CN101787796A - Suspended formwork bracing system for steel structure concrete floor slab construction - Google Patents
Suspended formwork bracing system for steel structure concrete floor slab construction Download PDFInfo
- Publication number
- CN101787796A CN101787796A CN201010100878A CN201010100878A CN101787796A CN 101787796 A CN101787796 A CN 101787796A CN 201010100878 A CN201010100878 A CN 201010100878A CN 201010100878 A CN201010100878 A CN 201010100878A CN 101787796 A CN101787796 A CN 101787796A
- Authority
- CN
- China
- Prior art keywords
- floor slab
- concrete floor
- steel structure
- suspended
- structure concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Landscapes
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
Abstract
The invention discloses a suspended formwork bracing system for steel structure concrete floor slab construction, which comprises a formwork bracing beam, block members, fastening bolts, a vertical lifting bolt, a horizontal fixing bolt and the like. The formwork bracing beam is suspended on a bottom flange of an H-shaped steel girder through the block members, the block members are fastened on the bottom flange of the H-shaped steel girder through the fastening bolts, the vertical lifting bolt is used for adjusting the height of the formwork bracing beam, and the horizontal fixing bolt is used for adjusting the horizontal positioning of the formwork bracing beam. Square timber and a formwork are arranged above the formwork bracing beam, which can conveniently and rapidly brace a steel structure concrete floor slab.
Description
Technical field
The present invention relates to a kind of construction formwork support system, relate in particular to a kind of suspended formwork bracing system for steel structure concrete floor slab construction.
Background technology
Along with economic construction and social development, steel work is used more and more.In most of steel work, what floor adopted is profiled sheet concrete combined floor or concrete floor at present.The profiled sheet concrete combined floor is with the construction formwork of profiled sheet as floor, direct fluid concrete and forming thereon, advantage such as it is fast that it has installation rate, easy and simple to handle.The profiled sheet concrete combined floor is divided into combined and non-combined.Combined composite floor substitutes the floor slab bottoms reinforcing bar with profiled sheet simultaneously, participates in the stressed of floor, but must carry out flameproof protection to profiled sheet, and it is less that expensive flameproof protection expense makes combined composite floor use.But not combined composite floor only adopts profiled sheet to use as construction formwork, has caused waste economically, causes expense higher indirectly.
Along with country to the advocating of energy-conservation and low-carbon (LC) building, steel house has obtained greatly developing as the dwelling house system of environment protecting and power-saving.Because use habit that people are long-term and developer's cost control, steel house is not generally done furred ceiling, but the processing of plastering, obviously concrete floor has absolute predominance than profiled sheet composite floor in economical and use.
In the prior art, the job practices that directly adopts concrete floor is exactly directly to set up scaffold, and wooden form is installed then.
There is following shortcoming at least in above-mentioned prior art: workload is big, long construction period.
Summary of the invention
The purpose of this invention is to provide a kind of suspended formwork bracing system for steel structure concrete floor slab construction that can carry out the steel structure concrete floor slab formwork erection quickly and easily.
The objective of the invention is to be achieved through the following technical solutions:
Suspended formwork bracing system for steel structure concrete floor slab construction of the present invention comprises the template supporting traverse, and described template supporting traverse is suspended on the bottom flange of the H section steel beam of steel structure concrete floor slab.
As seen from the above technical solution provided by the invention, suspended formwork bracing system for steel structure concrete floor slab construction of the present invention, because the template supporting traverse is suspended on the bottom flange of the H section steel beam of steel structure concrete floor slab, can carry out the steel structure concrete floor slab formwork erection quickly and easily.
Description of drawings
Fig. 1 is the plane structure schematic diagram of suspended formwork bracing system for steel structure concrete floor slab construction of the present invention;
Fig. 2 is the sectional view of the A-A direction of Fig. 1;
Fig. 3 is the sectional view of the B-B direction of Fig. 1;
Fig. 4 is the sectional view of the C-C direction of Fig. 2.
