CN101806067A - 一种利用气囊进行地下连续墙接头的施工方法 - Google Patents

一种利用气囊进行地下连续墙接头的施工方法 Download PDF

Info

Publication number
CN101806067A
CN101806067A CN200910046224A CN200910046224A CN101806067A CN 101806067 A CN101806067 A CN 101806067A CN 200910046224 A CN200910046224 A CN 200910046224A CN 200910046224 A CN200910046224 A CN 200910046224A CN 101806067 A CN101806067 A CN 101806067A
Authority
CN
China
Prior art keywords
air bag
construction
underground continuous
rubber pneumatic
continuous wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN200910046224A
Other languages
English (en)
Inventor
周蓉峰
马惠龄
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Co Ltd
Original Assignee
Shanghai Mechanized Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Co Ltd filed Critical Shanghai Mechanized Construction Co Ltd
Priority to CN200910046224A priority Critical patent/CN101806067A/zh
Publication of CN101806067A publication Critical patent/CN101806067A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

本发明涉及一种利用气囊进行地下连续墙接头的施工方法。其特征在于:将未充气的橡胶气囊附设钢筋笼内,然后放置在地下连续墙的柔性接头槽中,再对橡胶气囊进行充气,待充气完成后,进行水下混凝土浇注,待混凝土浇注达到一定强度后,释放橡胶气囊内的空气,提升橡胶气囊至地面。橡胶气囊为圆筒体。本发明的优点:可降低工程施工成本、简化施工工艺、缩短施工时间、减轻工人劳动强度、防止施工不良现象发生,保证施工质量。

Description

一种利用气囊进行地下连续墙接头的施工方法
技术领域
本发明涉及一种利用气囊进行地下连续墙接头的施工方法。
背景技术
目前地下连续墙柔性接头施工中常用的施工方法是采用圆形(或波形)钢体锁口管工艺。
随着我国城市建设的快速发展和地下空间的开发利用,促进深基坑围护的地下连续墙不断加深,目前已达到65米。安放和顶拔锁口管时间很长,影响成槽时的槽壁稳定。锁口管顶拔时间过早或过迟将影响地下连续墙的接头施工质量,锁口管拔不出或拔断的情况时有发生;锁口管顶拔时间过早,造成混凝土绕流,影响后道工序施工;锁口管的起拔时间过迟,造成地面(导墙)断裂,施工中断的情况也时有出现。因此地下连续墙接头施工方法有待完善和改进。
发明内容
本发明的目的是解决现有技术中采用圆形(或波形)钢体锁口管工艺进行地下连续墙柔性接头时所存在的上述问题,提供一种利用气囊进行地下连续墙接头的施工方法。本发明设计一种利用气囊进行地下连续墙接头的施工方法,其特征在于:将未充气的橡胶气囊附设钢筋笼内,然后放置在地下连续墙的柔性接头槽中,再对橡胶气囊进行充气,待充气完成后,进行水下混凝土浇注,待混凝土浇注达到一定强度后,释放橡胶气囊内的空气,提升橡胶气囊至地面。橡胶气囊为圆筒体。本发明的优点:可降低工程施工成本、简化施工工艺、缩短施工时间、减轻工人劳动强度、防止施工不良现象发生,保证施工质量。
附图说明
附图1为本发明的施工结构俯视示意图。
附图2为本发明的施工结构侧面示意图。
附图3为本发明的工艺流程图。
下面结合附图和实例对本发明作详细说明。
具体实施方式
将未充气的橡胶气囊1附设钢筋笼2内,然后放置在地下连续墙3的柔性接头槽4中,再对橡胶气囊1进行充气,待充气完成后,进行水下混凝土浇注,待混凝土浇注达到一定强度后,释放橡胶气囊1内的空气,提升橡胶气囊1至地面。橡胶气囊1为圆筒体。在完成施工后,形成了一个地下连续墙钢筋混凝土半圆形柱状体,保证相邻单元的地下连续施工的可靠连接,以达到承受土压力,防止接缝渗漏等具体技术要求。
橡胶气囊1在充气后的形状和膨胀度能满足防止混凝土绕流的作用。在满足浇注混凝土初凝时间的前提下,确定橡胶气囊1放气时间,防止混凝土坍塌。掌握橡胶气囊1的膨胀与收缩率,确定橡胶气囊1与接触面的粘结,使得橡胶气囊1顺利取出。
原工艺采用钢制锁口管和油缸顶升架的方法,选用的材料和设备的费用较高;相比采用气囊法,所需的费用较低,可降低施工成本。原工艺锁口管安放需要2至3个小时,现橡胶气囊1的安装、吊放与钢筋笼2施工同步进行,缩短施工时间,有利单元槽段稳定,加快施工进度。原工艺在单元槽段施工时需事先逐节安放钢锁口管外,锁口管的起拔需持续10小时以上;采用气囊施工工艺,释放橡胶气囊1内的空气,提升橡胶气囊至地面所需时间会大大缩短,减轻操作人员劳动强度。
随着我国城市建设的不断发展,地下空间的利用及开发日趋需求,地下连续墙体作为地下深基坑围护的方法已被普遍采用。同时,作为地下连续墙配套接头施工中的气囊法的发明和应用也有着广泛的前景。

