CN101788799A - Field signal acquisition method used for remote monitoring system - Google Patents

Field signal acquisition method used for remote monitoring system Download PDF

Info

Publication number
CN101788799A
CN101788799A CN200910044582A CN200910044582A CN101788799A CN 101788799 A CN101788799 A CN 101788799A CN 200910044582 A CN200910044582 A CN 200910044582A CN 200910044582 A CN200910044582 A CN 200910044582A CN 101788799 A CN101788799 A CN 101788799A
Authority
CN
China
Prior art keywords
signal
control system
relay
direct current
shielded cable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN200910044582A
Other languages
Chinese (zh)
Other versions
CN101788799B (en
Inventor
李劲柏
刘武林
朱晓星
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
Electric Power Research Institute of State Grid Hunan Electric Power Co Ltd
State Grid Hunan Electric Power Co Ltd
Original Assignee
HUNAN FOCUS ENVIRONMENTAL PROTECTION TECHNOLOGY CO LTD
HUNAN INSTITUTE OF POWER Co EXPERIMENT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by HUNAN FOCUS ENVIRONMENTAL PROTECTION TECHNOLOGY CO LTD, HUNAN INSTITUTE OF POWER Co EXPERIMENT filed Critical HUNAN FOCUS ENVIRONMENTAL PROTECTION TECHNOLOGY CO LTD
Priority to CN2009100445822A priority Critical patent/CN101788799B/en
Publication of CN101788799A publication Critical patent/CN101788799A/en
Application granted granted Critical
Publication of CN101788799B publication Critical patent/CN101788799B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Selective Calling Equipment (AREA)

Abstract

The invention relates to a field signal acquisition method used for a remote monitoring system, which comprises the following steps of 1, additionally installing a relay and a double-path DC signal isolator; 2, receiving a field signal; 3, separating the signal in good condition; 4, outputting the signal. In the method, the electrical appliance additionally installed is adopted for shunting the signal acquired on site in good condition, so that the signal can not only be used for field monitoring, but also be transmitted to a remote monitoring center for real-time monitoring, thereby effectively preventing the remote monitoring system from acquiring a spurious signal under the condition of saving investment. The invention has the following benefits that: (1) the method can ensure the authenticity of the signal and the remote monitoring; (2) the method can share a cable with the local control system, therefore, the investment is small; (3) the method can be applicable to the remote monitoring systems in various scales without the constraint of other factors.