The specific embodiment
Suspended formwork bracing system for steel structure concrete floor slab construction of the present invention, its preferable specific embodiment is:
Comprise the template supporting traverse, described template supporting traverse is suspended on the bottom flange of the H section steel beam of steel structure concrete floor slab.The two ends of template supporting traverse can be suspended on the bottom flange of two H section steel beams respectively by fastener.Can be provided with fastening bolt between the bottom flange of fastener and H section steel beam.
Fastener can have two, is suspended on the both sides of the bottom flange of H section steel beam respectively; Fastener also can have one, is suspended on a side of the bottom flange of H section steel beam.
Can be provided with the horizontal fixed bolt in the horizontal direction between fastener and the template supporting traverse, in the vertical direction can be provided with the vertical lift bolt.
The bottom of fastener is provided with square hole or hook, and the end of template supporting traverse is inserted in the square hole or hangs on the hook, and the horizontal fixed bolt is located on the sidewall of square hole or hook, and the vertical lift bolt is located on the diapire of square hole or hook.
In concrete the enforcement, template supporting traverse cross section can have any shape; The form of structure of fastener can be unrestricted, and template supporting traverse length can not be subjected to the restriction of H section steel beam spacing.
This support system can have a plurality of, and mutual dislocation is placed between a plurality of support systems.Wherein, the fastener of the mutually close end of the template supporting traverse of adjacent two support systems can merge into a single whole.
One or more layers lumps of wood is installed in the top of template supporting traverse, and the top of the lumps of wood is provided with template.The concrete lumps of wood can have two-layer, is respectively the horizontal lumps of wood, vertical lumps of wood.
Steel structure concrete floor slab construction of the present invention is with hanging template system, is made up of template supporting traverse and fastener, fastening bolt, vertical lift bolt, horizontal fixed bolt etc.The template supporting traverse is suspended on H section steel beam bottom flange by fastener, and fastener is anchored on H shaped steel bottom flange by fastening bolt, and the vertical lift bolt is used to regulate the height of template supporting traverse, and the horizontal fixed bolt is used to regulate the horizontal location of template supporting traverse.The horizontal lumps of wood, vertical lumps of wood and template can directly be installed on this support system.Have following beneficial effect:
But multilayer is constructed simultaneously, has improved operating efficiency;
The suspension technology makes the girder steel more reasonable stress, make template install, dismantle more quick and easy;
Be convenient to modularization and make, Construction Arrangement is more flexible, is beneficial to produce to promote;
Reusable, have better economic performance.
Also in conjunction with the accompanying drawings the application is described in detail below by specific embodiment:
As Fig. 1, Fig. 2, Fig. 3, shown in Figure 4, comprise steel column 1, steel girder 2, steel secondary beam 3 etc., template supporting traverse 4 hangs on by fastener 5 between the bottom flange of steel secondary beam 3, and fastener 5 is anchored between the bottom flange of steel secondary beam 3 by fastening bolt 6.Fastener 5 is provided with fastening bolt 6, vertical lift bolt 7, horizontal fixed bolt 8.The horizontal lumps of wood 9, the vertically lumps of wood 10 and template 11 etc. directly are installed on this support system.
The program of total construction is: hang on fastener 5 between the bottom flange of steel secondary beam 3 by fastening bolt 6 earlier, again template supporting traverse 4 is inserted the fastener 5 from the end, adjust the height of template supporting traverse 4 by vertical lift bolt 7, also fixing by the horizontal location of horizontal fixed bolt 8 adjusting template supporting traverses 4 then, the horizontal lumps of wood 9 is installed at last successively, vertically the lumps of wood 10, template 11.
The above; only for the preferable specific embodiment of the present invention, but protection scope of the present invention is not limited thereto, and anyly is familiar with those skilled in the art in the technical scope that the present invention discloses; the variation that can expect easily or replacement all should be encompassed within protection scope of the present invention.