Claims (2)

1.一种利用气囊进行地下连续墙接头的施工方法,其特征在于:将未充气的橡胶气囊附设钢筋笼内,然后放置在地下连续墙的柔性接头槽中,再对橡胶气囊进行充气,待充气完成后,进行水下混凝土浇注,待混凝土浇注达到一定强度后,释放橡胶气囊内的空气,提升橡胶气囊至地面。
2.按权利要求1所述的一种利用气囊进行地下连续墙接头的施工方法,其特征在于:橡胶气囊为圆筒体。
CN200910046224A 2009-02-16 2009-02-16 一种利用气囊进行地下连续墙接头的施工方法 Pending CN101806067A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200910046224A CN101806067A (zh) 2009-02-16 2009-02-16 一种利用气囊进行地下连续墙接头的施工方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200910046224A CN101806067A (zh) 2009-02-16 2009-02-16 一种利用气囊进行地下连续墙接头的施工方法

Publications (1)

Publication Number Publication Date
CN101806067A true CN101806067A (zh) 2010-08-18

Family

ID=42608009

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200910046224A Pending CN101806067A (zh) 2009-02-16 2009-02-16 一种利用气囊进行地下连续墙接头的施工方法

Country Status (1)

Country Link
CN (1) CN101806067A (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103015462A (zh) * 2013-01-20 2013-04-03 张永忠 布袋石子接头装置
CN103850271A (zh) * 2014-03-08 2014-06-11 山东省水利科学研究院 多功能气囊安置与回收车
CN104563162A (zh) * 2013-10-09 2015-04-29 山东省水利科学研究院 一种异型气囊及用异型气囊的地下连续墙接头快速施工法
CN111997095A (zh) * 2020-07-15 2020-11-27 武汉速安达建筑橡塑制品有限公司 一种囊中囊填充技术地连墙施工中的工法
CN113550331A (zh) * 2021-07-06 2021-10-26 上海市基础工程集团有限公司 基于十字钢板及限位气囊芯模的套铣接头及施工方法
CN114032913A (zh) * 2021-11-02 2022-02-11 上海市基础工程集团有限公司 地下水泥土连续钢墙锁扣气囊填充装置及方法

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0711698A (ja) * 1993-06-23 1995-01-13 Bridgestone Corp 土留め用エアーバッグ及び管体等の敷設工法
CN1243901A (zh) * 1999-06-15 2000-02-09 河南黄河工程局 地下连续墙接头施工专用装置及施工技术
CN201180268Y (zh) * 2008-02-03 2009-01-14 王平 地下连续墙防止砼绕流的柔性装置

