation spreadings are supported ship 8 No. one again, by steel rope 7 ship 8 is connected with winch 6, timber wedge piece 5 and the steel pier 4 that was used to support hull originally shifted out, slowly discharge steel ropes 7 with winch 6, continue to make 3 inflations of building berth rear end air bag simultaneously, No. one ship 8 rear ends are elevated, and a ship 8 relies on deadweight to drive air bag 3 and rolls on building berth 10, make hull slide to down aquaporin 11.
Behind 8 times water of a ship in the building berth 10, utilize the obstacle in the gantry crane removing building berth 10, after the displacement of carrying out No. two ships 9 on building berth 10 ground, need the mark line of in-position.On No. two ships 9, carry out the mark of location usefulness in advance, hull bottom is arranged air bag 3, No. two ship 9 hull rear ends link to each other with steel rope 7 on the winch 6, utilize Air compressor 1 to put on the air by 2 pairs of air bags 3 of flexible pipe, the hull of No. two ships 9 is by jack-up, take out timber wedge piece 5 and steel pier 4 that hull bottom supports, this moment, the weight of hull was all carried by air bag 3.
Continue to utilize 1 pair of air bag 3 of Air compressor to put on the air, the front-end and back-end that guarantee No. two ships 9 have diff-H, this moment, winch 6 began action, winch 6 slowly discharges steel rope 7, No. two ship 9 slowly moves to building berth 10 front ends because of the diff-H that air bag 3 inflations cause, the hull bottom of No. two ships 9 and air bag 3, air bag 3 are done relative rolling with building berth 10 ground, need constantly to arrange in front new air bag 3 in the process that No. two ships 9 move towards building berth 10 front ends, up to end-of-shift.
As Fig. 2, Fig. 3, Fig. 4 and shown in Figure 5, utilize the traction of trailer coupling that No. two ships 9 are finely tuned along the position that building berth 10 length directions arrive, rearrange steel pier 4 alow down, and on a part of steel pier 4, tentatively put into two timber wedge pieces 5.Close Air compressor 1 then, slowly bleed off the pressurized air in the air bag 3, allow the weight of No. two ships 9 all carry, remove air bag 3 by timber wedge piece 5 and steel pier 4.The several bench marks of sign on hull with the several bench mark tests on 13 pairs of hulls of laser transit of a side that is positioned at hull, are established a reference plane, analyze hull and whether are in horizontality.If hull also is not in horizontality, some manual jacks 12 being placed in first leading portion does not place on the steel pier 4 of alongside outside of timber wedge piece 5 again, the handle that shakes manual jack 12 is raised jack piston and is come the height of No. two ship 9 relative building berth reference planes is finely tuned, after regulating, again the timber wedge piece 5 on the steel pier 4 is laid again, the dip plane that makes the timber wedge piece 5 that is positioned at the below is towards the ship side outside, the dip plane of the timber wedge piece 5 above being positioned at is towards the ship side inboard, knock the timber wedge piece 5 of top and make between a plurality of timber wedge pieces 5 and fit mutually closely, guarantee accurate positioning.
After above-mentioned work is finished, remove trailer coupling, the last building berth 10 that carries out subsequent segment according to the hull of having had good positioning closes up work, perhaps puts in order the erection work before launching a ship.
This series connection building practices only needs a building berth 10 can carry out two ships to build simultaneously, can improve building berth 10 degree of utilizations, saves greatly and builds the place, and can make full use of the water, electricity, gas resource around the building berth 10.Air bag 3 is simple to operation with trailer coupling, and air bag 3 can directly be rented, and repeated use is simple and quick, and shipyard there is no need to purchase specially, has saved cost and time.Manually the effect of jack 12 is under laser transit 13 is measured, and utilizes manual shift can adjust the height of hull in narrow hull bottom space.Manual jack 12 low prices, simple to operate, alerting ability is good, applicable to various working environments.After the hull displacement, directly utilize steel pier 4 and timber wedge piece 5 can locate and support hull, do not need to make bow stern registration device, can save laid down cost greatly.
Embodiment two:
The present embodiment general contents is identical with embodiment one, and institute's difference is that No. two ships 9 only comprise the stern segmentation in the present embodiment.
Embodiment three:
The present embodiment general contents is identical with embodiment one, institute's difference is, detent mechanism in the present embodiment comprises at the laser transit 13 of hull one side and the steel pier 4 between hull bottom and ground, be provided with the hydraulic pressure buttress that to adjust oneself height between steel pier 4 and the hull bottom, the hydraulic pressure buttress comprises a bearing, have the screw rod of energy lifting on the bearing, screw rod is driven by a hydraulic efficiency gear, is provided with self-locking structure between screw rod and the bearing.The top of screw rod contacts with hull bottom, and the bottom surface of bearing contacts with the top of steel pier 4.When needs position body section or whole ship, at first the hydraulic pressure buttress is placed on the steel pier 4, measure the height situation of hull with laser transit 13, the overhang of adjusting screw(rod) rises hull or descends, after hull height is adjusted, by the height of the locking of the self-locking structure on hydraulic pressure buttress hydraulic pressure buttress.
Specific embodiment described herein only is that spirit of the present invention is made casehistory.The technical personnel of the technical field of the invention can be made various modifications or replenishes or adopt similar mode to substitute described specific embodiment, but can't depart from spirit of the present invention or surmount the defined scope of appended claims.

