CN101812882A CN200910072285A CN200910072285A CN101812882A CN 101812882 A CN101812882 A CN 101812882A CN 200910072285 A CN200910072285 A CN 200910072285A CN 200910072285 A CN200910072285 A CN 200910072285A CN 101812882 A CN101812882 A CN 101812882A
Authority
CN
China
Prior art keywords
wall
concrete shear
shear wall
concrete
prefabricated units
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910072285A
Other languages
Chinese (zh)
Other versions
CN101812882B (en
Inventor
刘文清
姜洪斌
闫红缨
耿伟常
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Heilongjiang Yuhui New Building Materials Co Ltd
Original Assignee
Heilongjiang Yuhui New Building Materials Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Heilongjiang Yuhui New Building Materials Co Ltd filed Critical Heilongjiang Yuhui New Building Materials Co Ltd
Priority to CN2009100722859A priority Critical patent/CN101812882B/en
Publication of CN101812882A publication Critical patent/CN101812882A/en
Application granted granted Critical
Publication of CN101812882B publication Critical patent/CN101812882B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Load-Bearing And Curtain Walls (AREA)

Abstract

The invention relates to a concrete shear wall with a once-molded filling wall and a manufacturing method thereof. A segmental construction method is generally adopted for the filling wall between traditional precast concrete filling walls, which has the defects of complicated processes causing influence on the construction progress and cracks easily appearing at the connecting position between the post-constructed filling wall and a structure to seriously influence use requirements. The concrete shear wall comprises a concrete shear wall structural prefabricated component (1), wherein a light filler (2) is filled inside the concrete shear wall structural prefabricated component, and the light filler is fixed at the middle part of the concrete shear wall structural prefabricated component through reinforcing mesh sheets (3) and lacing wires (4) and arranged according to a fixed space rule. The light filler is fixed at the middle part of the concrete shear wall structural prefabricated component through the reinforcing mesh sheets (3) and the lacing wires (4) at both sides, and then concrete is poured. The invention is used for a prefabricated or cast-in-situ concrete shear wall structure with the filling wall.

Description

Concrete shear force wall of band one-shot forming infilled wall and preparation method thereof
Technical field:
The present invention relates to a kind of precast concrete shear wall structure, be specifically related to a kind of concrete shear force wall with the one-shot forming infilled wall and preparation method thereof.
Background technology:
Infilled wall between the precast concrete shear wall generally adopts the method for branch's construction, promptly behind the precast concrete shear wall hoisted in position, carries out building by laying bricks or stones of infilled wall or installation according to conventional method again.This job practices not only the program complexity, influence construction speed, and being connected between the infilled wall of back construction and the structure very easily produce the crack, have a strong impact on instructions for use.
Summary of the invention:
The purpose of this invention is to provide a kind of concrete shear force wall, make that work progress is simple more, it is more reliable to connect with the one-shot forming infilled wall.
Above-mentioned purpose realizes by following technical scheme:
The concrete shear force wall of band one-shot forming infilled wall, its composition comprises: the concrete shear wall structure prefabricated units, there is the lightweight filler described concrete shear wall structure prefabricated units inside, and described lightweight filler is fixed in concrete shear wall structure prefabricated units middle part and regularly arranged according to fixing spacing by reinforced mesh and lacing wire.
The concrete shear force wall of described band one-shot forming infilled wall, described lightweight filler is made up of the thin-wall hollow pipe with certain intensity, foams or light porous body, described thin-wall hollow pipe closed at both ends, its shape of cross section is circle or rectangle or polygon, and described lightweight filler external diameter is less than described concrete shear wall structure prefabricated units thickness.
The concrete shear force wall of described band one-shot forming infilled wall, described reinforced mesh is welded according to fixing spacing anyhow by reinforcing bar, and to extending all around.
The preparation method of the concrete shear force wall of band one-shot forming infilled wall, this activities is: with the middle part that the lightweight filler is fixed in the concrete shear wall structure prefabricated units with the reinforced mesh and the lacing wire of both sides, carry out fluid concrete then and get final product.
Beneficial effect of the present invention:
1. it is simple to operate when the concrete shear force wall of the band one-shot forming infilled wall that the present invention realized is constructed, infilled wall was also constructed simultaneously and is finished when the concrete shear force wall construction finished, thereby realize the simplification of work progress, the filler both sides all are furnished with reinforced mesh and stretch into concrete shear force wall, thereby make that the connection of infilled wall is more reliable.This job practices is suitable for the construction of housing industrialization precast concrete and builds characteristics, also can produce enormous benefits if be used for the cast-in-situ concrete shear wall.
2. simple, the construction quality of this product processing technique is easy to guarantee that the job site be dried operation substantially, has fully avoided all disadvantages of traditional form of construction work.The building course environmental protection and energy saving, reduce cost, save construction fund.
Description of drawings:
Accompanying drawing 1 is this product schematic diagram.Fig. 2 is the A-A sectional drawing of Fig. 1.
The specific embodiment:
Embodiment 1:
The concrete shear force wall of band one-shot forming infilled wall, its composition comprises: concrete shear wall structure prefabricated units 1, there is lightweight filler 2 described concrete shear wall structure prefabricated units inside, and described lightweight filler is fixed in concrete shear wall structure prefabricated units middle part by reinforced mesh 3 and lacing wire 4 and according to the fixing regular arrangement of spacing.
Embodiment 2:
The concrete shear force wall of above-mentioned band one-shot forming infilled wall, described lightweight filler is made up of the thin-wall hollow pipe with certain intensity, foams or light porous body, described thin-wall hollow pipe closed at both ends, its shape of cross section is circular or rectangle or polygon or the like, and described lightweight filler external diameter is less than described concrete shear wall structure prefabricated units thickness.
Embodiment 3:
The concrete shear force wall of above-mentioned band one-shot forming infilled wall, described reinforced mesh is welded according to fixing spacing anyhow by reinforcing bar, and to extending all around.
Embodiment 4:
The preparation method of the concrete shear force wall of band one-shot forming infilled wall, this activities is: with the middle part that the lightweight filler is fixed in the concrete shear wall structure prefabricated units with the reinforced mesh and the lacing wire of both sides, carry out fluid concrete then and get final product.