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0711698A (ja) * 1993-06-23 1995-01-13 Bridgestone Corp 土留め用エアーバッグ及び管体等の敷設工法
CN1243901A (zh) * 1999-06-15 2000-02-09 河南黄河工程局 地下连续墙接头施工专用装置及施工技术
CN201180268Y (zh) * 2008-02-03 2009-01-14 王平 地下连续墙防止砼绕流的柔性装置

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103015462A (zh) * 2013-01-20 2013-04-03 张永忠 布袋石子接头装置
CN103015462B (zh) * 2013-01-20 2015-01-21 安徽省林锦记食品工业有限公司 布袋石子接头装置及其使用方法
CN104563162A (zh) * 2013-10-09 2015-04-29 山东省水利科学研究院 一种异型气囊及用异型气囊的地下连续墙接头快速施工法
CN103850271A (zh) * 2014-03-08 2014-06-11 山东省水利科学研究院 多功能气囊安置与回收车
CN103850271B (zh) * 2014-03-08 2015-10-07 山东省水利科学研究院 多功能气囊安置与回收车
CN111997095A (zh) * 2020-07-15 2020-11-27 武汉速安达建筑橡塑制品有限公司 一种囊中囊填充技术地连墙施工中的工法
CN111997095B (zh) * 2020-07-15 2022-04-15 武汉速安达建筑橡塑制品有限公司 一种囊中囊填充技术地连墙施工中的工法
CN113550331A (zh) * 2021-07-06 2021-10-26 上海市基础工程集团有限公司 基于十字钢板及限位气囊芯模的套铣接头及施工方法
CN114032913A (zh) * 2021-11-02 2022-02-11 上海市基础工程集团有限公司 地下水泥土连续钢墙锁扣气囊填充装置及方法

Similar Documents

Publication Publication Date Title
CN102425310B (zh) 装配式住宅剪力墙结构墙体竖向连接施工方法
CN101806067A (zh) 一种利用气囊进行地下连续墙接头的施工方法
CN103422674B (zh) 装配式混凝土结构现浇段混凝土施工方法
CN203022024U (zh) 一种管廊现浇施工整体移动式模架
CN209163214U (zh) 一种基于预留孔穿筋的构造柱施工结构
CN205012651U (zh) 一种地下空间新型侧墙单侧支模体系
CN103195450B (zh) 液压隧道仰拱作业台车及仰拱施工方法
CN108914965A (zh) 用于综合管廊的铝合金模板的连续施工方法
CN102966121A (zh) 一种管廊现浇施工整体移动式模架
CN206768813U (zh) 后注浆预应力管桩
CN106836213A (zh) 后注浆预应力空心方桩及其施工工艺
CN104295112B (zh) 一种钢筋混凝土柱上接钢管混凝土柱连接结构及施工方法
CN201225015Y (zh) 冶金大型地下水池施工支模
CN107191006B (zh) 一种导流槽耐火混凝土层拆除修复方法
CN210217774U (zh) 一种黄土隧道支护***
CN101245595A (zh) 大口径钻孔灌注桩钢筋笼的制作方法
CN103161298B (zh) 大面积混凝土地坪制作方法
CN205975637U (zh) 一种用于圆形井内混凝土浇筑的模板加固装置
CN107447771A (zh) 一种陆上承台施工***及施工方法
CN108678767B (zh) 挤压大变形围岩隧道开挖与让压-刚性联合支护施工方法
CN204174955U (zh) 钢筋混凝土柱上接钢管混凝土柱连接结构
CN103334771A (zh) 暗挖逆作法侧墙与中板、拱顶接头处的混凝土浇筑方法
CN107386638B (zh) 一种梁下现浇装饰挂板结构的施工方法
CN110258514A (zh) 一种地下连续墙用的钢导墙及其施工方法
CN111577345B (zh) 一种多层防渗隧底结构施工方法及施工***

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20100818