Claims (7)

1. the tandem shipbuilding method of a chemical carrier, comprise the building berth (10) of total length greater than the band slope of captain's degree, at the trailer coupling that is provided with the detent mechanism that is used to locate hull, the shift mechanism that is used for mobile hull on the building berth (10) and when hull utilizes the self gravitation displacement, draws, described shift mechanism comprises the air bag (3) that is used to support hull and is used for to the gas filed Air compressor of above-mentioned air bag (3) (1) that this tandem shipbuilding method comprises the steps:
A, in the lower end of building berth (10) when aquaporin (11) locates to build a ship (8) down, build the part-structure of No. two ships (9) or No. two ships (9) synchronously in building berth (10) upper end, a ship (8) and No. two ships (9) are respectively by detent mechanism location hull when building;
B, when a ship (8) build finish after, air bag (3) is laid in bottom at a ship (8), use Air compressor (1) that air bag (3) inflation spreading is supported hull again, originally the detent mechanism that was used to locate this hull is shifted out, oppositely draw hull and slowly release with trailer coupling, a ship (8) deadweight drives air bag (3) and goes up rolling at building berth (10), makes hull slide to down aquaporin (11);
Behind C, the following water of a ship (8), remove the place, lay air bag (3) in No. two ships (9) bottom, make air bag (3) inflation spreading support hull with Air compressor (1), originally the detent mechanism that was used to locate this hull is shifted out, with the oppositely hull and the slowly release of No. two ships of traction (9) of trailer coupling, No. two ships (9) are gone up rolling because deadweight drives air bag (3) at building berth (10), and air bag (3) drives hull and moves to building berth (10) the former ship in lower end (8) position;
D, after No. two ships (9) slide into the appointed place, on the length direction of hull, finely tune calibration with trailer coupling, arrange detent mechanism again in the bottom of hull, air bag (3) is exitted and is removed, with the short transverse second positioning of detent mechanism to hull;
E, No. two ships (9) location finished after, continue to build No. two ships (9), build the part-structure of another ship or ship simultaneously in former No. two ships (9) position synchronous, reciprocal with this.
2. the tandem shipbuilding method of a kind of chemical carrier according to claim 1 is characterized in that, described air bag (3) inflation back is cylindrical.
3. the tandem shipbuilding method of a kind of chemical carrier according to claim 1 is characterized in that, described No. two ships (9) include only the stern segmentation.
4. according to the tandem shipbuilding method of claim 1 or 2 or 3 described a kind of chemical carriers, it is characterized in that, described detent mechanism comprises the laser transit (13) that is positioned at hull one side and the steel pier (4) between hull bottom and ground, be placed with timber wedge piece (5) between part steel pier (4) and the hull, be placed with jack (12) between another part steel pier (4) and the hull, the top of described timber wedge piece (5) and jack (12) leans mutually with hull respectively.
5. according to the tandem shipbuilding method of claim 1 or 2 or 3 described a kind of chemical carriers, it is characterized in that, described detent mechanism comprises the laser transit (13) that is positioned at hull one side and the steel pier (4) between hull bottom and ground, be provided with the hydraulic pressure buttress that can adjust oneself height between described steel pier (4) and the hull bottom, the two ends of this hydraulic pressure buttress contact with above-mentioned steel pier (4) and hull bottom respectively.
6. according to the tandem shipbuilding method of claim 1 or 2 or 3 described a kind of chemical carriers, it is characterized in that described jack (12) is the manual type jack.
7. according to the tandem shipbuilding method of claim 1 or 2 or 3 described a kind of chemical carriers, it is characterized in that, described trailer coupling comprises a winch (6) that is fixed on the building berth (10) and is positioned at fore the place ahead, is connected with steel rope (7) between winch (6) and the hull.
CN201010159697.9A 2010-04-29 2010-04-29 Tandem shipbuilding method for chemical tanker Active CN101823546B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201010159697.9A CN101823546B (en) 2010-04-29 2010-04-29 Tandem shipbuilding method for chemical tanker

