CN101713178B - Method for creating three-stage flow passage of meandering riverway in lower Yellow River - Google Patents

Method for creating three-stage flow passage of meandering riverway in lower Yellow River Download PDF

Info

Publication number
CN101713178B
CN101713178B CN2009101772906A CN200910177290A CN101713178B CN 101713178 B CN101713178 B CN 101713178B CN 2009101772906 A CN2009101772906 A CN 2009101772906A CN 200910177290 A CN200910177290 A CN 200910177290A CN 101713178 B CN101713178 B CN 101713178B
Authority
CN
China
Prior art keywords
river
dam
flow
flood
riverway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN2009101772906A
Other languages
Chinese (zh)
Other versions
CN101713178A (en
Inventor
江恩慧
曹永涛
高航
赵连军
李军华
张林忠
刘燕
万强
张清
夏修杰
赵新建
董其华
黄鸿海
顾霜妹
刘杰
卢冬梅
常华
荆凯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yellow River Institute of Hydraulic Research
Original Assignee
Yellow River Institute of Hydraulic Research
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yellow River Institute of Hydraulic Research filed Critical Yellow River Institute of Hydraulic Research
Priority to CN2009101772906A priority Critical patent/CN101713178B/en
Publication of CN101713178A publication Critical patent/CN101713178A/en
Application granted granted Critical
Publication of CN101713178B publication Critical patent/CN101713178B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Revetment (AREA)

Abstract

The invention relates to a method for creating a three-stage flow passage of a meandering riverway in the lower Yellow River, of which the International Patent Classification (IPC) is E02B1/00 and E02B3/02. The method comprises the following steps of: constructing a control-guide engineering dam which comprises spur dikes made of waterproof earth-rock dams according to the radius of a river bend at the outermost side of a main design riverway; constructing a submerged dam at the chuting section at the tail part of the control-guide engineering dam, wherein the crest elevation is equal to the regulated-flow water level, and the top of the submerged dam is provided with a scour prevention facility; and distributing permeable pile dam at the two sides in a medium-size channel of a straight river section between two bends, wherein the crest elevation of the pile dam is the same as the water level with the local flow of 800m3/s. The three-stage flow passage created by the method can control the river pattern flow passages in different states of the small-size flow passage, medium-size flow passage and flood period, realize the river stability, enhance the capabilities of releasing flood and transferring sands in the riverway, and prevent the Yellow River levee from avulsion, breakdown and other dangerous situations, thereby achieving the goal of the comprehensive treatment of the riverway in the lower Yellow River.