Claims (10)
1. a suspended formwork bracing system for steel structure concrete floor slab construction is characterized in that, comprises the template supporting traverse, and described template supporting traverse is suspended on the bottom flange of the H section steel beam of steel structure concrete floor slab.
2. suspended formwork bracing system for steel structure concrete floor slab construction according to claim 1 is characterized in that, the two ends of described template supporting traverse are suspended on the bottom flange of two H section steel beams respectively by fastener.
3. suspended formwork bracing system for steel structure concrete floor slab construction according to claim 2 is characterized in that, is provided with fastening bolt between the bottom flange of described fastener and described H section steel beam.
4. suspended formwork bracing system for steel structure concrete floor slab construction according to claim 3 is characterized in that, described fastener has two, is suspended on the both sides of the bottom flange of described H section steel beam respectively; Or described fastener has one, is suspended on a side of the bottom flange of described H section steel beam.
5. suspended formwork bracing system for steel structure concrete floor slab construction according to claim 4, it is characterized in that, be provided with the horizontal fixed bolt in the horizontal direction between described fastener and the described template supporting traverse, in the vertical direction is provided with the vertical lift bolt.
6. suspended formwork bracing system for steel structure concrete floor slab construction according to claim 5, it is characterized in that, the bottom of described fastener is provided with square hole or hook, the end of described template supporting traverse is inserted in the described square hole or hangs on the described hook, described horizontal fixed bolt is located on the sidewall of described square hole or hook, and described vertical lift bolt is located on the diapire of described square hole or hook.
7. according to each described suspended formwork bracing system for steel structure concrete floor slab construction of claim 1 to 6, it is characterized in that this support system has a plurality of, mutual dislocation is placed between a plurality of support systems.
8. suspended formwork bracing system for steel structure concrete floor slab construction according to claim 7 is characterized in that, the fastener of the mutually close end of the template supporting traverse of adjacent two support systems merges into a single whole.
9. suspended formwork bracing system for steel structure concrete floor slab construction according to claim 7 is characterized in that one or more layers lumps of wood is installed in the top of described template supporting traverse, and the top of the described lumps of wood is provided with template.
10. suspended formwork bracing system for steel structure concrete floor slab construction according to claim 9 is characterized in that the described lumps of wood has two-layer, is respectively the horizontal lumps of wood, vertical lumps of wood.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101008784A CN101787796B (en) | 2010-01-25 | 2010-01-25 | Suspended formwork bracing system for steel structure concrete floor slab construction |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN2010101008784A CN101787796B (en) | 2010-01-25 | 2010-01-25 | Suspended formwork bracing system for steel structure concrete floor slab construction |
Publications (2)
Publication Number | Publication Date |
---|---|
CN101787796A true CN101787796A (en) | 2010-07-28 |
CN101787796B CN101787796B (en) | 2012-04-18 |
Family
ID=42531160
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN2010101008784A Expired - Fee Related CN101787796B (en) | 2010-01-25 | 2010-01-25 | Suspended formwork bracing system for steel structure concrete floor slab construction |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN101787796B (en) |