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201010159697.9A CN101823546B (en) 2010-04-29 2010-04-29 Tandem shipbuilding method for chemical tanker

Publications (2)

Publication Number Publication Date
CN101823546A true CN101823546A (en) 2010-09-08
CN101823546B CN101823546B (en) 2015-02-11

Family

ID=42687770

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201010159697.9A Active CN101823546B (en) 2010-04-29 2010-04-29 Tandem shipbuilding method for chemical tanker

Country Status (1)

Country Link
CN (1) CN101823546B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103507912A (en) * 2013-09-12 2014-01-15 南通明德重工有限公司 Installation process of chemical carrier cargo hold fitting-out parts
CN106542048A (en) * 2015-09-16 2017-03-29 上海船厂船舶有限公司 A kind of complete cross section movement for inclined building berth, method of construction and its mobile device
CN107914105A (en) * 2017-12-28 2018-04-17 上汽通用五菱汽车股份有限公司 One kind spells platform accurate positioning device
CN110027674A (en) * 2019-05-16 2019-07-19 上海外高桥造船有限公司 General section of shipbody shifts construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4018180A (en) * 1975-04-01 1977-04-19 Kawasaki Jukogyo Kabushiki Kaisha System for building and launching ships
CN1319533A (en) * 2001-03-08 2001-10-31 上海交通大学 Secondary positioner for stern section in dock
CN1586989A (en) * 2004-07-14 2005-03-02 江南造船(集团)有限责任公司 Sliding medium material for building berth serial shipbuilding
CN1926024A (en) * 2004-10-08 2007-03-07 现代重工业株式会社 Method and equipment for transversely launching ship built on the ground
JP2008143281A (en) * 2006-12-07 2008-06-26 Minami Nippon Zosen Kk Construction system of ship or the like
WO2008082076A1 (en) * 2006-12-29 2008-07-10 Hyundai Heavy Industries Co., Ltd. Inundation method used in tandem shipbuilding process
CN101298277A (en) * 2008-07-01 2008-11-05 渤海船舶重工有限责任公司 Wood pier combined supporting pier for boatyard
CN101356091A (en) * 2006-12-29 2009-01-28 现代重工业株式会社 Inundation method used in tandem shipbuilding process
CN101537875A (en) * 2008-05-05 2009-09-23 中交一航局第二工程有限公司 Process for shipping and launching wharfboat by floating same on vertical quay wall with assistance of airbag

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4018180A (en) * 1975-04-01 1977-04-19 Kawasaki Jukogyo Kabushiki Kaisha System for building and launching ships
CN1319533A (en) * 2001-03-08 2001-10-31 上海交通大学 Secondary positioner for stern section in dock
CN1586989A (en) * 2004-07-14 2005-03-02 江南造船(集团)有限责任公司 Sliding medium material for building berth serial shipbuilding
CN1926024A (en) * 2004-10-08 2007-03-07 现代重工业株式会社 Method and equipment for transversely launching ship built on the ground
JP2008143281A (en) * 2006-12-07 2008-06-26 Minami Nippon Zosen Kk Construction system of ship or the like
WO2008082076A1 (en) * 2006-12-29 2008-07-10 Hyundai Heavy Industries Co., Ltd. Inundation method used in tandem shipbuilding process
CN101356091A (en) * 2006-12-29 2009-01-28 现代重工业株式会社 Inundation method used in tandem shipbuilding process
CN101537875A (en) * 2008-05-05 2009-09-23 中交一航局第二工程有限公司 Process for shipping and launching wharfboat by floating same on vertical quay wall with assistance of airbag
CN101298277A (en) * 2008-07-01 2008-11-05 渤海船舶重工有限责任公司 Wood pier combined supporting pier for boatyard