Description

Method for creating three-stage flow passage of meandering riverway in lower Yellow River
Technical field:
The present invention relates to the method for river regulation, its IPC international Patent classificating number is E02B 1/00 and E02B3/02, and particularly a kind of braided channel, downstream, the Yellow River that the braided reache river gesture scope of going around is control effectively is renovated three grades of stream shaping methodses and moulded the dam.
Background technology:
The dredging waterway scheme in downstream, the Yellow River is to form gradually in the practice process of dredging waterway, and what adopt at present is little curved renovation scheme.This scheme is according to river gesture development law, plans as a whole the requirement of each department of national economy, chooses a kind of basic stream as the regulation stream; Concave bank in the bend section is built training works, the control lead the river potential barrier to.This scheme is because crooked amplitude significantly reduces than the bendability river course, and it is little curved that the river course is, so claim " little curved renovation scheme ".
To little curved renovation scheme, carried out a large amount of prototype measurements, analysis and river model test for many years, the research basis is comparatively sturdy, and theory is ripe relatively, and the regulation experience is than horn of plenty.In the long term studies process, progressively formed " flood control is main, makes overall plans; the regulation of middle water; withered the taking into account of flood, protect with the dam curved, with curved water conservancy diversion; initiatively layout; actively perfect, Liu Shiwei master, exploitation green wood " regulation principle and thinking, and, the perfect relatively regulation parameter determination method of a cover has been proposed in conjunction with the actual boundary condition of downstream, the Yellow River braided reache and the husky process of water.
By carrying out dredging waterway in the downstream, the Yellow River, the braided reache river gesture scope of going around is effectively controlled, and current are improved, and have improved flood control safety, and the fraction that draws yellow water intaking has been improved in the beach that prevented from effectively to collapse, the village of collapsing.Building of river training works created huge economic benefit and social benefit.But, also there is certain deficiency in little curved dredging waterway scheme, because river training works is by the thinking of " middle water regulation " design, engineering is laid near the middle current road compliance of the flow regulation flow better, but for flow less little water or great flood, also there is certain inadaptability in existing engineering; Particularly after the Xiaolangdi Dam Project utilization, downstream river course has 300 days time all to be in 400~800m every year approximately 3The little water process of/s, the little water duration increases greatly, engineering is more obvious to the performance of the inadaptability of little water, and outstanding behaviours increases in lopsided river bend, engineering changes than greatly or take off the river and lose effect is led in the control of river gesture by slipping the position, and the deformity river is bent totally unfavorable to the flood control in downstream, the Yellow River during little water.Can realize the combination of poised river gesture and flood control safety, regime channel combines with improving transportability of sediments, realizes the long-term stability of the Yellow River.
Summary of the invention:
The objective of the invention is to overcome the deficiencies in the prior art and provide a kind of on existing little curved dredging waterway scheme basis, replenish perfect to the river training works of laying, make its not only can adapt in the current road, potential barrier road, river in the time of also can adapting to little water and great flood, build three grades of streams gradually, the braided channel, downstream, the Yellow River that reaches the purpose of control potential barrier road, river, enhancing flood control safety is renovated three grades of stream shaping methodses and is moulded the dam.
As follows for realizing the technical scheme that purpose of the present invention takes:
Regulation three grades of stream shaping methodses in braided channel, downstream, a kind of the Yellow River is characterized in that:
(1), build the river control works dam, the river control works dam be to form the groynes group by fluid-tight earth and rockfill dam according to turning radius, and crest elevation is renovated the flow water level and added the 1m superelevation for designing in design main stem outermost;
(2), send at river control works dam afterbody and to slip shed repair and build the ground sills that can flood, crest elevation equals to renovate the flow water level, the ground sills dam crest is provided with the erosion control facility;
(3), in the Zhong Shui riverbed of straight section both sides between two bends, lay pervious dike, stake dam crest elevation and local 800m 3Water level during/s flow is identical.
(4), at flow 800m 3During the following little water of/s, the main flow constraint is controlled in the scope on weep road, groove width 500m is beneficial to form narrow relatively dark low flow channel; Regulation flow 4000m is taking place 3During middle Chang Hongshui about/s, the river control works that is formed by the groynes group and sending slips a section ground sills and plays a role, and in the scope of current road, groove width 800~1000m was beneficial to the stable Zhong Shui riverbed that comprises low flow channel during main flow was controlled at; When great flood takes place, effect is led in the river control works performance control that is formed by the groynes group, and ground sills that it is first down and permeable spur be overcurrent all, and most of current are constrained in the riverbed between the river control works of two sides, wide 2000~the 2500m in flood passage riverbed is to stablize river gesture flood period.
The dredging waterway dam that downstream, a kind of the Yellow River three grades of streams of braided reache are moulded, it is characterized in that: build the river control works dam in the river course outermost, the river control works dam is to form the groynes group by fluid-tight earth and rockfill dam according to certain turning radius, and crest elevation adds the 1m superelevation for design regulation flow water level when great flood takes place; River control works dam afterbody is built the ground sills that can flood, and crest elevation is that regulation flow 4000m is taking place 3The height of regulation flow water level during the middle Chang Hongshui of/s; Pervious dike is laid in both sides in the Zhong Shui riverbed of the straight section between two bends, stake dam crest elevation and local 800m 3Water level during/s is identical.
At flow 800m 3During the following little water of/s, river gesture main flow is restrained to be controlled in the scope on weep road, and groove width 500m forms narrow relatively dark low flow channel gradually; Regulation flow 4000m is taking place 3During the middle Chang Hongshui of/s, the river training works and the first down ground sills thereof that are formed by the groynes group play a role, and in the scope on current road, groove width 800-1000m formed the Zhong Shui riverbed that comprises low flow channel gradually during river gesture main flow was controlled in; When great flood takes place, effect is led in the river training works performance control that is formed by the groynes group, and ground sills that it is first down and permeable spur be overcurrent all, and most of current are constrained in the riverbed between the river control works of two sides, about groove width 2000m, form stable flood channel gradually.
The present invention has following advantage: three grades of streams that utilize this technology to build can satisfy control potential barrier road, river under weep road, middle current road, flood period different conditions; transportability of sediments drains off floodwaters for realization poised river gesture, enhancing river course; the generation of great dangerous situation such as prevent that Dike Along Lower Yellow River from bursting, bursting; reach the target of the Yellow River downstream channel comprehensive regulation, stable crucial meaning arranged what guarantee the Yellow River and Huai He River sea plain and even the Chinese nation.
Description of drawings:
Fig. 1 is existing little curved renovation scheme schematic diagram.
Fig. 2 is three grades of stream schematic diagrames of the present invention.
The specific embodiment:
As shown in Figure 1, 2, build the river control works dam in the river course outermost, the river control works dam is to form the groynes group by fluid-tight earth and rockfill dam according to turning radius, and crest elevation adds the 1m superelevation for design regulation flow water level.Send the slide shed repair to build the ground sills that can flood at river control works dam afterbody, crest elevation equals to renovate the flow water level.Pervious dike is laid in both sides in the Zhong Shui riverbed of straight section between two bends, stake dam crest elevation and local 800m 3Water level during/s flow is identical.
After the construction of above-mentioned river training works plane figure is finished, at flow 800m 3During the following little water of/s, all river training works all can be brought into play control and lead effect, and river gesture main flow is restrained to be controlled in the scope on weep road, about groove width 500m, forms narrow relatively dark low flow channel gradually; Regulation flow (4000m is taking place 3During near/ middle Chang Hongshui s), river training works that forms by the groynes group and the first down main effect of ground sills performance thereof, during river gesture main flow is controlled in the scope on current road, groove width 800~1000m, formation comprises the Zhong Shui riverbed of low flow channel gradually; When great flood takes place, effect is led in the river training works performance control that is formed by the groynes group, and ground sills that it is first down and permeable spur be overcurrent all, and most of current are constrained in the riverbed between the river control works of two sides (big flood stream), about groove width 2000m, form stable flood channel gradually.