Cited By (16)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102116084A (en) * | 2010-12-10 | 2011-07-06 | 陈永生 | Hanging formwork device replacing supporting formwork for pouring concrete floor slab in multilayer building |
CN102248599A (en) * | 2011-07-26 | 2011-11-23 | 江苏圣乐机械有限公司 | Inner mould hanging system for aqueduct mould |
CN102418418A (en) * | 2010-09-28 | 2012-04-18 | 杨峰 | Short-slab-span prefabricated beam floor formwork system |
CN102418425A (en) * | 2010-09-28 | 2012-04-18 | 杨峰 | Prefabrication integral casting building structure system with cast-in-site haunched beams, and construction method for prefabrication integral casting building structure system |
CN104652808A (en) * | 2015-01-29 | 2015-05-27 | 成都迅德科技有限公司 | Framework supporting system |
CN105019656A (en) * | 2015-08-07 | 2015-11-04 | 山东金城建设有限公司 | Construction method for floor system concrete post-cast strip suspended formwork |
CN105715063A (en) * | 2016-01-27 | 2016-06-29 | 北京筑福国际工程技术有限责任公司 | Aerated concrete roof panel reinforced through steel beam structure and construction method thereof |
CN110258887A (en) * | 2019-06-25 | 2019-09-20 | 杭州聚源建筑设计有限公司 | A kind of long-span beams rod structure and its construction method |
CN110439284A (en) * | 2019-07-23 | 2019-11-12 | 孟令红 | A kind of steel construction formwork |
CN111502252A (en) * | 2019-01-30 | 2020-08-07 | 河南天丰绿色装配集团有限公司 | Hanging type formwork-supporting-free system for beam system steel structure building floor and construction method |
CN111502254A (en) * | 2019-01-30 | 2020-08-07 | 河南天丰绿色装配集团有限公司 | Hanging type formwork support-free frame for construction of beam system steel structure floor slab |
CN111502253A (en) * | 2019-01-30 | 2020-08-07 | 河南天丰绿色装配集团有限公司 | Jacking type formwork-supporting-free system for beam-concentrating system steel structure building floor and construction method |
CN111576926A (en) * | 2020-05-12 | 2020-08-25 | 中铁十四局集团建筑工程有限公司 | Steel structure house floor formwork supporting structure and construction method |
CN111910914A (en) * | 2020-08-31 | 2020-11-10 | 中冶京诚工程技术有限公司 | Multi-story high-rise assembled steel structure non-composite floor slab supporting system and construction method thereof |
CN112538982A (en) * | 2020-11-06 | 2021-03-23 | 上海建工四建集团有限公司 | Interim bearing structure of truss floor |
CN112854746A (en) * | 2021-01-13 | 2021-05-28 | 北京拓翌建筑工程有限责任公司 | Inverted hanging type supporting system for steel truss floor support plate and construction method |
-
2010
- 2010-01-25 CN CN2010101008784A patent/CN101787796B/en not_active Expired - Fee Related
Cited By (19)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102418418A (en) * | 2010-09-28 | 2012-04-18 | 杨峰 | Short-slab-span prefabricated beam floor formwork system |
CN102418425A (en) * | 2010-09-28 | 2012-04-18 | 杨峰 | Prefabrication integral casting building structure system with cast-in-site haunched beams, and construction method for prefabrication integral casting building structure system |
CN102116084B (en) * | 2010-12-10 | 2013-09-04 | 陈永生 | Hanging formwork device replacing supporting formwork for pouring concrete floor slab in multilayer building |
CN102116084A (en) * | 2010-12-10 | 2011-07-06 | 陈永生 | Hanging formwork device replacing supporting formwork for pouring concrete floor slab in multilayer building |
CN102248599A (en) * | 2011-07-26 | 2011-11-23 | 江苏圣乐机械有限公司 | Inner mould hanging system for aqueduct mould |
CN102248599B (en) * | 2011-07-26 | 2013-02-13 | 江苏圣乐机械有限公司 | Inner mould hanging system for aqueduct mould |
CN104652808A (en) * | 2015-01-29 | 2015-05-27 | 成都迅德科技有限公司 | Framework supporting system |
CN105019656B (en) * | 2015-08-07 | 2017-04-12 | 山东金城建设有限公司 | Construction method for floor system concrete post-cast strip suspended formwork |
CN105019656A (en) * | 2015-08-07 | 2015-11-04 | 山东金城建设有限公司 | Construction method for floor system concrete post-cast strip suspended formwork |
CN105715063A (en) * | 2016-01-27 | 2016-06-29 | 北京筑福国际工程技术有限责任公司 | Aerated concrete roof panel reinforced through steel beam structure and construction method thereof |