Description

A kind of field signal acquisition method that is used for long distance control system
Technical field
The invention belongs to the control engineering technical field, be specifically related to a kind of field signal acquisition method that is used for long distance control system.
Background technology
Along with mechanics of communication and development of computer, long distance control system has all been developed in a lot of fields, the ruuning situation at a distance of the equipment of hundreds if not thousands of kilometers on the region is transferred to the remote monitoring center, with convenient supervision.If but this supervision has a negative impact to the manager of equipment, the phenomenon that signal is played tricks then appears probably, and for example environmental administration is so often just to the long distance control system of heat-engine plant desulfurizer ruuning situation.And the field signal acquisition mode overwhelming majority in the past is the control system by the scene, passes on out as DCS system (scattered control system) and SIS system (plant level supervisory information system).Though this technology implementation is got up simply, but owing to can handle arbitrarily signal easily in the control system at the scene, so the signal that such long distance control system collects often is false, thereby cause long distance control system to lose the meaning of monitoring.In order to prevent the generation of spurious signal, someone installs a cover signal measurement element at the scene separately, lay special cable and deliver to long distance control system, but that this mode is invested is excessive, and some scene can't install another set of measuring sensor, so can't large-scale promotion application.
Summary of the invention
The technical problem to be solved in the present invention is, the defective at known technology exists provides a kind of field signal acquisition method that is used for long distance control system, and this method can not only be guaranteed the authenticity of data-signal, and small investment, instant effect.
Technical solution of the present invention is that a kind of field signal acquisition method that is used for long distance control system that is provided is to be following step:
1, sets up relay and two-way direct current signal isolator.In existing field control system, set up a relay and a two-way direct current signal isolator.The input end of wherein said relay is inserted by shielded cable by on-the-spot switch on and off signal collecting element, and two output terminals of relay insert the switch on and off signal input part of field control system and long distance control system respectively by shielded cable; The input end of described two-way direct current signal isolator is inserted by shielded cable by on-the-spot 4~20mA standard signal acquisition elements, and two output terminals of two-way direct current signal isolator insert 4~20mA standard signal input end of field control system and long distance control system respectively by shielded cable.
2, receive on-site signal.By shielded cable on-the-spot switch on and off signal is received and import above-mentioned relay, by shielded cable scene 4~20mA standard signal is received and import above-mentioned two-way direct current signal isolator simultaneously.
3, harmless separation signal.The relay of setting up by above-mentioned steps 1 is divided into two the on-the-spot switch on and off signal lossless ground of step 2 input, and the two-way direct current signal isolator of setting up by above-mentioned steps 1 scene 4~20mA standard signal that step 2 is imported also nondestructively is divided into two simultaneously.
4, output signal.With the on-the-spot switch on and off signal after separating by relay is harmless in the step 3, the one tunnel is sent to field control system by shielded cable, and one the tunnel is sent to long distance control system; Simultaneously by shielded cable with the scene 4~20mA standard signal after separating by two-way direct current signal isolator is harmless in the step 3, the one tunnel is sent to field control system, the one tunnel is sent to long distance control system.
Workflow of the present invention can be referring to shown in the accompanying drawing 1.
Technological core of the present invention be adopt the relay set up and two-way direct current signal isolator with collection in worksite to standard signal can't harm shunting, make this signal both can continue on for on-the-spot monitoring and operation, can be sent to the remote monitoring center by communication apparatus again and monitor in real time, gather spurious signal so can under the situation of reducing investment outlay, effectively prevent long distance control system.
The invention has the beneficial effects as follows:
(1), what can guarantee that various long distance control system collected is from the signal of signal element on the spot, therefore can guarantee the authenticity of signal, the purpose of guaranteeing to carry out remote monitoring.
(2), share cable, small investment with local control system.
(3), be applicable to and the long distance control system of various scales be not subjected to the restriction of any other factors.
Description of drawings
Fig. 1 is a workflow reference diagram of the present invention.
Embodiment
Embodiment 1.
1, sets up relay and two-way direct current signal isolator.In existing field control system, set up a relay and a two-way direct current signal isolator.The SWP9034 type two-way direct current signal isolator that the DC48V type relay that wherein said relay adopts commercially available Omron (China) company limited to produce, described two-way direct current signal isolator adopt commercially available Yunnan Yun Run instrument Manufacturing Co., Ltd to produce.The input end of wherein said relay is inserted by shielded cable by on-the-spot switch on and off signal collecting element, and two output terminals of relay insert the switch on and off signal input part of field control system and long distance control system respectively by shielded cable; The input end of described two-way direct current signal isolator is inserted by shielded cable by on-the-spot 4~20mA standard signal acquisition elements, and two output terminals of two-way direct current signal isolator insert 4~20mA standard signal input end of field control system and long distance control system respectively by shielded cable.
2, receive on-site signal.By commercially available shielded cable on-the-spot switch on and off signal is received and import above-mentioned relay, also scene 4~20mA standard signal is received and import above-mentioned two-way direct current signal isolator simultaneously by commercially available shielded cable.
3, harmless separation signal.The relay of setting up by above-mentioned steps 1 is divided into two the on-the-spot switch on and off signal lossless ground of step 2 input, and the two-way direct current signal isolator of setting up by above-mentioned steps 1 scene 4~20mA standard signal that step 2 is imported also nondestructively is divided into two simultaneously.
4, output signal.With the on-the-spot switch on and off signal after separating by relay is harmless in the step 3, the one tunnel is sent to field control system by commercially available shielded cable, and one the tunnel is sent to long distance control system; Simultaneously also by commercially available shielded cable with in the step 3 by the scene 4~20mA standard signal after the harmless separation of two-way direct current signal isolator, the one tunnel is sent to field control system, the one tunnel is sent to long distance control system.

Claims (1)

1. field signal acquisition method that is used for long distance control system, this method is following step:
(1), sets up relay and two-way direct current signal isolator, in existing field control system, set up a relay and a two-way direct current signal isolator, the input end of wherein said relay is inserted by shielded cable by on-the-spot switch on and off signal collecting element, and two output terminals of relay insert the switch on and off signal input part of field control system and long distance control system respectively by shielded cable; The input end of described two-way direct current signal isolator is inserted by shielded cable by on-the-spot 4~20mA standard signal acquisition elements, and two output terminals of two-way direct current signal isolator insert 4~20mA standard signal input end of field control system and long distance control system respectively by shielded cable;
(2), receive on-site signal, by shielded cable on-the-spot switch on and off signal is received and imports above-mentioned relay, simultaneously by shielded cable with the reception of scene 4~20mA standard signal and import above-mentioned two-way direct current signal isolator;
(3), harmless separation signal, the relay of setting up by above-mentioned steps 1 is divided into two the on-the-spot switch on and off signal lossless ground of step 2 input, and the two-way direct current signal isolator of setting up by above-mentioned steps 1 scene 4~20mA standard signal that step 2 is imported also nondestructively is divided into two simultaneously;
(4), output signal, with the on-the-spot switch on and off signal after separating by relay is harmless in the step 3, the one tunnel is sent to field control system by shielded cable, the one tunnel is sent to long distance control system; Simultaneously by shielded cable with the scene 4~20mA standard signal after separating by two-way direct current signal isolator is harmless in the step 3, the one tunnel is sent to field control system, the one tunnel is sent to long distance control system.
CN2009100445822A 2009-10-21 2009-10-21 Field signal acquisition method used for remote monitoring system Active CN101788799B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009100445822A CN101788799B (en) 2009-10-21 2009-10-21 Field signal acquisition method used for remote monitoring system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009100445822A CN101788799B (en) 2009-10-21 2009-10-21 Field signal acquisition method used for remote monitoring system