Claims (1)

1. method for creating three-stage flow passage of meandering riverway in lower Yellow River is characterized in that:
(1), build the river control works dam, the river control works dam be the groynes group who is made up of according to turning radius fluid-tight earth and rockfill dam, and crest elevation is renovated the flow water level and added the 1m superelevation for designing in design main stem outermost;
(2), send at river control works dam afterbody and to slip shed repair and build the ground sills that can flood, crest elevation equals to renovate the flow water level, the ground sills dam crest is provided with the erosion control facility;
(3), in the Zhong Shui riverbed of straight section both sides between two bends, lay pervious dike, stake dam crest elevation and local 800m 3Water level during/s flow is identical.
(4), at flow 800m 3During the following little water of/s, the main flow constraint is controlled in the scope on weep road, groove width 500m is beneficial to form narrow relatively dark low flow channel; Regulation flow 4000m is taking place 3During middle Chang Hongshui about/s, the river control works that is formed by the groynes group and sending slips a section ground sills and plays a role, and in the scope of current road, groove width 800~1000m was beneficial to the stable Zhong Shui riverbed that comprises low flow channel during main flow was controlled at; When great flood takes place, effect is led in the river control works performance control that is formed by the groynes group, and ground sills that it is first down and permeable spur be overcurrent all, and most of current are constrained in the riverbed between the river control works of two sides, wide 2000~the 2500m in flood passage riverbed is to stablize river gesture flood period.
CN2009101772906A 2009-09-29 2009-09-29 Method for creating three-stage flow passage of meandering riverway in lower Yellow River Expired - Fee Related CN101713178B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN2009101772906A CN101713178B (en) 2009-09-29 2009-09-29 Method for creating three-stage flow passage of meandering riverway in lower Yellow River

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN2009101772906A CN101713178B (en) 2009-09-29 2009-09-29 Method for creating three-stage flow passage of meandering riverway in lower Yellow River

Publications (2)

Publication Number Publication Date
CN101713178A CN101713178A (en) 2010-05-26
CN101713178B true CN101713178B (en) 2011-02-16

Family

ID=42417140

Family Applications (1)

Application Number Title Priority Date Filing Date
CN2009101772906A Expired - Fee Related CN101713178B (en) 2009-09-29 2009-09-29 Method for creating three-stage flow passage of meandering riverway in lower Yellow River

Country Status (1)

Country Link
CN (1) CN101713178B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094404A (en) * 2011-02-21 2011-06-15 河海大学 Method for constructing deep pool and shoal in straight river channel
CN102220745A (en) * 2011-02-23 2011-10-19 河海大学 Small and medium straight river longitudinal winding form construction method