CN111502252A (en) * | 2019-01-30 | 2020-08-07 | 河南天丰绿色装配集团有限公司 | Hanging type formwork-supporting-free system for beam system steel structure building floor and construction method |
CN111502254A (en) * | 2019-01-30 | 2020-08-07 | 河南天丰绿色装配集团有限公司 | Hanging type formwork support-free frame for construction of beam system steel structure floor slab |
CN111502253A (en) * | 2019-01-30 | 2020-08-07 | 河南天丰绿色装配集团有限公司 | Jacking type formwork-supporting-free system for beam-concentrating system steel structure building floor and construction method |
CN110258887A (en) * | 2019-06-25 | 2019-09-20 | 杭州聚源建筑设计有限公司 | A kind of long-span beams rod structure and its construction method |
CN110439284A (en) * | 2019-07-23 | 2019-11-12 | 孟令红 | A kind of steel construction formwork |
CN111576926A (en) * | 2020-05-12 | 2020-08-25 | 中铁十四局集团建筑工程有限公司 | Steel structure house floor formwork supporting structure and construction method |
CN111910914A (en) * | 2020-08-31 | 2020-11-10 | 中冶京诚工程技术有限公司 | Multi-story high-rise assembled steel structure non-composite floor slab supporting system and construction method thereof |
CN112538982A (en) * | 2020-11-06 | 2021-03-23 | 上海建工四建集团有限公司 | Interim bearing structure of truss floor |
CN112854746A (en) * | 2021-01-13 | 2021-05-28 | 北京拓翌建筑工程有限责任公司 | Inverted hanging type supporting system for steel truss floor support plate and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN101787796B (en) | 2012-04-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101787796B (en) | Suspended formwork bracing system for steel structure concrete floor slab construction | |
CN201627362U (en) | Suspended formwork support device for construction of steel structured concrete slabs | |
CN103635643B (en) | The construction method of nigh-level synthesis steel bar concrete cylindrical shell | |
CN101974974B (en) | Support device for template for construction of steel structure concrete floor slab | |
WO2016077943A1 (en) | Building supporting unit and building supporting structure employing same | |
CN103352563A (en) | Self plate-bearing type steel bar mesh support combined template and construction method thereof | |
CN201943344U (en) | Supporting device of template used in the construction of steel structure concrete floor | |
CN203394027U (en) | Semi-assembled construction system for frame-shear wall tube structure | |
CN203257090U (en) | Framework system of cantilever slab | |
CN109162437B (en) | Integral steel platform for multi-cylinder steel plate shear wall and construction method thereof | |
CN201991226U (en) | Flange template support structure | |
CN207700680U (en) | A kind of roof boarding hangs mould | |
CN201915629U (en) | Novel quick detaching template for cast-in-situ concrete floor of steel structure building | |
CN201943345U (en) | Tool-type steel bracket for horizontal formwork | |
CN102418417B (en) | Long-slab-span cast-in-situ beam ribbed floor early-dismantling template formwork system | |
CN204728688U (en) | A kind of combined template for architecture | |
KR20130065941A (en) | Arch type system scaffolding and the construction method of the same | |
RU146196U1 (en) | CONNECTION JOINT FOR COLUMN AND FLAT REINFORCED CONCRETE FLOORING | |
CN203430006U (en) | Quick disassembly and assembly cantilever bracket for building outer wall construction | |
RU108472U1 (en) | SUPPORTING FORMWORK FOR COMBINED REINFORCED CONCRETE COVERING OF THE CESON TYPE | |
CN202338108U (en) | Steel-wood support rigid supporting structure fixed on lower wing plates of steel beams of floor | |
KR20110001884U (en) | Supporting system for reinforcing beam of slab pannel | |
CN205224579U (en) | Steel framework template and self -supporting truss board combination concrete quick detach system | |
CN208981761U (en) | Combined aluminum alloy template | |
CN115126233B (en) | Construction method for using cantilever beam plate high formwork with complex outer vertical surface as outer wall scaffold |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C10 | Entry into substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C17 | Cessation of patent right | ||
CF01 | Termination of patent right due to non-payment of annual fee |