Publications (2)

Publication Number Publication Date
CN101788799A true CN101788799A (en) 2010-07-28
CN101788799B CN101788799B (en) 2011-12-07

Family

ID=42532041

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009100445822A Active CN101788799B (en) 2009-10-21 2009-10-21 Field signal acquisition method used for remote monitoring system

Country Status (1)

Country Link
CN (1) CN101788799B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115195069A (en) * 2022-06-27 2022-10-18 佛山市南海区广工大数控装备协同创新研究院 Universal data acquisition module and system for injection molding machine

Family Cites Families (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN100368949C (en) * 2005-04-28 2008-02-13 南京科远控制工程有限公司 Automatic control system based on artificial intelligence for heat-engine plant
CN101157006B (en) * 2007-07-27 2010-04-21 江苏方天电力技术有限公司 Real time monitoring and information management system of coal-firing units gas desulfurization

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115195069A (en) * 2022-06-27 2022-10-18 佛山市南海区广工大数控装备协同创新研究院 Universal data acquisition module and system for injection molding machine

Also Published As

Publication number Publication date
CN101788799B (en) 2011-12-07

Similar Documents

Publication Publication Date Title
CN204515048U (en) Digital transformer substation intelligent tester
CN104935079A (en) Station-domain protection system of intelligent transformer station and function debugging method of system
CN103743967A (en) Remote test system and method for substation high frequency protection channel state
CN202661863U (en) Remote monitoring system for reliability test
CN204649927U (en) A kind of primary cut-out state monitoring device
CN102364784B (en) Method for realizing distribution network load automation acquisition and displaying by using load control terminal
CN101788799B (en) Field signal acquisition method used for remote monitoring system
CN109357166A (en) LoRa type low-power consumption gas pipeline cathodic protection potential monitors system
CN208571705U (en) A kind of 500kV substation fault recording teletransmission data monitoring system
CN203251142U (en) Switch cabinet integrated monitoring terminal
CN203287101U (en) On-site noise acquisition system
CN214041605U (en) Edge computing system and power distribution terminal with high-low voltage synchronous measurement and protection
CN103499763A (en) Real-time on-line remote monitoring transformer iron core current device
CN208158587U (en) A kind of optical cable is automatically to fine test macro
CN202471891U (en) DC feeder line small current grounding line selection device for DC power cabinet
CN202093580U (en) Coal mine patrol inspection management system
CN202197149U (en) Transformer station safety early warning system
CN201742169U (en) Digital real-time testing analyzer of secondary system in transformer station
CN201812154U (en) Frequency detection module of satellite synchronous clock device
CN203324263U (en) Signal acquisition and processing system
CN113960411B (en) Power transmission line fault tripping comprehensive research and judgment method based on multi-source data fusion
CN221099880U (en) Vibration monitoring system for blast furnace blower
CN219643660U (en) Intelligent electricity management system
CN213126060U (en) Distribution network automation testing arrangement
CN108754505A (en) NB-IoT type low-power consumption gas pipeline cathodic protection potentials monitor system

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
ASS Succession or assignment of patent right

Owner name: THE RESEARCH ACADEMY OF HU'NAN ELECTRIC POWER COMP

Free format text: FORMER OWNER: EXPERIMENT RESEARCH ACADEMY OF HU'NAN ELECTRIC POWER COMPANY

Effective date: 20121206

Owner name: HU'NAN HUICUI ELECTRIC POWER TECHNOLOGY CO., LTD.

Free format text: FORMER OWNER: HU'NAN HUICUI ELECTRIC POWER TECHNOLOGY CO., LTD.

Effective date: 20121206

C41 Transfer of patent application or patent right or utility model
TR01 Transfer of patent right

Effective date of registration: 20121206

Address after: 410007 No. 79 hydroelectric power street, east pond, Hunan, Changsha

Patentee after: Science Research Institute of Hunan Electric Power Co., Ltd.

Patentee after: Hunan Focus Environmental Protection Technology Co.,Ltd.

Patentee after: State Grid Corporation of China

Address before: 410007 No. 79 hydroelectric power street, east pond, Hunan, Changsha

Patentee before: Hunan Institute of Power Company Experiment

Patentee before: Hunan Focus Environmental Protection Technology Co.,Ltd.

TR01 Transfer of patent right

Effective date of registration: 20180810

Address after: 410004 398 new Shao Dong Road, Tianxin District, Changsha, Hunan

Co-patentee after: Power Science Research Institute of Hunan Electric Power Co., Ltd.

Patentee after: State Grid Hunan Electric Power Co., Ltd.

Co-patentee after: State Grid Corporation of China

Address before: No. 79, Dongtang hydropower street, Changsha, Hunan Province

Co-patentee before: Hunan Focus Environmental Protection Technology Co.,Ltd.

Patentee before: Science Research Institute of Hunan Electric Power Co., Ltd.

Co-patentee before: State Grid Corporation of China

TR01 Transfer of patent right