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
戴凤波等: "浅谈气囊下水造船技术的研究与应用", 《第十届全国内河船舶与航运技术学术会议论文集》, 31 December 2006 (2006-12-31) *
朱小滇: "串联造船法在3880/6150吨货船建造中的应用", 《造船技术》, no. 2, 31 March 1984 (1984-03-31), pages 6 - 11 *
杨启等: "船坞串联造船法中艉段再定位分析", 《造船技术》, no. 2, 16 April 2002 (2002-04-16), pages 8 - 10 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103507912A (en) * 2013-09-12 2014-01-15 南通明德重工有限公司 Installation process of chemical carrier cargo hold fitting-out parts
CN106542048A (en) * 2015-09-16 2017-03-29 上海船厂船舶有限公司 A kind of complete cross section movement for inclined building berth, method of construction and its mobile device
CN107914105A (en) * 2017-12-28 2018-04-17 上汽通用五菱汽车股份有限公司 One kind spells platform accurate positioning device
CN110027674A (en) * 2019-05-16 2019-07-19 上海外高桥造船有限公司 General section of shipbody shifts construction method

Also Published As

Publication number Publication date
CN101823546B (en) 2015-02-11

Similar Documents

Publication Publication Date Title
CN108454798B (en) Integrated construction and installation method of upper process module of floating production facility
CN101492140B (en) Aluminum alloy catamaran whole-boat afloat process
CN203224347U (en) Towing tank trailer
CN101823546B (en) Tandem shipbuilding method for chemical tanker
CN105667737A (en) Ship launching method and ship moving trolley system used for implementing method
CN107226182A (en) A kind of method and system that shift building berth under water of large ship
CN106950027A (en) The device of horizontal impact experiment can be carried out
CN103803036A (en) Technology for launching large shipping vessel through air bag
CN105151239A (en) Shipboard supporting structure used for integrally dismounting offshore platform topside module by means of two boat flotage
CN103910041A (en) High-precision offshore wind turbine hoisting and mounting ship
CN101844611B (en) Method used for carrying and launching drilling platform in ocean engineering
CN110541445A (en) Control method for buffer oil cylinder of cutter suction dredger
CN103738484A (en) Sliding track vehicle for dragging and launching drilling ship
CN202138503U (en) Ship sectionalized rapid shifting device
CN111874181B (en) Device and method for offshore installation and maintenance of telescopic upright column of dry tree semi-submersible platform
CN202609052U (en) Leading-in limiting hydraulic device for floating dock wall
CN201071199Y (en) Sliding plate type mobile device
CN208715441U (en) A kind of oblique unwheeling of comb slideway is synchronous and load balancing monitors adjustment system
CN204846306U (en) A shipboard bearing structure that is used for superficial support of two ships wholly to demolish offshore platform upper portion chunk
CN203629799U (en) Stretching device of tensile force testing machine
CN207737454U (en) A kind of stern chute formula marine equipment draw off gear driving structure
CN109204738B (en) Lifting type ship launching slideway
CN203903939U (en) Transformer pushing system
CN102530200A (en) Hydraulic location device for guiding ship in floating dock and working method thereof
CN203819105U (en) Engineering truck for ship emergency upgrading and downgrading repair

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: ZHEJIANG TIANSHI SHIPBUILDING CO., LTD.

Free format text: FORMER OWNER: ZHEJIANG JINGANG SHIPBUILDING CO., LTD.

Effective date: 20150202

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20150202

Address after: Wenling City, Taizhou City, Zhejiang province 317511 Songmen town of white village

Patentee after: Zhejiang Tian Shi Shipbuilding Co., Ltd

Address before: 317511 Zhejiang province Taizhou city Wenling city loose door town stone tablet Hall Village

Patentee before: Zhejiang Jingang Shipbuilding Co., Ltd.