Claims (4)

1. concrete shear force wall with the one-shot forming infilled wall, its composition comprises: the concrete shear wall structure prefabricated units, it is characterized in that: there is the lightweight filler described concrete shear wall structure prefabricated units inside, and described lightweight filler is fixed in concrete shear wall structure prefabricated units middle part and regularly arranged according to fixing spacing by reinforced mesh and lacing wire.
2. the concrete shear force wall of band one-shot forming infilled wall according to claim 1, it is characterized in that: described lightweight filler is made up of the thin-wall hollow pipe with certain intensity, foams or light porous body, described thin-wall hollow pipe closed at both ends, its shape of cross section is circle or rectangle or polygon, and described lightweight filler external diameter is less than described concrete shear wall structure prefabricated units thickness.
3. the concrete shear force wall of band one-shot forming infilled wall according to claim 1 and 2 is characterized in that: described reinforced mesh is welded according to fixing spacing anyhow by reinforcing bar, and to extending all around.
4. the preparation method with the concrete shear force wall of one-shot forming infilled wall is characterized in that: with the middle part that the lightweight filler is fixed in the concrete shear wall structure prefabricated units with the reinforced mesh and the lacing wire of both sides, carry out fluid concrete then and get final product.
CN2009100722859A 2009-06-15 2009-06-15 Concrete shear wall with once-molded filling wall and manufacturing method thereof Expired - Fee Related CN101812882B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100722859A CN101812882B (en) 2009-06-15 2009-06-15 Concrete shear wall with once-molded filling wall and manufacturing method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100722859A CN101812882B (en) 2009-06-15 2009-06-15 Concrete shear wall with once-molded filling wall and manufacturing method thereof

Publications (2)

Publication Number Publication Date
CN101812882A true CN101812882A (en) 2010-08-25
CN101812882B CN101812882B (en) 2012-07-25

Family

ID=42620237

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100722859A Expired - Fee Related CN101812882B (en) 2009-06-15 2009-06-15 Concrete shear wall with once-molded filling wall and manufacturing method thereof

Country Status (1)

Country Link
CN (1) CN101812882B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979220A (en) * 2012-12-06 2013-03-20 郑州大学 Hollow shear wall structure for cross diagonal reinforcing bar and construction method thereof
CN104727464A (en) * 2015-03-26 2015-06-24 江苏永通市政园林建设有限公司 Weather-resistant thermal insulation exterior wall
CN104831829A (en) * 2015-05-11 2015-08-12 孟凡林 Integrated prefabrication method for connecting concrete shear wall and filler wall
CN106088603A (en) * 2016-07-27 2016-11-09 张晶廷 A kind of construction method of cast-in-place concrete building structure
CN108301538A (en) * 2018-03-22 2018-07-20 吉林长发建筑产业化有限公司 Filling wall and its construction method under a kind of prefabricated windows
CN108412094A (en) * 2018-05-08 2018-08-17 中建四局第四建筑工程有限公司 The construction method and device of the hollow concrete wall of masonry between a kind of replacement shear wall
CN115095052A (en) * 2022-08-02 2022-09-23 江苏扬建集团有限公司 Cast-in-place weight-reducing filler wall and construction method thereof