Families Citing this family (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103898867A (en) * 2014-03-13 2014-07-02 重庆交通大学 Spur dike, for inland waterway improvement, not connected with embankment
CN104264626A (en) * 2014-09-02 2015-01-07 中国水利水电科学研究院 Structure for controlling and guiding river regime and stabilizing river mainstream
CN104652353B (en) * 2015-01-16 2016-04-20 河海大学 A kind of gradually sequence encrypted sections point type river control works method for arranging for braided channel
CN109295915A (en) * 2017-07-25 2019-02-01 广州市景秀环境科技有限公司 The riverbed naturalization remodeling method in a set of wide shallow river
CN111177875B (en) * 2019-12-24 2021-11-05 天津大学 River regulation scheme simulation and optimization method
CN111666667B (en) * 2020-05-29 2023-06-13 黄河水利委员会黄河水利科学研究院 Method for determining bed-making flow of wandering river
CN113886922B (en) * 2021-10-08 2022-04-15 河北省水利水电勘测设计研究院集团有限公司 Spur dike group design method based on big data and field test
CN115075184B (en) * 2022-07-08 2024-05-17 江苏百绿园林集团有限公司 Urban inland river curved river erosion protection shore structure layout and construction method

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2429870A1 (en) * 1978-06-26 1980-01-25 Sif Entreprise Bachy Control of river meander in arid land - using vertical slab deflectors at intervals to divert flood flows towards centre of channel
CN1970889A (en) * 2006-12-04 2007-05-30 何富荣 Method for building deep sea passage
CN100445470C (en) * 2005-04-19 2008-12-24 中国科学院生态环境研究中心 Underwater groins system for growing various living things

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR2429870A1 (en) * 1978-06-26 1980-01-25 Sif Entreprise Bachy Control of river meander in arid land - using vertical slab deflectors at intervals to divert flood flows towards centre of channel
CN100445470C (en) * 2005-04-19 2008-12-24 中国科学院生态环境研究中心 Underwater groins system for growing various living things
CN1970889A (en) * 2006-12-04 2007-05-30 何富荣 Method for building deep sea passage

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张红武,张俊华,钟德钰,卜海磊.黄河下游宽河道的治理方略.《第十届中国科协年会黄河中下游水资源综合利用专题论坛文集》.2008,55-64. *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102094404A (en) * 2011-02-21 2011-06-15 河海大学 Method for constructing deep pool and shoal in straight river channel
CN102094404B (en) * 2011-02-21 2013-04-03 河海大学 Method for constructing deep pool and shoal in straight river channel
CN102220745A (en) * 2011-02-23 2011-10-19 河海大学 Small and medium straight river longitudinal winding form construction method

Also Published As

Publication number Publication date
CN101713178A (en) 2010-05-26

Similar Documents

Publication Publication Date Title
CN101713178B (en) Method for creating three-stage flow passage of meandering riverway in lower Yellow River
CN105603943B (en) What tunnel formula imitated nature fish pass blocks fish lifting means and method
CN103510493B (en) Low overflow dam cave depot type hydropower station
CN104480914B (en) The fish pass structure that fish pass combines with ship lock and method
CN102733351B (en) Method for treating river entrance
CN106638482A (en) Sectional curtain water barrier structure
CN107620285A (en) A kind of a copious, rapid flow of words governing system and method
CN201610539U (en) Lower Yellow River wandering river way three-grade flow path building dam system
CN208717853U (en) The sinuous formation of self-adapting type plane for repairing linear channelized course
CN102561260A (en) Water-permeable waterway improvement spur dike
CN105421309A (en) Overlap joint device between water retaining curtains
CN204000745U (en) A kind of bulwark
CN105603942B (en) Dykes and dams super standard flood flood diversion siphon pipe band
CN105649140B (en) Intake strucure, water intake system, the method for construction of circulation and intake strucure
CN103614986A (en) Free surface flow water inflow method suitable for draining off floodwaters of tailing pond
CN106149647B (en) It is a kind of artificially not controlled down the method and structure for letting out ecological flow
CN203383184U (en) Step type ecological landscape water retaining dam suitable for city watercourse
CN203729376U (en) Water intake well pipe structure used for hydraulic and hydropower engineering
CN106702968A (en) Arc type overflow dam capable of automatically washing away sand and reducing siltation and running method of arc type overflow dam
CN206554031U (en) It is a kind of sand washing to subtract the arc line type overflow dam of silt automatically
CN207988083U (en) The orthogonal anti-structure of drainning off floodwaters of Gobi Region solar energy optical-thermal place
CN207331601U (en) A kind of ecological, environmental protective permeable spur structure
CN203834420U (en) Tidal reach staggered pressing foot bundle-shaped ecological river channel
CN103938579B (en) Wrong presser feet bundle shape ecological riverway between tidal reach
CN205530160U (en) Drop energy absorber

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
C17 Cessation of patent right
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20110216

Termination date: 20110929