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201517253U (en) * 2009-06-15 2010-06-30 黑龙江宇辉新型建筑材料有限公司 Concrete shear wall with one-step formed filler wall

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102979220A (en) * 2012-12-06 2013-03-20 郑州大学 Hollow shear wall structure for cross diagonal reinforcing bar and construction method thereof
CN102979220B (en) * 2012-12-06 2015-06-10 郑州大学 Hollow shear wall structure for cross diagonal reinforcing bar and construction method thereof
CN104727464A (en) * 2015-03-26 2015-06-24 江苏永通市政园林建设有限公司 Weather-resistant thermal insulation exterior wall
CN104831829A (en) * 2015-05-11 2015-08-12 孟凡林 Integrated prefabrication method for connecting concrete shear wall and filler wall
CN104831829B (en) * 2015-05-11 2016-11-16 孟凡林 The method of attachment that a kind of concrete shear force wall is integrated prefabricated with filling wall
CN106088603A (en) * 2016-07-27 2016-11-09 张晶廷 A kind of construction method of cast-in-place concrete building structure
CN108301538A (en) * 2018-03-22 2018-07-20 吉林长发建筑产业化有限公司 Filling wall and its construction method under a kind of prefabricated windows
CN108301538B (en) * 2018-03-22 2024-02-02 吉林长发建筑产业化有限公司 Prefabricated window lower filling wall and construction method thereof
CN108412094A (en) * 2018-05-08 2018-08-17 中建四局第四建筑工程有限公司 The construction method and device of the hollow concrete wall of masonry between a kind of replacement shear wall
CN115095052A (en) * 2022-08-02 2022-09-23 江苏扬建集团有限公司 Cast-in-place weight-reducing filler wall and construction method thereof

Also Published As

Publication number Publication date
CN101812882B (en) 2012-07-25

Similar Documents

Publication Publication Date Title
CN101812882B (en) Concrete shear wall with once-molded filling wall and manufacturing method thereof
CN100393969C (en) Ribbed concrete column with built-in high-strength or super-strength concrete core column
CN204645278U (en) A kind of precast plate connected node with liner plate
CN102011442A (en) Light steel-concrete combination structure shear wall and manufacturing method thereof
CN105507462A (en) Composite wall with bearing and heat insulation functions and construction method of composite wall with bearing and heat insulation functions
CN104831829A (en) Integrated prefabrication method for connecting concrete shear wall and filler wall
CN103737718B (en) Prefabricated reinforced concrete hollow column template and preparation method thereof
CN206157913U (en) Assembled square steel tube concrete post and girder steel connected node
CN203049846U (en) Permanent compound heat preservation external framework cast-in-situ lightweight concrete wall structure
CN103741883B (en) Prefabricated reinforced concrete column template and preparation method thereof
CN204626770U (en) A kind of prefabricated panel with liner plate
CN204645248U (en) A kind of prefabricated balcony with liner plate
CN201517253U (en) Concrete shear wall with one-step formed filler wall
CN201567719U (en) Inner casing pipe type armoured concrete hollow beam
CN103790266B (en) Steel tube concrete core pillar is put more energy into prefabricated assembled shear-wall element
CN203876035U (en) Precast reinforced concrete hollow column template
CN101736857A (en) Hollow reinforced concrete beam
CN211622269U (en) Hollow sandwich steel pipe concrete beam with eccentrically placed inner pipe
CN204626782U (en) A kind of prefabricated post with liner plate
CN202689278U (en) Superimposed hollow slab
CN203626128U (en) Outer wall partition board
CN101812900A (en) Reinforced mortar pipe with reserved hole and method for steel bar connection
CN101532322A (en) Rectangular concrete filled beam with hollow steel tube
CN111321844A (en) Hollow sandwich steel pipe concrete beam with eccentrically placed inner pipe
CN204252337U (en) Assembled architecture wall body construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
PE01 Entry into force of the registration of the contract for pledge of patent right

Denomination of invention: Concrete shear wall with once-molded filling wall and manufacturing method thereof

Effective date of registration: 20150216

Granted publication date: 20120725

Pledgee: The Bank of Jinzhou Limited by Share Ltd. Harbin Qunli branch

Pledgor: Heilongjiang Yuhui New Building Material Co.,Ltd.

Registration number: 2015230000003

PC01 Cancellation of the registration of the contract for pledge of patent right

Date of cancellation: 20160905

Granted publication date: 20120725

Pledgee: The Bank of Jinzhou Limited by Share Ltd. Harbin Qunli branch

Pledgor: Heilongjiang Yuhui New Building Material Co.,Ltd.

Registration number: 2015230000003

PLDC Enforcement, change and cancellation of contracts on pledge of patent right or utility model
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20120725